3) Section B-Oct2023
3) Section B-Oct2023
6. The fees for Internal Assignment will be Rs.200/- per subject. This is to be paid
through Demand Draft or Online only (Cheque payment will not be accepted) DD
drawn in favour of Indian Institution of Industrial Engineering, payable at
Mumbai and sent along with Assignment. Write your name and membership
number on the back side of the Demand Draft, Online payment / transaction details
should be attached with assignment. Bank details is given below for Online
payment.
If students still have any doubt they may email their queries to Controller of
Examinations, IIIE.
Sd/-
Controller of Examinations
Mandatory Format for who have done online payment for
Internal Assignments October 2023 Examination.
Section: _______________________________________
_______________________________ Q.2
Total
Signature of Student:
Signature of Examiner
Note: 1. Solve all questions by sequence. Question Numbers are to be written clearly in
Bold Font, in center of the line, also in the left-hand margin.
2. Keep copy of this page and assignment for your record.
3. Student must pass individually in assignment and written papers.
INDIAN INSTITUTION OF INDUSTRIAL ENGINEERING
GRADUATESHIP EXAMINATION
Internal Assignment for October-2023
Section-B
IEB 01: FACILITIES PLANNING AND MANAGEMENT
Max. Marks: 140
Instruction: All questions are compulsory.
Q. 1 a) What is 'Production Flow analysis (PFA)'? Explain the steps in PFA. (10)
b) What are the functions of the Storage and Warehouse System? (10)
b) Write a note on Machine Flexibility. Explain the effect of machine flexibility (10)
on facility layout.
Q. 4 a) Explain the concept of production line balancing with a suitable example. (10)
Q. 5 a) Explain technical and economic factors for the replacement of equipment. (10)
b) What are different Computerized Plant layout Planning Techniques? Explain (10)
any one technique in detail.
Q.1 a) What is Supply Chain? Explain in detail about Supply Chain Management with (10)
suitable example.
Q.2 a) Explain Material management along with Procurement and Purchasing policy. (10)
b) Explain EOQ and its derivative models. (10)
Q.3 a) What do you mean By Inventory and Inventory Control in supply chain (10)
perspective?
b) What are the drivers of supply chain? Explain them in brief. (10)
Q.4 a) Explain the concept of customer service from a logistics and supply chain (10)
perspective.
Q.6 a) Mention the various types of issues that need to be addressed in supplier and (10)
distributor benchmarking.
b) Explain E-Business in Supply Chain with its advantages and drawbacks. (10)
Q.7 a) Write a short note on vendor development and evaluation method. (10)
Q.3 a) What is the difference between quantitative forecast methods and (10)
qualitative forecast methods?
b) The Neo E-vehicle motorcycle dealer in the south Delhi wants to be able to (10)
forecast accurately the demand for the Super motorcycle during the next
month. From sales records, the dealer has accumulated the data in the
following table for the past year.
a. Compute a three-month moving average forecast of demand for April
through January (of the next year).
b. Compute a five-month moving average forecast for June through January.
c. Compare the two forecasts computed in parts (a) and (b) using MAD.
Which one should the dealer use for January of the next year?
Q.4 a) Demand for Renuka Company’s Educational toy series follows a seasonal (10)
pattern.
Each worker can produce on average 100 cases of educational toys each
month. No educational toys are currently in inventory. The wage rate is $10
per case for regular production. Holding cost is $1 per case per month.
Increasing the workforce costs approximately $1000 per worker; decreasing
the workforce costs $500 per worker.
Demand
Month (Cases) Month Demand (Cases)
January 1000 July 500
February 400 August 500
March 400 September 1000
April 400 October 1500
May 400 November 2500
June 400 December 3000
b) Describe a flexible manufacturing system. How does it differ from a cellular (10)
layout?
Q.5 a) What are the objectives, inputs, and outputs of an MRP system? (10)
b) How is a master production schedule created? What type of information is (10)
included in the item master production schedule?
Q.6 a) Explore capacity planning at your university or place of business. How is (10)
capacity measured? What factors influence the acquisition and allocation of
resources?
b) What type of layout(s) would be appropriate for: (10)
a. A grocery store.
b. Home construction.
c. Electronics assembly.
d. A university.
