Final Report: Preparatory Survey ON The Project For The Improvement OF The Tema Motorway Roundabout (Phase-2)
Final Report: Preparatory Survey ON The Project For The Improvement OF The Tema Motorway Roundabout (Phase-2)
Final Report: Preparatory Survey ON The Project For The Improvement OF The Tema Motorway Roundabout (Phase-2)
PREPARATORY SURVEY
ON
THE PROJECT FOR THE IMPROVEMENT
OF
THE TEMA MOTORWAY ROUNDABOUT
[Phase-2]
FINAL REPORT
February 2020
EI
JR
20-014
MINISTRY OF ROADS AND HIGHWAYS
GHANA HIGHWAY AUTHORITY
PREPARATORY SURVEY
ON
THE PROJECT FOR THE IMPROVEMENT
OF
THE TEMA MOTORWAY ROUNDABOUT
[Phase-2]
FINAL REPORT
February 2020
Japan International Cooperation Agency (JICA) decided to conduct the preparatory survey and
entrust to CTI Engineering International Co., LTD.
The survey team held a series of discussions with the officials concerned of the Government
of the Republic of Ghana, and conducted field investigations. As a result of further studies in Japan, the
present report was finalized.
I hope that this report will contribute to the promotion of the project and to the enhancement
of friendly relation between two countries.
Finally, I wish to express my sincere appreciation to the officials concerned of the Government
of the Republic of Ghana for their cooperation extended to the survey team.
February 2020
Itsu ADACHI
Director General
Infrastructure and Peacebuilding Department
Japan International Cooperation Agency
Location Map
View from Aflao side
PERSPECTIVE
TABLE OF CONTENTS
Preface
Location Map / Perspective
Contents
List of Tables & Figures
Abbreviations
Contents
1. Background of the Project .......................................................................................................................... 1
1.1 Background and Outline of the Project ................................................................................................ 1
1.2 Requested Scope .................................................................................................................................. 2
1.3 Objective of the Survey ........................................................................................................................ 2
1.4 Outline of the Project ........................................................................................................................... 3
1.5 Study on Environmental and Social Considerations ............................................................................ 3
1.5.1 Study on Initial Environment Examination ................................................................................... 3
1.5.2 The System and Administration on Environmental and Social Consideration .............................. 6
1.5.3 Environmental Standard ................................................................................................................ 6
1.5.4 Procedure on Environmental Assessment ..................................................................................... 8
1.5.5 Scoping .......................................................................................................................................... 9
1.5.6 Survey Plan on Environmental and Social Considerations ......................................................... 12
1.5.7 The Survey Results of Environmental and Social Considerations .............................................. 13
1.5.8 Environmental Impact Assessment.............................................................................................. 15
1.5.9 Major Mitigation Measures and Cost .......................................................................................... 18
1.5.10 Environmental Monitoring Plan ................................................................................................ 20
1.5.11 Stakeholder Meeting .................................................................................................................. 23
2. Contents of the Project ............................................................................................................................. 24
2.1 Basic Concept of the Project .............................................................................................................. 24
2.2 Outline Design of the Japanese Assistance ........................................................................................ 24
2.2.1 Design Policy .............................................................................................................................. 24
2.2.2 Basic Plan .................................................................................................................................... 27
2.2.3 Outline Design Drawings ............................................................................................................ 70
2.2.4 Implementation Plan ................................................................................................................... 71
2.3 Security Plan ...................................................................................................................................... 84
2.4 Obligations of Recipient Country....................................................................................................... 85
2.5 Project Operation Plan ....................................................................................................................... 86
2.5.1 Organization for Operation and Maintenance ............................................................................. 86
2.5.2 Contents of Operation and Maintenance ..................................................................................... 88
- i -
2.5.3 Points to Consider in Road Operation and Maintenance ............................................................. 89
2.5.4 Gender Equality Approach .......................................................................................................... 89
2.5.5 The Policy on Gender Consideration in Phase-2 ......................................................................... 91
2.6 Project Cost Estimate ......................................................................................................................... 94
2.6.1 Initial Cost Estimation ................................................................................................................. 94
2.6.2 Operation and Maintenance Cost ................................................................................................ 95
3. Project Evaluation .................................................................................................................................... 96
3.1 Preconditions to implement the project .............................................................................................. 96
3.2 Necessary input by Recipient Country ............................................................................................... 96
3.3 Important assumptions ....................................................................................................................... 97
3.4 Evaluation .......................................................................................................................................... 98
3.4.1 Relevance .................................................................................................................................... 98
3.4.2 Effectiveness ............................................................................................................................... 99
3.4.3 Impacts to Green House Gas (GHG) and Future Traffic Volume ................................................ 99
Appendices
- ii -
TABLES
Table 1.4-1 Outline of the Project .................................................................................................................. 3
Table 1.5-1 Ambient air standard (2016 version) ........................................................................................... 7
Table 1.5-2 National ambient noise level standards ....................................................................................... 8
Table 1.5-3 Scoping Result ............................................................................................................................ 9
Table 1.5-4 Method and Contents of the survey........................................................................................... 12
Table 1.5-5 Measurement Result of ambient air around Tema (December 2015) ........................................ 14
Table 1.5-6 Noise level around Tema roundabout ........................................................................................ 14
Table 1.5-7 Monitoring results on construction phase (February 2019) ...................................................... 14
Table 1.5-8 Assessment results ..................................................................................................................... 15
Table 1.5-9 Major Mitigation Measures and Cost ........................................................................................ 18
Table 1.5-10 Environmental Monitoring Plan .............................................................................................. 21
Table 1.5-11 Summary of stakeholders meeting .......................................................................................... 23
Table 2.2-1 List of Surveys Conducted ........................................................................................................ 25
Table 2.2-2 Level of Service ........................................................................................................................ 27
Table 2.2-3 Traffic Count Survey at Tema Intersection................................................................................ 28
Table 2.2-4 Vehicle Classification (GHA Pavement Design Manual) .......................................................... 29
Table 2.2-5 Results of traffic survey for each section .................................................................................. 31
Table 2.2-6 Results of Traffic Survey by direction ...................................................................................... 31
Table 2.2-7 Comparison of peak traffic volume for each section between Saturday and Tuesday .............. 32
Table 2.2-8 Peak traffic volume for each section ......................................................................................... 33
Table 2.2-9 Comparison of Traffic Volume between Phase-1 and Phase-2 .................................................. 33
Table 2.2-10 Setting of current traffic volume (2019).................................................................................. 35
Table 2.2-11 Population frame around Tema Roundabout ........................................................................... 36
Table 2.2-12 Tema Port Cargo Volume ........................................................................................................ 36
Table 2.2-13 Model Parameters.................................................................................................................... 37
Table 2.2-14 Toll revenue of Accra - Tema Motorway................................................................................. 37
Table 2.2-15 Estimated results ..................................................................................................................... 37
Table 2.2-16 Traffic Volume according to Direction at Peak Hours in 2025(Veh./hr) ................................. 39
Table 2.2-17 Traffic Volume according to Direction at Peak Hours in 2035(Veh./hr) ................................. 39
Table 2.2-18 Investigation Items and Scopes ............................................................................................... 40
Table 2.2-19 Investigation Results ............................................................................................................... 42
Table 2.2-20 Analysis Result ........................................................................................................................ 46
Table 2.2-21 Unit Weight of Materials ......................................................................................................... 48
Table 2.2-22 Values of bending moment at an intermediate support (kNm) ................................................ 51
Table 2.2-23 Comparison Study of Superstructure ...................................................................................... 54
Table 2.2-24 Comparison Study of Deck Slab ............................................................................................. 55
Table 2.2-25 Comparison of Abutment Type ............................................................................................... 57
- iii -
Table 2.2-26 Comparison of Foundation Type ............................................................................................. 58
Table 2.2-27 Design Criteria (General and Geometric Condition)............................................................... 59
Table 2.2-28 Cross section Elements and Widths......................................................................................... 61
Table 2.2-29 Reference Point (Axis) ............................................................................................................ 62
Table 2.2-30 Comparison of Retaining Structures ....................................................................................... 63
Table 2.2-31 Pavement Composition of Approach Roads ............................................................................ 64
Table 2.2-32 Study Cases ............................................................................................................................. 66
Table 2.2-33 Study Results........................................................................................................................... 69
Table 2.2-34 Table of Contents .................................................................................................................... 70
Table 2.2-35 Major Engineer/Local Procurement Categories ...................................................................... 73
Table 2.2-36 Responsibility of Each Government ....................................................................................... 74
Table 2.2-37 Quality Management Plan for Flyover (Bridge) Superstructure ............................................. 76
Table 2.2-38 Quality Management Plan of Concrete Works ........................................................................ 77
Table 2.2-39 Quality Management Plan for Earthwork and Pavement Work .............................................. 77
Table 2.2-40 Procurement Area of Major Construction Materials ............................................................... 79
Table 2.2-41 Major Construction Equipment to be Procured ....................................................................... 82
Table 2.2-42 Implementation Schedule of Phase-2 of the Project................................................................ 83
Table 2.5-1 Regionals Heads of Maintenance Department .......................................................................... 87
Table 2.5-2 GHA Road Areas ....................................................................................................................... 88
Table 2.5-3 Road Sector Personnel in GHA ................................................................................................. 88
Table 2.5-4 Woman, Business and the Law index scores (a part of result) .................................................. 90
Table 2.5-5 Working ration of woman in construction industry ................................................................... 90
Table 2.5-6 Gender Consideration Policy .................................................................................................... 91
Table 2.5-7 Client Staffs Involvement in Phase-2 ........................................................................................ 92
Table 2.5-8 Monitoring method on participation of women ........................................................................ 93
Table 2.6-1 Approximate Cost Estimate of Japanese Contribution .............................................................. 94
Table 2.6-2 Approximate Cost Estimation of Ghana Contribution .............................................................. 94
Table 2.6-3 Maintenance Item to be checked and Annual Maintenance Cost .............................................. 95
Table 3.4-1 Quantitative Effect .................................................................................................................... 99
Table 3.4-2 Emission factor of carbon dioxide (CO2) on representative car type ...................................... 100
Table 3.4-3 CO2 emission factor on Greenhouse gas reporting ................................................................. 101
Table 3.4-4 Car category and car type ........................................................................................................ 101
Table 3.4-5 Prediction condition for emission volume of CO2 .................................................................. 102
Table 3.4-6 Estimated traffic volume and prediction of CO2 emission ...................................................... 102
- iv -
FIGURES
Figure 1.5-1 Outline diagram of intersection ................................................................................................. 4
Figure 1.5-2 Comparison of ROW on Phase-1 and Phase-2 .......................................................................... 5
Figure 1.5-3 Renewal period of environmental permit .................................................................................. 8
Figure 2.2-1 Survey Locations in and around Tema Intersection ................................................................. 28
Figure 2.2-2 Results of Traffic Volume Survey on Road Sections ............................................................... 29
Figure 2.2-3 Survey Points (Ashaiman Roundabout)................................................................................... 30
Figure 2.2-4 Traffic Count Result (Inflow to Ashaiman Roundabout) ......................................................... 31
Figure 2.2-5 Verification Results of Existing Traffic Characteristics ........................................................... 34
Figure 2.2-6 Review of Phase-1 traffic volume ........................................................................................... 35
Figure 2.2-7 Location of the section number in Table 2.2-16 and Table 2.2-17........................................... 38
Figure 2.2-8 Location of Drilling Points and CBR Test ............................................................................... 41
Figure 2.2-9 Geological Profile .................................................................................................................... 43
Figure 2.2-10 Review of Configuration (Inflow from Aflao Road) ............................................................. 45
Figure 2.2-11 Pictures Showing Flow Condition for LOS A-D ................................................................... 45
Figure 2.2-12 Cross Section of the Flyover.................................................................................................. 47
Figure 2.2-13 Loading curve for UDL of HA loading.................................................................................. 49
Figure 2.2-14 HB Loading of One Unit Vehicle .......................................................................................... 49
Figure 2.2-15 Typical Cross Section of Superstructure ................................................................................ 50
Figure 2.2-16 Live Load Application on Influence Line (Intermediate Support) ........................................ 50
Figure 2.2-17 Bridge Length and Span Length ............................................................................................ 53
Figure 2.2-18 Integrated Steel Pier and Girder ............................................................................................ 56
Figure 2.2-19 Horizontal Alignment ............................................................................................................ 60
Figure 2.2-20 Typical Cross Section (Diagram not included in the hardcopy document)............................ 61
Figure 2.2-21 Design Vehicle ....................................................................................................................... 62
Figure 2.2-22 Akosombo Road – Ashaiman Roundabout ............................................................................ 65
Figure 2.2-23 Improvement Proposed by Third Country Study ................................................................... 65
Figure 2.2-24 Case-1:At-grade Improvement ........................................................................................... 66
Figure 2.2-25 Case-2:At-grade Signalized Intersection ............................................................................ 67
Figure 2.2-26 Case-3:North-South Direction Grade Separation ............................................................... 68
Figure 2.2-27 Proposed Detour .................................................................................................................... 74
Figure 2.2-28 Location of Borrow Pit and Aggregate Plant ......................................................................... 79
Figure 2.5-1 Organizational Framework of MRH ........................................................................................ 86
Figure 2.5-2 Department in Charge of Maintenance in GHA ...................................................................... 86
Figure 2.5-3 Organization of Regional Head ............................................................................................... 87
- v -
ABBREVIATIONS
- vi -
1. Background of the Project
1.1 Background and Outline of the Project
The Republic of Ghana (hereinafter “Ghana”) has been making remarkable progress recently in expanding
international trunk roads to facilitate both the international and the domestic transportation. Currently, road
traffic in the country accounts for about 95% of the total transportation volume of roads, railways, water
transportation, and airports. The need for expansion and stretching of the road network to cater for the
increasing trade volume resulting from the recent rapid economic growth of the country is high and growing.
Greater Accra Region, where the capital city Accra and the port city of Tema are is highly concentrated with
traffic as the Region is not only home to over 16.3% of the country’s total population but also has high
percentage of registered vehicles that accounts to 65% of the total vehicles while it occupies only 1.4% of the
country’s total land area.
The Tema Motorway Roundabout connects two international arterial roads, the Lagos-Abidjan Corridor,
which is a part of the Dakar to Lagos Trans African Highway (TAH) No.7 of the Economic Community of
Western African States (ECOWAS), and the Eastern Corridor of Ghana, which links Tema Port to the
landlocked countries of Burkina Faso, Mali and Niger. Tema Roundabout is a 5-leg roundabout where traffic
inflow to and from Accra and Tema Port converge causing traffic congestions and serving as a bottleneck for
long-distance logistics. Usually during rush hours that is at the peak of morning and evening the roundabout
is heavily congested with vehicles cueing for over a distance of 5 km from the intersection and running in a
retarded speed lower than 10 km/h. The congestion and the decrease in speed at the roundabout is becoming
an impediment to smooth and safe movement of people and traffic. This is compounded by the increase in
traffic to and from Tema Port due to the increase in cargo handling volume at the port. The port has seen an
increase of more than 60% in 10 years, from 2007 to 2016. The Government of Ghana (GOG) has plans to
expand the Tema Port and put a bridge over Lake Volta under the ODA loan project “Eastern Corridor Volta
River Bridge Project”. Materialization of the port expansion and construction of the bridge will further attract
traffic at Tema Roundabout contributing to significant rise of traffic volume in the region and at the
roundabout as well. In order to enhance smooth and safe traffic flow (logistics) both within the country and
the West African Region, urgent improvement of Tema Motorway Roundabout is inevitable.
The GOG formulated the National Transport Policy in 2008 and has been expanding and upgrading
international corridors with an aim to achieve integrated, efficient, and sustainable transport system and
further strengthen the function of the country with an aim to becoming the transport hub of the West African
region. The Ministry of Roads and Highways (MRH) in its “Sector Medium -Term Development Plan: 2014-
17” identifies improvement of Tema Intersection as one of the top priority projects for enhancing safe and
smooth transportation at the intersection thereby contributing to enhancing the economic activities of the
region including the entire country.
Under such circumstance, the GOG made a request to the Government of Japan (GOJ) for a grant aid
assistance to improve the Tema intersection. In response to the request, JICA conducted “the Preparatory
Survey on the Project for the Improvement of the Tema Motorway Roundabout” (hereafter “first Survey”)
- 1 -
from April 2016 to February 2017, where grade separation of the roundabout was recommended to be
implemented in two phases: Phase-1 recommended development of an underpass in the east-west direction
and Phase-2 recommended putting a flyover/overpass in the north-south direction.
Exchange of Notes (E/N) was signed in April 2017 between the GOG and the GOJ for implementation of the
“Ghanaian International Corridor Improvement Project” (hereinafter “Project under construction”) for Phase-
1 of the project. This was followed by signing of the Grant Agreement (G/A) between JICA and Ministry of
Roads and Highways, Ghana Highway Authority (MRH/GHA). Based on these agreements, the detailed
design, construction and construction supervision of the Phase-1 infrastructure was conducted. As of
February 2020, construction of an underpass in the east-west direction (Motorway-Aflao) and an at-grade
intersection are on-going. Completion of Phase-1 construction is scheduled in June 2020.
This report is prepared for Phase-2 (development of flyover/overpass along north-south direction), which
compiles the results of the outline design drawing carried out reflecting the results of various engineering
surveys undertaken in Ghana and information gathered from discussions and hearings conducted with the
GHA and other relevant agencies of Ghana for assessment by JICA on the feasibility of the Phase-2
component request by GOG.
The request made by the GOG for Phase-2 is to construct a flyover bridge over Tema Motorway Roundabout
after completion of Phase-1 project, which is under construction at the same project site, including to develop
the detailed design of the flyover and to carry out its construction supervision.
Phase-2 is the continuity of Phase-1. The requested scope by the GOG for Phase-1 was to construct an
underpass, improve at-grade intersection, conduct the detailed design and supervise the construction. Phase-
1 is at the construction stage, where the underpass (box-culvert) for through traffics in the east-west direction
and an at-grade intersection for other traffics are currently under construction.
• Understand the background, purpose, and scope of project under the Grant Aid Assistance Scheme
of Japan,
• Study the feasibility of the project in terms of effectiveness, technical and economic justification,
• Conduct outline design for minimum and optimal scope and scale of the project to achieve the
outcome of the assistance,
• Propose the contents, implementation and maintenance plan as well as critical points to be
undertaken by the GOG in order to achieve the outcome and targets set for the project.
- 2 -
1.4 Outline of the Project
Targets, expected outcome, survey location and project beneficiaries are summarized in Table 1.4-1.
In general, environmental and social considerations is conducted to evaluate the impacts from a development
project to the environment and social conditions in and around the project area. The potential impacts to
various parameters, such as fauna, flora, ambient air, ambient water and noise/vibration, resettlement, are
studied through screening and scoping and mitigation measures suggested to be monitored and implemented
accordingly before, during and after implementation of the project.
