2016PSMelements ProcessSafetyProgress
2016PSMelements ProcessSafetyProgress
net/publication/299591559
CITATIONS READS
8 3,265
3 authors:
Risza Rusli
Universiti Teknologi PETRONAS
54 PUBLICATIONS 813 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
Task Specific Transition Temperature Mixtures Based on Potassium Carbonate: New Solvents for CO2 Capture View project
All content following this page was uploaded by Hanida Abdul Aziz on 12 January 2018.
OSHA PSM standard has been established with 14 ele- astrophic releases of toxic, reactive, or flammable chemicals
ments that define the management principles to control pro- from a covered process that deal with any of the 137 HHC
cess hazards and protect the workplace. One of the key as per the listed quantities of Appendix A of the regulation,
factors to the success of Process Safety Management (PSM) it also includes flammable liquids and gases in quantities of
implementation is that each element comes as a component 10,000 pounds or more in one location. It also applies to
in an integrated PSM program. Although various kind of pyrotechnics and explosives manufacturers covered under
integrated safety management systems have been introduced, OSHA rules and has special provisions for contractors work-
direct integration system between PSM elements was not ing in covered facilities [4,5]. Outside the United States, Euro-
extensively studied due to vague concept on interrelation pean Union adopted EC Seveso Directive II or Control of
between PSM elements. This also hampers efforts in designing Major Accident Hazards (COMAH) Regulations in United
and developing integrated system for PSM. In this study, the Kingdom which has similar purpose to OSHA PSM [6].
interrelation of critical PSM elements was analyzed based on PSM regulation has been established with the interrelated
objectives and information functional of the elements stipu- elements that define the management principles. Whereby,
lated in OSHA PSM regulations. From the conducted analy- change information of one PSM element may effects the
sis, all the critical elements are interrelated at least with other interrelated elements. For example, pilot studies indi-
other seven PSM elements. Among the elements, Process Haz- cate that higher yields can be obtained by maintaining higher
ard Analysis and Mechanical Integrity were identified to temperatures in a reaction vessel. A change in operating tem-
have the highest interrelations comprising of 12 interrelated perature must be approved by all technical and supports
PSM elements. The developed PSM matrix has systematically functions through Management of Change (MOC) process.
showed the interrelation of critical PSM elements that useful The impact of this change is assessed through revision of
for the development of Integrated PSM system. VC 2016 American
Process Hazard Analysis (PHA), which results in a recom-
Institute of Chemical Engineers Process Saf Prog 000: 000–000, 2016 mendation to modify the pressure relief system. The modifi-
Keywords: process safety management; PSM elements; cations in temperature and pressure system mandate new
OSHA PSM; process safety; interrelations of PSM element steps for process operators through Operating Procedures
(OP), who require Training (TNG) and verification in the
INTRODUCTION new procedures [5]. Therefore, change of process safety data
Large-scale accidents like those in Flixborough (1974), should be captured, managed, and communicated efficiently
Saveso (1976), and Bhopal (1984) caused much grief and are in order to avoid major safety and regulatory implications
major tragedies that have forever altered the process industry [7,8].
landscape and have led to widespread changes in regulations One of the key factors to the success of PSM implementa-
and development of standards and safety management sys- tion is that each element comes as a component in an inte-
tems [1,2]. In response to these accidents, US Occupational grated PSM program [5,9]. A concept that has combined
Safety and Health Administration (OSHA) enacted Process plant reliability programs with PSM efforts, with a focus on
Safety Management (PSM) requirements in the Code of Fed- Mechanical Integrity (MI) program has been developed. The
eral Regulations (CFR) Chapter 29, Section 1910.119, titled steps include identifying safety-critical equipment, ensuring
Process Safety Management of Highly Hazardous Chemicals accurate and up-to-date Process Safety Information (PSI),
(HHC). It was developed through OSHA rulemaking process establishing the MI program, establishing planned mainte-
which includes robust stakeholder involvement. The notice nance programs, and creating equipment-specific mainte-
of proposed rulemaking invited comments on any aspect of nance procedures. Inherent in the approach is adequate
the proposed PSM requirements. In response to the pro- understanding and sharing of critical PSI between the PSM
posed rulemaking, OSHA received more than 175 comments, elements including PHA, MOC, Pre-startup Safety Review
4,000 pages of testimony, and almost 60 posthearing com- (PSSR), and OP besides adherence to the Operational Disci-
ments [2,3]. The purpose of the 14 elements regulation plines (OD) requirements. By combining these reliability and
(Table 1) is to prevent or minimize the consequences of cat- safety efforts, the maintenance, operations, engineering, and
safety groups will speak the same equipment reliability and
integrity language, thus minimizing the overall business risk
C 2016 American Institute of Chemical Engineers
V [10]. Vaughen and Muschara (2011) recommended linking
2 Month 2016 Published on behalf of the AIChE DOI 10.1002/prs Process Safety Progress (Vol.00, No.00)
Figure 1. PSM matrix for critical PSM elements.
