This document provides calculations for materials needed for a building demolition and foundation construction project. It calculates the quantities of cement, fine aggregates, and coarse aggregates needed for blinding concrete for pad footings and strip footings. The calculations determine that 891 bags of cement, 62.045 tonnes of fine aggregates, and 152.727 tonnes of coarse aggregates will be required.

Uploaded by

James Aswa
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
923 views8 pages

Material Schedule Calculation Sheet

This document provides calculations for materials needed for a building demolition and foundation construction project. It calculates the quantities of cement, fine aggregates, and coarse aggregates needed for blinding concrete for pad footings and strip footings. The calculations determine that 891 bags of cement, 62.045 tonnes of fine aggregates, and 152.727 tonnes of coarse aggregates will be required.

Uploaded by

James Aswa
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 8

ELEMENT 1 SUB-STRUCTURE

A Demolition and Site clearance


LENGTH WIDTH
BUIDING DIMENSIONS 15.7 12.275

Add an offset of 3m from all sides


of the building line for clearance 18.7 15.275
2
Removal of topsoil 285.6425 m
2
Preservation of topsoil 285.6425 m
Reduction of levels at 100mm 19.27175 m3
3
Disposal of reduction materials 19.27175 m

B Setting out of the building


make an offset of 1.2m from all
sides of the building line for the
profileboard
Pegs 45 pcs
softwood 20 pcs
Nails kg
Rolls of line Rolls
Ash Tin

C Excavation works
excavation of column bases
according to structural drawings to
a depth not less than 1200mm to
receive blinding for pad
3
foundaation 12 m
excavation of strip footing 690mm
wide and 950mm deep to receive
3
mass concrete 14 m

D concrete works
cement F.A C.A
provision of concrete for
bllinding of ratio; 1 1.5 3
3
total volume of blinding 100 m

CEMENT
3
density 1400 kg/m
3
volume 1m
mass 1400 kg
weight of 1 bag of cement 50 kg
implying 1m3 of cement contains 28 bags of cement

Page 1 of 8
3
total volume ratio 5.5 m
shrinkage 40 %
3
volume of wet concrete 3.3 m
3
implying 1m of concrete contains 8.48 bags of cement
wastage 5%
3
if we add wastage, implying 1m of
concrete contains; 8.9090909 bags of cement

therefore for the blinding works for


pad footing and strip footing, we
require; 891 bags of cement

FINE AGGREGATES
3
density 1300 kg/m
3
volume 1.5 m
mass 1950 kg

3
total volume ratio 5.5 m
shrinkage 40 %
3
volume of wet concrete 3.3 m
implying 1m3 of concrete contains 590.91 kg of F.A
wastage 5%
if we add wastage, implying 1m3 of
concrete contains; 620.45455 kg of F.A

therefore for the blinding works for


pad footing and strip footing, we
require; 62.045 tonnes of F.A Using a truck of say 4 tonnes
then we would convert it into trips
COARSE AGGREGATES
3
density 1600 kg/m
3
volume 3m
mass 4800 kg

3
total volume ratio 5.5 m
shrinkage 40 %
3
volume of wet concrete 3.3 m
implying 1m3 of concrete contains 1454.55 kg of C.A
wastage 5%
if we add wastage, implying 1m3 of
concrete contains; 1527.2727 kg of C.A

Page 2 of 8
therefore for the blinding works for
pad footing and strip footing, we
require; 152.727 tonnes of C.A Using a truck of say 4 tonnes
then we would convert it into trips
cement F.A C.A
provision of concrete for Pad
footing of ratio; 1 1.5 3
3
total volume of blinding 100 m

CEMENT
3
density 1400 kg/m
3
volume 1m
mass 1400 kg
weight of 1 bag of cement 50 kg
implying 1m3 of cement contains 28 bags of cement

3
total volume ratio 5.5 m
shrinkage 40 %
3
volume of wet concrete 3.3 m
implying 1m3 of concrete contains 8.48 bags of cement
wastage 5%
if we add wastage, implying 1m3 of
concrete contains; 8.91 bags of cement

therefore for the blinding works for


pad footing and strip footing, we
require; 891 bags of cement

FINE AGGREGATES
3
density 1500 kg/m
3
volume 1.5 m
mass 2250 kg

3
total volume ratio 5.5 m
shrinkage 40 %
3
volume of wet concrete 3.3 m
implying 1m3 of concrete contains 682 kg of F.A
wastage 5%
if we add wastage, implying 1m3 of
concrete contains; 716 kg of F.A

therefore for the blinding works for


pad footing and strip footing, we
require; 72 tonnes of F.A Using a truck of say 4 tonnes

Page 3 of 8
then we would convert it into trips
COARSE AGGREGATES
3
density 1600 kg/m
3
volume 3m
mass 4800 kg

3
total volume ratio 5.5 m
shrinkage 40 %
3
volume of wet concrete 3.3 m
3
implying 1m of concrete contains 1455 kg of C.A
wastage 5%
3
if we add wastage, implying 1m of
concrete contains; 1527.2727 kg of C.A

therefore for the blinding works for


pad footing and strip footing, we
require; 153 tonnes of C.A Using a truck of say 4 tonnes
then we would convert it into trips
cement F.A C.A
provision of concrete for strip
footing of ratio; 1 1.5 3
3
total volume of blinding 100 m

CEMENT
3
density 1400 kg/m
3
volume 1m
mass 1400 kg
weight of 1 bag of cement 50 kg
implying 1m3 of cement contains 28 bags of cement

3
total volume ratio 5.5 m
shrinkage 40 %
3
volume of wet concrete 3.3 m
implying 1m3 of concrete contains 8.48 bags of cement
wastage 5%
if we add wastage, implying 1m3 of
concrete contains; 8.91 bags of cement

therefore for the blinding works for


pad footing and strip footing, we
require; 891 bags of cement

FINE AGGREGATES
3
density 1500 kg/m

Page 4 of 8
3
volume 1.5 m
mass 2250 kg

3
total volume ratio 5.5 m
shrinkage 40 %
3
volume of wet concrete 3.3 m
3
implying 1m of concrete contains 682 kg of F.A
wastage 5%
3
if we add wastage, implying 1m of
concrete contains; 716 kg of F.A

therefore for the blinding works for


pad footing and strip footing, we
require; 72 tonnes of F.A Using a truck of say 4 tonnes
then we would convert it into trips
COARSE AGGREGATES
3
density 1600 kg/m
3
volume 3m
mass 4800 kg

3
total volume ratio 5.5 m
shrinkage 40 %
3
volume of wet concrete 3.3 m
implying 1m3 of concrete contains 1455 kg of C.A
wastage 5%
if we add wastage, implying 1m3 of
concrete contains; 1527.2727 kg of C.A

therefore for the blinding works for


pad footing and strip footing, we
require; 153 tonnes of C.A Using a truck of say 4 tonnes
then we would convert it into trips
cement F.A C.A
provision of concrete for column
dowels of ratio; 1 1.5 3
3
total volume of blinding 100 m

CEMENT
3
density 1400 kg/m
3
volume 1m
mass 1400 kg
weight of 1 bag of cement 50 kg
implying 1m3 of cement contains 28 bags of cement

Page 5 of 8
3
total volume ratio 5.5 m
shrinkage 40 %
3
volume of wet concrete 3.3 m
3
implying 1m of concrete contains 8.48 bags of cement
wastage 5%
3
if we add wastage, implying 1m of
concrete contains; 8.91 bags of cement

therefore for the blinding works for


pad footing and strip footing, we
require; 891 bags of cement

FINE AGGREGATES
3
density 1500 kg/m
3
volume 1.5 m
mass 2250 kg

3
total volume ratio 5.5 m
shrinkage 40 %
3
volume of wet concrete 3.3 m
implying 1m3 of concrete contains 682 kg of F.A
wastage 5%
if we add wastage, implying 1m3 of
concrete contains; 716 kg of F.A

therefore for the blinding works for


pad footing and strip footing, we
require; 72 tonnes of F.A Using a truck of say 4 tonnes
then we would convert it into trips
COARSE AGGREGATES
3
density 1600 kg/m
3
volume 3m
mass 4800 kg

3
total volume ratio 5.5 m
shrinkage 40 %
3
volume of wet concrete 3.3 m
implying 1m3 of concrete contains 1455 kg of C.A
wastage 5%
if we add wastage, implying 1m3 of
concrete contains; 1527.2727 kg of C.A

Page 6 of 8
therefore for the blinding works for
pad footing and strip footing, we
require; 153 tonnes of C.A Using a truck of say 4 tonnes
then we would convert it into trips
E REINFORCEMENT WORKS
G FORMWORK
H BACKFILLING AND COMPACTION
J DAMP PROOF MEMBRANE
K BRC MESH
L GROUND FLOOR SLAB
cement F.A C.A
provision of concrete for ground
floor slab of ratio; 1 1.5 3
3
total volume of blinding 100 m

CEMENT
3
density 1400 kg/m
3
volume 1m
mass 1400 kg
weight of 1 bag of cement 50 kg
implying 1m3 of cement contains 28 bags of cement

3
total volume ratio 5.5 m
shrinkage 40 %
3
volume of wet concrete 3.3 m
implying 1m3 of concrete contains 8.48 bags of cement
wastage 5%
if we add wastage, implying 1m3 of
concrete contains; 8.91 bags of cement

therefore for the blinding works for


pad footing and strip footing, we
require; 891 bags of cement

FINE AGGREGATES
3
density 1500 kg/m
3
volume 1.5 m
mass 2250 kg

3
total volume ratio 5.5 m
shrinkage 40 %
3
volume of wet concrete 3.3 m
implying 1m3 of concrete contains 682 kg of F.A
wastage 5%

Page 7 of 8
3
if we add wastage, implying 1m of
concrete contains; 716 kg of F.A

therefore for the blinding works for


pad footing and strip footing, we
require; 72 tonnes of F.A

COARSE AGGREGATES
3
density 1600 kg/m
3
volume 3m
mass 4800 kg

3
total volume ratio 5.5 m
shrinkage 40 %
3
volume of wet concrete 3.3 m
implying 1m3 of concrete contains 1455 kg of C.A
wastage 5%
if we add wastage, implying 1m3 of
concrete contains; 1527.2727 kg of C.A

therefore for the blinding works for


pad footing and strip footing, we
require; 153 tonnes of C.A

Page 8 of 8