(TW-P6-F14) - Testing Commissioning of Distribution Board, Feeder Pilars
(TW-P6-F14) - Testing Commissioning of Distribution Board, Feeder Pilars
(TW-P6-F14) - Testing Commissioning of Distribution Board, Feeder Pilars
:
Client:
Consultant:
Contractor:
INSPECTION / TESTING & COMMISSIONING FOR DISTRIBUTION BOARDS / Date :
FEEDER PILLARS Page : Page 1 of 2
ITEM : REF DRG/ DOCUMENT:
OBSERVATION/
Sr. No. SEQUENCE REMARKS
RESULT
1 Mechanical / Visual checks
1.1 Outside dimensions
1.2 Paint finish, plating and corrosion protection
(Internal/external)
1.3 Ingress protection - IP ------------
1.4 Size of conductors
1.5 Availability of earth bar or earth strip
1.6 a) Clearances and creepage distances
b) Segregation and partition of compartments and
live parts
1.7 Colour coding , identification and marking of
conductors
1.8 Firmness of connections
1.9 Door handles, locks keys and hinges
1.10 Name plates, labels stickers etc.
1.11 Earthing of doors, components and other related
connections
1.12 Protection of internal cables & wires
1.13 Cable entry and clearance for cable connections
APPROVED / NOT
INSTRUMENTS USED TESTED BY WITNESSED BY
APPROVED BY
Client:
Consultant:
Contractor:
INSPECTION / TESTING & COMMISSIONING FOR DISTRIBUTION BOARDS / FEEDER Date :
PILLARS
Page : 2 of 2
Sr. No. SEQUENCE OBSERVATION/ RESULT REMARKS
2
Electrical / Functional checks
Operation of incomer and outgoing
2.1 isolators / MCBs / RCBOs
Operation of indicating devices
2.2
L1 - (L2+L3+N+E)
L2 - (L1+L3+N+E)
L3 - (L2+L1+N+E)
N - (L2+L3+L1+E)