Table 4. Interrelations of PSI element [3–5,7,17]. The outcome of analysis on interrelation of PHA element
with other PSM element is tabulated in Table 5. The objec-
tive of PHA is to determine areas of exercise risk where pre-
PSM Interrelates
ventive and mitigative measures may be warranted to better
Element Element Details
control the hazards [5]. Thus, adequate and accurate informa-
PSI EP Process chemicals, technology tion from PSI, Trade Secret (TS), previous MOC and reported
and equipment information Incident Investigation (II) must be available to support PHA
should be accessible to all exercises. The outcomes from PHA should be communicated
affected personnel to all affected employers, thus they shall be used in other
PHA The compilation of written PSI program including OP, TNG, MI, Contractor (CON), and ERP
should be completed before [[3–5,17,19]]. PHA has direct application for identifying chem-
conducting any PHA ical process hazards which is useful in support of emergency
OP Update PSI information may planning program. They should be used whenever possible
result in changes to the written to satisfy all PSM program requirements [5]. The recommen-
OP and SWP dations from PHA require careful resolution and may repre-
TNG Update PSI information may sent changes to process chemicals, technology and
result in changes to the TNG equipment, standard procedures, as well as MI program.
contents for plant personnel Thus, MOC and PSSR may need to be performed prior to
MOC Change to PSI except for RIK changes [7].
must undergo MOC process As presented in Table 6, OP element has the interrelations
CON Process chemicals, technology with Employee Participation (EP), PSI, PHA, TNG, MI, MOC,
and equipment information CON, HWP, II, Compliance Audit (CA), and TS elements. OP
should be accessible to all
is an important element for achieving safe, consistent, and
affected contractor workers
efficient process operation. OP must discuss operating limits,
HWP Information of process chemi-
the consequences of deviating from these limits and recovery
cals and equipment involving
from deviation. OP must address normal, abnormal, and
in process should be accurate
to ensure save hot works emergency conditions to prepare workers for any event that
ERP PSI is referred to construct may reasonably occur. Adequate technical and administrative
emergency response planUp- information from PSI, PHA, TS, and reported II are vital to
date PSI information may result support the preparation of OP [3–5,7,17]. High quality proce-
in changes to the emergency dures alone achieve nothing unless the plant personnel and
plans or procedures contractor workers are trained in their use. Thus, a close
CA PSI documentation should be relationship exists between OP and TNG element. Estab-
assessed during audit process lished OP shall be used in other program including EP, TNG,
TS Any related information neces- MI, HWP, CON, and ERP. Besides that, proposed change in
sary to comply with PSI should OP requires a critical and technical soundness justification.
be available for compilation Thus, MOC needs to be performed to manage and control
the change appropriately [3,17,19,20].
From the analysis on the interrelation of TNG element, it
is found that TNG has the interrelations with EP, PSI, OP, MI,
is predicated on a framework of information systems that CON, II, and CA elements (Table 7). All plant personnel
was used to document and communicate essential PSI across involved in operating and maintaining the process must be
the organization [18]. trained to ensure safe operations. This requirement is catered
Process Safety Progress (Vol.00, No.00) Published on behalf of the AIChE DOI 10.1002/prs Month 2016 3
Table 5. Interrelations of PHA element [3–5,7,17].
