(TW-P6-F14) - Testing Commissioning of Distribution Board, Feeder Pilars

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 3

PROJECT NAME : CONTRACT NO.

:
Client:
Consultant:
Contractor:
INSPECTION / TESTING & COMMISSIONING FOR DISTRIBUTION BOARDS / Date :
FEEDER PILLARS Page : Page 1 of 2
ITEM : REF DRG/ DOCUMENT:

OBSERVATION/
Sr. No. SEQUENCE REMARKS
RESULT
1 Mechanical / Visual checks
1.1 Outside dimensions
1.2 Paint finish, plating and corrosion protection
(Internal/external)
1.3 Ingress protection - IP ------------
1.4 Size of conductors
1.5 Availability of earth bar or earth strip
1.6 a) Clearances and creepage distances
b) Segregation and partition of compartments and
live parts
1.7 Colour coding , identification and marking of
conductors
1.8 Firmness of connections
1.9 Door handles, locks keys and hinges
1.10 Name plates, labels stickers etc.
1.11 Earthing of doors, components and other related
connections
1.12 Protection of internal cables & wires
1.13 Cable entry and clearance for cable connections

1.14 Mounting of parts on doors / covers


1.15 Make, rating and type of components
(MCBs,RCBOs, etc.)
1.16 Operation of handles, toggles, knobs, actuators
etc.
1.17 Drawings, Operation manual etc

APPROVED / NOT
INSTRUMENTS USED TESTED BY WITNESSED BY
APPROVED BY

Name Name Name Name

Signature Signature Signature Signature

Date Date Date Date


SUB MAIN
CONSULTANT KAHRAMAA
CONTRACTOR CONTRACTOR

TW/P6-F14 Issue 1 01-01-2023 Internal Page 1 of 2


PROJECT NAME : CONTRACT NO.:

Client:
Consultant:
Contractor:
INSPECTION / TESTING & COMMISSIONING FOR DISTRIBUTION BOARDS / FEEDER Date :
PILLARS
Page : 2 of 2
Sr. No. SEQUENCE OBSERVATION/ RESULT REMARKS

2
Electrical / Functional checks
Operation of incomer and outgoing
2.1 isolators / MCBs / RCBOs
Operation of indicating devices
2.2

Operation of protective devices


2.3

Check the interfacing with other systems


2.4

Verify cables and terminations are as per


2.5 approved drawings
Carry out Voltage availability checks at
2.6 incoming terminals and outgoing
terminals
Carry out Phase sequence checks at
2.7 incoming terminals and outgoing terminals
Insulation resistance (IR) test
2.8 IR Values

Megger Voltage : 500V / 1 Min.

L1 - (L2+L3+N+E)

L2 - (L1+L3+N+E)

L3 - (L2+L1+N+E)

N - (L2+L3+L1+E)

INSTRUMENTS USED TESTED BY WITNESSED BY APPROVED / NOT APPROVED BY

Name Name Name

Signature Signature Signature

Date Date Date

TW-P6/F14 Issue 1 01-01-2023 Internal Page 2 of 2