MEMORANDUM No. 2 0 2 3 - 2 ,1
This is to provide you with the 2023 Policy/Guidelines on Annual EC Overall Performance
Assessment which was approved by the NEA Board of Administrators on April 25, 2023
under RB Resolution Number 2023-65.
This Policy shall take effect 15 days upon its filing with the University of the Philippines
(UP) Law Center pursuant to the Presidential Memorandum Circular No. 11 dated
October 9, 1992.
The Policy was filed with the UP Law Center on 02 May 2023.
NATIONAL ELECTRIFICATION
ADMINISTRATION
l l l l l~f1
l~ill[i1i[1~~~1~1~ii f~~II I I I
l·lEA-•:•.~7 1664
(02)8-929-1909
www.nea.gov.ph
!~bl'
_.;
~~ ,
,t''?.:~_!-10,t,
...o"
"'°'11-N
·
NATIONAL ELECTRIFICATION ADMINISTRATION
c; "The Performance Governance atem-Inatitutlonallzed lational Government Agency"
"'i
,.•
ttO'..,_
J.11
57 NIA Road, Government Cent!l Dillman, Quezon City 1100
I IJ:.
TOVRhelnland
®
Management
System
ISO 9001:2016
www.tuv.com
10 9105082030
02 May 2023
THE DIRECTOR
Office of the national Administrative Register
University of the Philippines Law Center
U.P. Law Center, Diliman
Quezon City
Sir:
Thank you very much for the usual and kind assistance of the U.P. Law
Center.
1: . . . . . . ,
-·
r r--s·;!::~r::~~:-:.:~~~-:.:;· . :.:?..~;·· >-.ii:~.'\'i:" ,...... :~--- ,-
c.,p,:,_:;_ ,.: l
r,\.1...:..1.U.:.~.U..:,..v;,.U,r, I ' l
~ \\
ll
BY:
(02)8-929-1909
www.nea.aov.ph
2023 Policy/Guidelines on Annual Electric Cooperative (EC)
Overall Performance Assessment
I. RATIONALE
Section 58 of RA 9136 otherwise known as the Electric Power Industry Reform Act (EPlRA)
of 2001 mandates NEA to:
1. Prepare the ECs to operate and compete under the deregulated electricity market;
2. Strengthen the technical capability and financial viability of the rural ECs; and
3. Review and upgrade regulatory policies to enhance the viability of rural ECs as electric
utilities.
On the other hand, RA 10531 or the NEA Reform Act of 2013 mandates NEA to:
1. Promote the sustainable development in the rural areas through rural electrification;
2. Pursue electrification program and bring electricity, through the ECs to the countryside,
even in missionary or economically unviable areas; and
3. Empower and enable ECs to cope with the changes brought about by the restructuring
of the electric power industry.
Pursuant to the said mandate and to address the heightened demands for power rate
reduction, security of power supply, reliability of service, 9..ood governanceJ, and m~~-.
co~sumer-~wners' (MCOs) empowerment, it is imperati r~~~q f'r..Yi~~.:~nwlj!'?J..,~~~~91i1!tl~I
existing Polley/Guidelines on Annual EC Overall Performa ce Ai~ssr.nent., ... o 1.,,.,,d11~,,1
II. OBJECTIVES
Ill. POLICY
It shall be the policy of NEA to implement a set of performance parameters that will serve
as basis of the Annual EC Overall Performance Assessment.
IV. SCOPE
The performance parameters shall cover all ECs connected with the main power grid (on-
grid) and those ECs isolated from the main power grid (off-grid).