PSM Interrelates
Element Element Details
PHA EP PHA outcomes and resolution of recommendation should be informed to affected personnel
PHA activities must be conducted by a PHA team with specific expertise
PSI Up-to-date PSI is vital to conduct PHA in order to draw accurate conclusions about the
present process hazards and risks
OP Identified process hazards should be included in the written operating procedures as a
warnings and cautions
TNG The content of training module for plant personnel involved in operating the process
should include information of identified process hazards from PHA
MI The content of training module for maintenance personnel should include information of
the identified hazards from PHA
Resolution of recommendations made from PHA may require update in ITPM program
MOC MOC documentation is often reviewed during PHA revalidations to determine what
changes warrant study during the revalidation
Resolution of recommendations made from PHA may require use of the MOC process
CON PHA outcomes and resolution of recommendation should be informed to affected con-
tractor workers
II Reports from previous accidents are reviewed during PHA revalidations
Investigation process for process safety accident may require PHA to be performed as
part of the process
ERP Hazards scenarios identified in the PHA should be considered in ERP program
CA PHA information and documentation should be assessed during audit process
TS Any related information should be available to those involving in the development of
PHA if necessary
PSM Interrelates
Element Element Details
OP EP Written OP should be accessible to all affected personnel to perform their jobs safely
The plant operators and maintenance personnel often initiate the safe work practices
PSI The knowledge and technical information are used in the development of OP (i.e., save
upper and lower operating limits)
PSI should be reflected accurately in the written OP
PHA Written OP of each operating phases should include steps to avoid the hazards and con-
sequences of deviations identified during the PHA
TNG Plant personnel should be trained thoroughly in the content of OP
MI Maintenance personnel should be trained thoroughly in the content of OP
MOC Change to OP except for RIK must undergo MOC process
CON Written OP should be accessible to all affected contractor workers
HWP The SWP or nonroutine procedures must be in place for hot work activities
II The findings of incident investigation may result in changes to the written OP
CA OP-related information and documentation should be assessed during audit process
TS Any related information should be available to those involving in the development of OP
if necessary
through the linkage with the implementation EP and CON for process safety-related reasons. Therefore, cross checking
programs [4]. TNG must result in plant personnel understand- of information pertaining PSI, PHA, OP, TNG, MI, and MOC
ing of chemical hazards and the controls, proper procedures, elements is essential as process conformation [3–5,17,21].
safe operating limits and how to avoid unsafe conditions, Rashid et al. (2013) has emphasized that PSSR must be con-
how to respond to upset and emergency conditions, and ducted before the installation of facility. If not, it becomes dif-
opportunities available for plant personnel to contribute of ficult to implement the PSSR recommendations after facility
process safety improvements [3–5]. Thus, development of installation as the items have not been agreed upon at the
TNG program is highly depended with PSI, OP, PHA, MI, and time of contract. As a consequence, complete safety consider-
reported II to achieve the above necessities. Any changes of ations also cannot be confirmed of new facilities or modified
the information from these elements may reflect in update or as recommended by OSHA. On top of that, PSSR information
additional TNG program [4,5,17]. and resolution must be made available throughout affected
Details interrelation of PSSR element with other OSHA PSM plant personnel and contractor’s workers. This is to ease their
elements is shown in Table 8. The purpose of PSSR is to job and the safety of process depends on making sure that
ensure the readiness of new or modified process especially the workers were accessible to accurate PSSR [21].
4 Month 2016 Published on behalf of the AIChE DOI 10.1002/prs Process Safety Progress (Vol.00, No.00)
Table 7. Interrelations of TNG element [3–5,17].
PSM Interrelates
Element Element Details
TNG EP All the plant personnel involved in operating a process of covered area should be trained
in overview of the process, operating procedures, safety and health hazards, emergency
operations, and safe work practices applicable to their job tasks.
Training materials, training schedule, and training record should be accessible to all
affected plant personnel
Employer should acquire consultation from plant personnel on frequency of operational
training
PSI The content of training module for plant personnel involved in operating the process are
developed utilizing data from PSI
OP The OP should form the technical basis for the training and qualification program of plant
personnel
MI The maintenance personnel should be thoroughly trained in the contents of the corrective
and preventive maintenance procedures
There are several speciality training and qualification needs that should be obtained to
support MI activities such as welding, pressure vessel, tank and piping inspections, non-
destructive testing, vibration monitoring, etc.
CON Contractor workers should be trained prior to perform the work they are hired to do
II The findings of incident investigation may result in change to the training content and
increasing the frequency of refresh training
Plant personnel should be trained in the lessons learned from investigations
CA TNG-related information and documentation should be assessed during audit process
PSM Interrelates
Element Element Details
PSSR EP PSSR information and resolution of recommendation should be accessible to all affected
plant personnel
PSI Review and confirm construction and equipment is in accordance with design specifica-
tions prior to startup of a change or new process
PHA Review and confirm that PHA has been done for new process
Review and confirm that recommendation from conducted PHA has been completed prior
to startup of a change or new process
OP Review and confirm safety, operating and emergency procedures are in place, and
adequate prior to startup of a change or new process
TNG Review and confirm that training of affected personnel has been completed prior to
startup of change or new process
MI Review and confirm that maintenance procedures are in place and adequate prior to
startup of a change or new process
MOC Review and confirm that modified process meet the requirements contained in MOC
CA PSSR information and documentation should be assessed during audit process
MI universally recognized as one of the most impactful tion should be communicated to all affected employers, thus
elements of a facility’s PSM program. Some might view it to they shall be used in other program including EP and CON
operate in its own separate universe, however, in reality its elements. Managing equipment deficiency may require
importance to and interrelationships with other PSM ele- changes to the process equipment, as well as ITPM program.