The project area of Phase-2 lies within the existing right-of-way (ROW) - to be precise in the middle of the
existing ROW or within the Phase-1 area. Initial Environmental Examination (IEE) was conducted during
Phase-1 which also covered the survey area of Phase-2. According to the Environmental Protection Agency
(EPA), the responsible agency for environmental and social considerations, the environmental permit issued
for Phase-1 is valid for Phase-2 also. This Survey therefore checked the permissibility of the existing
environmental permit including necessity for conducting the Environmental and Social Considerations
survey additionally and comparison of the impacts between Phase-1 and Phase-2.
1.5.1.1 Project Components and the Category of Environmental and Social Consideration
The outline of the project components is as given below. The project components are to be implemented in
two phases. Phase-2 project is categorized as class “B” by JICA.
Phase-2 Components
• Flyover (142 m) in the north-south direction (Harbour Road – Akosombo Road) 1.75 km
• Signalled-controlled at-grade intersection
• Ancillaries : (Traffic lights, Street lights, Drainage facilities, Safety facilities (crash barriers, road signs etc.))
Phase-1 Components
2-tier intersection (730 m underpass with 190 m long box-culvert in the east-west direction) (Motorway – Aflao
Road)
East-west: 2.1 km, north-south :1.9 km
Ramps: approx. 7 km, Service roads: approx. 3.5 km
Signalled-controlled at-grade intersection
Ancillaries: (Traffic lights, Drainage facilities, 4 Pedestrian bridge , Safety facilities (crash barriers, road signs etc.)
- 3 -
As aforementioned, Phase-1 components are currently under construction. Figure 1.5-1 shows the major
components of each phase. The blue line highlights the Phase-1 major component (a box-culvert in the east-
west direction), and the red line highlights the Phase-2 major component (a flyover in the north-south
direction over Tema Motorway Roundabout).
LEGEND
The survey area is located at Tema in the Greater Accra region and is straddled by the Tema, Kpone
Katamanso and Ashaiman assemblies. Tema is located in the southwest, Kpone Katamanso in the south-east
and Ashaiman in the north of Tema Roundabout. It is a convergence point of the National Roads N1 and
Akosombo and urban road (Harbour Road). The section of National Road N1 is an access-controlled
Motorway. The convergence point used to be a roundabout, which is now being improved under Phase-1 by
a 2-tier intersection. Originally, the target area of the Project used to be a roundabout. This roundabout
underwent temporary improvement (provision of slip roads for providing free flow of vehicles turning right
from each legs of the roundabout) under project carried out by Meridian Port Service. Currently, construction
works to improve the roundabout by converting it to a 2-tier intersection is ongoing. This is being done under
the Phase-1 project. This survey is the continuity of Phase-1 project which is undertaking a study to check
the viability of the project that will put a flyover over the underpass constructed in Phase-1. The target area
of Phase-2 lies within the ROW of Phase-1, to be precise in the middle of the Phase-1 area. Figure 1.5-2 shows
the target area of this survey.
- 4 -
Phase 1 Objective Area:
Phase 2 Objective Area
- 5 -
Acquisition area managed by long-term lease hold, therefore problems associated with ownership of land are
not anticipated to be high. However, there are some simple business stores within the ROW. The most
prominent ones are facilities such as fast food joints, filling stations, bus terminals, sale of used cars and heavy
machinery for hiring, and mechanic shops for car repairs that are related to transportation. The designated
Tema Heavy Industry Area (about 50 km2) lies southeast of Tema intersection. The open spaces, particularly
between the Tema - Aflao Road and Tema - Akosomobo Road, are full of vendors/small shops.
Basic understanding on Phase-2 does not require re-settlement of stores due to completion of settlement of
all stores during Phase-1.
Major law and regulation related environmental and social consideration is below. These systems are the for
Phase-1 survey.
Environmental standards related environment and social consideration in Ghana are shown below, and some
of these standards are considering updating for 2016 version from 2007 version.
- 6 -
Table 1.5-1 Ambient air standard (2016 version)
Substance Averaging Time Time Weighed Average (TWA)
Industrial 1 hr
520 µg/m3 Adopted for all zones
Residential 1 hr
Industrial
Sulphur Dioxide (SO2) 24 hr 150 µg/m3 Adopted for All zones
Residential
Industrial
1 yr 80 µg/m3 Adopted for all zones
Residential
Industrial 1 hr.
250 µg/m3 Adopted for all zones
Nitrogen Oxides Residential 1 hr.
(Measured as NO2) Industrial 24 hr
150 µg/m3 Adopted for all zones
Residential 24 hr
Industrial 24 hr
150 µg/m3 Adopted for all zones
Residential 24 hr
Total Suspended Particulate
Industrial 1 yr
80 µg/m3 Adopted for all zones
Residential 1 yr
24 hr 70 µg/m3 Adopted for all zones
PM10
1 Yr 70 µg/m3 Adopted for all zones
PM2.5 24hr 35 µg/m3 Adopted for all zones
Industrial 24 hr
Smoke 100 µg/m3 Adopted for all zones
Residential 24 hr
Industrial
Black Carbon 24hr 35 µg/m3
Residential
15 min 100 mg/m3
30 min 60 mg/m3
Carbon Monoxide
1 hr 30 mg/m3
8 hr 10 mg/m3 Adopted
Benzene 1 yr 5 µg/m3 Adopted
Hydrogen Sulphide 24 hr 150 µg/m3 Adopted
Hydrogen Cyanide 24hr 220 µg/m3 Adopted
Hydrogen Chloride 24hr 20 µg/m3
24hr 15 ng/m3 Adopted
Mercury (and its compounds)
1 yr 1 µg/m3 Adopted
24hr
Lead 1 µg/m3 for 24 hrs. Adopted
1 yr
Cadmium 1 yr 5 ng/m3 Adopted
Manganese 24 hr 1 µg/m3 Adopted
Dichloromethane (Methylene 24 hr
3 mg/m3 Adopted
Chloride)
1,2-Dichloroethane 24 hr 0.7 mg/m3 Adopted
Trichloroethane 24 hr 0.7 mg/m3 Adopted
Tetra chloroethane 24 hr 5 mg/m3 Adopted
Toluene 24 hr 8 mg/m3
Industrial 24 hr
Arsenic 15 ng/m3 Adopted for all zones
Residential 24 hr
Fluoride 24 hr 10 µg/m3 Adopted
8 hr 100 µg/m3 Adopted for all zones
Ozone
1 hr 160 µg/m3 Adopted
Nickel 1 yr 20 ng/m3 Adopted
PAH 1 hr 1 ng/m3 Adopted
Xylene 1 yr 700 µg/m3
24hr 0.1 pg TEQ/m3
Dioxins/Furans
1 yr 0.6 pg TEQ/m3
24 hr 0.6 pg TEQ/m3
Total PCB
1 yr 0.035 µg/m3
- 7 -
National ambient noise level standards was updated in the version 2016, but the values of noise did not change
from the version 2007.
According to the Environmental Assessment Regulations 1999, LI 1652 of Ghana, all developmental projects
which will cause significant environmental impacts have to undergo the EIA procedure prior to project
implementation.
Environmental Permit for implementation of the Project has been acquired in Phase-1. This environmental
permit covers the entire 3-tier grade separation of Tema Motorway Roundabout including construction works/
project of phase-1 and Phase-2. The Survey Team together with GHA had discussed with EPA and confirmed
with EPA that Phase-2 does not require to obtain a separate environmental permit including IEE for Phase-2
for the above reason. However, the permit issues are valid for 18 months and need to be renewed every 18
months until the construction of Phase-2 components is completed. The permit was issued in December 2017.
Therefore, the timings of renewals in every 18 months are as shown in Figure 1.5-3.
- 8 -
1.5.5 Scoping
Scoping is necessary for evaluating the impact of the project before its commencement ordinarily. Phase-2
follows the results of scoping of Phase-1 by the reasons below.
✓ Target area of Phase-2 is within the ROW or within the construction limits of Phase-1.
✓ The environmental impact will be small compared with Phase-1
✓ No separate environmental permit for Phase 2 is required as the permit issued during Phase 1 is
also valid for Phase 2.
✓ According to results of Phase-1 monitoring data, changing the assessment results for environmental
impact is not necessary
Construction Phase
No. Impact Item Phase Reason / Remarks
Construction
Phase
1 Air pollution B- B± Construction Phase: Emission of dust and exhaust gas will
increase due to construction equipment operations and traffic
congestion in construction site.
Operation Phase: In the future, the total amount of air pollutant
caused by vehicle exhaust gas will increase. However, because of
improved traffic efficiency, the amount may be reduced compared
to current situation.
2 Water pollution B- D Construction Phase: Turbid water will be generated during rainfall
periods. However, because there are no water resource areas, rivers
and lakes in and around the project site, impact of turbid water
caused by construction works will be very limited.
Operation Phase: Because water quality of drains will not change
significantly, water pollution is unlikely to occur.
3 Waste B- D Construction Phase: Construction waste caused by construction
and demolition works, and general waste from construction office
will be generated.
Operation Phase: Considerable generation of solid waste is
Pollution
unlikely to occur.
4 Soil pollution D D Because materials that may cause soil pollution such as heavy metal
and toxic organic matter will not be used in the construction and
maintenance works, soil pollution is unlikely to occur.
5 Noise and B- B± Construction Phase: Construction equipment operation will cause
vibration noise and vibration.
Operation Phase: Increased traffic volume and speed will elevate
noise level. However, decrease in horning frequency, the noise level
might be reduced compared to current situation.
6 Ground D D Because the ground is hard and groundwater withdrawal will not be
subsidence included, ground subsidence is unlikely to occur.
7 Offensive odors D D Because materials and equipment that may cause offensive odors
will not be used in construction and maintenance works,
considerable offensive odors are unlikely to occur.
8 Bottom sediment D D Because there are no rivers and lakes near by the project site,
considerable impacts of turbid water caused by construction works
or drainage form roads in operation phase on bottom sediment are
unlikely to occur.
- 9 -
Assessment
Pre- Operation
Category
Construction Phase
No. Impact Item Phase Reason / Remarks
Construction
Phase
9 Protected areas D D Sakumo Ramsar Site (1,364 hectares) is located in a lagoon of
approximately 1.5 km southwest from Tema roundabout. However,
because the zone between the lagoon and Tema roundabout
comprise residential and industrial area and drainage from Tema
roundabout does not flow into the lagoon, impact on ecosystem in
Natural Environment
- 10 -
Assessment
Pre- Operation
Category
Construction Phase
No. Impact Item Phase Reason / Remarks
Construction
Phase
19 Existing social B- B- Pre-Construction Phase: Relocation or protection of utilities
infrastructures and (service lines) such as water and sewer pipes, electric cable,
services telephone line and gas pipe will be required.
Construction Phase: Temporary traffic congestion, shift of bus and
taxi stations, and disturbance of access to roadside facilities will
occurred.
Operation Phase: Crossing of roads by pedestrians would only be
allowed at designated places (footbridge).
20 Social institutions D D Because the project is located in a developed area, considerable
such as social impact on social institutions is unlikely to occur.
infrastructure and
local decision-
making
institutions
21 Misdistribution of C- C- Because the project lies in a developed area, considerable
benefits and misdistribution of benefit among local people is unlikely to occur.
damages However, misdistribution of benefit between relocated and
remaining business stores may occur.
22 Local conflicts of C- C- Because the project lies in a developed area, considerable impact
interest due to local conflict is unlikely to occur. However, local conflict
between relocated and remaining business stores may occur.
23 Cultural heritage D D There are no cultural heritages around Tema Roundabout.
24 Landscape B- D Construction Phase: Loss of vegetation and construction work will
change the landscape.
Operation Phase: Appearance of footbridges will change the
landscape. However, as Tema roundabout is located in commercial
and industrial areas, particular landscape conservation measures
will not be required.
25 Gender D D Because the project is improvement works of existing roundabout,
considerable impact only on gender is unlikely to occur.
26 Children’s rights D D Because the project is improvement works of existing roundabout,
considerable impact only on children’s rights is unlikely to occur.
27 Infectious diseases D D Increased earning power may encourage workers to have multiple
such as HIV/AIDS sexual partners. This phenomenon may expose workers and the
community to HIV and other STI’s.
28 Working B- D Construction Phase: Impact of waste from construction workers
conditions on sanitary conditions around the construction site is likely to occur.
(including Because construction will include works in heights, various
occupational accidents may occur.
Operation Phase: Road operation will not have impacts on
safety)
working conditions.
29 Accidents B- B± Construction Phase: Labor accident, including tumble accident
may involve pedestrians and street vendors
Operation Phase: Decrease of minor accidents in Tema
Roundabout will be expected. On the other hand, traffic accident
may increase in newly constructed intersection at the initial stage.
30 Trans-boundary D D Trans-boundary impacts such as climate change are unlikely to
impacts or climate occur.
Other
change
C+/-: Extent of positive/negative impact is unknown. (A further examination is needed, and the impact could be clarified as the
- 11 -
study progresses)
D: No impact is expected
* Impact Items refer to “JICA Guidelines for Environmental and Social Considerations April 2010”
The result of baseline survey of environment and social considerations of Phase 1 is adopted for Phase-2 as
the scoping items are similar. The survey methodology of Phase-1 is shown in Table 1.5-4.
Monitoring item/
No. Impact item Construction Operation parameter
Method
Phase
Construction Phase
Phase
1 Air pollution B- B± 1. Ambient air quality ・ Exsiting data
2. Environment standard ・ Measurement of NO2 in roadside
3. Affect of construction ・ Confirmation of construction
4. Forecasting traffic contents and the method
condition in future
・ Prediction of pollution load based
on future traffic
2 Water pollution B- D 1. water quality ・ Survey of exsting data
2. Influence by ・ Confirmation of effluent on road
construction side
Pollution
・ Confirmation of construction
method and components
3 Waste B- D 1. Treatment method of ・ Hearing to staff
waste around ・ Survey of similar countermeasure
construction site
4 Noise and B- B± 1. Noize and vibration ・ Survey of exsting data
Vibration 2. Environmental ・ Measuerment of noise level on road
standard side
3. Hospital and school ・ Predict of nosie level based on
4. Influence by future traffic
construction
・ Confirmation of construction
method and components
1 Resettlement/ B- D 1. Scale of resettlement ・ Survey of related regulations
Land 2. Preparation of ・ Survey of socila economic
Acquisition abbreviated ・ Survey of resttelment cost
resettlement action
・ Hearing of stakeholders
plan
・ Survey of similar countermeasure
2 Impoverished/P B± D 1. Living conditions of ・ Survey of social economic
Social Environment
- 12 -
Assessment
Category Pre-
Construction Monitoring item/
No. Impact item Operation parameter
Method
Phase
Construction Phase
Phase
4 Land use and B- B+ 1. Land use of target area ・ Field survey
utilization of 2. Social economic ・ Survey of exsting data
local resources condition ・ Hearing to steakholders
・ Survey of similar countermeasure
5 Existing social B- B- 1. Utilities condition on ・ Field survey
infrastructures road side ・ Survey of exsting data
and services 2. Situation of vehicles ・ Hearing of stakeholders
and pedestrians
・ Survey of similar countermeasure
crossing the road
3. Inflence of
improvement of
intersection
6 Misdistribution C- C- 1. Living conditions of ・ Survey of social economic
of benefits and affected residents ・ Survey of exsting data
damages 2. Preparation of ・ Survey of similar countermeasure
abbreviated
resettlement action
plan
7 Local conflicts C- C- 1. Living conditions of ・ Survey of social economic
of interest affected residents ・ Survey of exsting data
2. Preparation of ・ Survey of similar countermeasure
abbreviated
resettlement action
plan
8 Landscape B- D 1. Distribution of tree ・ Field survey
2. Procedure related to ・ Survey of exsting data
tree cutting ・ Hearing of stakeholders
9 Working B- D 1. Labour condition ・ Hearing of stakeholders
conditions ・ Survey of similar countermeasure
(including
occupational
safety)
10 Accidents B- B± 1. Occupational accident ・ Survey of exsting data
2. Number of traffic ・ Hearing of stakeholders
accidents ・ Survey of similar countermeasure
The Survey Team measured the quality of air around Tema in December 2015. PM10 and Total Suspended
Particular matter (TSP) exceeded the threshold of the environmental standard values in Ghana. Currently, the
- 13 -
Ghana’s environmental standard is under the process of updating to version 2016.
Table 1.5-5 Measurement Result of ambient air around Tema (December 2015)
Env. Standard in
Parameter Tema roundabout Ghana WHO Guideline
(Ave. 24hr)
NO2 (µg/m3) 4.1 150 200 (Ave, 1hr)
SO2 (µg/m3) 52.5 150 20
PM10 (µg/m3) 150 70 50
TSP (µg/m3) 230 (2007)
290 -
150 (2016)
Measurement of noise level conducted at 5 points in and around Tema Roundabout under this survey indicates
that the noise levels except for the measurement point at the center of the roundabout exceeded 75dB (as
Aeq), which is the Permissible Noise Level in predominantly commercial areas.
- 14 -
1.5.8 Environmental Impact Assessment
Environmental impact was assessed based on baseline survey results and monitoring results of Phase-1.
4 Soil D D D D Because materials that may cause soil pollution such as heavy
pollution metal and toxic organic matter will not be used in the
construction and maintenance works, soil pollution is unlikely to
occur.
5 Noise and A- B± B- B± Construction Phase: Construction equipment operation will
vibration cause noise and vibration, but the impact is not big according to
monitoring results.
Operation Phase: Increased traffic volume and speed will
elevate noise level. However, decrease in horning frequency, the
noise level might be reduced compared to current situation.
6 Ground D D D D Because the ground is hard and groundwater withdrawal will not
subsidence be included, ground subsidence is unlikely to occur.
7 Offensive D D D D Because materials and equipment that may cause offensive odors
odors will not be used in construction and maintenance works,
considerable offensive odors are unlikely to occur.
8 Bottom D D D D Because there are no rivers and lakes near by the project site,
sediment considerable impacts of turbid water caused by construction
works or drainage form roads in operation phase on bottom
sediment are unlikely to occur.
9 Protected D D D D Sakumo Ramsar Site (1,364 hectares) is located in a lagoon of
areas approximately 1.5 km southwest from Tema roundabout.
Natural Environment
- 15 -
Assessment results Assessment results
in 2015 in 2019
Pre- Pre-
Constru Constru
Category
- 16 -
Assessment results Assessment results
in 2015 in 2019
Pre- Pre-
Constru Constru
Category
- 17 -
Assessment results Assessment results
in 2015 in 2019
Pre- Pre-
Constru Constru
Category
C+/-: Extent of positive/negative impact is unknown. (A further examination is needed, and the impact could be clarified as the
study progresses)
D: No impact is expected
* Impact Items refer to “JICA Guidelines for Environmental and Social Considerations April 2010”
The updated assessment results were show in bold based on monitoring results.
There is no significant change in the assessment results between for Phase-1 and for Phase-2. Therefore, the
mitigation method on Phase-2 will be applied to the same method of Phase-1 as shown in Table 1.5-9. The
issues regarding abbreviated resettlement are not included in Phase-2 as there is no resettlement required in
Phase-2. The resettlement issues of Phase-1 were completely resolved as of August 2019.
- 18 -
Catego Impact Cost
No. Mitigation Measures
ry item (US$)
Contractor shall manage the oil and fuel properly.
Cleaning machinery in river is prohibited.
