MS Project - Assign Resources To Task - Tutorialspoint
MS Project - Assign Resources To Task - Tutorialspoint
Once the task and resource list are complete, resources need to be assigned to tasks in order to work
on them. With MS Project you can track task progress, resource and tasks costs.
Method 1
Click the box below the Resource Name column for the task you need the resource to be assigne
From the dropdown, choose the resource name. In the following screenshot as an
example. For Task 1 “PT1”, we have chosen the resource “Celic”.
Method 2
In the Assign Resources dialog box, click the resource name you like to assign.
https://www.tutorialspoint.com/ms_project/ms_project_assign_resources_to_task.htm 1/4
12/5/2019 MS Project - Assign Resources to Task - Tutorialspoint
Method 3
Click the cell below the Resource Name column. Select the resource from the dropdown list.
Method 4
https://www.tutorialspoint.com/ms_project/ms_project_assign_resources_to_task.htm 2/4
12/5/2019 MS Project - Assign Resources to Task - Tutorialspoint
The window is split in two, Gantt Chart view and Task Form view below it.
In the Task Form view, click under the Resource Name column and select the resource.
Click the cell below the Resource Name column. Select the resource from the dropdown list.
In the following example below, let’s choose “Travel” as cost resource and enter the cost at $800.
We can also assign other material resources to the same task.
https://www.tutorialspoint.com/ms_project/ms_project_assign_resources_to_task.htm 3/4
12/5/2019 MS Project - Assign Resources to Task - Tutorialspoint
https://www.tutorialspoint.com/ms_project/ms_project_assign_resources_to_task.htm 4/4