ments are unquestioned [11]. Table 9 tabulates the interrela- Thus, MOC and PSSR may need to be performed prior to
tion between MI element and other PSM elements. The changes.
purpose of MI element is to ensure the integrity and safe Interrelation of MOC element with other PSM elements is
operation through inspection and maintenance program and presented in Table 10. In PSM, anytime that process chemi-
QA. Equipment in contact with HHC forms the first line of cals, equipment, technology, or facilities are intended to be
defense in preventing uncontrolled catastrophic HHC release. changed, MOC requires procedures that guarantee advance
The second line of defense is typically a combination of con- consideration of impacts and approval of that change. There-
tainment and safety system. The MI program must ensure fore, up-to-date PSI and PHA outcomes are vital in order to
that components in both primary and secondary lines of address the technical soundness of proposed change and
defenses are designed, installed, and operated properly. assess the potential safety and health impact. Once the pro-
Thus, development of MI program must be supported with posed change is approved, the PSI, PHA, OP, TNG, and MI
accurate and up-to-date information from PSI, PHA, OP, elements must be considered and addressed whenever a
TNG, PSSR, II, and ERP elements [4,5,10,17,22]. MI informa- change is made to the PSM-covered process [3–5,23]. On the
Process Safety Progress (Vol.00, No.00) Published on behalf of the AIChE DOI 10.1002/prs Month 2016 5
Table 9. Interrelations of MI element [4,5,10,17,22].
PSM Interrelates
Element Element Details
MI EP MI procedures, ITPM, and equipment deficiency information should be accessible to all
affected plant personnel
PSI The ITPM procedures and program relies heavily on the data from PSI specifically RAGAGEP
PSI is referred for the development of training module for maintenance personnel
PHA In addition to the equipment that required in the MI program by the governing regula-
tion, the selection of equipment to be included in the MI program should also rely on
the identified PHA, that the failure could contribute to a process safety accidents and the
action to add protective equipment to serves as a safeguard against such accidents
OP Placing the process in the appropriate mode of operation to support maintenance activity
requires the use of correct OP
TNG All the maintenance personnel involved in maintenance activities of covered area should be
trained in overview of the process, maintenance procedures, ITPM procedures, operating
procedures, safety and health hazards, emergency operations, and safe work practices
applicable to their job tasks
PSSR Verifying equipment under MI program should be installed according to plan, standards,
etc. before start-up
MOC Managing equipment deficiency may require the use of MOC
CON MI procedures, ITPM, and equipment deficiency information should be accessible to all
affected contractors workers
II The findings of incident investigation may result in changes to the MI program
ERP Equipment relied upon in the emergency response plan should be maintained as part of
the MI program
CA MI information and documentation should be assessed during audit process
PSM Interrelates
Element Element Details
MOC EP Approved change of process should be notified to all affected personnel prior to start-up
PSI Up-to-date PSI is required to support the generation of MOC in order to address the tech-
nical soundness of proposed change and assess the potential safety and health impact
PSI must be updated accordingly if process change results in a change of PSI
PHA While not mandatory, PHA may be performed to assess the impact of proposed change
on process safety
OP OP must be updated accordingly if process change results in a change of OP
TNG Plant personnel should be trained in the process change if the job tasks will be affected
by a change prior to start-up of the process
MI Maintenance personnel should be trained in the process change if the job tasks will be
affected by a change prior to start-up of the process
PSSR PSSR recommendation must be resolved prior to start-up in change
CON Contractor workers should be informed and trained in change prior to start-up with the
change in place if necessary
CA MOC information and documentation should be assessed during audit process
other hand, PSSR element is important in MOC after a pro- significantly interrelated with other PSM elements. The devel-
cess has been modified or shut down prior to ensure the oped PSM matrix has showed the interrelation between PSM
readiness. Approved changes should be communicated to all elements in structured manner and provides the flow of pro-
affected employers, thus they shall be used in other program cess safety data. As PSM program is poor without good com-
including EP and CON elements. MOC, when put in effect in munication and coordination among elements, the use of
isolation its benefit will not fully materialize. integration system to implement PSM becomes a possible
Finally, PSI, PHA, OP, TNG, PSSR, MI, and MOC programs approach in improving the effectiveness of implementation
will be assessed through CA element (Tables (4–10) to see PSM program from this perspective. At this point, informa-
whether the management system in place adequately tion of interrelation between the elements would be useful
addresses all the above PSM elements requirements [4,17]. to guide PSM data linkages that eases the data sharing in the
development of integration system which resulting up-to-
CONCLUSION date and consistent PSM data of any update. This is neces-
Analysis of interrelation between PSM elements showed sary to prevent safety implication and assist organizations
that PSI, PHA, OP, TNG, PSSR, MI, and MOC elements have compliance with the OSHA PSM regulation.
