Jsa For Inst. of TSF & Laydown Area

Download as pdf or txt
Download as pdf or txt
You are on page 1of 23

PROJECT: CONSTRUCTION OF PERIMETER FENCE AND

NEW PATROL ROADS AT RLIC.

CASTLE INFRASTRUCTURE CONTRACTING WLL.

JOB SAFETY ANALYSIS FORM

JSA FOR INSTALLATION OFTEMPORARY SITE FACILITIES & LAYDOWN AREA

7/18/2023
CHANGING CONDITIONS & EMERGENCY PROCEDURES
Stop Work, switch off Equipment, Supervisor Directs Personnel to Nearest and Safest Muster Point Considering Wind direction.
Supervisor accounts for all workers.
RLIC EMERGENCY TELEPHONE NO. 135/#2, Note: If any of the tasks involves biological, physical or chemical hazards, then QP Industrial Hygienists to approve the work.
Details on safety and environment requirements can be found in project HSE Plan No.
JSA NUMBER 001 NEW REVISED
Type of Job Being Analyzed JSA FOR INSTALLATION OFTEMPORARY SITE FACILITIES & LAYDOWN AREA

Department/Section originated JSA JSA Members Construction Department


CASTLE INFRASTRUCTURE CONTRACTING WLL. JOB Performers Site Supervisor & Construction Teams
Normal Approvals: Name Signature Date
JSA Prepared By: Augustine 7/18/2023
JOB Supervisor: Rahul
GENERAL JOB REQUIREMENTS
Additional Approvals (Determined by JOB Supervisor in correlation with HSE Manager)
COMMON PPE
Name Signature Date
Hard barricading of working areas
Certified & tagged scaffolding
PROJECT MANAGER Ashir Riz 7/18/2023 Certified & tagged access cradles
Task & Safety lighting.
Toolbox Talks.
Start Cards Daily.
HSE ENGINEER Augustine Eze 7/18/2023
Personal Protective Equipment
Safety footwear w/steel toe.
Coveralls color coded.
CONSTRUCTION MANAGER Zuber Dastagir 7/18/2023 Safety glasses clear & dark.
Hard hat with chin strap.
Gloves.
Safety Harness.
Licensed operators.
Hi-Vis vest.

Implementation of heat stress measures


PPE Matrix
Cotton
Safet Apron Gloves Weldin Safet Dust Transpare Ear Gloves Dus Har Safety Gu
Overal Spat / Respirato
JOB/PPE y (leather (leather g y mas nt Face Defende (Rubbe t d Harnes m
l s Dotted r
shoe ) ) screen Glass k shield r r) coat hat s boot
gloves
X X X X
General labor x x x *3 x x
*4 *1 *4 *4
Concreting x x x x X x x x X X
X X X
Shuttering x x x X x x X
*4 *4 *5
Support X X X X X
x x x X x
work/scaffold *2 *1 *4 *5 *4
X X X X X
Steel fixing x x x x x
*4 *2 *3 *5 *4
X X X X
Grinding x x x x x X x x
*2 *3 *5 *3
X X X X X X
Welding x x x x x x x
*4 *3 *2 *1 *5 *4
X X X X X
Compacting x x x x X X
*4 *3 *1 *4 *5
Gas cutting(Oxy X X X X X
x x x x X x X
and acetylene) *4 *2 *3 *2 *5
X X
Digging x x x X x x X X
*4 *4
X X X X
Carpentry x x x x x X
*3 *2 *1 *5
X X X X X
Drilling x x x x x X
*4 *3 *2 *1 *5
X X X X X
Jackhammer x x x x x X
*4 *3 *2 *1 *5
X X X X X
Paving breaker x x x x x X
*4 *3 *2 *1 *5
Explosivepower X X X X X
x x x x X
tool *4 *2 *3 *1 *5
Chemicalsprayi X X
x x x X x x X X x
ng *1 *5
Cutting of fiber X X X X X
x x x x x x X
or concrete pipe *4 *3 *2 *1 *5
Material X X X X
x x x x X
handling *4 *3 *1 *5
Operators/drive X X X
x x x x X
rs *3 *1 *5
Note: all PPE requirements are to further subject to the main contractor’ and JSA safety stipulations
*1. Ear protection to be worn in areas of noise above 85 decibels *2. Double- Eye protection to be used whenever power tools are been used *3. Dust masks to be worn as
atmospheric condition dictates *4. Gloves as identified in JSA/JHA (Task-specific) *5. Safety harness mandatory over 1.8meters height level
Ste Action /
Sequence of Who or what may
p Hazard Control Measures / Recovery Measures Responsibl
activities be harmed?
No. e Party
Entry to Entry of unauthorized Proper information, valid entry permits, and gate pass from Construction
1, QatarEnergy/RLIC personnel QatarEnergy/RLIC for entering project-related areas. manager,
Facilities/Plant Gate. Entry of equipment Workers, staff and Existing facilities drawing shall be available along with permit Safety Site
without a valid gate pass nearby workers, signboards to be posted on prohibited items at the main entrance of the Engineer,
Entry to the premises visitors, properties, station plant gate. Site
with Cigarette, lighter, equipment. Random checks to be carried out to ensure no one carries any Supervisor,
and mobile phone prohibited items. Site
(prohibited items). 100% supervision by an experienced Supervisor during the activities. Incharge,
Damaged to existing Do not go to plant locations without proper authorization. Transport
facilities Do not touch plant equipment without authorization. incharge
Trip, Slip & Fall. Only personnel with QatarEnergy/RLIC mandatory training shall enter
the QatarEnergy/RLIC station.
Coach personnel on situational awareness.
Conduct Last-Minute Risk Assessment (LMRA) document and discuss
findings with the team.
Activities (Possible Preparation of Method Statement and JSA against Violation of
Obtain a Work Permit Violation of QatarEnergy work stoppage and/or QatarEnergy/RLIC Approval. Construction
2, from /RLIC Procedures removal from site or The eCPW/Work permit shall be obtained before the start of work. manager,
QatarEnergy/RLIC both). The work Permit shall be displayed at the work site permit box as per Site
(General) QatarEnergy/RLIC regulations. Engineer,
All project team shall undergo through QatarEnergy/RLIC induction Site
training. Supervisor,
Ensure the workforce understands the task requirements through Task Site,
Briefing and Tool Box Talk (TBT)meetings. Safety officer
Site supervisor name and phone number shall be displayed on the
permit boxes.
Emergency contact numbers and grid locations reference should be
displayed on the permit boxes.
Discussion with all personnel involved in the job to understand the
permit, Method Statement and JSA.