Q.7 a) Following are the new project implementation activities with time duration, (10)
Activity 1-2 1-3 2-4 3-4 3-5 4-9 5-6 5-7 6-8 7-8 8-9 8-10 9-10
Time in Weeks 4 1 1 1 6 5 4 8 1 2 1 8 7
Q.3 a) What are the objectives of ISO 9000? State it’s the advantages of ISO 9000 (10)
standards to buyer and seller?
b) Explain quality management system (10)
Q.5 a) What is the significance of vendor development? What are the methods used for (10)
vendor assessment?
b) Distinguish between ‘Withdrawal Kanban’ and ‘Production Kanban’. (10)
Q.6 a) What is Failure Modes and Effects Analysis? Explain its stages. (10)
b) Explain P-D-C-A cycle in detail (10)
Q.7 a) What do you mean by quality of conformance? Discuss the factors influencing it (10)
b) Explain any two types of control charts use for quality control. (10)
INDIAN INSTITUTION OF INDUSTRIAL ENGINEERING
GRADUATESHIP EXAMINATION
Internal Assignment for October-2023
Section-B
Q1 a) Discuss about need and challenges of innovation for survival and excellence. (10)
Q2 a) Write basic and secondary function of computer, printer, watch, Automobile, (10)
pen.
b) Explain the concept of product Life cycle with suitable case study. (10)
Q.1 a) Using Lagrangean Function, find the optimum solution to the problem, (10)
Minimize z = X12 + X22 + X32
Subject to 4X1+ X22 + 2X3 - 14 =0
b) A company produces two products, where the labor and profit are: (10)
Product 1 Product 2 Target
Labor (Hrs) 4 2 32
Profit $ 4 2 48
Demand 7 10
The company incurs a penalty of $1 for each dollar it falls short of the profit.
A $2 penalty is incurred for each hour of overtime, and a $1 penalty is
incurred for each hour of labor that is not used. A penalty of $5/unit is
assessed for any shortfall in meeting demand. Formulate an LP to minimize
the penalty. Use Goal Programming method.
Q.2 a) Describe various methods to solve NLPP and its applications. (10)
b) Explain Integer programming with its applications and methods in detail. (10)
Q.5 a) The following table gives the activities in a construction project and the time (10)
duration of each activity:
Activity Preceding activity Normal Time (Days)
A -- 16
B -- 20
C A 8
D A 10
E BC 6
F DE 12
Find: (i) Draw the activity network of the project. (ii) Find critical path.
(iii) Find the total float and free-float for each activity.
b) Illustrate the formulation and application of Kuhn- Tucker conditions for the (10)
following two variable nonlinear problem.
Maximize f(x) = In (X1 + 1) +X2
subject to
2X1 + X2 <=3
And X1 >= 0 X2 >= 0
Q.7 Write short notes on following: (20)
1. Lagrangian Optimization.
2. Principles of optimality in Dynamic programming.
3. Applications to real life simulations.
4. Goal Programming.
INDIAN INSTITUTION OF INDUSTRIAL ENGINEERING
GRADUATESHIP EXAMINATION
Internal Assignment for October-2023
Section-B
Q.2 a) Why knowledge management practices are important for Industry? (10)
b) What are various knowledge management tools and techniques? Explain in (10)
brief
Q.4 a) Explain different types of ropes and chains used for material handling (10)
equipment’s.
b) Discuss cradle conveyor with suitable diagram and also highlight its (10)
applications.
Q.6 a) Explain bucket elevator with its working and applications. (10)
Q.1 a) Explain with example about machine tool automation using hydraulics. (10)
b) State the any five Rules for PLC Ladder Diagram. Explained with Diagram. (10)
Q.2 a) Draw a hydraulic circuit to explain the regenerative function. Write the specification of (10)
the elements used.
b) Explain each element in FRL unit with its symbol. (10)
Q.3 a) What is the electrical timers and counters? Explain it with reference to the type of (10)
contacts used.
b) Discuss the factors in implementation of industrial automation to improve (10)
Company profit?
Q.4 a) What is the actuator and its role in automation? Draw the symbols and briefly explain the (10)
types of actuators
b) Develop a ladder program for Traffic light control system with following conditions: (10)
i) Red light ON for 30 sec, ii) green light ON for 25 sec, and iii) Yellow light on for 05 sec. iv)
Repeat the sequence until stop push button is pressed.
