MS Project - Assign Resources To Task - Tutorialspoint

This document describes four methods for assigning resources to tasks in Microsoft Project. Resources can be material resources or cost resources. Material resources are people assigned to work on and complete tasks. Cost resources track expenses associated with tasks. The methods include assigning resources via the Gantt chart view, resource tab, task information dialog box, and task form view. Multiple resources can be assigned to a single task to work on it or track costs.

Uploaded by

Rafael Obusan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
67 views4 pages

MS Project - Assign Resources To Task - Tutorialspoint

This document describes four methods for assigning resources to tasks in Microsoft Project. Resources can be material resources or cost resources. Material resources are people assigned to work on and complete tasks. Cost resources track expenses associated with tasks. The methods include assigning resources via the Gantt chart view, resource tab, task information dialog box, and task form view. Multiple resources can be assigned to a single task to work on it or track costs.

Uploaded by

Rafael Obusan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

12/5/2019 MS Project - Assign Resources to Task - Tutorialspoint

MS Project - Assign Resources to Task

Once the task and resource list are complete, resources need to be assigned to tasks in order to work
on them. With MS Project you can track task progress, resource and tasks costs.

Assign Material Resource to Task

Method 1

Click View Tab → Gantt Chart View → Resource Name column.

Click the box below the Resource Name column for the task you need the resource to be assigne

From the dropdown, choose the resource name. In the following screenshot as an
example. For Task 1 “PT1”, we have chosen the resource “Celic”.

You can also select multiple resources to work on a single task.

Method 2

Click Resource tab → Under Assignments group → Assign Resources.

In the Assign Resources dialog box, click the resource name you like to assign.

Here let’s choose “Hitesh”. Now click the Assign button.

You can also select multiple resources to work on a single task.

https://www.tutorialspoint.com/ms_project/ms_project_assign_resources_to_task.htm 1/4
12/5/2019 MS Project - Assign Resources to Task - Tutorialspoint

Method 3

Click View Tab → Gantt Chart → Task Name column.

Double-click the Task Name. Task Information dialog box opens.

Click the Resources tab.

Click the cell below the Resource Name column. Select the resource from the dropdown list.

You can also select multiple resources to work on a single task.

Method 4

https://www.tutorialspoint.com/ms_project/ms_project_assign_resources_to_task.htm 2/4
12/5/2019 MS Project - Assign Resources to Task - Tutorialspoint

Click View Tab → Split View group → Details → Task Form.

The window is split in two, Gantt Chart view and Task Form view below it.

In the Task Form view, click under the Resource Name column and select the resource.

You can also select multiple resources to work on a single task.

Assign Cost Resource to Tasks

Click View Tab → Gantt Chart View → Task Name column.

Double-click the Task Name. Task Information dialog box opens.

Click the Resources tab.

Click the cell below the Resource Name column. Select the resource from the dropdown list.

In the following example below, let’s choose “Travel” as cost resource and enter the cost at $800.
We can also assign other material resources to the same task.

https://www.tutorialspoint.com/ms_project/ms_project_assign_resources_to_task.htm 3/4
12/5/2019 MS Project - Assign Resources to Task - Tutorialspoint

https://www.tutorialspoint.com/ms_project/ms_project_assign_resources_to_task.htm 4/4