Page 1 of 17
V. PERFORMANCE ASSESSMENT CRITERIA
Performance
Performance Indicators Point Score
Level
1·. Leverage
Debt Ratio Up to 0.60 2
2. Liquidity Ratio
Working Capital Ratio At least 1. 00 2
3. Efficiency
a. Payment to Power Suppliers
On-Grid Off-Grid
a.1. GENCOs/Market
Current ECs ECs
Operators/lEMOP/NPC-SPUG)
10
a.2. Payment to Transmission
Company/ies (Main Grid/sub- Current 3 13
Transmission)
b. Payment to NEA Current 3
c. Payment to Banks/Other Financing
Current 3
Institutions -
d. Collection Efficiency
d.1. Averaoe 97% and above 5
d.2. Current to Current 99% and above 4
4. Result of Financial Operation,
inclusive of Reinvestment Fund for Positive 3
Sustainable CAPEX (RFSC)
Sub-Total 35
5. NEA Audit Rating Not less than 9n0,t,.. t:;
--··
TOTAL 1orr1rF Inf nu.:"~~ \1~~·,,.,•, ' rfl.Q, ,,ft<,,111~ Kt-:l~lSTE i
A"'"""-:,.;.~• ~",.; ,.,o ""• '""'""~- _ I
I
DEFINITION OF TERMS, FORMULA AND SCORING SYST :11 MAY O2 t:J 1ID'
1. Leverage
1· r~., rr<; _r~·k~'· JLN.-T~. I, :'
I ,\
Total Liabilities*
Debt Ratio=
Total Assets
* Excluding Accounts Payable - Subsidy, except for any subsidy funds that are for
return to NEA.
Page 2 of 17
2. Liquidity Ratio
Working Capital Ratio measures the EC's ability to cover the monthly operating costs.
3. Efficiency
For purposes of assessment, the cut-off date is October of the year under review.
Point Score
Status of Payment
On-Grid ECs Off-Grid ECs
Current; Restructured/Special Payment
10 13
Arrangement (SPA) - Current
Arrears 0 0
Point Score
Status of Payment
On-Grid ECs Off-Grid ECs
Page 3 of 17
dJ/
b. Payment to NEA refers to the EC's ability to pay its maturing loans to NEA
Incentive Point:
• One (1) incentive point for every quarter of advance payment but not to exceed
two (2) incentive points.
• EC must consistently maintain the advance payment all throughout the year.
• EC with Restructured Accounts/Special Payment Arrangement (SPA) but with
advance payment are qualified to the incentive points
• ECs with no loan are excluded
c. Payment to Banks/Other Financing Institutions refers to the EC's ability to pay its
maturing loans to Banks/other Financing Institutions.
*If the EC has no loan from banks/financial institutions, the point score attributable
for such shall be added to Payment to NEA and vice versa.
In the event that the EC has no loan from both NEA and other Banks/Fis, the total
six (6) points shall be re-allocated to all efficiency parameters, provided that, it
garnered points from the other efficiency parameters, as follows:
d. Collection Efficiency (CE) refers to the capability of EC to collect power bills from
member-consumer-owners (current and overdue accounts).
Average Method
Collection for the Year
Average CE = Gross CAR Beg. + Gross Sales for the Year - Gross
Current Month Sales
Page 4 of 17
Gross Consumer Accounts Receivable Beginning, Gross Sales, Gross Current
Month Sales and Collection for the Year are inclusive of VAT, UC, FIT All, and RFSC.
Demerit Points
Related Obligation refers to the ECs' compliance with the provisions of the Electric
Power Industry Reform Act, its Implementing Rules and Regulations and Energy
Regulatory Commission-approved Universal Charge (UC) Guidelines.
Page 5 of 17
IP
4. Result of Financial Operation, inclusive of RFSC refers to the amount of Net Margin
after all costs and expenses have been deducted.
Positive 3
Neoative 0
5. NEA Audit Rating refers to the EC's final score on itemized audit findings by the
NEA-Electric Cooperative Audit Department (ECAD).
However, ECs not audited or monitored by NEA for four (4) years or more may be rated
based on the latest External Audit Opinion at EC's request provided , that it obtained a
minimum of 80% total points for the other financial parameters for the year being rated.
GENERAL REQUIREMENTS
,:i.,
0
Page 7 of 17
V
a. Performance Rating of Board of Directors (BOD)
t"~rn,
.