Supervising consultant shall consider proper drainage plan in
advance.
Contractor shall be plant grasses and flowers on road slopes and pit
in order to prevent soil runoff.
Contractor and supervising consultant shall be monitoring the
occurring condition of dirty water and review the construction
method, if needed.
3 Waste Construction Phase: Construction Phase:
Contractor shall conduct proper waste management other cost shall be included in
Contractor shall prepare toilet and waste management space in the construction contract
construction site
Contractor shall collect separately solid waste materials
Contractor shall consider reuse and recycle of construction waste
Contractor and supervising consultant shall be monitoring the waste
treatment method and improve the treatment method, if needed.
4 Noise and Construction Phase: Construction Phase:
Vibration Contractor shall make construction plan to avoid concentrating many Noise monitoring cost
construction machineries for long near residential area 6,000 (6 times)
Contractor shall maintain proper condition of the construction Vibration monitoring cost
machineries to avoid abnormal noise 6,000 (6 times)
Construction work in night is prohibited near residential area
Contractor shall select the low noise machinery as possible other cost shall be included in
Contractor and supervising consultant shall explain construction plan the construction contract
to residence around the site in advance
Contractor and supervising consultant shall be monitoring the noise,
vibration with residence’s opinion and reviewing the construction
method, if needed
Operation Phase
Operation Phase Noise monitoring cost
GHA shall maintain properly the road 2,000 (2 times/2 years)
GHA shall monitor the noise and vibration level along road if the Vibration monitoring cost
results violate significantly the environmental standard. GHA must
2,000 (2 times/2 years)
consider countermeasures for mitigation such as planting.
1 Resettlem Pre-Construction Phase the cost estimation in Phase-1
ent/ Abbreviated resettlement action plan shall be prepared and implanted app. 820,000
Land properly (GH₵ 3,112,786)
Acquisiti In Phase-2 does not require
on resettlement
2 Impoveri Construction Phase: other cost shall be including to
shed/Poor Disclose information on construction plans and off-limits areas, etc. construction contract
people to ensure safety for street vendors that belong to the poverty zone。
Social Environment
- 19 -
Catego Impact Cost
No. Mitigation Measures
ry item (US$)
5 Existing Pre-Construction Phase the cost is included in the
social Consult with the owners of existing infrastructure facilities such as construction contract or
infrastruc telephone poles, water pipes, and optical cables to implement with miscellaneous expenses
tures and develop relocation and protection plans.
services Construction Phase:
Consultants for detail design will design a temporary road for detour.
Contractor shall conduct traffic control to avoid traffic jam
Consultants for detail design shall consider temporary land use in
construction phase by sharing the construction plan among TDC and
related organizations in early stage
Operation Phase
In order to ensure the pedestrians traffic, GHA will improve the
sidewalks, if needed
GHA shall be monitoring a pedestrian’s traffic and shall take
countermeasure, if need.
6 Misdistri Pre-Construction Phase the cost is included in the
bution of Abbreviated resettlement action plan shall be prepared and implanted resettlement budget
benefits properly In Phase-2 does not require
and Operation Phase the resettlement
damages GHA and TDC shall be monitoring living condition of affected
people and shall take countermeasure, if needed
7 Local Pre-Construction Phase the cost is included in the
conflicts Abbreviated resettlement action plan shall be prepared and implanted resettlement budget
of interest properly In Phase-2 does not require
Operation Phase the resettlement
GHA and TDC shall be monitoring living condition of affected
people and shall take countermeasure, if needed
8 Landscap Construction Phase: other cost shall be included in
e Supervising consultant and contractor shall consider minimizing the construction contract
cutting of trees under the construction plan.
Contractor shall plant green grasses along the roadside and slope on
road.
9 Working Construction Phase: other cost shall be included in
condition Supervising consultant and contractor shall conduct preventive the construction contract
s countermeasures on accident before construction.
(includin Contractor shall sprinkle water on the grass as a countermeasure for
g dust
occupatio Contractor shall prepare toilet and dumping site in construction site.
nal
safety)
1 Accidents Construction Phase: the cost is included in the
Supervising consultant and contractor shall conduct preventive construction contract or
countermeasures on accident before construction. miscellaneous expenses
Contractor shall prepare traffic control and setting of traffic signboard
Others
Conducting monitoring activities is to obtain basic information for assessment of Environmental Impact and
it is a requirement of Environmental Permission in Ghana. The monitoring results were submitted to EPA for
renewal of the environmental permission in June 2019. Therefore, the monitoring activities in Phase-2 are
- 20 -
desirable and shall be conducted the same activities of Phase-1.
Responsible
Environmental Monitoring Item/
Person and Location Method Frequency
Item Parameter
Organization
Air pollution Construction Phase: Supervising Construction site Visual observation Visual observation: Daily
・ Dust Consultant/ and interview of Interview:
Contractor pedestrians Monthly or as needed
・ PM10 、 PM2.5 、 Instrumental analysis:
NOx、SOx Instrumental Pre-Construction Phase
analysis 1 time
Construction Phase
5 times
Total 6 times
Operation Phase: GHA Around Tema Instrumental 1 time in dry season and 1
・ PM10 、 PM2.5 、 intersection. analysis time in rainy season per
NOx、SOx year for 2 years after
completion
Total 4 times
Water pollution Construction Phase: Supervising Construction site Visual observation During rainfall
Turbid water and Consultant/
Pollution
plan
Poor people Construction Phase: Supervising Construction site Visual observation Daily
Activity conditions Consultant/
of street venders Contractor
Local Pre-Construction GHA Around Tema Site survey and Monthly or as needed
economies, such Phase: intersection and meeting with PAPs
as employment, Progress of relocation sites
livelihood, etc. resettlement action
plan
- 21 -
Category Environmental Monitoring Item/
Responsible
Person and Location Method Frequency
Item Parameter
Organization
Construction Phase: Supervising Construction site Site survey and Monthly or as needed
Business activity Consultant/ interview of local
around construction Contractor people and
site unskilled labors
Employment
situation of
unskilled labor
Land use and Pre-Construction GHA Around Tema Site survey and Monthly or as needed
utilization of Phase: intersection and meeting with PAP
local resources Progress of relocation sites
resettlement action
plan
Operation Phase: GHA In and around Site survey and Monthly or as needed for 2
Condition of land TDC Tema interview of local years after completion
use intersection people
Condition of
business activity
Existing social Pre-Construction GHA In and around Site survey and Monthly or as needed
infrastructures Phase: Tema meeting with
and services Relocation status of intersection facility owners
existing
infrastructure
facilities
Construction Phase: Supervising Construction site Visual observation Daily
Condition of traffic Consultant/
congestion around Contractor
construction site
Operation Phase: GHA In and around Site survey and Monthly or as needed for 2
Crossing Tema interview of local years after completion
conditions of intersection people
pedestrians
Misdistribution Pre-Construction GHA Around Tema Site survey and Monthly or as needed
of benefits and Phase: intersection and meeting with PAPs
damages Progress of relocation sites
resettlement action
plan
Operation Phase: GHA Around Tema Site survey and Monthly or as needed for 2
Living situations of intersection and meeting with PAPs years after relocation
Project Affected relocation sites
Persons (PAPs)
Local conflicts Pre-Construction GHA Around Tema Site survey and Monthly or as needed
of interest Phase: intersection and meeting with PAPs
Progress of relocation sites
resettlement action
plan
Operation Phase: GHA Around Tema Site survey and Monthly or as needed for 2
Living situations of intersection and meeting with PAPs years after relocation
Project Affected relocation sites
Persons (PAPs)
Landscape Construction Phase: Supervising Construction site Visual observation Daily
Status of tree felling Consultant/ and meeting with
Status of Planting Contractor contractor
works
- 22 -
Category Environmental Monitoring Item/
Responsible
Person and Location Method Frequency
Item Parameter
Organization
prevention
measures
Operation Phase: GHA In and around Site survey and Monthly or as needed for 2
Number of traffic Tema traffic accident years after completion
accident intersection data
The stakeholder meeting was held on 31st of May, 2019 for explanation of the construction schedule and
outline of the project. The result of meeting is compiled in Table 1.5-11. This stakeholder meeting was held
during the construction period of Phase-1, hence opinions includes the current construction condition. As a
general opinion, it can be judged that the project itself has been positively evaluated although there were some
requests/opinions with regards to the current construction works in Phase-1.
Major Project timeline and schedule must be provided and should be clearly made visible.
discussion/ Emergency health units should be built at/or close to the site.
Recommend The temporary fences provided to cordon the construction area of Phase 1 make the Aflao bus
ation station difficult to be seen easily.
- 23 -
2. Contents of the Project
2.1 Basic Concept of the Project
In July 2013, the Government of Ghana (GOG) requested the Government of Japan (GOJ) to provide grant aid for
improvement of the Tema intersection into phases. In response, JICA conducted the 1st preparatory survey in 2015.
Based on the survey result, the construction of the underpass in the east-west direction (Motorway-Aflao) and
ground intersection for right-left turn has started from February 2018 as first phase of this project, and will be
expected completion on June 2020. The second phase of the project will basically follow the plan prepared during
the 1st preparatory survey, and build a flyover in north-south direction (Akosombo-Habour) including approach
roads.
• January 2019 to February 2019: Inception Report (IC/R) explanation and first site survey (work in
Ghana)
• March 2019 to June 2019: Determination of project Scopes; Outline Design; and Project cost
estimate (work in Japan)
• May 2019 to June 2019: Technical design review by GHA; Agreement with GHA on the project
scopes; and Second site survey (work in Ghana)
• July 2019 to October 2019: Outline Design and Review of the Outline Design Drawings; and Project
cost estimate review by JICA (work in Japan)
• November 2019: Draft Final Report (DF/R) Explanation and Agreement with GHA on the contents
of the Outline Design (work in Ghana)
- 24 -
that it meets the vertical clearance requirement and has minimal impact to the ramps and service roads that
merges with the Phase-2 road and are currently under construction.
The project objective road is located at a nodal point between high standard highways (national roads). The
construction is required to be done where the diversion road is adjacent to the construction premises. In
addition, since the impact to road users and alongside residents are significant as the volume of existing traffic
is high and the road sides are occupied by residents and vendors, it is important that safety and construction
efficiency are given proper consideration.
Engineering surveys were conducted to ensure all relevant and necessary data and information are obtained
for planning and design while taking the above issues into consideration. The surveyed items, survey purpose,
survey location, scale and survey method are summarized in Table 2.2-1.
3. Traffic Survey To collect Traffic On all the roads ・ Counting peak hour traffics Subcontracting
data for future traffic connecting to Tema
demand forecast Roundabout
To understand Existing Ashaiman ・ Counting peak hour traffics Counting traffic volume by
traffic behavior at the Roundabout vehicle type and direction by
intersection AI analysis of videos taken
Roundabout by drone
4. Existing Drainage To comprehend the Areas along ・ Study direction of flow Collection of available data
Survey existing condition of objective road ・ Grasp the existing provision and site observation
road incidental of drainage facilities
facilities so that it ・ Check on outlets
could be reflected in
the design work
- 25 -
Survey Purpose Location Scope Methodology
5. Other Surveys To comprehend the In and around the ・ Current traffic operation Collection of available data
existing condition of objective ・ Pedestrian volume and site observation
road ancillary intersection ・ Pavement surface condition
facilities for design ・ Land use
work ・ Gender and Population
・ Economic & industrial
survey
The future traffic volume which is the basis for determining the scale of the project was estimated in the
preparatory survey in Phase-1. This Survey reviewed the future traffic volume taking into account the changes
of the site condition beyond the preparatory survey of Phase-1.
The condition agreed upon with regards to the Level of Service (LOS) of each major leg of the intersection
was to attain a level of ‘C’ or higher. Since traffic concentrates during the morning and evening peak time,
the LOS generally becomes low. Securing a high LOS at the peak time is therefore considered to be an
excessive design. Therefore, the LOS of ‘D’ is planned to be attained for these roads.
- 26 -
On the other hand, the future traffic volume that is the basis for the intersection improvement plan is estimated
on the assumption that there will be no development of the road network near the Tema intersection until
2035. This means that there is no change in traffic flow pattern (improvement of LOS by traffic change).
LOS is defined in accordance with traffic conditions such as travel speed, travel time, traffic obstruction, and
comfort. LOS with respect to the general operating conditions is as shown in Table 2.2-2.
1) Basic Policy
The configuration and structures of Phase-2 were planned based on the results of traffic demand forecast from
the results of the traffic count survey carried out during Phase-1. Therefore, basic principal with regards to
traffic forecast for Phase-2 follows the results of Phase-1. However, supplementary traffic count survey is
carried out for verification of the traffic volume forecasted in Phase-1. Possible detours are included in the
target locations of the survey to capture the vehicles that would use these detours to avoid the impacts of the
ongoing Phase-1 construction area. The results would be compared and should significant difference be
admitted, the demand forecast of Phase-1 will be re-analyzed.
With regards to the Ashaiman Roundabout, a traffic survey is conducted to understand the traffic behavior
and issues. The Team study the possible remedial measures to mitigate the traffic congestion in and around
the roundabout and share it with GHA for its reference.
The traffic count survey was conducted from January 26 to February 22, 2019. Survey locations, which
included objective and the detours are as shown in Figure 2.2-1. Seven items as shown in Table 2.2-3 were
surveyed.
- 27 -
Figure 2.2-1 Survey Locations in and around Tema Intersection
- 28 -
Table 2.2-4 Vehicle Classification (GHA Pavement Design Manual)
Classification of vehicles in the survey GHA classification of vehicles
1. Motor Cycle Motor bike
Car
2. Passenger Car Taxi
Pick-up/Van/4WD vehicle
3. Minibus Small bus
Medium bus/Mammy wagon
4. Bus
Large bus
5. Light Truck Light truck
Medium truck
6. Heavy Truck
Heavy truck
Semi-trailer (Light, Heavy)
7. Trailer
Truck-trailer
8. Others Extra-large truck & others
Figure 2.2-2 shows the actual measured values at the time of Phase-1 (2015), the estimated values for 2019,
and the results of this traffic survey. Comparison and analysis with the measured and estimated values
during Phase-1 is described in Section 4) “Phase-1 Traffic Analysis and Verification” hereunder.
1514
1864
1077 Tema Intersection
To Accra 1220 Aflao Road
Ashaiman IC 305
1524
1354
1237
918
862
Hospital Road
Habour Road
Ashaiman Road
339
Unit: vehicle/hr.
- 29 -
3) Results of Traffic Survey on Road Sections (Ashaiman Roundabout)
[Survey Overview]
Traffic survey by direction was conducted during peak hours on weekdays. The target route and survey points
are shown in Figure 2.2-3. The number in the figure refers to each section number (Akosombo Road is defined
as No. 2 at the Tema Roundabout, so the branch number of No. 2 is adopted).
2-2
2-3
2-1
2-4 Ashaiman Roundabout
Figure 2.2-4 gives the traffic volume entering the Ashaiman Roundabout. Apparently, the volumes in the
north-south direction is greater than those ply in the east-west direction, but the difference is not significant.
- 30 -
To Akosombo
To Tema
The share of large-size vehicles is almost 2%, which is much lower than that of the Tema Roundabout.
- 31 -
4) Analysis and Verification of Phase-1 Traffic Volumes
Table 2.2-7 shows the results of the traffic count survey for each leg of the roundabout conducted on Saturday
and Tuesday. The ratio of total number of traffic volumes of weekday to weekend (Tuesday / Saturday) 1.3,
meaning the traffic volume on Tuesday is 1.3 times than that of Saturday. Phase-1 defines 7:00am of a
weekday as the peak hour. Therefore, peak hour in Phase-2 was also defined on Tuesday and the survey
results observed on the morning of this day is applied in the analysis.
Table 2.2-7 Comparison of peak traffic volume for each section between Saturday and Tuesday
Saturday,26/January
No.1 No.2 No.3 No.4
Classification Accra-Tema MotorWay Tema-Akosombo Road Tema-Aflao Road Tema Harbor Road
Volume Volume Volume Volume
Motorcycle 68 158 287 161
Car & Taxi 1,870 604 1,420 1,198
Minibus 409 545 526 727
Bus 46 13 131 82
Light Truck 101 34 80 41
Heavy Truck 88 26 55 51
Trailer 38 22 23 44
Others 2 7 36 20
Total(All type of Veh.) 2,622 1,409 2,558 2,324
Tuesday,29/January
No.1 No.2 No.3 No.4
Classification Accra-Tema MotorWay Tema-Akosombo Road Tema-Aflao Road Tema Harbor Road
Volume Volume Volume Volume
Motorcycle 109 329 237 231
Car & Taxi 2,142 749 1,947 1,588
Minibus 612 348 650 1,011
Bus 145 71 47 56
Light Truck 80 94 54 60
Heavy Truck 72 43 52 61
Trailer 41 60 36 55
Others 0 0 8 4
Total(All type of Veh.) 3,201 1,694 3,031 3,066
Tuesday/Saturday
No.1 No.2 No.3 No.4
Classification Accra-Tema MotorWay Tema-Akosombo Road Tema-Aflao Road Tema Harbor Road
Volume Volume Volume Volume
Motorcycle 1.6 2.1 0.8 1.4
Car & Taxi 1.1 1.2 1.4 1.3
Minibus 1.5 0.6 1.2 1.4
Bus 3.2 5.5 0.4 0.7
Light Truck 0.8 2.8 0.7 1.5
Heavy Truck 0.8 1.7 0.9 1.2
Trailer 1.1 2.7 1.6 1.3
Others 0.0 0.0 0.2 0.2
Total(All type of Veh.) 1.2 1.2 1.2 1.3
Table 2.2-8 shows the results of the road section traffic survey for each leg of the roundabout at peak time
from 7:00am to 8:00am. The highest traffic volume was on point No. 1 on the Accra-Tema Motorway with
3,201 vehicles per hour, followed by point No.4 on the Tema Horbour Road with 3,066 vehicles per hour.
Traffic volume on point No.3 on the Tema-Aflao Road and point No.2 on Tema-Akosombo Road was 3,031
and 1,694 vehicles per hour respectively.
Looking at the composition of vehicle types, the highest proportion of large size vehicle was on Tema-
- 32 -
Akosombo Road at 10%. Proportion on other points were less than 10%.
Table 2.2-9 shows the comparison of Phase-1 and Phase-2 traffic volume. Traffic volumes of Phase-1 are the
forecasted figures for 2019, while traffic volumes of Phase-2 are actual traffic volume counted in this Survey.
As shown in the table, the total traffic volume counted during Phase-2 is higher at point No. 1 on the
Motorway, while it is smaller at point No.2 on Akosombo Road. The volumes at point No. 3 on Aflao Road
and point No.4 on Harbour Road are almost similar to the volumes forecasted for 2019. In terms of total
volume, traffic volume counted in Phase-2 is approx. 20% less than the volume estimated for 2019 in Phase-
1. This is assumed to be the effect of the vehicles that use the detours without passing through the intersection
anticipating congestion at the intersection due to ongoing construction activities.
Entry Exit Total Entry Exit Total Entry Exit Total Entry Exit Total
No.1 Accra-Tema MotorWay 926 894 1,820 1,524 1,245 2,769 1,354 1,847 3,201 0.9 1.5 1.2
No.2 Tema-Akosombo Road 1,330 738 2,068 1,891 1,211 3,102 929 765 1,694 0.5 0.6 0.5
No.3 Tema-Aflao Road 1,220 1,091 2,311 1,864 1,714 3,578 1,514 1,517 3,031 0.8 0.9 0.8
No.4 Tema Harbor Road 918 1,663 2,581 1,237 2,361 3,598 862 2,204 3,066 0.7 0.9 0.9
No.5 Tema-Hospital Road 469 404 873 607 592 1,199 - - - - - -
Total 4,863 4,790 9,653 7,123 7,123 14,246 4,659 6,333 10,992 0.7 0.9 0.8
- 33 -
⚫ The following four roads are detours at the Tema
Roundabout.
Based on the above analysis and verification results, Phase-1 traffic volume in Aflao Road was reviewed in
Phase-2, and used for input for demand forecast. The review outline and result are shown in Figure 2.2-6.
⚫ Compared to the values of 2019 estimated during Phase-1, the current cross-sectional traffic volume was
confirmed to be decreasing. This is thought due to traffic detours to avoid construction congestion.
⚫ However, when the surrounding traffic and the traffic on the detour is viewed from a wide perspective, the
traffic volumes counted are almost the same as the ones estimated in Phase-1 for 2019. Therefore, the
estimated value in Phase-1 can be considered to be appropriate.
- 34 -
⚫ As of February 2019, about 17% of traffic volume has diverted from Aflao Road to Steel Work Road, which
is currently under construction.
1891
of Aflao Road and Harbor Road even after the
1771 (95% of 1864)
completion of this project, but since the Tema Accra-Tema Motorway
Intersection may receive traffics on these detours
1524 Aflao Road
after completion of the project, the current traffic
1237
volume at the Tema Intersection is sets as follows. Harbour
Road
➢ 5% of the traffic from the estimated traffic volume
during Phase-1 is expected to divert to the Steel Work Road and only 95% will ply along the Aflao Road
and the intersection.
➢ Traffic volume on all other legs of the intersections will be similar to the volume estimated during Phase-
1.
1) Basic consideration
In Phase-1, the future traffic demand forecast was calculated as the product of the current traffic volume and
the rate of future traffic growth. The demand forecast model that defines the Accra Motorway’s toll revenue
as the explanatory variable was applied to calculate the rate of traffic growth. The population growth rate of
Tema Metropolitan, the growth rate of freights handled at Tema Port were taken as the explanatory variable
and the growth rate of the toll revenue was calculated using the demand forecast model. This value was
applied for the traffic growth rate
Since new findings regarding the populations and cargo handling volume of Tema Port were not available,
- 35 -
the demand forecast model of Phase-1 was applied.
2) Socio-economic Framework
In calculating the future traffic demand, first, the socioeconomic framework was set based on the available
data. The set framework included the local population, and the volume of cargo handled at Tema Port. The
concept of calculation of each indicator is as follows.
[Population]
The population framework was set using the population of the Greater Accra Region, excluding the Ga West
District. This judgement came from the traffic volume at the Tema Roundabout with a high correlation with
this region. The values for the framework are shown in Table 2.2-11.
[Cargo Volume at Tema Port] Table 2.2-12 Tema Port Cargo Volume
Year Volume Handled (×1000 tonne)
The central predicted values from the Ghana Master Ports 2010 8,460
Development Plan -Cargo Forecast- were adopted for the 2011 10,578
volumes of cargo that would handle at Tema Port in the 2012 11,419
2013 12,129
future. Marine transshipment volume, which does not
2014 15,370
affect the land traffic, was excluded. On the other hand, 2015 18,610
dry bulk cargos, general cargos, container cargos, and 2020 26,350
liquid cargos were included. Table 2.2-12 shows the cargo 2025 35,480
2030 44,800
volume handled in the future at the Tema Port.
2035 55,130
- 36 -
3) Formulation of Demand Forecast Model
In calculating the growth rate in the traffic volume, first, a demand forecast model was built for two types of
vehicles using the toll revenue of the Accra - Tema Motorway as an explained variable. The explanatory
variables were the population of the Tema region, and the volume of cargos handled at Tema Port. From the
demand prediction model, the percentage increase in the toll revenue was calculated, and this applied to the
growth rate in the traffic volume. There were two types of prediction models, a passenger car model and a
freight vehicle model. The model equation was a linear regression equation. The model parameters and the
toll revenue of the Accra - Tema Motorway are shown in Table 2.2-13 and Table 2.2-14. Either model was
high in a coefficient of determination, so the applicability was good.
The future toll revenue was estimated based on the model prepared in the previous section. The average
annual percentage increase for every five years obtained from the estimated results are shown in Table 2.2-15.
The light truck values are average values of passenger cars and heavy trucks because light trucks have
characteristics of intermediate of the two.
Future traffic demand was calculated by multiplying the 2019 traffic volume reviewed in Section 2.2.2.1 by
- 37 -
the rate of future traffic growth. The estimated traffic volume by peak direction in each year is shown in Table
2.2-16 and Table 2.2-17. The numbers in 1st row and 1st column in each table indicate the section numbers
shown in Figure 2.2-7.
1: Accra-Tema Motorway
2-1:Ashaiman Roundabout WEST 2-2
2-2:Ashaiman Roundabout NORTH 2-3
2-3:Ashaiman Roundabout EAST
2-1
3:Tema-Aflao Road Ashaiman
4:Tema Harbor Road Roundabout
Tema Roundabout
1 3
Figure 2.2-7 Location of the section number in Table 2.2-16 and Table 2.2-17
- 38 -
Table 2.2-16 Traffic Volume according to Table 2.2-17 Traffic Volume according to
Direction at Peak Hours in 2025(Veh./hr) Direction at Peak Hours in 2035(Veh./hr)
- 39 -
(3) Geo-technical Investigation
1) Objectives
⚫ To provide specific site information to confirm and amplify the geotechnical and geomorphologic
findings of the desk study;
⚫ To obtain detailed knowledge of the soils to be encountered at the site and their likely behavior on
substructures ;
⚫ To foresee and provide against difficulties and delays that may arise during construction due to
groundwater and other local conditions;
⚫ To establish design parameters and present basis for the design of substructures.
2) Scope of Investigation
The investigation consists of field work and laboratory work. The scopes of each work are shown in Table
2.2-18.
3) Investigation Period
The investigation works were carried out from end of January 2019 till end of March 2019.
4) Investigation Results
[Geo-technical Investigation]
⚫ Desk study and field reconnaissance (geological and geotechnical information on the project area)
⚫ Laboratory testings
- 40 -
The ground investigation was undertaken in accordance with the ASTM D220. For drilling and sample
extraction, five (5) boreholes were drilled at the site. The location of the boreholes is presented in Figure 2.2-8.
In-situ Standard Penetration Test (SPT) was carried out at every 1 m interval up until refusal was recorded.
Akosombo Rd.
BH-3
To Accra
Aflao Rd.
BH-4 BH-4 BH-3
BH-2
BH-5
BH-2
BH-5
BH-1
BH-1
Standard Penetration Test (SPT)
was carried out at every 1m
interval up to till refusal was
recorded. To Tema Port
The disturbed and SPT samples recovered from the boreholes have been tested at the laboratory for the
following items;
The composition of the ground, soil distribution layer and its N-value and soil properties for all five (5)
locations where drilling was conducted are summarized in Table 2.2-19. Based on the results of drilling at
five locations, the geological profile of the target flyover location is assumed as shown inTable 2.2-19 and
Figure 2.2-9. The presence of weathered rocks with an N value of more than 50 was confirmed at G.L.-2 m
to -5 m.
- 41 -
Table 2.2-19 Investigation Results
Layer
Depth N-value
No. Thickness Soil Properties Remarks
(m) (Nos.)
(m)
Stiff, dry, greyish sandy CLAY with medium
2.0 2.0 10
sized sandstone particles
Medium density, hard and slightly damp
5.0 3.0 SANDY SOIL with a mixture of light brownish 18-25
BH1
clay
Very hard and slightly moist, light brown
6.0 1.0 19
SANDY SILT
7.0 and below >5 m Rock >50 Refusal
Medium density, hard and slightly damp
2.0 2.0 CLAYISH GRAVEL mixed with light 29-50
BH2
brownish clay
6.0 and below >4 m Rock >50 Refusal
Medium density, hard and slightly damp
3.0 3.0 SANDY SOIL with a mixture of light brownish 18-25
BH3
clay
4.0 and below >5 m Rock >50 Refusal
Medium density, hard and slightly damp
1.0 1.0 SANDY SOIL with a mixture of light brownish 24
clay
BH4
Very hard and slightly moist, light brown
2.0 1.0 43
SANDY SILT
3.0 and below >5.0 Rock >50 Refusal
Hard and slightly damp brown sand and gravel
5.0 5.0 mixed CLAY 9-39
BH5
- 42 -
- 43 -
※1
Materials such as soil for fill and aggregates for concrete and asphalt are available locally and from the same
sites of Phase-1. As these materials have already been tested during Phase-1, the results of Phase-1 are referred.
The Phase-1 construction has identified various utilities in the project area. Electrical poles and cables
belonging to Electricity Company of Ghana (ECG), water pipes belonging to Ghana Water Company Limited
(GWCL), telecommunication cables belonging to MTN, TIGO, AIRTEL, VODAFONE, GLO etc. Basically,
all the utilities within the Phase-1 construction premises have been identified and relocated outside of Phase-
1 construction limits. The area of Phase-2 construction lies within the premises of Phase-1, in the middle of
Phase-1 area to be precise. As such, existence of utilities that would affect the construction of Phase-2 are not
anticipated.
Phase-1 construction is already underway, and it is fundamentally important to ensure that the basic structures
of phase-2 are in harmony with Phase-1. However, taking the decrease of traffic volume plying to Aflao-
Tema direction, the demand foreast conducted during Phase-1 was reviewed. The capacity analysis of the
intersection was re-done and as the construction of the intersection was yet to be undertaken as of May, 2019,
the alteration of the configuration, if justifiable was agreed to be undertaken through design change in the
Phase-1 construction.
The subject of examination is the number of lanes at the inflow of the intersection of Aflao Road. In Phase-
1, 3 lanes were planned as exclusive left-turning lanes. However, taking the decrease of the traffic volume
into consideration, capacity analysis of the intersection was re-checked.
(3) Condition
・ As in Phase-1, the traffic volume by direction of peak hours as of 2035 is used as input.
・ Analysis based on HCM2010
・ LOS to be secured will be level ‘D’ or higher
Analysis result is shown in Table 2.2-20. It is evident from the result that LOS ‘D’ can still be secured even in
case the number of inflow lanes (left-turn lanes) is reduced to 2-lanes (Figure 2.2-10).
- 44 -
Akosombo Road Akosombo Road
SBR SBL SBL SBR SBL SBL
1
WBR
1 WBL WBR
WBL WBL
Af l ao Road
Af l ao Road
Mot or way
Mot or way
WBL WBL
LOS:C LOS:D
EBL EBL
EBL EBL
EBR
1 EBR
In a technical design review by GHA in May 2019, the change in the number of lanes was explained to GHA
The consent was obtained and it was approved in September 2019 for design change to be reflected in Phase-
1 construction.
- 45 -
Table 2.2-20 Analysis Result
1) Flyover Location
The location and alignment of the flyover was planned in Phase-1 and the underpass including ramps and an
at-grade intersections of Phase-1 were designed based on the outline design of the flyover. Review of the
- 46 -
bridge plan conducted in Phase-1 concludes that the plan is appropriate from traffic safety and economic
point of view. For this reason and as changing the plan would incur impact on the road already constructed
in Phase-1, the alignment and location of the bridge determined in Phase-1 is applied.
2) Technical Specifications
1) Pre-requisites
The flyover abutments are positioned at locations that would have no impact to the ramps (left-turn). The
bridge is planned to span over the box culvert and the at-grade intersection of Phase-1. Locating substructures
within the at-grade intersection is also difficult as there is no suitable space for such provision.
3) Width of Carriageway
The Ghanaian Guide for Bridge Design requires provision of two-lane carriageway having a width of 8.5 m.
The width of the flyover applied is as shown in Figure 2.2-12. This is determined with reference to the
requirements and results of discussion with GHA.
Inner
Outer
- 47 -
4) Loads
[Dead Load]
Dead load is calculated using the unit weight given in the Specifications for Highway Bridges (JRA) shown
in Table 2.2-21.
[Live Load]
GHA has requested that the design live load be defined according to BS5400, which is the basis of Ghana for
Bridge Design. The BS5400 adopts the limit state design method, but the Specifications for Highway Bridges
(JRA) use the allowable stress method, so it is unable to apply the design live load of BS 5400 straight to the
allowable stress method. For this reason, the HA + 45HB vehicle load, the design live load of BS 5400 needs
to be examined and compared with the B live load of the Specifications for Highway Bridges (JRA). Among
them, the live load strength and conditions that have the most adverse effect will be employed.
HA Loading
HA loading consists of a uniformly distributed load (UDL) and a knife edge load (KEL) combined, including
a dynamic effect of vehicle loading. The UDL is distributed on the linear meter of notional lane which
determines the values of the load given in the loading curve illustrated in Figure 2.2-13. The KEL per notional
lane is taken as 120 kN. The UDL and KEL are taken to occupy one notional lane, uniformly distributed over
the full width of the lane.
- 48 -
Figure 2.2-13 Loading curve for UDL of HA loading
HB Loading
Figure 2.2-14 shows the plan and axle arrangement for one unit of nominal HB loading. One unit is taken as
equal to 10 kN per axle. The HB loading includes a dynamic effect.
To examine the live load effect, for 3-span continuous steel I-shaped girder bridge, as shown in Figure 2.2-15
with the length of 142 m (45 + 54 + 43 m), the values of bending moments at an intermediate support are
calculated and compared. The result is summarized in Table 2.2-22.
- 49 -
Figure 2.2-15 Typical Cross Section of Superstructure
B live load
HA+45HB
- 50 -
Table 2.2-22 Values of bending moment at an intermediate support (kNm)
From the table above, the bending moment derived by applying HA + 45HB is about 7.5% larger than that
by applying the B live load. From this result, for the safety level in yielding, the values of the B live load and
the impact coefficient incorporate the 7.5% increment of load effect, and then the design is performed in
accordance with the Specifications for Highway Bridges (JRA).
[Impact]
Application of live load will take into account the impact or the dynamic effect. Impact coefficient is
calculated in accordance with the Specifications for Highway Bridges (JRA). The impact due to the live load
is not considered in calculating the reaction forces which are used in the design of substructures.
[Wind Load]
Wind loads acting on piers and girders vary greatly depending on the location of the bridge, topography and
surface conditions, bridge structural characteristics, and cross-sectional shape. In Ghana's bridge design data
(2014), the average hourly wind speed within 160 km inland from the coast is V=21 m/s (100-year return
period). According to the Specifications for Highway Bridges (JRA), the basic wind speed, V=40 m/s, is
described. For the bridge design, the design wind speed, V=40 m/s, is adopted.
[Temperature Impact]
The design temperature in the vicinity of the bridge location varies from 8 degree Celsius to 51 degree Celsius
(± 21.5 degree Celsius according to Ghana's bridge design data (2014). On the steel structure: -10 degree
Celsius to 50 degree Celsius (± 30 degree Celsius). The one with the larger amount of temperature change
is applied to the calculation of the amount of the movement on the support and the expansion joint.
[Seismic Design]
The seismic impact is taken into account in accordance with the Specifications for Highway Bridges (JRA),
but the seismic ground motion varies depending on the regional nature. According to Ghana's bridge design
data (2014), it defines that the amount of seismic load is set as 8% of the dead load. In Ghana's Building Code,
a = 0.35 is adopted as the acceleration coefficient, so the design horizontal seismic coefficient Kh = 0.35 is
considered in the static seismic design.
Since the flyover (substructure) may be at the risk of vehicle collision, the flyover should be designed to be
sufficiently stable against the collision impact. To consider this impact, the design impact force is defined in
- 51 -
accordance with the Specifications for Highway Bridges (JRA).
The flyover to be constructed in the Phase-2 has a bridge length of 400 m in total (125 m length of 5-span
PC-I girder + 200 m length of 3-span steel box girder + 75 m of 3-span PC-I girder) considered in the Phase-
1 survey. Based on the bridge length of the Phase-1, the intersection shape and ramp road alignment are
planned and designed. Since the reduction of the bridge section greatly contributes to the reduction of the
project cost, the bridge length was re-examined in the Phase-2 study.
In the Phase-1 survey, the pier of the main bridge over the intersection was planned to be a three-column steel
frame pier. Due to the installation position of the middle steel column and the road vertical alignment, the
flyover was planned to be a three-span continuous steel box girder bridge with rigid-connecting of
superstructure and substructure. There is no restrictions on abutment position since the side span length 60 m
of the main bridge planned in the Phase-1 was determined in consideration of the stress balance of the main
girder.
Therefore, the Phase-2 study examined the possibility of shortening the center span length. As a result, when
the pier with more high-strength steel material is placed as close as possible to the box culvert of the Phase-
1, the number of column of the steel frame pier can be changed to two from three for the original plan. With
this change, the length of the center span and the bridge were reduced to 54 m and 142 m, respectively. In
addition, the PC-I girder section planned in the Phase-1 is changed to the mechanically stabilized earth wall
method. This is expected to lead to further reduction of the project cost. The bridge length and span
arrangement are as shown in Figure 2.2-17.
- 52 -
フェーズ1
Phase-1
R=1000
A=80
STA
A=8 0
.7
2
0
R=1
N=0
.99
4%
G-R
R=
A=65 A MP
90
STA
STA.6
R=553.65 A=65
5
A.
0
.3
ST
STA.5
C-RA
R=550 MP
STA.9
STA.7
0
12
R=
STA.6
85
R=
Harbour Akosombo
STA.8
R=
R=520
ST
85
A.
6
A=70
STA.6
STA.6
A=80
A-RAMP 80.0m 60.0m
60.0m
50000
11190 11190
445 10300 4000 10300 445
CL
80
5.7% 5.7%
420
2550
2000
2300
2150 6890 7410 6890 2150
Phase-2
R=1
0
R=
A=8
3%
85
J-STA.1
003.6
10
1.
R=
R=150
9.50
142000
R=2
210
0.8
54000
STA.6+1
33
25
43000 45000
% .7
ST
A= 54000 TA
A.
A-S 65
42950
70
44950 A=
1
.50
.2
TA
STA.7+61
J-S
J-STA.0
R=
F-S
J'
90
ST
R=550 R=6
B-
J
C-ST
5
D-ST
R=550 R=180
STA.9 R=6
STA.7
R= 0 R=165
A.5
A.7
70
R= R= ST
54. A.6
75 85 95
STA.6
+4
R= R= 0.0
0
0
12
STO
80
Akosombo
STA.8
BH-1 R= BH-3
R
Harbour
C-
=8
R=520
ST
RA
BH-5 5
A.
GE
R=210
0.937
6
A=65
R=85
%
A=65
R=550
LAN
R=550
R=225
R=550
A.6
A=70
R=55000
E
A-ST
.6
R=50
B-STA
L=3
I-STA.0
I-STA.2
A=80
0
R=80
.00
R=
I'
m
0.174
R
%
88.
I
R=60
=
R=80
R
83.
E-STA.1
65
STA.6
78.
60
STA.6 +10.0
0
55
+10.0
0
44000
455 1250 7300 5002000500 7800 750 455
500 3650 3650 3650 3650 500
▽46.002 ▽46.002
▽42.950
300
5500
2500 2500
▽34.916 (GROUND HEIGHT)
▽34.317 ▽34.317
7500
7500
▽26.817 ▽26.817
ƒÓ
5 000 ƒÓ
5 000
- 53 -
2) Comparison Study of Superstructure
Constraints in selecting the superstructure type are the vertical gradient, vertical and horizontal limits, and the
range where piers can be installed. From the above-mentioned bridge length, the allowable height of the
superstructure of this flyover (height from the road surface to the bottom of the girder) is about 3.0 m. It is
physically not possible to apply a concrete bridge as simply estimating from the ratio of span to the girder
height, for the given span the girder height will exceed the allowable height mentioned above. Therefore
application of steel bridge was considered. For the given span, the applicable girders are the plate girder type
and the box girder type. A comparative study between the 2 types, as shown in Table 2.2-23 were performed.
The results conclude that Option-1, the plate girder is superior to the box girder.
2000
It is inferior to Option-2 in terms of torsional Suitable for curved bridges as this has high
Structure rigidity, but is applicable as this type can be torsional rigidity
found in many bridges in Japan
The weight of the components is light Installation requires heavy crane as the girder is
Construction compared to Option-2 and can be installed with heavier than plate girders
a small crane.
Estimated girder weight:approx 750 ton Estimated girder weight:approx 1,000 ton
Cost
Superior to the second plan in terms of The box girder is hollow and the unit price per
Efficiency
transportation also weight is high in terms of transportation
Visual inspection from outside possible. Don’t The inside of the box girder gets hot and humid
need special equipment or apparatus area and needs to be inspected regularly. Special
Maintenance
equipment such as a blower is required for
inspection inside the box girder.
Evaluation Superior (Recommended) Inferior
Table 2.2-24 shows the comparison of deck slab types. Although the initial cost is expensive, a steel-concrete
composite slab is adopted as it is superior in terms of construction safety, maintenance efficiency and
durability (contributes to long-term economic efficiency).
- 54 -
Table 2.2-24 Comparison Study of Deck Slab
Option-1 Option-2
Reinforced Concrete Slab Steel Concrete Composite Slab
Requires scaffolding and support Scaffolding and support are not required
Construction
Efficiency Construction schedule of the deck is longer than Construction period of the deck is shorter than
Option-2 Option-1
Since detour road is right below, careful attention No impact to detour below.
Safety is required for the installation and operation of
support structures and scaffolds.
Compared to the second plan, it is less durable High durability, no need to replace floor slabs
Maintenance* and requires multiple slab replacements during during service period
the service period
*Return period for design of major bridges in Ghana Bridge Design Data 2014 is 100 years
- 55 -
4) Pier Type
For the reasons mentioned below, a rigid frame that supports the superstructure is applied for the substructure
(pier).
b) The pier is required to be located outside the ramp at the at-grade intersection
From the above requirements, the flyover is not applicable to a steel girder mounted on a general concrete
pier. Therefore, the type to be applied will be a gate type (gantry type) structure as shown Figure 2.2-18 in
supported by the out riggers that are extended in the direction perpendicular to the bridge axis to the edge of
the road.
If the outrigger is supported by a simple beam structure with hinges at both ends, the amount of vertical
deflection at the center of the beam is large, and it is difficult to ensure sufficient rigidity at an allowable
girder height. Therefore, a steel pier with a rigid frame structure that is rigidly connected at both ends and
integrated with the main girder is adopted. The cross-sectional area of the steel pier will be minimized in
accordance with the planned location and scale of the deep foundation pile to minimize the impact to the box
culvert and the ramps of the intersection constructed in Phase-1.
45500
The abutments of the flyover are about 10 m tall, which is generally higher than the normal abutments. In
such case, commonly used inverted T type abutment is expected to have a wall thickness of about 2 m to
withstand the large earth pressure that is exerted at the back side of the abutment. Therefore, a comparison
was made with a reinforced earth wall-combined abutment that can support the earth pressure on the back
and reduce the amount of concrete in the abutment. The examination results are shown in Table 2.2-25.
Considering economic efficiency and workability, the reinforced earth wall combined abutment was adopted.
- 56 -
Table 2.2-25 Comparison of Abutment Type
Option-1 Option-2
(Reversed T Abutment) (Earth Retention Wall Combined Abutment)
Schematic
Drawing Excavation
area Excavation
area
Standard type. Footing is provided by excavating The earth pressure is retained by the reinforced
upto load bearing layer. The wall thickness earth wall and a pier-type abutment is provided
increases with respect to the height of abutment to in front of wall. Since the wall retains the earth
Outline
resist earth pressure exerted on the back of the pressure on the back side contributing to reduction
abutment. of concrete volume of the abutment even though
the height of the abutment is high.
Earth volume to be excavated is big (approx. 2,800 Application of deep foundation pile minimizes
Construction
m3) and so is the frequency of soil transport excavation of soil volume (about 150 m3) thereby
Efficiency
reducing the frequency of soil transport
Footing construction requires large amount of soil Minimizes excavation area and the ramps
Impact to
volume to be excavated. Ramps constructed in constructed in Phase-1 is unlike to be affected.
Environment
Phase-1 might be affected.
Overall
Inferior Superior (Recommended)
Assessment
According to the results of the drilling survey at the bridge position, the load bearing layer was found at G.L.-
2 m to -5 m, which is the range where spread foundation application is possible. However, it is assumed that
the scale of the direct foundation will be about 10 m x10 m (assumed from the construction of the railway
bridge adjacent to the first phase construction), which is very likely to affect the approach slabs of the box
culvert constructed in Phase-1. Therefore, minimization of impact on infrastructures constructed during
Phase-1 is given due consideration along with construction and cost efficiency, and adverse impact to
environment. The comparison is provided in Table 2.2-26. Cast-in-situ pile method, which is commonly used
for foundations has been excluded from the comparison in view with the results of the geo-technical
investigation (drilling) which indicates the load bearing layer in a rather shallow depth. The result of the
comparison recommends use of Option-1, deep foundation pile.
- 57 -
Table 2.2-26 Comparison of Foundation Type
Option-1 Option-2
Deep Foundation Pile Spread Footing
Excavation Approach Excavation Approach
area slab area slab
Schematic
Illustration
Although construction is close to existing The maximum depth is about 5 m, and the opening
Impact to
structures (attention range 2), impact is minimal as at the surface is about 17 x 17 m. Very likely to
existing
excavation is possible without producing affect the box culvert constructed in Phase-1. Also,
structures
vibrations needs removal of approach slabs
Large diameter requires heavy machinery, but Requires excavation by heavy machines and
small ones can be excavated manually utmost consideration is required to avoid from
Construction
Excavated soil volume is small and transport cost possible impacts to existing structures
Efficiency
to the dumping site is also low Excavated soil volume is huge and transport cost
to the dumping site is high
The section that connects the existing road and the flyover is defined as an approach road. The design of approach
roads is carried out in accordance with the Road Design Guidelines of Ghana. Approach roads consists of two
different classes of roads. The northern approach road is a part of Akosombo Road, which is classified as a national
road. The southern approach road is a part of Harbor road and is an urban road. However, after improvement of
the intersection, based on the discussion with GHA, the jurisdiction for approach road in the south, which connects
with the urban road (harbor Road) and is originally belonged to the jurisdiction of DUR will be transferred to GHA.
Approach roads to be planned and designed under Phase-2 will include through traffics in the north-south direction.
The lanes that cater for turning purpose have been designed and are under construction being carried out under
Phase-1. Table 2.2-27 shows general and geometric conditions used for the design of both roads.
- 58 -
Table 2.2-27 Design Criteria (General and Geometric Condition)
National Urban
HIGHWAY / ROAD CLASSIFICATION
(Akosombo Approach) (Harbour Approach)
GENERAL
Flat Terrain (inside bracket for urban area) 100 (80) 80 (60)
Min. Design
Speed (km/hr) Rolling Terrain (inside bracket for urban area) 80 (60) 60 (40)
Mountenous (inside bracket for urban area) 60 (40) 50 (30)
Level of Service C D
CROSS-SECTION ELEMENTS
ROW Width (m) Urban 90 -
Rural 10 4
Min. Median (m)
Urban 2- 4 2- 4
Median Shoulder 0.3 - 0.5 0.3 - 0.5
Road Cross
Flat/Rolling 3.65-3.25
Section Width Vehicle Lane 3.65-3.25
Mountenous 3.5-3.25
Ramp width (m) -
Flat/Rolling 2.50 2.0 - 3.0
Right Shoulder (m)
Mountenous 3.00 -
VERTICAL ELEVATION CONTROLS
Carriageway 5.5 5.5
Minimum Vertical Clearance (m)
Sidewalk 2.5 2.5
TRAFFIC VOLUME
Design Traffic Volume (ADT) >10,000 <150
STRUCTURE LOADING
Structure Live Loading (Minimum)
PAVEMENT STRUCTURE
Surface Type
Pavement
Crossfall (%) 1.5 - 2.5 1.5 - 2.5
GEOMETRIC CONDITIONS
HORIZONTAL ALIGNMENT
100 40
Min. Horizontal Curvature
Desirable (5% SE) m 700 100
Minimum (9%SE) m 370 50
Maximum Superelevation %
Min. Curvature Length m 170 70
Min. Transition Curve Length m 56 22
Radius not requiring Transition Curve m 910 150
6% 694 174
Values of Superelevation with respect 5% 849 212
4% 1091 273
to Radius of Curvature
3% 1348 347
Reverse (2%) 2560 525
Min. Radius not requiring Superelevation m 5000 800
Superelevation Run-off 1/175 1/100
VERTICAL ALIGNMENT
Standard % 3 7
Gradient with % (m)
4% (700m) 8% (400m)
Max. Gradient
% (m)
5% (500m) 9% (300m)
limitations
% (m)
6% (400m) 10% (200m)
Sight Distance
Stopping m 160 40
Passing m 620 210
K-Value 64 4
Min. Radius Crest Curve
Radius m 6400 400
K-Value 28 5
Min. Radius Sag Curve
Radius m 3000 500
Min. Vertical Curve Length m 85 35
Note: Those not provided in GRDG is referred from AASHTO's Standard as shown by the italic figures
The improvement plan of the intersection fundamentally follows the prevailing standards and guidelines of
- 59 -
Ghana. Other international standards and guidelines as listed below are referred to items not covered in the
Ghanaian standards. The above policy regarding standards and guidelines has been agreed with GHA.
3) Pavement Design
• Guide for Design of Pavement Structure (American Association of State Highway and
Transportation Officials: AASHTO, 1993)
4) Drainage Design
• Road Design Guide (GHA, March 1991)
• Guidelines for Drainage Design (Japan Road Association, 2006)
Aflao Road
P
A-R
AM
- 60 -
(4) Vertical Alignment
Vertical alignment was also planned and agreed during the preparatory survey of Phase-1. The alignment satisfies
vertical clearance (5.5 m from road surface to the bottom of flyover girder) and other geometric requirements given
in Table 2.2-27. The maximum grade was limited to 4.0% taking smooth and safe flow of high volume of large
and heavy vehicles that use the Tema Port.
The cross section elements of the approach section include the median, strips (inner shoulders), carriageways, outer
shoulders, and railings. The width of each element is as shown in Table 2.2-28. The standard cross slope is 2.5%
and the steepest superelevation is 4.7%. The typical cross section of the approach section is shown in Figure 2.2-20.
Figure 2.2-20 Typical Cross Section (Diagram not included in the hardcopy document)
There are two methods in determining the reference points (axis) of a road for the design of vertical alignment and
cross section on divided highways. These methods are described in Table 2.2-29. As the objective roads are wide
(4-10 m median strip with dual or triple lane double carriageway) and has a superelevated section of about 800 m,
the effect on the abutting houses/residences or facilities as well as to the sectional area of the box culvert at the
underpass is less if the reference point is taken in the middle of the carriageways. Therefore, Type A is applied for
the alignments in this project.
- 61 -
Table 2.2-29 Reference Point (Axis)
RP
Image RP
Applicable to superelevated sections. Elevation difference Since RP is close to center of the road, it is simple to
Feature
between right and left edge of the road can be smaller design according to design standard.
Condition Having median and being large in width Particularly None
Applied ○ -
WB-20 classified by AAHTO and agreed with GHA during Phase-1 will apply for Phase-2 design vehicle. The
basic dimension of the vehicle is illustrated in Figure 2.2-21.
- 62 -
(8) Retaining Structures
The approach roads are elevated making it higher than the ramps/existing ground. The ramps were planned in
Phase-1 under the precondition that the elevated section of the approach road will be retained by structures. During
Phase-2, the optimum method for retaining structures was studied. Reinforced earth wall method was selected
from among the methods shown in Table 2.2-30. This method has minimal adverse impact on the ramps
(infrastructures) of which was already constructed and is superior to other methods in terms of cost-efficiency,
construction ability and aesthetics. In addition, this method is getting popular in Ghana recently.
Overview
Reinforced Concrete Wall is the most This method is one of MSE method This method is one of MSE method with
general retaining wall method, which with concrete wall face, that produces vegetation wall face, that produces the
resists as a cantilever against the the earth retaining effect by pulling earth retaining effect by pulling
Structural backside earth pressure. resistance due to the frictional force resistance due to the frictional force
between the steel strip plate (or anchor between the geogrid and the
bar) and the embankment material embankment material arranged in layers
arranged in layers in the embankment. in the embankment.
H≦8 m 3≦H≦18 m 3≦H≦18 m
Applicable Height
Evaluation: Not Applicable Evaluation: Applicable Evaluation: Applicable
Concrete Wall cannot be constructed This MSE method has been This MSE method can be applicable in
at the site because it exceeds the experienced in Ghana, and there are no terms of the height. But because the site
applicable height. particular problems with its adoption. is in urban area, it is not preferable in
Applicability
terms of maintenance work such as
mowing.
Evaluation: Not Applicable Evaluation: Applicable Evaluation: Fair
Total Evaluation Not Applicable Superior (Recommended) Inferior
Future traffic volume in Phase-1 was calculated based on the results of traffic survey and analyzed during the
preparatory survey. The results were applied in determining the pavement structure (composition) of the then target
roads. As shown in the analysis results described in Section 2.2.2.1(1), there is no significant difference between
the traffic volume forecasted for 2019 in Phase-1 and the traffic volume actually measured under this survey. On
the other hand, the CBR of the subgrade has not been subjected to significant change. Therefore, both approach
roads will have the same pavement structure as Phase-1. Table 2.2-31 shows the pavement composition of each
approach road. A description of the pavement plan in the Phase 1 report, “3-2-3-4 Pavement Plan,” is attached in
Appendix-7.
- 63 -
Table 2.2-31 Pavement Composition of Approach Roads
Harbour Road AkosomboRoad
Approach Road
(Start point - Flyover) (Flyover - end point)
Wearing/Surface Course 5 cm 5 cm
Binder Course 10 cm 8 cm
Base Course 20 cm 15 cm
Sub-base Course 20 cm 20 cm
Goose asphalt, generally used in the steel slab will be used for pavement on top of the flyover (bridge). The
pavement thickness commonly applied is 6-8 cm, but considering the traffic characteristics of the road of the
project area, where there are many large trucks, it is set to 8 cm. Modified asphalt with improved fluidity and
enhanced wearing durability by mixing polymer or runner with straight asphalt as in Phase-1 is planned to be
provided for on the wearing/surface course of the access road including the bridge.
In Phase-1, road lighting is planned to be installed in the east-west direction and north-south ramps. In this phase,
road lighting will be installed in the straight lane section in the north-south direction. The median strips will be
installed in the approach road section, and the handrails will be installed in outside of the bridge section. In addition,
safety facilities such as road signs, fall prevention fences, road markings etc. are planned. The design standard was
in accordance with the Japanese stadard "Road Lighting Facility Installation Standards and Explanations, Japan
Road Association, October 2007".
(1) Outline
The location and general features of Ashaiman Roundabout is presented in Figure 2.2-22. Ashaiman Intersection
is a 4-leg roundabout with an inscribed circle diameter of about 50 m and is located about 1.5 km north of Tema
Intersection. 3 out of 4 legs are single lane --only Ashaiman Road, the west leg is a dual carriageway-- and the
circulatory road has 2 lanes. The roundabout has been experiencing traffic congestion throughout the day time
even before the commencement of Phase-1 preparatory survey. The congestion is severe during peak hours.
The improvement of Ashaiman Roundabout is not included in the scope of this survey. However, improvement of
the roundabout is indispensable to eliminate the congestion that occasionally affects the flow at Tema Intersection.
A brief study on causes of the congestion is conducted and suggestion for remedial measures is forwarded.
- 64 -
Accra N To Akosombo Ashaiman
Aprox. 1.5km Roundabout
N
Tema RA
Ashaiman RA
To Aflao To Tema RA
Comprehensive improvement is ideal. However, the survey considers improvement in phases, temporal
improvement and then permanent improvement. First improvement will apply slip roads to provide exclusive lanes
for right-turning vehicles on all legs.The fact that slip roads contribute to a certain limit in alleviating traffic
congestion has been substantiated by the MPS project at the then Tema Roundabout. The next step is to convert to
signalized interchange or to grade separated intersection, similar to Tema Intersection.
As shown in Table 2.2-32, a three-stage development plan that will improve traffic capacity was considered as the
study case. Analysis based on HCM2010 (static) and continuous traffic micro simulation (dynamic) for the
configuration of each case was done. The year when the capacity of the improvement method reaches the limit
was taken as the output of the analysis.
- 65 -
Table 2.2-32 Study Cases
Case No. Study Cases (Improvement Method)
Case-0 Existing (No improvement)
At-grade improvement
Case-1 (4-lane upgrading of south-leg (Ashaiman Roundabout– Tema Intersection stretch),
provision of slip roads on all legs, and expansion of circulatory lanes of the roundabout
Case-2 Signalized at-grade intersection (provision of left-turn exclusive lanes)
Case-3 Grade separation of north-south direction (Prioritizing the East Corridor)
2) Outline of Study
[Case-1:At-grade Improvement]
i) Widening of Akosombo Road on the south side to 4-lane (4-lane is recommended to maintain
consistency with the improvement of Tema Intersection)
ii) Provision of slip roads (single lane) at all legs and connect lanes to roundabout to allow free flow to
vehicles turning to the right.
iii) Dualization of roundabout circulatory roads (currently the circulatory road of the roundabout seems
to have 10 m width but is not sufficient to cater smooth and safe flow to heavy vehicles)
iii)Dualization (3.65 m x 2) of
roundabout circulatory roads
- 66 -
[Case-2:Signalized at-grade Intersection]
* The roundabout will be converted to an at-grade intersection controlled by traffic signals. All traffics
going straight and turning left will meet at the intersection. Slip roads provided in Case-1 is used
continuously.