Q.6 a) What do you mean by low-cost automation? Discuss its implementation with suitable case (10)
study.
b) Explain the importance of control system engineering in day-to-day life and industry. (10)
Q.7 a) Differentiate between open loop control system and closed loop control system. List (10)
examples of both systems.
b) Explain the use of G & M codes required in CNC milling program. (10)
INDIAN INSTITUTION OF INDUSTRIAL ENGINEERING
GRADUATESHIP EXAMINATION
Internal Assignment for October-2023
Section-B
IEE 07: INDUSTRIAL SAFETY ENGINEERING
Max. Marks: 140
Instruction: All questions are compulsory.
------------------------------------------------------------------------------------------------------------------------------
Q.1 (a) What is the importance of safety? Explain various losses which may occur (10)
due to an accident in a factory.
(b) Elaborate the safety committee structure in an industrial organization. (10)
Q.2 (a) What are the various safety considerations to be kept in mind in regard to (10)
machine tools?
(b) How is injury by electric shock prevented? (10)
Q.4 (a) What is safety audit? How it is useful for employees? (10)
(b) Discuss electrical, mechanical and other hazards harmful for maintenance (10)
personnel.
Q.5 Discuss various types of chemical hazards and also explain method of (20)
controlling them.
Q.6 Discuss the safety measures to adopted under the factory act 1948 for the (20)
production of workers against fire, explosive and inflammable dust, gas etc.
Q.2 a) What is the difference between preventive and breakdown maintenance (10)
Q.5 a) Explain man-power planning and workforce control in maintenance system? (10)
Q.6 a) Explain the terms: static spares, insurance spares with and without salvage (10)
value.
b) What do you mean by Optimal overhaul and Spare parts (10)
management? Explain in brief
Q.7 a) Explain how MTTF and MTBF help in preventive maintenance (10)
management?
Q.1 a) Explain any one of the forms of business organizations with sketches (10)
b) Differentiate short term and long-term financing with case study (10)
Q.2 a) List various financial institutions and Explain role of various financial (10)
institutions in India
b) Explain tax framework and its effect on business policies (10)
Q.3 a) Discuss the significance of cost of capital and its effect on investment (10)
decisions
b) Describe working capital management and its types explain any one of the types? (10)
Q.5 a) List the different current assets and current liabilities and prepare format of (10)
Profit and loss account
b) List the different assets entities and liabilities and frame format of Balance (10)
sheet account with case study
Q.6 a) Explain operating cycle of business and its effects on inventory (10)
(b) Discuss significance of financial ratios. (10)
Q.7 a) Explain various types of borrowings and interest rates? (10)
b) Draw Cash flow diagram with formulae of the following criteria (10)
(i) Present worth (ii) Future value with usual notations
INDIAN INSTITUTION OF INDUSTRIAL ENGINEERING
GRADUATESHIP EXAMINATION
Internal Assignment for October -2023
Section-B
IEE10: TOTAL PRODUCTIVITY MANAGEMENT &
BUSINESS PROCESS RE-ENGINEERING
Max. Marks: 140
Instruction: All questions are compulsory.
b) During last three months, a firm spent Rs. 6,000 on wages paid to (10)
workers, Rs. 3,000 on procurement of material including the cost of
material, and Rs. 300 on energy expenditures. Firm made capital
expenditure of Rs. 4,000 and other miscellaneous expenses Rs. 500.
It got revenues worth Rs. 16,000. Determine Labour, Capital, Material
and Energy productivities. Also determine the Total productivity.
Q.2 a) Explain the strategic, corporate, and annual productivity plans. (10)
b) How do the trade unions influence the welfare and productivity of an (10)
organization?
Q.3 a) Discuss the challenges faced while implementing total productivity (10)
management?
Q.1 a) How the simulation software’s can be used in the domain of new (10)
process/assembly line design and development?
b) How the simulation software’s can be used for inventory management (10)
problems. Comment on the scope and type of inventory problems we can
model and simulate.
Q.3 a) With suitable example, explain any inventory classification method. (10)
Q1 a) What is Break even analysis? Discuss the importance of a breakeven point? (10)
b) Explain the difference between "Feasibility Report” and "Project Report". (10)
Q2 a) Discuss the salient features of present industrial policy of Govt of India? (10)
b) List and explain the different factors contributing to the failure of (10)
entrepreneurial ventures?