Page 8 of 17
The BODs rating shall be determined by the following scheme:
The performance rating of the General Manager shall be determined through the EC
Board of Directors, Department Managers/Area Managers and Self Rating Scheme
using the following weight:
IV
a. 97% and above 20
b. If below 97%
• Increase of 1% and above 18
2. Collection • Increase of 0.90% to 0.99% 16
Efficiency • Increase of 0.80% to 0.89% 14
• Increase of 0.70% to 0.79% 12
• Increase of 0.60% to 0.69% 10
• Increase of 0.01 % to 0.59% 5
a. At least 1 month working capital for operating 10
expenses
b. Working capital is less than 1 month
3. Liquidity Level - 9
• 0.90 to 0.99
Cash General 8
• 0.80 to 0.89
Fund 7
• 0.70 to 0.79
• 0.60 to 0.69 6
• 0.50 to 0.59 5
4. Availability of
Retirement Availability of Fund 10
fund/plan
SAIDI & SAIFI Compliant 10
5. System 5
One (1) !\Ion-compliant (SAIDI & SAIFI)
Reliability
Two (2) !\Ion-compliant (SAIFI & SAIDI) 0
6. No penalties Has not been sanctioned by the NEA Board of
imposed by the Administrators for violation of Code of Conduct and
10
NEA Board Ethical Standards, NEA policies or other
administrative charges for the year
No pending labor cases or conflicts as certified
7. Leadership
under oath by the HR Manager and/or DOLE or 10
Functions
NLRC Certification
8. Complaints/
Response to/action on verified complaints lodged
Requests Acted 10
through NEA/DOE/8888/PCC
upon
Total 100
The GM's Performance level shall be determined using the following scheme:
Submission of the BOD and GM's performance evaluation starts on January until the
28th day of February of each year. This is to provide sufficient time for the Institutional
group's assessment and validation of reports/information prior to the KPS Overall
Committee's annual rating period.
To ensure confidentiality of the said evaluations, all filled out evaluation forms (hard
copies) must be placedf'mosi:il5ii'ifttetirra--sealed-emt.e1ope or ECs may opt to submit
through virtual applicatio 'usirt{;it''a ·cledieated,:email ~F.i~rt, upon prior information and
W
U)... ~
t ~' r
f'--·-
/v_l~ Y_ -~
"'1 :;,
~
/
1·r
.J.
,1~;,1
i .·r J.I
proper assistance from ur Consl'.lffl~f m~vetc:tf)mem and rotection Division personnel.
I
1
1
Page 10of 17
•
-- --... il( . .., .
~
-
. . ~ .
II. STAKEHOLDERS
This refers to the number qtca.mpJai~_ t s/requests received_and acted upon by the EC
to validate its performanc in.providing -efficieiifservice towards attaining customer
Sa .ISfact·IOn.
t FF-i\~ ~' lht ~ .. ., t nv1,.11-..l t< ,-. 11 ,J~ r_Ji:.:.t',1!\i:'~I
1 , , 1; •
· ., n . - - ,. ,
&,~Hl1111.,: 1"')v··· -;'U lt;J •' •U t<i:_.;f 11,11,1,fl; I
I
*IAY i::i 1 -~ .. •,. -.• !
1··w
~ I"(' --~-., ·-] _1~:~·;. TE /11 i Page 11 of 17
~- . -- -- ~--. 8 f:~.:-·:~==i
Action on Complaints/Requests Point Score
Compliant 2
Non-Compliant 0
This refers to the suNey conducted within the EC coverage area pertaining to the
level of customer satisfaction on its de r1very of seN1ce
· t o mem ber-consum ers-owners.