6 Month 2016 Published on behalf of the AIChE DOI 10.1002/prs Process Safety Progress (Vol.00, No.00)
12. J.A. Klein and B.K. Vaughen, A revised program
LITERATURE CITED for operational discipline, Process Saf Prog 27 (2008), 58–
1. J. Atherton and F. Gil, Incidents that Define Process 65.
Safety, Wiley, New Jersey, 2008. 13. L.A. Long, M.L. Marshall, and J. Lay, Update on OSHA’s
2. L.A. Long, History of Process Safety at OSHA, Process Saf PSM national emphasis programs, Process Saf Prog 30
Prog 28 (2009), 128–130.
(2011), 303–306.
3. CCPS, Guidelines for Risk Based Process Safety, Wiley,
New Jersey, 2007. 14. H. Luo, The effectiveness of U.S. OSHA process safety
4. U.S. Occupational Safety and Health Administration management inspection - A preliminary quantitative eval-
(OSHA). OHSA Law & Regulations, 2011, Available at uation, J Loss Prev Process Ind 23 (2010), 455–461.
http://www.osha.gov/law-regs.html, Accessed on Decem- 15. B.A. Schuldt, Concept matrix approach to teaching man-
ber 20, 2014. agement information systems, J Learn Higher Educ 1
5. Department of Energy, Process Safety Management for (2005), 11–16.
Highly Hazardous Chemicals, US DOE, Washington, 1996. 16. R. Klopper and S. Lubbe, The matrix method of literature
6. A.C. Brackey, Process safety management: 21 Years plus or review, Alternation 14 (2007), 262–276.
minus what i wish i’d known then and what we can’t afford 17. CCPS, Guidelines for Auditing Process Safety Manage-
to forget now! Process Saf Prog 32 (2013), 260–263. ment Systems, 2nd Edition, Wiley, New York, 2011.
7. M.I. Rashid, N. Ramzan, T. Iqbal, S. Yasin, and S. Yousaf, 18. M. Alloco, Safety Analyses of Complex Systems: Consid-
Implementation issues of PSM in a fertilizer plant: An erations of Software, Firmware, Hardware, Human, and
operations engineer’s point of view, Process Saf Prog 32 the Environment, Wiley, Hoboken, NJ, 2010.
(2013), 59–65. 19. J.F. Louvar, Improving the effectiveness of process safety
8. K. Hanchey and J.R. Thompson, The challenge to imple- management in small companies, Process Saf Prog 27
ment and maintain an effective PSM program, Process Saf (2008), 280–283.
Prog 30 (2011), 319–322.
20. D.J. Leggett, Process safety in the future - A view from
9. CCPS, Guideline for Process Safety Documentation,
AIChE, New York, 1995. the chemistry, Process Saf Prog 23 (2004), 163–169.
10. B.K. Vaughen, J.F. Nagel, and M.J. Allen, Integrate plant 21. CCPS, Guidelines for Performing Effective Pre-Startup
reliability efforts with mechanical integrity, Process Saf Safety Review, Wiley, New Jersey, 2007.
Prog 30 (2011), 323–327. 22. CCPS, Guidelines for Mechanical Integrity Systems, Wiley,
11. C. Reese and B. Taylor, Surviving and thriving in the era New Jersey, 2006.
of enhanced OSHA PSM audits, Hydrocarbon Process 91 23. CCPS, Guidelines for Management of Change for Process
(2012), 47–48. Safety, Wiley, New Jersey, 2008.
Process Safety Progress (Vol.00, No.00) Published on behalf of the AIChE DOI 10.1002/prs Month 2016 7