Q6 a) What is the difference between capital funding and operation funding in the (10)
business? What is different source of funds for small business?
b) What are different types of inventory small manufacturing firms can hold? (10)
How can the entrepreneur decide how much to order and when to order?
Q.7 a) What is an entrepreneurial decision process? Explain in detail the various (10)
stages involved in this process.
b) Explain various types of small industries. Also explain their characteristics. (10)
INDIAN INSTITUTION OF INDUSTRIAL ENGINEERING
GRADUATESHIP EXAMINATION
Internal Assignment for October-2023
Section-B
Q.1 a) Define material management. Explain the function of material manager. (10)
b) Write a short note on JIT philosophy and its impact on management. (10)
Q.3 a) What is procurement cycle? Briefly explain different steps of a purchase (10)
cycle.
b) What is EOQ? What are the costs associated with EOQ? Explain with graph. (10)
Q.5 a) Explain the MRP in detail with the use of suitable example. (10)
b) What do you mean by demand forecasting and its type? Discuss any one in (10)
detail.
Q.1 a) Explain the term 'Green House Effect'. What are its causes and why it is being (10)
debated?
b) In what way do our changing lifestyles and consumption patterns lead to (10)
biodiversity loss?
Q.2 a) Differentiate between short term and long-term impact of global climatic (10)
changes.
Q.3 a) Why we need water preservation? Write methods for water preservation. (10)
Q.4 a) With example, state and explain the application of Chemical Sensor? (10)
Q.5 a) Discuss the salient features of present industrial policy and economic (10)
environment of our country?
Q.7 a) What are the benefits of Environmental Impact Assessment (EIA)? Describe (10)
the process of EIA.
Q.1 a) What do you mean by Human resource planning and development? State its (10)
objectives.
b) Explain different theories of motivation? (10)
Q.2 a) What is career planning? Explain the objectives of career planning. (10)
b) Explain the upskilling of employee is related to promotion. (10)
Q.3 a) Define training and what are the strategies deployed for orienting new employees. (10)
b) Explain the need for performance evaluation and appraisal. (10)
Q.4 a) Differentiate between Strategic Planning and Human Resource Planning. (10)
b) What do you mean by succession planning? What are the seven steps to (10)
succession planning?
Q.5 a) Define quality circles. State its benefits and limitation in a organizations. (10)
b) What is promotion? Discuss various basis of promotion. (10)
b) What do you understand by Job Evaluation? What are its objectives? (10)
INDIAN INSTITUTION OF INDUSTRIAL ENGINEERING
GRADUATESHIP EXAMINATION
Internal Assignment for October-2023
Section-B
IEE 16: PROJECT MANAGEMENT
Max. Marks: 140
Instruction: All questions are compulsory.
Q.1 a) What are the different types of contracts? State the salient features of the (10)
contracts.
Q.2 a) With suitable flow chart, explain the various phases of project management. (10)
b) What is social cost benefit analysis (SCBA)? Explain the need of SCBA in (10)
appraising the projects.
Q.3 a) What is the criteria for selecting good forecasting method? Explain any two (10)
methods of demand forecasting.
Q.4 a) Briefly discuss various types of financing estimates as used in costing and (10)
pricing of project.
b) What are the criteria used for selecting contractors in projects? How do they (10)
monitor contracts?
Q.5 a) What is 'Project Cost Management'? Explain the various processes involved in (10)
Project Cost Management process.
Q.6 a) What is PERT technique in scheduling? Explain three-time estimates used in (10)
PERT technique.
Q.1 a) Explain the construction and working of a torque converter with a sketch. (10)
b) Explain the construction and working of a constant mesh gearbox with a sketch. (10)
Q.2 a) Draw a layout of hydraulic front disc brakes and rear drum brakes for a car and (10)
explain its working.
b) Draw a neat sketch and explain the working of a rack and pinion steering gearbox. (10)
Q.3 a) What do you understand by independent suspension system? Explain the working of (10)
wishbone type of a suspension system with a sketch.
Q.6 a) Explain the working of an electronic spark control system with its circuit diagram. (10)
b) Explain the working of an engine coolant temperature sensor and electronic fuel (10)
injector.
Q.7 a) Explain the working of an alternator with its circuit diagram. (10)
b) Give troubleshooting for a transmission system. (10)