Customer Satisfaction Survey Point Score
Very Satisfactory 2
Satisfactory 1
GENERAL REQUIREMENTS
Point
Technical Parameter Passing Criterion
Score
1. System Loss
Within the cap 6
(Feeder loss cap by EC Cluster)
System Reliability
SAIFI 20 interruptions/consumer 7
SAIDI 2,700 minutes/consumer 7
TOTAL 20
1. Feeder Loss Cap. By virtue of ERC Resolution No. 20 series of 2017, the Distribution
System Feeder Loss Cap shall be used as standard level in the Electric Cooperatives
Clusters. This refer to the feeders' total technical and non-technical losses, that can be
recovered through system loss rates using the formula shown below:
\\'h,·r,·. . -
.··- • • .. . I
-· ---s1., ..•.~-~\••··~
..,_l - :,
-, -
- Total Di:-lrih11ti11n Sj,h'lll IJ1.,, that \'all b,·
0r11~( c.f !r,._ "" 1: 1 ,1.,..I .nMINl,:..1,\.-\11<1~ N~,11STER! f\Tll\'\·r,·,I throu~h th,· SJ ,11·111 Loss ClwrJ;t', in
+"'lti111l111.,1;1c.:.ivr '1'1Jlt-f ..,1.Q 1-\:;:;f 1,,1ol,II) i 1tt·m·nt:
1
vlAY O7 4",J1,.,J
"""'" nSI J'I " Suh Tr;1n .. mi~sinn ;incf S11hst,1t11111 l.os-", in 1wrn·nt;
I . .
" h•1·1h·r 'l't·d111ir;1I l.11~,. lll 1wrn·nt:
CLUSTER 2
ABREGO CASURECO I ILECO If NEECO II - AREA 1 SAMELCO I
AKELCO CASURECO If ILECO Ill NEECO If - AREA 2 SAMELCO If
ALECO CASURECO Ill !NEC NOCECO SOLECO
ANECO CASURECOIV ISECO NONECO SORECO I
ANTECO CEBECO I ISELCO I NORECO I SORECO II
ASELCO CEBECO If ISELCO If NORECO II SUKELCO
AURELCO CEBECO Ill LANECO NORSAMELCO SURNECO
BATELEC I CENPELCO LASURECO NUVELCO SURSECO I
BENECO COTELCO LEYECO I PANELCO I SURSECO II
BILECO COTELCO-PPALMA LEYECO Ill PANELCO Ill TARELCO I
BOHECOI DANECO LEYECO IV PELCO I TARELCO If
BOHECO II DASURECO LEYECO V PELCO II ZAMECOI
BUSECO DORECO LUELCO PELCO Ill ZAMECO II
CAGELCO I ESAMELCO MAGELCO PRESCO ZAMSURECO I
CAGELCO II FIBECO MOELCII QUEZELCO I ZAMSURECO If
CAMELCO FLECO MOELCI II QUEZELCO II ZANECO
CANORECO GUIMELCO MORESCO II QUIRELCO
CAPELCO ILECO I NEECO I SAJELCO
CLUSTER3
BATELEC II PENELCO CENECO SOCOTECO II
MORESCO I SOCOTECO I LEYECO II ZAMCELCO
2. System Reliability is the indicator of the distribution system service performance towards
its customer and measured by the ·vefcigeffl]ffl~~r-:Ufinterraption-and average duration
of interruption within the specified erl6'd:·' "'·· ··· •·· ,.,, n.,,,.,,; ,,, .. 1, • fi r:i;1s 1E;;I
• ,..:11~1111 .. :111 ... v•' -t u1 1:: ~ . inJ k :;~ .. 1+1i,:..u ~
MAY C '"""
Page 13 of 17
tilJ
a. System Average Interruption Frequency Index (SAIFI) refers to the annual average
number of sustained unscheduled interruptions experience by a customer.
b. System Average Interruption Duration Index (SAIDI) refers to the annual average
duration of sustained unscheduled interruptions experienced by a customer.
Demerit Point:
A demerit of two (2) points shall be imposed against ECs which were not able to conduct
Competitive Selection Process (CSP) as scheduled in the Power Supply Procurement Plan
(PSPP); the list of ECs which were not able to conduct CSP on time, shall be provided by the
NEA Regulatory Affairs Office (RAO).
