CPM - 1st Example
CPM - 1st Example
We need to calculate Node-7 but as node-6 value is not available for Latest completion time, we
have to calculate node-6 first.
Out of two values i.e., for Node-7: 19-7 = 12 and 22-4 = 18. So, out of 12 and 18, 12 is
minimum.
Now find out Critical Path: