JS Scaffolding

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 24

INVENTARISASI TANAMAN / BANGUNAN

Sheet : Of
Keperluan / Proyek :
Letak / Lokasi :
Desa : Pemilik Tanaman / Bangunan
Kecamatan :
Kabupaten : Nama :
CC / AFE No. : Alamat :
SPK No. : Hp :

Tanaman :
Klasifikasi Tanaman Jumlah
No Jenis Keterangan Tanaman
Hasil Sedang Kecil Tanaman

Bangunan :
Klasifikasi Tanaman
No Jenis Keterangan Tanama
Ukuran Luas Kondisi

Sketch / Gambar :

Dihitung Oleh, Diperiksa Oleh, Disetujui Oleh, Disaksikan Oleh Aparat

Juru hitung Surveyor Pemilik Tnm / Bang Pertanahan PT. PHR Desa
SURVEY FIELD SKETCH

Date : Location :
Job Description : Project Title :
SR No :

Checked by, Checked by, Witness by:

Drafter/instrumen-Survey PMCoW-Survey QS/CS-


PT. PERTAMINA HULU ROKAN
Construction Services Work Unit Rate Earthwork Package
Contract No :
SKETCH DRAWING (JOINT SURVEY)
Initiated Date : Location : EXISTING POLE SINTONG FEEDER
Work Title : Install Bruching power pole sintong feeder dan ketigul feeder SPK No. :

Checked by, Witness by:

QS-PDC QS-TPE
PT. PERTAMINA HULU ROKAN
Construction Services Work Unit Rate Earthwork Package
Contract No : SPHR00361A
SKETCH DRAWING (JOINT SURVEY)
Initiated Date : 03-May-23 Location : 29 AB 8
Work Title : Install Braching power pole sintong feeder dan ketigul feeder SPK No. : CCMSPHR/SPK/3700103287

SCAFFOLDING CALCULATION
SPOT L x P x T = M3

1 2.97 x 1.9 x 2.25 = 12.70 m3

2 2.97 x 3.8 x 3.05 = 34.42 m3

TOTAL = 47.12 m3

Spot 1 1.9

2.25

Spot 2
1.9

3.05

3.8
2.97

Checked by, Checked by, Witness by:

QS-PDC CS-TPE QS-TPE


PT. PERTAMINA HULU ROKAN
Construction Services Work Unit Rate Earthwork Package
Contract No : SPHR00361A
SKETCH DRAWING (JOINT SURVEY)
Initiated Date : 03-May-23 Location : 29 AC 6
Work Title : Install Braching power pole sintong feeder dan ketigul feeder SPK No. : CCMSPHR/SPK/3700103287

SCAFFOLDING CALCULATION
SPOT L x P x T = M3

1 2.92 x 1.85 x 2.4 = 12.96 m3

2 2.92 x 3.65 x 2.94 = 31.33 m3

TOTAL = 44.30 m3

Spot 1 1.82

2.4

Spot 2
1.83

2.94

3.65
2.92

Checked by, Checked by, Witness by:

QS-PDC CS-TPE QS-TPE


PT. PERTAMINA HULU ROKAN
Construction Services Work Unit Rate Earthwork Package
Contract No : SPHR00361A
SKETCH DRAWING (JOINT SURVEY)
Initiated Date : 03-May-23 Location : 29 AC 1
Work Title : Install Braching power pole sintong feeder dan ketigul feeder SPK No. : CCMSPHR/SPK/3700103287

SCAFFOLDING CALCULATION
SPOT L x P x T = M3

1 3.80 x 1.7 x 2.5 = 16.15 m3

2 3.80 x 3.5 x 2.8 = 37.24 m3

TOTAL = 53.39 m3

Spot 1 1.7

2.5

Spot 2
1.8

2.8

3.5
3.8

Checked by, Checked by, Witness by:

QS-PDC CS-TPE QS-TPE


Contractor PT.PDC
SPK No. CCMSPHR/SPK/3700103287

Scaffolding Report - Summary


Work Title Power pole Braching Installation at Ketigul and
Sintong Feeder
PHR User Chandra Sitorus / Misli
TPE CS Yudhi Novarse

Actual Scaffolding Installed


Billable Qty
No. Spot/Location ID Duration Description
Length wide Hight Volume (m3) Typical Total (m3days)
(days) (m3days)
3.00 1.50 3.50 15.75 1.00 5 78.75 78.75
1 28 AB 8 B Take measure, Welding, Penetran, Painting
3.00 4.00 2.90 34.80 1.00 5 174.00 174.00
2.85 2.70 3.80 29.24 1.00 5 146.21 146.21
2 28 AB 11 B Take Measure, Welding, Penetran, Painting
2.85 3.90 2.73 30.34 1.00 5 151.72 151.72
3.86 1.40 2.96 16.00 1.00 5 79.98 79.98
3 29 AB 15 Take measure, Fit Up, Welding, Penetran & Painting
3.86 2.85 2.86 31.46 1.00 5 157.31 157.31
4.07 1.25 2.87 14.60 1.00 5 73.01 73.01
4 29 AB 17 Take measure, Fit Up, Welding, Penetran & Painting
4.07 3.07 2.73 34.11 1.00 5 170.56 170.56
2.90 1.49 2.20 9.51 1.00 5 47.53 47.53
5 29 AB 26 B Take measure, Fit Up, Welding, Penetran & Painting
2.90 3.43 2.45 24.37015 1.00 5 121.85 121.85
2.85 0.99 2.15 6.066225 1.00 5 30.33 30.33
6 29 AB 19 Take measure, Fit Up, Welding, Penetran & Painting
2.85 2.89 2.58 21.25017 1.00 5 106.25 106.25
2.95 1.2 3.00 10.62 1.00 5 53.10 53.10
7 29 AB 16 Take measure, Fit Up, Welding, Penetran & Painting
2.95 2.91 2.89 24.809205 1.00 5 124.05 124.05
2.85 1.8 1.75 8.9775 1.00 5 44.89 44.89
8 29 AA 10 Take measure, Fit Up, Welding, Penetran & Painting
2.85 3.85 3.00 32.9175 1.00 5 164.59 164.59
3.85 1.9 2.1 15.3615 1.00 5 76.81 76.81
9 29 AA 8 Take measure, Fit Up, Welding, Penetran & Painting
3.85 2.95 2.9 32.93675 1.00 5 164.68 164.68
3.92 1.72 2.75 18.5416 1.00 5 92.71 92.71
10 29 AA 1 Take measure, Fit Up, Welding, Penetran & Painting
3.92 2.95 2.75 31.801 1.00 5 159.01 159.01
Total Actual Qty 2217.32 Total Billable Qty 2217.32

Note:
1. In the event the Actual Installed Quantities are greater than the Scaffolding Plan and assuming there are no approved charges, the Billing Quantities should equal the agreed upon Scaffoldng Plan Quantities.
2. In the event the Actual Installed Quantities are less than the Scaffolding Plan and assuming there are no approved charges, the Billing Quantities should equal the agreed upon Scaffoldng Plan Quantities
3. Billable Quantities will be measured by the actual installed quantities ± any approved change.
4. Scaffolding Report - Summary should be accompanied by the Scaffolding Report-Plus any revisions and Scaffolding Report-Actual for all periods as documentation to support the summary.

Prepared by, Checked by, Reviewed by Approved by,


Quantity Surveyor PDC ECM Construction TPE ECM Quantity Surveyor TPE CPI User/Facility Representative

Name : Name : Name : Name :


Date : Date : Date : Date :
PT. PERTAMINA HULU ROKAN
Construction Services Work Unit Rate Earthwork Package
Contract No :
SKETCH DRAWING (JOINT SURVEY)
Initiated Date : 28-Apr-23 Location : 29 AB 3
Work Title : Install Bruching power pole sintong feeder dan ketigul feeder SPK No. :

SCAFFOLDING CALCULATION
SPOT L x P x T = M3

1 3.95 x 1.8 x 3 = 21.33 m3

2 3.95 x 3.07 x 2.95 = 35.77 m3

TOTAL = 57.10 m3

Spot 1 1.8

3.0

Spot 2
1.27

2.95

3.07
3.95

Checked by, Checked by, Witness by:

QS-PDC CS-TPE QS-TPE


PT. PERTAMINA HULU ROKAN
Construction Services Work Unit Rate Earthwork Package
Contract No :
SKETCH DRAWING (JOINT SURVEY)
Initiated Date : 28-Apr-23 Location : 29 AC2
Work Title : Install Bruching power pole sintong feeder dan ketigul feeder SPK No. :

SCAFFOLDING CALCULATION
SPOT L x P x T = M3

1 3.80 x 1.85 x 2.53 = 17.79 m3

2 3.80 x 2.9 x 3.5 = 38.57 m3

TOTAL = 56.36 m3
Spot 1 1.85

2.53

Spot 2
1.05

3.5

2.9
3.8

Checked by, Checked by, Witness by:

QS-PDC CS-TPE QS-TPE


PT. PERTAMINA HULU ROKAN
Construction Services Work Unit Rate Earthwork Package
Contract No :
SKETCH DRAWING (JOINT SURVEY)
Initiated Date : 28-Apr-23 Location : 29 AC 11
Work Title : Install Bruching power pole sintong feeder dan ketigul feeder SPK No. :

SCAFFOLDING CALCULATION
SPOT L x P x T = M3

1 3.84 x 1.67 x 2.9 = 18.60 m3

2 3.84 x 2.9 x 3.4 = 37.86 m3

TOTAL = 56.46 m3

Spot 1 1.67

2.9

Spot 2
1.23

3.4

2.9
3.84

Checked by, Checked by, Witness by:

QS-PDC CS-TPE QS-TPE


PT. PERTAMINA HULU ROKAN
Construction Services Work Unit Rate Earthwork Package
Contract No :
SKETCH DRAWING (JOINT SURVEY)
Initiated Date : 28-Apr-23 Location : 29 AC 12
Work Title : Install Bruching power pole sintong feeder dan ketigul feeder SPK No. :

SCAFFOLDING CALCULATION
SPOT L x P x T = M3

1 2.96 x 1.9 x 4.1 = 23.06 m3

2 2.96 x 3.6 x 3.95 = 42.09 m3

TOTAL = 65.15 m3

Spot 1 1.9

4.1

Spot 2
1.7

3.95

3.6
2.98

Checked by, Checked by, Witness by:

QS-PDC CS-TPE QS-TPE


PT. PERTAMINA HULU ROKAN
Construction Services Work Unit Rate Earthwork Package
Contract No :
SKETCH DRAWING (JOINT SURVEY)
Initiated Date : 17-Apr-23 Location : 29 AA 1
Work Title : Install Bruching power pole sintong feeder dan ketigul feeder SPK No. :

SCAFFOLDING CALCULATION
1 1.80 x 2.9 x 2.75 = 14.36 m3

2 2.90 x 2.9 x 2.95 = 24.81 m3

TOTAL 39.16 m3

Spot 1 1.8

2.75

Spot 2
2.75

2.95

2.9
2.9

Checked by, Checked by, Witness by:

QS-PDC CS-TPE QS-TPE


PT. PERTAMINA HULU ROKAN
Construction Services Work Unit Rate Earthwork Package
Contract No :
SKETCH DRAWING (JOINT SURVEY)
Initiated Date : 17-Apr-23 Location : 29 AA 8
Work Title : Install Bruching power pole sintong feeder dan ketigul feeder SPK No. :

SCAFFOLDING CALCULATION
1 1.72 x 2.88 x 3.92 = 19.42 m3

2 2.94 x 3.92 x 2.76 = 31.81 m3

TOTAL 51.23 m3

Spot 1 1.72

2.88

Spot 2
1.22

2.76

2.9
4
2
3.9

Checked by, Checked by, Witness by:

QS-PDC CS-TPE QS-TPE


PT. PERTAMINA HULU ROKAN
Construction Services Work Unit Rate Earthwork Package
Contract No :
SKETCH DRAWING (JOINT SURVEY)
Initiated Date : 13-Apr-23 Location : 29 AA 10
Work Title : Install Bruching power pole sintong feeder dan ketigul feeder SPK No. :

SCAFFOLDING CALCULATION
1 1.77 x 2.9 x 1.7 = 8.73 m3

2 2.90 x 2.9 x 3.08 = 25.90 m3

TOTAL 34.63 m3

Spot 1 1.7
7
1.7

Spot 2
3.08

2.9
2.9

Checked by, Checked by, Witness by:

QS-PDC CS-TPE QS-TPE


PT. PERTAMINA HULU ROKAN
Construction Services Work Unit Rate Earthwork Package
Contract No :
SKETCH DRAWING (JOINT SURVEY)
Initiated Date : 13-Apr-23 Location : 28 AB 8 B
Work Title : Install Bruching power pole sintong feeder dan ketigul feeder SPK No. :

SCAFFOLDING CALCULATION
1 3.0 x 1.5 x 3.5 = 15.75 m3

2 3.0 x 4 x 2.9 = 34.80 m3

TOTAL 50.55 m3

1.5
Spot 1 0
3.50

Spot 2
2.90

4.0
0
0
3.0

Checked by, Checked by, Witness by:

QS-PDC CS-TPE QS-TPE


PT. PERTAMINA HULU ROKAN
Construction Services Work Unit Rate Earthwork Package
Contract No :
SKETCH DRAWING (JOINT SURVEY)
Initiated Date : 13-Apr-23 Location : 29 AB 11 B
Work Title : Install Bruching power pole sintong feeder dan ketigul feeder SPK No. :

Spot 1 2.7
SCAFFOLDING CALCULATION
1 2.9 x 2.7 x 3.8 = 29.24 m3

2 2.9 x 3.9 x 2.73 = 30.34 m3

TOTAL 59.58 m3
3.8

Spot 2
2.73

3.9
0
5
2.8

Checked by, Checked by, Witness by:

QS-PDC CS-TPE QS-TPE


PT. PERTAMINA HULU ROKAN
Construction Services Work Unit Rate Earthwork Package
Contract No :
SKETCH DRAWING (JOINT SURVEY)
Initiated Date : 13-Apr-23 Location : 29 AB 15
Work Title : Install Bruching power pole sintong feeder dan ketigul feeder SPK No. :

SCAFFOLDING CALCULATION

Spot 1 1.4
1 3.86 x 1.4 x 2.96 = 16.00 m3

0 2 3.86 x 2.85 x 2.86 = 31.46 m3

TOTAL 47.46 m3
2.96

Spot 2
2.86

2. 8
5
6
3.8

Checked by, Checked by, Witness by:

QS-PDC CS-TPE QS-TPE


PT. PERTAMINA HULU ROKAN
Construction Services Work Unit Rate Earthwork Package
Contract No :
SKETCH DRAWING (JOINT SURVEY)
Initiated Date : 13-Apr-23 Location : 29 AB 15
Work Title : Install Bruching power pole sintong feeder dan ketigul feeder SPK No. :

SCAFFOLDING CALCULATION
1 2.95 x 1.2 x 3 = 10.62 m3

2 2.95 x 2.89 x 2.91 = 24.81 m3


Spot 1 TOTAL 35.43 m3
3

Spot 2
2.89

2.9
1
6
2.9

Checked by, Checked by, Witness by:

QS-PDC CS-TPE QS-TPE


PT. PERTAMINA HULU ROKAN
Construction Services Work Unit Rate Earthwork Package
Contract No :
SKETCH DRAWING (JOINT SURVEY)
Initiated Date : 13-Apr-23 Location : 29 AB 17
Work Title : Install Bruching power pole sintong feeder dan ketigul feeder SPK No. :

Spot 1 1.2
5 SCAFFOLDING CALCULATION
SPOT 1
4.07 M X 1.25M X 2.87M = 14.60 M3
SPOT 2
4.07M X 3.07M X 2,73M = 34,11 M3
TOTAL VOLUME
2.87

14.60M3 + 34.11M3 = 48.71 M3

Spot 2
2.73

3.0
7
7
4. 0

Checked by, Checked by, Witness by:

QS-PDC CS-TPE QS-TPE


PT. PERTAMINA HULU ROKAN
Construction Services Work Unit Rate Earthwork Package
Contract No :
SKETCH DRAWING (JOINT SURVEY)
Initiated Date : 13-Apr-23 Location : 29 AB 19
Work Title : Install Bruching power pole sintong feeder dan ketigul feeder SPK No. :

Spot 1 0.9
9 SCAFFOLDING CALCULATION
SPOT 1
2,85 M X 0,99M X 2.15M = 06,06 M3
SPOT 2
2,89M X 2,85M X 2,58M = 21,25 M3
TOTAL VOLUME
2.15

06,06M3 + 21,25M3 = 27,3 M3

Spot 2
2.58

2.8
9
5
2. 8

Checked by, Checked by, Witness by:

QS-PDC CS-TPE QS-TPE


PT. PERTAMINA HULU ROKAN
Construction Services Work Unit Rate Earthwork Package
Contract No :
SKETCH DRAWING (JOINT SURVEY)
Initiated Date : 13-Apr-23 Location : 29 AB 26 B
Work Title : Install Bruching power pole sintong feeder dan ketigul feeder SPK No. :

Spot 1 1.4
9 SCAFFOLDING CALCULATION
SPOT 1
2,9 M X 1,49M X 2.2M = 09,50 M3
SPOT 2
3,43M X 2,9M X 2,45M = 24,57 M3
TOTAL VOLUME

2.2
09,50M3 + 24,57M3 = 33,87 M3

Spot 2

2.45
3.4
3
2.9

Checked by, Checked by, Witness by:


QS-PDC CS-TPE QS-TPE
PT. PERTAMINA PDC PATRA DRILLING CONTRACTOR
Construction Services Work Unit Rate Earthwork Package
Contract No : 39PHR21-0681

SURVEY FIELD SKETCH

PROPOSED FINAL
WELL NO NORTHING EASTING ELEVATION NORTHING EASTING LATITUDE LONGITUDE

ELEVATION
NORTHING EASTING ELEVATION
METER FEET

You might also like