GENERAL REQUIREMENTS
1. Reports
Page 14 of 17
LEVEL OF ELECTRIFICATION (20)
DEMERIT POINTS
A demerit of three (3) points shall be imposed against ECs for non-submission of any of the
following:
1. Financial Reports
2. Institutional Reports
3. Technical Reports
4. Energization Reports
5. Distribution Development Plan
Only the reports submitted on time with complete and accurate data shall be considered .
The data information shall be sourced from the NEA-BIT as provided by the
department/office Subject Matter Experts•'{SMt:'s}F1friri£t5mpliar.ili:e··of ECs to the DDP shall
be provided by the NEA Corporate Plann PfQ"~nJ.~: tQrQt~::1
~:.;:•.:~.'., ..~rG,s rH:
MAY O? t::::1
r~ - .,..• .~, ~ ·,:t y
!I .
! r~\
.•-
~.:!J~ ~ ~~.i? u•~ J~ ,-,-·
.;;1., u .
L.!..;
Page 15 of 17
1H · . _ ••. _ . _ ·-·--·---·-·· .. --. ,
2. Show Cause Orders Issued by ERC to ECs (1)
A demerit of one point shall be imposed against ECs which received three (3) or more Show
Cause Orders rendered with final judgments and with imposed monetary penalties issued
by the ERC during the year under assessment. Show Cause Orders issued are for violation
of ERC rules and regulations.
A. FINANCIAL 8 40
Leverage 1 2
Liquidity Ratio 1 2
Efficiency 4 28
Result of Financial Operation 1 3
NEA Audit Rating 1 5
8. INSTITUTIONAL AND GOVERNANCE 7 20
Human Resource 2 7
Stakeholders 5 13
C. TECHNICAL 3 20
System Loss 1 6
System Reliability 2 14
0. LEVEL OF ELECTRIFICATION 3 20
TOTAL 21 100
1. To earn Category AAA, the ECs must have complied with all the standards on System
Loss, Reliability Indices (SAIDI/SAIFI), Collection Efficiency, Result of Financial
Operations, Payment to Power Suppliers, conduct of District Election and AGMA. An
EC which failed to comply in any-ef- -tt'le·-~fetA-···listed-·parameters shall only be
categorized as "AA" notwithstandltlQ,<it~,tG>talsc.oreo't i9S:ru annv~.!
J:
( •,,,.,,,,:.. '.," ,,,,.,, , 1, l " t,,1,\l,C, -~ :
. ----- '.=::-/
2. Incentive points shall be given provided that the EC Overall Point Score shall not
exceed 100%.
IX. RESPONSIBILITY
(e) "The ECs shall ensure that all information is correct and accurate to reflect
the true state of health of the electric cooperative. This information shall
become the bases for assessment and early warning signals for crafting of
solutions that will improve the EC efficiency and seNice reliability. An affidavit
duly signed by the EC General Managers will be required to ensure the
correctness and completeness of all inputs in the DETs.
(f) The ECs are responsible and accountable for submitted data through the
DETs and the final outcome of Operational Reports
2. In cases of erroneous or false data submitted, the EC's final rating may retrogress after
validation without prejudice to motu proprio Administrative investigation.
3. The ECs are likewise responsible and accountable for the submission of additional
supporting documents/ documentary evidence that will substantiate and/or further justify
the truthfulness/ correctness of the submitted reports.
5. Upon approval of the Administrator and confirmation of the Board of Administrators, the
results of the EC Overall Performance Assessment shall be released in the NEA website.
X. AMENDATORY CLAUSE
This supersedes Memorandum No. 2019 - 045, Series of 2019, "Amended Enhanced
Policy/Guidelines on Electric Cooperatives (ECs) Overall Performance Assessment".
XI. EFFECTIVITY
This policy shall take--effect 15 days upon filing with the University of the Philippines Law
Center pursuant to the Presidential Memorandum Circular No. 11, dated October 9, 1992,
and operationalize beginning the 2023 EC Overall Performance Assessment.