Construction Data
June 2022
Total Project Costs
vs Construction
Costs
How To Build a Project Estimate of Probable Cost
1 2
Gross Current Cost Per Project
Project
Scope
Determines Square Market = Square = Const.
Feet Value Foot Cost
Soft Costs
(permits, surveys, fees)
Technology
(servers, computers, security, cameras)
Contingency
(funds to cover unforeseen circumstances)
Materials Costs Data
Producer Price Index March 2022
%change
since
1 Month % 12 Month % February
Product/ Material Change Change 2020
Prepared Asphalt, Tar Roofing and Siding Products 1.6% 22.6% 29.2%
Frisco ISD 5th/6th Grade Campus 2021 1,000 $29,374,000 104,812 $280.25
Cheek Middle School –Denton ISD 2021 1,000 $ 59,901,958 175,000 $342.30
Rodriguez Middle School – Denton ISD 2016 1,000 $ 36,000,000 175,000 $205.71
May 2022
Bond Election Data
May 2022 Bond Program
New Middle School Bond Cost Comparisons – Total Project Costs
Published
School Bid Date # Students Construction Costs Square feet $/SF
Rockwall ISD New Middle School #4 May ‘23 $68,000,000** 185,000 $367.56
Tyler ISD New Early College HS May ‘22 300 $21,731,000* 61,300 $354.50
Tyler ISD New Hubbard MS June ’22 1,000 $55,000,000** 170,000 $323.52
New Bushland High School May ‘22 750 $56,700,000* 179,908 $315.16