Signalized Intersection
ii) Left-Turing vehicles on north-south direction to be connected with the roundabout by off-ramps
- 67 -
i) north-south grade separation
Study results are compiled in Table 2.2-33. Case-0, the existing condition (do nothing scenario) shows that
the capacity of the roundabout already exceeded causing severe traffic congestion throughout the day.
Case-1 improvements will ease the current congestion. However, the roundabout will exceed its capacity
in 2022 and will be in similar condition like in the present.
Similarly, Case-2 improvements will improve the situation until 2025. In this case, all direction except for
the east leg will exceed the capacity and see significant traffic congestion.
Finally, Case-3 improvements will be a solution for further easing of the traffic congestion. And this will
show positive results until 2028.
Note that the simulation has been conducted in a worst scenario meaning although it reflects the current
improvements being applied at Tema Intersection, including improvement to be applied in Phase-2, it does
not reflect other potential developments/improvements in and around Ashaiman Roundabout. The results
may differ, possible in a positive manner, should improvement works pertaining to road network is carried
out in near future.
A 3-tier intersection would be the optimum solution and could be applied anytime but the scope of the
improvement will be big.
- 68 -
Table 2.2-33 Study Results
Case No. Limit Year Result of Traffic Simulation for the Limit Year
Case-1 2022
Case-2 2025
- 69 -
Case No. Limit Year Result of Traffic Simulation for the Limit Year
Case-3 2028
Outline Design Drawing is attached in Appendix-6 and its table of contents is Table 2.2-34.
- 70 -
2.2.4 Implementation Plan
The project will be implemented under the Grant Aid Scheme of the Government of Japan (GOJ) in
accordance with the Grant Agreement (G/A) and the Exchange of Notes (E/N) between the Republic of
Ghana and the GOJ.
The executing agency for the implementation of the project is Ghana Highway Authority (GHA) of the
Republic of Ghana.
The consulting services including detailed design, tender-related works and construction supervision
services will be provided by a Japanese consulting firm(s) in accordance with the consultancy contract
that shall be signed with the Republic of Ghana.
The construction will be executed by a Japanese construction firm(s) that shall be selected through pre-
qualification and bidding, in accordance with the construction work contract that shall be signed between
the said construction firm(s) and the Republic of Ghana.
The basic policies for the construction/procurement of this project are as follows:
➢ The construction will give high consideration to minimize adverse impact to the infrastructures
constructed in Phase-1.
➢ The equipment, materials and labor for construction will be, to the possible extent, procured locally.
Where local procurement is impractical, third country procurement or procurement from Japan will
be considered given the required quality and supply quantity are secured.
➢ Construction methods and the construction processes shall be consistent with the local climate,
topography, geology and natural conditions.
➢ Construction methods that are common and easy and will not require special or sophisticated
equipment or technology will be applied.
➢ The contractor’s site organization shall be planned to satisfy the established construction
specifications and construction management standards set for this project. Likewise, the
consultant’s organization shall be based on such specified project management standards.
➢ In order to reduce the influence of construction works on the environment of project site,
appropriate preservation methods of the environment, such as the selection of temporary garbage
- 71 -
dumping sites which were specified from the Republic of Ghana shall be adopted.
(1) Labors
Following points were identified from the field survey carried out with regards to local labors in Ghana.
⚫ There are less than 10 contractors with track records of flyover and road improvement.
⚫ Civil engineers, bridge engineers, bridge skilled labors, skilled workers, scaffold workers, welder,
form builder, and machine operators can be procured from the site and from Accra.
From above, workers for construction of superstructures who have high skill and experiences are planned to
be procured from Japan.
Daytime work is limited to 8 hours per day and 48 hours per week. Dayshift is between 6:00 am and 8:00
pm, and night shift is between 8:00 pm to 6:00 am
2) Overtime
Overtime and working on holidays require allowances equal to the basic salary
According to the law, payment of workers takes precedence over other debts. Workers' salaries are not
affected by bidding, bankruptcy or succession and must be paid immediately.
After one year (12 months) of continuous work, the workers have the right to receive a one-month (13th
month) additional salary. In addition, if the work period is between a month and a year, the workers have
the right to receive additional salary as stipulated in the employment contract for the corresponding period.
5) Dismissal
Employers are obliged to pay a worker a month's salary if they are dismissed after working continuously for
one year. Table 2.2-35 shows major engineer/labor procurement categories.
- 72 -
Table 2.2-35 Major Engineer/Local Procurement Categories
In charge of Bridge
Works
Bridge construction ✔ Japan
Being a grant aid of Japan, the contract is awarded to a Japanese firm. However, labors such as construction
supervisor, skilled workers, and skilled drivers, if required, for the construction of this project can be procured
from the local contractors. Execution of works other than steel bridge installation can be carried out through
sub-contracting to these firms
Major construction materials other than those pertaining to the steel bridge can be procured locally.
Local contractors in Accra can procure and provide most of the construction machines required for the
construction. Also, common machines with high versatility such as backhoes and bulldozers are easy to
procure as these are available for lease. Cranes up to 300 ton is also procurable locally.
Serving as a nodal point between national roads, Tema Intersection is a strategically very important
intersection. The intersection receives more than 32,000 vehicles per day. A biggest issue during construction
is to secure safe and smooth detours for the existing traffics. Therefore, construction methods that does not
hinder existing traffic operations is inevitable. To secure sufficient construction space of the intersection, an
elliptical-shaped roundabout with semi-major axis in the north-south direction will be provided. Vehicles
using the route that need to turn are only those going to the left direction. Therefore, this is deemed to have
- 73 -
minimal impact on other traffics thereby minimizing congestion.
Basic policies with regard to detour during construction are set as below;
South Detour
North Detour
Aflao
The responsibilities to be borne by Japan and the Republic of Ghana are summarized in Table 2.2-36.
- 74 -
2.2.4.4 Consultant Supervision/Procurement
Basically, the Japanese Consultant will enter into an agreement with the Republic of Ghana to request their
support for the bidding activities and the construction supervision.
The major works to be carried out by the detailed design consultant are as follows:
Undertake consultations with concerned authorities of Ghana and carry out field surveys,
Detailed design and drawings preparation
Project cost estimate
The duration to carry out the detailed design work is about 2.5 months.
The major tasks to be undertaken between the time of inviting contractors to bid and the time for signing of
contract for construction includes:
The Consultant will supervise the Contractor’s planning and implementation of the construction contract. The
major tasks under this stage include:
- 75 -
2.2.4.5 Quality Control Plan
The tasks to be carried out for quality control during the construction period are as follows:
Bridge Erection Works
Concrete Works
Reinforcing Bars and Formworks
Earthwork
Pavement Works
Based on the above, the quality control of main items for Steel works and concrete works are presented in
Table 2.2-37 and Table 2.2-38 and for earthwork and pavement as provided in Table 2.2-39.
JIS K 5551, JIS K 5552, Confirmation of specification of steel and collate with
Paint JIS K 5553, JIS K 5659 the product before delivery (shipping)
Coating/ Film thickness Confirmation of management record and sampling
Inspection inspection
Finishing Confirmation of color, appearance
Bearing Confirmation of quantity before shipping, confirmation
Product, installation, of installation after completion, After casting of
completion concrete, checking condition/finishing of bolts and
filling of non-shrink mortar
Expansion joint Acceptance inspection JIS B2352 or equivalent Similar to bearing
- 76 -
Table 2.2-38 Quality Management Plan of Concrete Works
Item Test Items Test Method Test Frequency
Cement Cement Property/Physical Once before trial mix and once every 500 m3 batch; or
AASHTO M85
Test once during production of cement (Mill sheet)
AASHTO M6 Once before trial mix and once every 500 m3 batch; and
Property/Physical Test all changes of quarry source/location (check supplier
data)
3
AASHTO M80 Once before trial mix and once every 500 m batch of
Property/Physical Test concrete; and every change of source/quarry location
Aggregate (check supplier data)
Sieve Analysis AASHTO T27 Once a month
Alkali-silica Reactive ASTM C1260 Once before trial mix and every change of source/quarry
Test(Mortar Bar Method) location (check supplier data)
ASTM C295 Once before trial mix and every change of source/quarry
Mineral Composition Test
location (check supplier data)
Water Water Quality Test AASHTO T26 Once before trial mix and when necessary
Admixture Quality Test ASTM C494 Once before trial mix and when necessary (Mill Sheet)
Concrete Slump Test AASHTO T119 Once every 75 m3 or per batch
Air Content Test AASHTO T121 Once every 75 m3 or per batch
AASHTO T22 6 Samples per batch or 6 samples for every 75 m3 of
Compressive Strength Test concrete (3 samples each for 7-day strength and 28-day
strength)
Temperature ASTM C1064 Once every 75 m3 or per batch
Table 2.2-39 Quality Management Plan for Earthwork and Pavement Work
Item Test Items Test Method Test Frequency
Embankment Density Test
AASHTO T191 Every 500 m2
(Compaction)
Material Test Once before placing and once every 1,500 m3 or change
AASHTO T27
(Sieve Analysis) in source/quarry location.
Material Test Once before placing and once every 1,500 m3 or change
AASHTO T193
Base course (CBR Test) in source/quarry location.
Dry Density Test Once before placing and twice every 1,500 m3 or change
AASHTO T180
(Compaction) in source/quarry location.
Field Density Test
AASHTO T191 Every 500 m2
(Compaction)
Material Test AASHTO
(Sieve Analysis) M43,M80 Once before placing and once every 1,500 m3 or change
Asphalt paving Material testing (density and in source/quarry location.
AASHTO T84
percentage of absorption).
Density-in-situ examination. AASHTO T209 Every 200m
Temperature survey Every track
Modified asphalt Marshall stability test ASTM D 1559-89 Design stage:5 samples per mix, 3 pieces = 15 times
paving Trial mix stage::3 samples per mix, 3 pieces= 9 times
Paving stage: Once before placing
Dynamic Stability Test Measurement of At Trial Mix: Once per 1 mix
plastic deformation At Construction : Once per paving asphalt of 1,000 ton
by Wheel
Tracking Machine
Other test JIS as may be necessary
- 77 -
2.2.4.6 Procurement Plan
The major construction materials and equipment to be procured, based on field research for procurement, are
mentioned below.
Since steel materials used for bridge members are special steel materials using Japanese technology, it is
difficult to procure them in Ghana. Therefore, the steel materials will be procured from Japan.
Ready-mixed Concrete for the retaining wall and substructure of the bridge shall be procured from the local
concrete plants located around the project site. A photo of concrete plant near the project site is Photo 2.2-1.
There are several asphalt plants within the distance that can be procured.
Base and subbase materials shall be procured from quarrying plant located at Shai Hill on Akosombo road.
Photo 2.2-2 shows the plant in production, and Figure 2.2-28 shows the location of borrow pit and aggregate
plant.
Photo 2.2-1 Concrete Plant in Production Photo 2.2-2 Quarry Plant in Production
- 78 -
Figure 2.2-28 Location of Borrow Pit and Aggregate Plant
5) Procurement Area of Major Construction Materials
Procurement area of major construction materials are summarized into Table 2.2-40.
- 79 -
Items Procurement Area
Procurement Procurement Routes
Item Name Description Local Japan Third Reason Local
Country
Steel for temporary
H-steel ✔ N/A in Ghana. Marine transport from JP
works
Support Supported frame ✔ Accra
Rubber bearing ✔ Marine transport from JP
Ensure quality
Sealing and assurance and
✔ Marine transport from JP
Bonding on-schedule
Sealing strip delivery
✔ Marine transport from JP
(water stoppage)
Difficulty in local
Traffic Signal ✔ Marine transport from JP
procurement
Steel materials related steel bridge is special materials using Japanese technology, hence the materials
will be procured from Japan.
The rubber bearing is an apparatus that transmits the load from the approach slab to the abutment. Igus
is a device that connects the abutment and the approach slab, and serves as a buffer against shaking and
dislocation of approach slabs. Both the bearing and the Igus are important materials for prolonging
durability. In Ghana, these are imported from foreign countries, but it is judged that procurement from
Japan is appropriate for ensuring quality and timely and soundly delivery.
A sealing strip or water stoppage (waterproof sheet) will be installed because water seepage and leakage
from the bottom plate of the L-type retaining wall and the joints on the side walls are assumed. The
general items in Ghana can be procured, but there are concerns about quality and delivery time. In Japan,
stock is sufficient and reliable procurement including delivery deadlines are ensured.
Cushion Drum
Photo 2.2-3 shows major construction equipment which can be procured from local contractors and leasing
company.
- 80 -
Concrete pump vehicle Concrete mixer vehicle
- 81 -
Construction equipment to be procured is summarized in Table 2.2-41.
Table 2.2-42 presents the implementation schedule of detail design and construction period.
- 82 -
Table 2.2-42 Implementation Schedule of Phase-2 of the Project
- 83 -
2.3 Security Plan
The safety plan is prepared in accordance with the ODA Construction Safety Management Guidance
(September 2014). The detailed design and supervision consultant together with GHA will check the safety
plan prepared by the contractor and provide comments and instructions for any improvement required. The
safety plan will consist of, but not limited to;
1. Safety policies
4. Monitoring
- 84 -
2.4 Obligations of Recipient Country
The undertakings required from the GOG for the smooth execution of this project are as follows:
• To provide documents, data and information necessary for the execution of this project;
• To acquire land for construction yard;
• To secure land for construction yard, stock yard, disposal area for construction debris, site office yard, and
detour routes;
• To secure borrow pits, spoil-banks, and industrial waste disposal areas;
• To obtain all necessary permits, to coordinate and share necessary information with concerned
organizations regarding the method of road occupancy of the Motorway, procedure for allowing public
vehicles, traffic restrictions, and day-time, night time works;
• To get the public informed and take necessary steps before hand regarding blockage of road for public
vehicles during relocation of overhead facilities such as traffic signs;
• To coordinate with concerned organizations and agencies in charge of underground utilities pertaining to
its protection, reinforcement / repair and to pre inform all road users and local inhabitants in case
disruption of water and electricity are anticipated;
• To coordinate with concerned organizations and agencies in charge of street lights and electronic traffic
signs regarding its protection and/or its relocation and to take necessary steps to inform road users
beforehand in case disruption of electricity is anticipated;
• To obtain necessary permits that would allow the personnels engaged in the construction work such as the
supervision engineer, construction workers etc. to access ROW;
• To obtain necessary permits to allow the construction vehicles/ equipment enter and exit the ROW;
• To bear the cost of bank charges such as the Advising Commission and Payment Commission to the
Japanese bank where an account related to the project is opened;
• To bear the value-added-tax related to the project;
• To bear all expenses required for 15% of VAT (Value Added Tax);
• To bear all expenses required for 2.5% of NHI (National Health Insurance);
• To assist in the process for exemption of materials imported for the construction work from taxation and
Customs clearance in order to ensure smooth inland transportation;
• To assist in the process for exemption of Japanese nationals engaged in the construction work from
Customs duties and other fiscal levies on products and services necessary for the execution of the project;
• To assist in the process for exemption of Japanese nationals from all legislation measures necessary for
entering and staying in the Republic of Ghana;
• To ensure proper use and maintenance of the road after its construction;
• To cooperate in solving potential troubles with the local people or any third party in connection with the
execution of the project;
• To bear all expenses required for the execution of the project, other than those borne by the Grant-Aid of
Japan.
- 85 -
2.5 Project Operation Plan
Roads in Ghana are administered by the Ministry of Roads and Transport (MRT) through three agencies
namely Ghana Highway Authority (GHA), Department of Feeder Roads (DFR) and the Department of Urban
Roads (DUR).
- 86 -
Table 2.5-1 Regionals Heads of Maintenance Department
Upper East Region
Upper West Region
Northern Sector Northern Region
Brong Ahofo Region
Ashanti Region
Eastern Region
Central Region
Southern Sector Western Region
Great Accra Region
Volta Region
- 87 -
Table 2.5-2 GHA Road Areas
Region No. of Areas Covered Areas
Ashanti Region 3 Kumasi, Mampong, Bekwai
Eastern Region 4 Koforidua, Oda, Nsawam, Nkawkaw
Volta Region 3 Ho, Hohoe, Keta
Central Region 3 Cape Coast, Dunkwa, Winneba
Western Region 3 Takoradi, Tarkwa, Wiawso
Greater Accra Region 1 Accra
Brong-Ahafo Region 4 Sunyani, Goaso, Kintampo, Atebubu
Northern Region 4 Tamale, Yendi, Gambaga, Saula
Upper East Region 1 Bolgatanga
Upper West Region 2 Wa, Tumu
Total No. of Road Areas 28
Each Region has a Special Team made up of personnel with specialization in materials, topographic surveying,
traffic and quantity surveying. Greater Accra Region is responsible for the road maintenance for the project
Table 2.5-3 shows road sector personnel in GHA by Staff Category as of 2015.
Road maintenance work conducted by GHA is shown below. Most of the works are done by subcontracting.
Pavement repair
Road structure repair
Cleaning on pavement surface and drainage
- 88 -
Planting
Traffic signal and street lighting
Bridge inspection and repair
To realize full benefits of the project and its facilities, and to sustain its operation and keep it in good driving
condition, it is important to improve its durability. In addition, the objective road is as the full access controlled
motorway hence it is of great significance to secure the highway characteristics which matter most to the
driver which includes speed of travel, safety, comfort, and convenience, and also implementing facility
maintenance related to road functional management, traffic management and safety management. The
following needs should be noted:
• Inspect the facility regularly to abreast with its condition at all times
• Regular cleaning of road and incidental road facilities – especially drainage system
• Implementing regular facility inspection, cleaning and maintenance related to road functional
management, traffic management and safety management
• Secure budget necessary for maintenance
With that in mind, it is important to allocate budget for operation and maintenance.
Gender equality is an idea to eliminate gender-based discrimination. In the employment environment, it will
be promoting equal opportunities, equal working conditions and soundness of working environment through
consideration for women who are vulnerable to social disadvantages. This section focuses on the promotion
of women's active participation at construction sites.
Laboure Act, 2003 in Ghana shows the regulation for pregnant woman in section 55-57 of Part VI
“Employment of Woman”.
World Bank has published the report of “WOMEN, BUSINESS AND THE LAW 2019: A DECADE OF
REFORM” in 2019, it was comparing the equal opportunities, equal working conditions for woman on each
country. In Table 2.5-4 show a part of the comparison results. Ghana is positioned in middle class in the world,
and high class in African countries.
- 89 -
Table 2.5-4 Woman, Business and the Law index scores (a part of result)
Rank Economy WBL2019 Score Rank Economy WBL2019 Score
1 Belgium 100 65 America 83.75
1 Denmark 100 83 Japan 79.38
1 France 100 100 China 76.25
1 Latvia 100 103 Cambodia 75
1 Luxembourg 100 103 Ghana 75
1 Sweden 100 103 Honduras 75
37 Taiwan 91.25 103 Thailand 75
2.5.4.3 Japanese Case Study regarding Equal Opportunities, Equal Working Conditions for Woman
In Japan, “Act on Promotion of Women's Participation and Advancement in the Workplace” was established
in August 2015, efforts by various actors have been carried out in order to promote women's participation in
the construction industry and construction sites.
MLIT have shown four (4) promotion packages regarding “construction industry active of woman” below.
JICA has in its proposal evaluation system started giving account to the efforts of firms that has been
aggressive in employment of females and participation of females in JICA projects.
- 90 -
2.5.5 The Policy on Gender Consideration in Phase-2
The project is implemented under the grant aid scheme of Japan. General procedure of selection of contractors
covers pre-qualification, confirmation of technical and financial bid. Pre-qualification is not used to judge
superiority, but to assess whether the companies are qualified or not. On the other hand, bidding is just
evaluation of the bidding price, and is not assessment of the qualification of a company. Considering these
circumstances, consideration for gender is proposed as shown in Table 2.5-6.
As the results of above consideration, three policies regarding gender consideration policy are proposed.
Gender consideration policy: 1) Obligating to setting the female’s toilet and dressing room
2) Requiring to 5% women’s ratio of engineer in tender document
3) Educational duties for staff regarding gender considerations in tender
document
It is assumed that many subcontractors will be engaged in the construction during Phase 2. Subcontractors
include suppliers of equipment and companies that undertake the subcontract for delivery of materials and
equipment. The degree of involvement for each job is also different. For this reason, it is not reasonable to
give the sub-contractor a uniform ratio of female participation.
In Phase-1, number of females engaged in construction work is virtually null (zero) although there were few
- 91 -
women undertaking field works under the sub-contractors. The construction companies say it has not set
employment conditions that are favorable to males and has rather been open for female participation also, but
application from women seem to be negligible.
Sub-contractors are managed by contracts with bidders (contractors). Interventions that affect the selection
of sub-contractors are far from the actual construction industry in Ghana and prevent appropriate competition.
Judgment should be avoided as it may interfere fair and square competitive grounds.
For this reason, with regard to sub-contractor or on-site female work, a policy limiting to promotion of
voluntary based understanding and realizing the actual situation is set.
The consultant who supervises the Project is involved in the detailed design (DD) and construction
supervision (SV) of the project.
Many members of the preparatory survey will continue to be involved in the detail design. Currently, 11
members of the Phase 2 Preparatory Survey are dominated by male members, and only local employment
secretaries are women. Many members of the preparatory survey stage are assigned to the detail design stage.
There is only one female working during the preparatory survey stage but as a project coordinator.
However, during the detailed design, as most of the work is done in Japan, a policy is set that asks for active
involvement of females. It is thus proposed that the target for involvement of women during the detailed
design is set to 10% of the total man-month.
Construction supervision is normally carried out by a few persons. The resident engineer of Phase-1 is a male
engineer and it is very likely that the same person will work as the resident engineer for Phase-2. However,
0.5 man-month involvement of a female engineer for spot supervision should be set as a striving target.
Table 2.5-7 is the list of organizations related to the project including personnel that were met for meetings or
hearings with regards to Phase-2 survey. Females in the list account to more than 10% , which is relatively
higher compared to the ratio of females employed by the consultants, the contractors and the sub-contractors.
- 92 -
# Organization Designation Name
7 Ag. Director of Bridges Mr. Yaqub Koray
8 Strategic Planning, M&E Manager Mr. Shelter Y. Lotsu
9 Project Coordinator Mrs. Mercy Akyaa Payne
10 EMU Manager Mrs. Rita Ohene Sarfoh
11 Senior Environmental Officer Mrs. Hilda Annan
12 Highway Design engineer Mr. Bernard Owusu
13 Engineer Mr. Divine Kehodu
In Ghana, the person in charge of the relevant position plays an active role regardless of gender in meeting
with the parties concerned or solving problems when proceeding with the project. The degree of involvement
in actual projects is also unevenly distributed by position. In light of these circumstances, instead of setting a
threshold of ratio with regards to female involvement, it is rather suggested that measures to encourage active
participation and put forward frank remarks are recommended.
More specifically, 1) provide opportunities for women staffs to participate in the meetings 2) encourage such
participants for putting forward opinions,etc. In case of the Client side, these two points are as targets to
promote female involvement and promotion of female status.
Percentage of women’s staff in JICA is around 30%, and working staff in overseas is around 25%. In light of
these circumstances, JICA aims to involve more than 30% of women staffs in this project.
Basically, the monitoring results will be reported in each half year by consultants as shown in Table 2.5-8.
- 93 -
2.6 Project Cost Estimate
The total estimated cost for implementation of this project amounts to XXXXXXX Japanese Yen. This
amount is provisional and is the amount of the Grant. This amount is subject to examination further by the
Government of Japan for approval of the Grant.
The estimated project cost is the total of contributions to be made by both governments of Japan and Ghana
and consists of items explained in next sections. These costs have been calculated based on the cost estimate
conditions mentioned in Section 2.6.1.3.
The approximate amount estimated for contribution from Japan is as shown in Table 2.6-1.
The approximate amount estimated for contribution from Japan is Table 2.6-2 Ghana Cedis.
- 94 -
2.6.2 Operation and Maintenance Cost
Table 2.6-3 represents operation and maintenance cost for the major works. Since operation and maintenance
works are conducted by subcontracting, there are no technical problems on maintenance work.
- 95 -
3. Project Evaluation
3.1 Preconditions to implement the project
The Project preconditions related to the required undertaking from the Republic of Ghana are as follows:
i) Banking Arrangement (B/A) with a Bank in Japan shall be concluded within one (1) month after
the signing date of Grant Agreement (G/A).
ii) The payments will be made when payment requests are presented by the Bank under an
Authorization to Pay (A/P). This A/P shall be issued to the Bank that concluded B/A within one
(1) month after Consulting Service Agreement is made.
iii) Utility relocation issues are very unlike in Phase-2 as the construction area is strictly in the middle
of the Phase-1 premises. Should such utilities nevertheless be identified before the date of formal
invitation to Pre-Qualification, such public utilities, like power poles, electric lines/cables, and
communication network lines/pipes that will affect the Project works shall be all relocated to the
locations where no hindrance and inconvenience shall occur.
iv) Any necessary actions for tax exemption shall be taken keeping to the regulations of E/N and G/A.
v) Quick and smooth customs declaration and import tax formalities shall be completed when the
imported materials or goods arrive from Japan and any other third countries.
vi) Should renewal of environment permit is permissible, GHA shall ensure renewal procedures are
taken in a timely manner. Throughout the construction period, monitoring Report shall be prepared
and submitted to JICA. This Report shall describe monitoring data about such potential natural
environmental items as air quality, water pollution, etc. which are more likely to give impacts on
the works during construction phase and even after it is completed.
vii) During construction period, eminent assistance shall be given to traffic handling and management
plus safety control management.
viii) The power pipes/lines and water supply pipes/lines necessary for the construction work at site shall
be routed and installed.
ix) As a means of dispute resolution while the works proceed, discussion and assistance in good earnest
shall be made to reach agreement on disputes with people in the vicinity or any other third party
around.
To derive benefit from the entire Project and to make it sustainable, the necessary input by recipient country
is shown as follows.
To secure the service life(durability) of pavement, approach road, structure, and other related
appurtenant facilities, periodic maintenance inspection or patrol shall be firmly carried out under
annual approximate maintenance cost of Ghana Cedis GH₵ 173,700 as shown in Table 2.6-3.
- 96 -
Necessary arrangements shall be done to secure the required budget every year. It is necessary as well
to get it repaired appropriately and instantly soon after the damage is discovered. Routine maintenance
operations such as cleaning, removal of sediment, debris and obstacles on the road pavement surface
or at the drainage facilities shall be done.
This action will bring about further and bigger improvement of road services and more safer transport
measures for the road users.
Bearing in mind that regular maintenance, inspection and safety patrol to check the road lights and
traffic signals are an absolute must. In terms of sustainable safety performance, daily maintenance
inspection shall be performed surely and steadily. It is highly suggested to take consideration into
building up the traffic management system to deal with traffic control of left-turn vehicles on the road
by way of directing traffic flow by the policeman in case of sudden black-out.
The improvement will be effective if the pedestrians are kept-off from haphazardly crossing the ramps,
main carriageways. GOG should raise awareness of the public and take measures to encourage use of
footbridges. This action shall require full collaboration with the Police authority.
In Ghana, overloading is controlled on the main national road. From the aspect of ensuring the
durability of the bridge and road pavement, stringent regulation of overloaded vehicles is inevitable.
The bus terminal that was confirmed in the northeast of the intersection at the time of the Phase-1
survey was moved to the southeast of the intersection. But this location is temporary. Since there are
many users including long-distance buses, it is necessary to install a new bus terminal in cooperation
with related organizations in consideration of the convenience of residents in the vicinity.
Eastern and Western Highways passing through Tema Motorway roundabout is regarded to be a part
of Accra-Tema Motorway. The Government of Ghana is planning to expand both directions (inbound
and outbound) on Accra-Tema Motorway to 6-lanes (3 lanes each side) most probably under PPP
Scheme. Feasibility Study on its development is going on. This Motorway is taking up the position
of a component of total development plan of ECOWAS, namely, Abidjan-Lagos Highway
Development (Trans-Coastal Highway, ECOWAS Highway).
- 97 -
In the top-level governmental conference among the leaders from each concerned country, the idea that
design of inbound and outbound 3-lane carriageways all through the distance in Abidjan-Lagos
Highway is accepted.
In view of the above circumstances, the adopted structural design requirement for Eastern and Western
Highways are to cope with the works for this 3-lane carriageway expansion. Earliest widening to 3-
lanes both for inbound lane and for outbound lane on the Eastern and Western Highways is highly
expected such that it would contribute in enhancing the project outcome.
Southern and Northern Highways are linked to Ashaiman Roundabout with 52-meter diameter, located
in the distance of approximately 1.5 km north of Tema Motorway Roundabout.
Traffic congestion at Tema Motorway Roundabout comes partly from the current severe congestion at
Ashaiman Roundabout. Early commencement of the Project is of importance since the Government of
Ghana well understand this Ashaiman Roundabout improvement will turn out to be a good solution to
inconvenient traffic flow at Tema Motorway Roundabout. The primary objective of improving heavy
congestion at Ashaiman Roundabout is to moderate and ease traffic congestion at Tema Motorway
Roundabout.
3.4 Evaluation
3.4.1 Relevance
・ 353,000 residents of Tema Metropolitan (estimated in 2000 by Ghana Statistical Service) are direct
beneficiaries of the Project. On the other hand, an approximate 86.6 million people is assumed (2015
survey) as users of Tema Motorway Roundabout.
・ This Project will contribute to mitigating traffic congestion and securing smooth and safe mobility of
pedestrians and freight as well. It is highly expected that this will eventually lead to a comprehensive
transport network development for logistics throughout the nation and entire West African Regions.
・ Expansion and development of major national integrated arterials covering international transit road as
a part of it will be brought about. This Project will be immediately and strongly needed to secure stability
of people’s lives, development of their livelihood, and securing the BHN (Basic Human Needs).
・ Excessively advanced technique is not necessary for this Project. The Government of Republic of Ghana
can manage to run, operate and maintain the improved road, related structures, and facilities by using
own fund, own local manpower and locally available technical skills.
・ National integrated trunk road network system including international transit road as a part will be
equally consistent with the policy and target described in the Government National Development Master
Plan. This Project can help in achieving enhancement of national trunk road network improvement.
・ There is little negative impact upon environmental and social conditions.
- 98 -
・ Performing the Project will justify the incentive as well as necessity to utilize Japanese most advanced
and cutting-edge construction technology including knowledge with regards to schedule management,
safety control, and quality control of a construction project. The project is expected to be implemented
under Japan’s Grant Aid Scheme without having to face any outstanding issues.
3.4.2 Effectiveness
The expected quantitative effect by the Project is shown in Table 3.4-1. The values of base year (2015) was
calculated based on the result of Phase-1 survey. The value of the target year, 2026 which is three year after
the completion of the Project, was recalculated in Phase-2 survey.
3.4.3 Impacts to Green House Gas (GHG) and Future Traffic Volume
The current traffic volume was calculated using the peak hour traffic count survey conducted in 2019 (Phase-
2) and converting it to volume per day by taking the traffic count volume surveyed in 2015 and the growth
rates used in the then analysis. The analysis was conducted to examine the traffic capacity during peak hours.
For this reason, in order to study the impact on the greenhouse gases, the daily traffic volume is necessary,
which requires taking traffic volumes and congestion condition for both the peak hour and off-peak hours
into consideration. Baseline is set on the traffic volume of 2015, which will be compared with that of 2035.
- 99 -
(2) Reduction of GHG
The “Grounds for Calculation of Vehicle Emission factors applied for Evaluation of Environmental Impact
Assessment of Road Projects, 2012”, which is the Technical Note of National Institute for Land and
Infrastructures Management, is referred for prediction of the GHG emission volume. The unit of vehicle
emission factor is given for passenger car as per car per 1 km travel, while for other vehicle types it is given
by per ton per 1 km travel. For Tema intersection, CO2 emissions by vehicle type were estimated with an
average distance of 1 km. Table 3.4-2 gives the emission factor of CO2 for a different types of vehicles. The
Estimation on Emission amount of greenhouse gas is calculated the 1 km distance around the Tema junction.
Table 3.4-2 Emission factor of carbon dioxide (CO2) on representative car type
Gasoline car Deasel car
Average Freight vehicle Freight vehicle
Passenger car Passenger car
velocity Lightweight Mediumweight Heavyweight Lightweight Mediumweight Heavyweight
(g-CO2/km) (g-CO2/km・t) (g-CO2/km・t) (g-CO2/km・t) (g-CO2/km) (g-CO2/km・t) (g-CO2/km・t) (g-CO2/km・t)
5 318.1 295.9 288.7 288.7 461.0 275.5 252.9 128.9
10 235.3 228.9 223.4 223.4 357.1 213.4 195.9 107.6
15 165.5 171.8 167.7 167.0 269.7 161.2 147.9 86.3
20 145.4 153.0 149.3 149.3 242.1 144.7 132.8 79.7
20 159.7 153.0 149.3 149.3 242.1 144.7 132.8 79.7
25 140.7 138.4 136.4 136.4 216.2 128.8 119.8 72.6
30 127.6 127.7 126.9 126.9 195.8 117.2 110.1 66.6
35 118.1 119.6 119.7 119.7 179.2 108.2 102.7 61.7
40 111.1 113.3 114.2 114.2 165.5 101.0 97.0 57.7
45 106.0 108.5 110.0 110.0 154.4 95.4 92.7 54.5
50 102.4 105.0 106.9 106.9 145.5 91.0 89.7 52.1
55 100.0 102.5 104.7 104.7 138.6 87.6 87.8 50.4
60 98.6 100.9 103.5 103.5 133.7 85.1 86.9 49.6
65 98.2 100.3 103.2 103.2 130.6 83.5 87.0 49.4
70 98.6 100.6 103.6 103.6 129.3 82.8 88.1 50.1
75 99.9 101.7 104.8 104.8 129.7 82.8 90.1 51.4
80 101.9 103.5 106.7 106.7 131.9 83.5 93.0 53.5
85 104.7 106.2 109.4 109.4 135.7 8.5 96.8 56.3
90 108.2 109.6 112.8 112.8 141.2 87.2 101.5 59.9
95 112.3 113.7 116.9 116.9 148.3 90.0 107.0 64.2
100 117.1 118.6 121.7 121.7 157.1 93.5 113.4 69.2
105 122.6 124.2 127.2 127.2 167.5 97.8 120.7 74.9
110 128.7 130.5 133.4 133.4 179.6 102.6 128.8 81.3
𝑄𝑖 = ∑𝑛𝑖=1(𝑊𝑖 × 𝐸𝑖 )
Here,
Qi: Quantity of CO2 per 1 km (g-CO2/km)
Ei: Emission unit of CO2 on car type (g-CO2/km, g-CO2/km・t)
Wi: Weight of car (t)
- 100 -
The greenhouse gas emission factor on Motor Cycle is referred to “Greenhouse gas reporting: conversion
factors 2019”, in UK, but the emission factor is not set on each speed. Therefore, emission factor on Motor
Cycle apply to 60% value on factor of small car (Light weight car) based on the ratio of emission factor of
Small car and Motor Cycle.
The vehicle classification in the traffic survey was consistent with the vehicle classification in the GHA
pavement design manual. This study was conducted based on the classification of eight types of vehicles
under the idea that the purpose is to understand traffic conditions. On the other hand, in setting the carbon
dioxide emission coefficient, the vehicle weight given in the Technical Note of National Institute for Land
and Infrastructure was referred and the carbon dioxide emission coefficient setting model was set as shown
in Table 3.4-4.
Regarding the traffic condition to predict the GHG emission volume under this project is set in a manner that
the traffic volume change includes both the changes of Phase-1 and Phase-2. The calculation conditions are
shown in Table 3.4-5.
- 101 -
Table 3.4-5 Prediction condition for emission volume of CO2
Without Without (2025/2035) Project (2025/2035)
Intersection shape Roundabout Roundabout Three-layer intersection
Peak time Hour 3 hour 3 hour 3 hour
Traffic each Car type each Car type each Car type, each direction
volume lane
Velocity 10 km/h 5 km/h each direction lane
Non-peak time Hour 21 hour 21 hour 21 hour
Traffic each Car type each Car type each Car type, each direction
volume lane
Velocity 20 km/h 10 km/h each direction lane
Note: JICA team
Emission volume of CO2 are calculated based on the emission factor using car type, car weight, average
velocity at Tema intersection.
Traffic volume will increase 3 times from 29,000 per day in 2015 to 88,000 per day in 2035.
As the results of the prediction of CO2, if the intersection uses continually on roundabout, the emission
volume of CO2 will increase to 6 times by considering the increment of traffic volume and traffic jam until
2035. On the other hand, CO2 emission volume on 3-layer intersection are 3,559 t-CO2/ year (29% /without)
in 2025, 7,806 t-CO2/ year (40%/ without) in 2035. Therefore, the Project can obtain reduction impact on
CO2 of 8,819 t-CO2/ year in 2025 and 11,381 t-CO2/ year in 2035.
- 102 -
APPENDICES
18 January, 2019
28 November, 2019
1 st : 19 February, 2019
2 nd : 11 June, 2019
AP1-1
【Appendix-2】
Survey Schedule
First Field Survey (13 Jan 2019-21 Feb 2019)
Contents of Survey
Mr.Tanaka Dr.Tsuchida Mr.Watanabe Mr.Shrestha Mr.Ogawa
No Date Day
Chief Deputy Chief
Team Leader Consultant/Road and Consultant/Road and Bridge Design Road Design
Bridge Planning 1 Bridge Planning 2
1 13-Jan Sun Dep. Tokyo Dep. Tokyo
2 14-Jan Mon Dep. Tokyo Arr. Accra Arr. Accra
3 15-Jan Tue Arr. Accra Courtesy call to JICA Site Survey
4 16-Jan Wed Preparation Work for
Meeting with GHA
5 17-Jan Thu Site Visit Site Visit with JICA 1st Site Survey
Explanation/discussio Explanation/discussio
Explanation/discussion on the Inception
6 18-Jan Fri n regarding to the n on the Inception
Report
Survey Report
7 19-Jan Sat Dep. Accra Site Survey Site Survey
8 20-Jan Sun Documentation Documentation
9 21-Jan Mon Site Survey
10 22-Jan Tue Meeting with GHA Meeting with GHA
Meeting with GHA
11 23-Jan Wed
12 24-Jan Thu Engaged for
Documentation Other Work (CS of Work in GHA office
13 25-Jan Fri Phase-1)
14 26-Jan Sat Internal Meeting Internal Meeting
15 27-Jan Sun Documentation Documentation
AP2-1
Contents of Survey
Mr.Suzuki Mr.Ogata Dr.Baik Mr.Onuma Mr.T oyokawa
No Date Day Construction
T raffic Survey / Natural Condition Social Environment Assistant of Road and
Planning/Cost
Analysis Survey Consideration Bridge Design
Estimate
1 13-Jan Sun Dep. T okyo
2 14-Jan Mon Arr. Accra
3 15-Jan T ue Site Survey
4 16-Jan Wed Preparation for Re-
5 17-Jan T hu commissioned Survey
Explanation/discussion
6 18-Jan Fri on the Inception
Report
7 19-Jan Sat Site Survey
8 20-Jan Sun Dep. T okyo Dep. T okyo Documentation
9 21-Jan Mon Arr. Accra Arr. Accra Data Analysis
10 22-Jan T ue Site Survey
Site Survey Evaluation/Contract Meeting with GHA
11 23-Jan Wed
to Local Company
12 24-Jan T hu Data Analysis
Data Analysis for Soil
13 25-Jan Fri Data Collection Site Survey
14 26-Jan Sat Internal Meeting Internal Meeting Internal Meeting
15 27-Jan Sun Documentation Documentation Documentation
Site Inspection for Site Inspection for Soil
16 28-Jan Mon Data Analysis Dep. T okyo
Soil Investigation Investigation
17 29-Jan T ue Meeting with GHA Arr. Accra Meeting with GHA Meeting with GHA
18 30-Jan Wed 1st T echnical Meeting 1st T echnical Meeting
19 31-Jan T hu Internal Meeting Internal Meeting
20 1-Feb Fri Dep. Accra Site Survey Dep. Accra Engaged for
21 2-Feb Sat Via. Paris Site Survey Via. Paris Other Work (CS of
22 3-Feb Sun Arr. T okyo Documentation Arr. T okyo Dep. T okyo Phase-1)
Visit to Borrow Pit
23 4-Feb Mon Arr. Accra
and Quarry Site
Visit to Local
24 5-Feb T ue Construction Site Survey
Company
Survey and Hearing Meeting with
25 6-Feb Wed with the Contractor of Environmental
Phase-1 Section in GHA
AP2-2
Second Field Survey and 1st Design Review by GHA (23 May 2019-14 June
2019)
Contents of Survey
Dr.T suchida Mr.Watanabe Mr.Shrestha Mr.Ogawa Dr.Suzuki Mr.Fujita Mr.Ochi
No Date Day Chief Deputy Chief
BIM/CIM BIM/CIM BIM/CIM
Consultant/Road and Consultant/Road and Bridge Design Road Design
Adviser Expert Manager
Bridge Planning 1 Bridge Planning 2
1 23-May T hu Dep. T okyo Dep. T okyo
2 24-May Fri Arr. Accra Arr. Accra Dep. T okyo
3 25-May Sat Site Survey Site Survey Arr. Accra
4 26-May Sun Internal Meeting Dep. T okyo Internal Meeting
5 27-May Mon Documentation Arr. Accra Documentation
6 28-May T ue Meeting with GHA Site Survey and Discussion with the Contractor of Phase-1
7 29-May Wed T echnical Meeting T echnical Meeting
8 30-May T hu Meeting with GHA Dep. T okyo Meeting with GHA Preparation of SM
9 31-May Fri Stakeholder Meeting Arr. Accra Stakeholder Meeting
10 1-Jun Sat Dep. Accra Dep. Accra Documentation,
Documentation, Internal Meeting
11 2-Jun Sun Via. Istanbul Via. Istanbul Internal Meeting
12 3-Jun Mon Discussion with GHA Arr. T okyo Arr. T okyo
Report to JICA,
13 4-Jun T ue Report to JICA Internal Meeting
Dep. Accra
14 5-Jun Wed Via. Paris Dep. Accra Making Minutes Site Survey
Photogrammetry by
15 6-Jun T hu Arr. T okyo Via. Paris Discussion with Dep. Accra
UAV
16 7-Jun Fri Arr. T okyo GHA Via. Paris
17 8-Jun Sat Arr. T okyo
Documetation
18 9-Jun Sun
19 10-Jun Mon Discussion with GHA
20 11-Jun T ue Report to JICA Dep. Accra
21 12-Jun Wed Dep. Accra Via. Istanubul
22 13-Jun T hu Via. Paris Arr. T okyo
22 14-Jun Fri Arr. T okyo
* GHA: Ghana Highway Authority
JICA: Japan International Cooperation Agency
AP2-3
Third Field Survey (23 Nov 2019-1 Dec 2019)
Contents of Survey
Mr.T anaka Mr.Nito Dr.T suchida Mr.Watanabe Mr.Shrestha Dr.Suzuki
No Date Day
Chief Deputy Chief
Planning BIM/CIM
T eam Leader Consultant/Road and Consultant/Road and Bridge Design
Coordinator Adviser
Bridge Planning 1 Bridge Planning 2
1 23-Nov Sat Dep. T okyo Dep. T okyo Arr.Accra
2 24-Nov Sun Dep. T okyo (Next morning Arr. Accra) Arr. Accra Dep. T okyo Arr. Accra Documentation
3 25-Nov Mon Meeting with JICA Ghana
4 26-Nov T ue AM: Courtesy call to MRH, MOF and GHA, PM: Site Visit
5 27-Nov Wed Meeting with GHA
6 28-Nov T hu Signature on Minutes of Discussions
7 29-Nov Fri AM: Meeting with EOJ, PM: Dep. Accra Meeting with EOJ Documentation Dep. Accra
8 30-Nov Sat Arr. T okyo Dep. Accra
9 1-Dec Sun Arr. T okyo
* GHA: Ghana Highway Authority
M RH: M inistry of Roads and Highways
M OF: M inistry of Finance
JICA: Japan International Cooperation Agency
EOJ: Embassy of Japan in Ghana
AP2-4
【Appendix-3】
Recipient Country
JICA Ghana Representative Office
Maki OZAWA Senior Representative
Masashi YAMAMOTO Representative
Ayumi GOSHO Project Formulation Advisor (Infrastructure)
Syoko NAKANO Project Formulation Advisor (Infrastructure)
MABE Biliwi Joshua Programme Officer
Ministry of Finance
Mr. Emmanuel Edumadze Principal Budget Analyst
Mensah
Ms. Vivian Darah N/A
AP3-1
SHIMIZU-DAI NIPPON JV (Contractor of Phase-1)
Mr. UEMURA Yujin Project Manager
Mr. NARITA Susumu Deputy Project Manager
Mr. OKABE Masayoshi Construction Manager
AP3-2
【Appendix-4】
Minutes of Discussion
18 January, 2019
AP4-1
AP4-2
AP4-3
AP4-4
AP4-5
AP4-6
AP4-7
AP4-8
AP4-9
AP4-10
AP4-11
AP4-12
AP4-13
AP4-14
AP4-15
AP4-16
AP4-17
AP4-18
AP4-19
AP4-20
AP4-21
AP4-22
AP4-23
AP4-24
AP4-25
AP4-26
AP4-27
AP4-28
AP4-29
AP4-30
28 November, 2019
AP4-31
AP4-32
AP4-33
AP4-34
AP4-35
AP4-36
AP4-37
AP4-38
AP4-39
AP4-40
AP4-41
AP4-42
AP4-43
AP4-44
AP4-45
AP4-46
AP4-47
AP4-48
AP4-49
AP4-50
AP4-51
AP4-52
AP4-53
AP4-54
AP4-55
AP4-56
AP4-57
AP4-58
AP4-59
AP4-60
AP4-61
AP4-62
AP4-63
AP4-64
AP4-65
AP4-66
【Appendix-5】
Technical Notes
TECHNICAL NOTES
ON
IMPROVEMENT 0F
This note is signed between The Team, Ministry of Roads and Highways (MRH) and
Ghana Highway Authority GHA) to sh\are mutual understandings and agreement on the
matters mentioned in Appendix-1.
AP5-1
The Preparatory Survey on the Project for Improvement of
Tlema Motorvay Roundabout (Phase 2)
in the Republic of Ghana
1. Project Bacl(ground
The construction for the Proj.ect for Improvement of Ghanaian International Corridors (Grade
Separation of Tema Intersection in Tema), hereinafter referred to as "Phase 1'', commenced in
February 2018 and the construction works are currently under progress. The completion is
scheduled in June 2020. Major scopes of the Phase 1 covers widening and improvement of Accra -
Tema Motorway and Aflao Road in the East-West direction (underpass), construction/widening of
at-grade carriageway in the North-South direction, connecting ramps (slip roads) for right turning
vehicles at all directions, at-grade traffic signal controlled intersection, and provision of pedestrian
bridges.
According to the study conducted during Phase 1 outline design stage, the outcome of phase 1
improvement is effective until year 2023. Beyond 2023, the capacity of the intersection will start to
decrease as it becomes saturated due to the increase of traffic volume and the intersection will
start getting congested. In order that the intersection continues to enjoy safe and smooth flow,
implementation of Phase 2, which plans to provide a fly-over in the north-south direction for the
through traffics, needs to be completed before the intersection becomes saturated.
To ensure the intersection functions efficiently beyond 2023, the Government of Ghana (GOG)
made a request to the Government of Japan (GOJ) for a Grant Aid Assistance to implement Phase 2.
The GOJ decided to conduct the preliminary survey and examine the viability of the project and
entrusted the Survey to Japan International Cooperation Agency (JICA).
2. Generalltems
The Team distributed and explained the contents of the Inception Report of the Project during the
meetings held on January 15 and 16. MRH and GHA basically agree on its contents as also indicated
in sub-clause 9-1 of the Minutes of Discussions signed between Ghana side and Japan side on
January 18, 2019.
I) Project scopes
The requests made by the GOG are to construct a flyover at the Tema Motorway Roundabout and
carry out the detailed design and construction supervision.
2) Survey objective
• Understand the background, purpose, and scope of proj.ect under the Grand Aid
• Study the feasibility of the project in terms of effectiveness, technical and economic
justification,
Zjzjf.,,,,-.
A-I
AP5-2
The Preparatory Survey on the Project for Improvement of
Tema Motorway Roundabout (Phase 2)
in the Republic of Ghana
• Estimateprojectcost,and
• Propose the contents, implementation and maintenance plan as well as critical points to be
undertaken by the GOG in order to achieve the outcome and targets set for the project
i) Highway Design: Ghana Road Design Guideline, Survey & Design Division,1991
(Items not covered in the guideline will be referred from and in the order of " A Policy on
Design of Highways and Streets, 2004" (AASHTO: American Association of State Highway and
iii) Bridge/Structural Design: Specifications for Highway Bridges (Japan Road Association) or
equivalent (wind speed/load will be based on Ghana standard, for live load refer to 3.5)
ln order to secure consistency with Phase 1, the same design condition which was agreed during
Phase 1 applies. The major conditions are given in Table 3-1.
3.3 Alignments
Construction of Phase 1 is based on the horizontal and the vertical alignments designed for the
ultimate stage of improvement (3-tier intersection) during phase 1. Therefore, the alignments of
Phase 2 are fixed and shall not be subject to significant change.
A.-2 %„
AP5-3
The Preparatory Survey on the Project for Improvement Of
Tema Motorway Roundabout (Phase 2)
in the Republic of Ghana
Number of lanes proposed during Phase 1 will be maintained, except at the at-grade intersection in
the Aflao-Tema direction where it will be reduced to 2 lanes, given that the reduction can still be
• The elevated section on the north-south direction will consist of bridges and retaining walls.
• Cross section of the bridge (one direction) will be asshown in the figure below.
• Bridge type and the layout of the fly-over are derived from the result of the comparative
study. The Team explained on the configuration of the flyover that applies 3-column pier and
2-column pier. GHA and the Team agreed on the latter as it reduces the bridge spans and
etc.) confines to application of steel type girders for superstructure and steel outer-rigger
(gantry/gate) frame with concrete pier and caisson foundation. GHA has no objection with
regards to application of such structures.
• TheTeam explained thatthe design calculation will be based onJapanese standards as the
steel plate girder or steel box girder is planned to be fabricated and procured from Japan.
• GHA understands and agreesto usingtheJapanese standards forthe bridge design, butGHA
and The Team will agree on a safety factor that will not make the results of Japanese
Standards inferior to the results of BS 5400 Code.
• Asphalt concrete pavement will be planned both on standard section and on the elevated
ELEZZI
A-3
AP5-4
The Preparatory Survey on the Project for Improvement of
Tema Motorway Roundabout (Phase 2)
in the Republic of Ghana
• The EIA/lEE permit covers the overall improvement ofTema Motorway Roundabout (3~tier
intersection) and not just the scopes of Phase 1 improvement works. Ghana`s prevailing
environmental related laws do not require a separate EIA/IEE for projects implemented in
phases, given that there is no drastic change in the existing conditions of the project site
and/or in the plans/design in the phases.
• The existing permit`svalidity is till June 4, 2019. GHAwill take all necessary initiativesforthe
• A roundabout is one of the possible detours during construction that is deemed to minimize
the impact to the roads constructed under Phase 1. The area within the roundabout can also
that of the signal-controlled intersection to control traffic until the commencement of Phase
• Construction debris will be disposed at the disposal area designated by GHA. GHA is
requested to provide information of the disposal area by the end of February, 2019.
6. Designchange
• Should a roundabout is to be applied for detour, GHA understands that change of final
design change. In such case, GHA will submit the request for review of the modification
accordingly.
7. Others
• GHA will furnish TheTeam with available data and information requested bythe Team in the
attachment (revised and submitted to GHA on February 13, 2019) of the Inception Report
by its earliest possible convenience, but not later than March 31, 2019.
A-4
EZZzzi
AP5-5
The Preparatory Survey on the Project for Improvement of
Tema Motorway Roundabout (Phase 2)
in the Republic of Ghana
Quany site
•Z¢„
A-5
AP5-6
sl IJICA Survey Teom
CTI Engineering Inlernqlionol Co., Ltd.
Tochibono Annex Building
2-25-14 Komeido Phone: +81-3-3538-2561
Koto-ku, Tokyo 13,5-0071, Jopon Fox: +81 -3-3638-2560
ON
THE PREPARATORY SURVEY ON THE PROJECT FOR
IMPROVEMENT OF
TEMA MOTORWAY ROUNDABOUT (PHASE 2)
This note is signed between The Team, MRH and GHA on items discussed and agreed on
the matters mentioned in Appendix-1.
Accra, June l-1, 2019
WITNESS:
U'-X'
Mr. Edmund Offei-Annor
Chief Director
Ministry of Roads and HighwaYs
AP5-7
The Preporatory Survey on the Project for lmprovement of
Temo Motorway Roundabout (Phase 2)
in the Republic of Ghana
Appendix-1
1. Project Background
The construction for the project for lmprovement of Ghanaian lnternational Corridors (Grade Separation
of Tema lntersection in Tema), hereinafter referred to as "Phase 1", commenced in February 2018 and
the construction works are currently under progress. The completion is scheduled in June 2020. Major
scopes of the Phase 1 cover widening and improvement of sections of Accra-Tema Motorway and Aflao
Road in the East-West direction (underpass), construction/widening of at-grade carriageway in the
North-South direction, connecting ramps (slip roads) for right turning vehicles at all directions, at-grade
traffic signal controlled intersection, and provision of pedestrian bridges.
According to the study conducted during Phase 1 outline design stage, the outcome of phase 1 is
effective until year 2023. Beyond2023, the capacity of the intersection will become saturated due to the
increase of traffic volume and the intersection will start getting congested. ln order that the intersection
continues to enjoy safe and smooth flow, implementation of Phase 2, which plans to provide a fly-over
in the North-South direction for the through traffics, needs to be completed before the intersection
becomes saturated.
To ensure the intersection functions efficiently beyond 2023, the Government of Ghana (GOG) made a
request to the Government of Japan (GOJ) for a Grant Aid Assistance to implement Phase 2. The GOJ
through JICA decided to conduct the preliminary survey and examine the viability of the Project.
JICA dispatched a mission to Ghana in January 2019 (first field survey) to conduct a preliminary survey
of Phase 2. During the course, JICA Survey Team (the Team) carried out surveys and meetings with GHA
and mutually agreed on the design conditions for the outline design of the road and bridge design in the
Technical Notes signed on February L9,20L9.
2. Generalltems
The Team made presentations explaining the purpose of visit to Ghana, which was followed by an
explanation on the output of the draft outline design, construction planning, traffic safety measures
applied, importance of Building and Construction lnformation Modelling/Management (BlM/ClM) and a
virtual simulation of the entire project.
1) Proiect Scopes
The requests made by the GOG are to construct a flyover at the Tema Motorway Roundabout and carry
out the detailed design and construction supervision.
2) Survey Obiective
A- 1
'R.5 C,b^tl-
AP5-8
The Preporatory Survey on the Project for lmprovement of
Temo Motorwoy Roundabout (Phose 2)
in the Republic of Ghano
justification,
Conduct outline design for minimum but optimal scope and scale of the project required for
achieving the outcome of the assistance,
a Estimate project cost, and
a Propose the contents, implementation and maintenance plan as well as critical points to be
undertaken by the GOG in order to achieve the outcome and targets set for the Project
3. Technical ltems
All items agreed in the 1't Technical Note signed on 19 February 2O!9, except for those covered in this
technical note, still applies.
3.2 Response to Comments from GHA on Outline Design and Traffic Safety
GHA basically agreed on the contents of the output of the outline design and traffic safety plans
presented by the Team during the technical meeting held on May 29, 2019, except for some concerns,
which were compiled in the form of comments and provided to the Team on June 6, 2019. The response
to the comments were furnished by the Team on June 7, 2019.
GHA has no objection on the changes proposed by the Team with regards to the configuration of the at-
grade intersection of Phase-1 as illustrated in Figure-l below.
O.
.o,
s,
o,
o,
.tt
<l
ol
ts/,
1999'
'R.S
A-2
AP5-9
The Preporotory Survey on the Project for lmprovement of
Tema Motorwoy Roundabout (Phase 2)
in the Republic of Ghana
Subsequently, GHA agreed application of a 1.25m wide outer shoulder as proposed by the Team.
construction that will require maintenance (painting) only in every 40 years. GHA agreed on the Material
Choice for construction.
3.8 Others
. GHA requested the Team to provide a guideline for the maintenance of the proposed bridge.
Preparation of a guideline is not under the present scope of this preparatory survey. The topic will
be discussed with JICA.
. GHA assured the Team to provide land area sufficient for fabrication of steel girder for the
construction of Phase 2. tT<'S
A- 3 END drV
AP5-10