Work beyond PTW Serious Violation and All the work will cease once the PTW time expires. Construction
stipulated time. damage to the Only work to commence after the PTW has been validated for the shift. manager,
company’s reputation No work shall carry out beyond the given permit time. Site
Proper planning to be done to finish the activity within the permitted Engineer,
time frame. Site
Any deviation from the work permit, MS and JHA shall be Supervisor,
communicated and approved by relevant permit authorities.
Site Preparation as Unauthorized access Damage to existing All workforces/staff should undergo safety induction prior to Construction
per method Slip, trip & fall Facilities commencement of work. manager,
statement/Permit Contact with sharp Injury to workers, Ensure the area has been confirmed and cleared by the concerned Site
3, requirements. objects site staff and authority, prior to entry into the work area. Engineer,
Incompetent Personnel operators, Wear PPEs (helmet, safety glass, safety shoes, hand gloves, face Site
Mobilization of Lack of knowledge on Damage to mask and high visibility vest). Supervisor,
personnel and the operating task equipment & Take the necessary work permits for the activities to be carried out. HSE officer.
equipment Exposure to hash property Only existing roads and pedestrian access would be used.
weather condition All the road signs must be followed (speed limits signs, No entry sign,
Poor Ground/ Base etc).
Condition, uneven Vehicles will be parked only at the designated areas.
ground surface Always use designated pedestrian walkway and keep work area tidy
and clean to avoid slip, trip and falls.
Vehicle and pedestrian movements shall be separated and minimized
reversing operations.
All operators should have a valid license and third party assessment for
the equipment/machinery they operate.
Castle Infrastructure management will ensure competent persons
deployed.
To avoid hash weather all employees must comply with CASTLE
summer working plan.
Poor Communication All operative persons to have received site induction and additional
between work parties appropriate training
All tasks carried out by trained, authorized and competent personnel
only
Secure / apply all PTW and support documents prior to start of job
Conduct safety toolbox meeting and discuss the JSA and work
procedure prior to start of work
Evident document to be produced
All personnel will wear the appropriate PPE for their specific task
Supervision to be at the work front at all times by performing party to
ensure that the work force has good understanding of the task and
working to the approved JSA and permit requirements
Collapse of load Loads shall be adequately secured before travel and the vehicle shall
not be over loaded
Loads shall be off loaded with care, mechanical means of lifting to be
carried by complying all the safety requirements as per QatarEnergy
standard.
Keep personnel at least 3 meter away 360º from the equipment
/vehicles.
Competent banks men to be deployed to ensure safe reaching out and
unloading of loads.
Falling objects Barricade the area from unauthorized entry and place relevant signage
All loads shall be properly covered/Secured, no loose materials shall be
left alone.

Collision with Segregate vehicular traffic route from pedestrian walkways using hard
pedestrians, structures barriers and signs
and other mobile Comply with site speed limit 15 KPH while working in and around the
equipment plant.
Provided banks man with equipment at all times
Beacon light and 360 º vision camera/mirror to be installed with all
mobile equipment.
Adequate lighting to be provided during night or poor lighting
conditions.
Traffic Hazard Traffic controller/banks men to wear reflective vest and traffic cones
must be deployed at traffic site to control the flow of traffic
Provide proper barricade and traffic signage for unauthorized vehicle
entry to the area
Provide blinker lights on barricades for proper visibility

Ensure all personnel should have safety briefing


To follow CASTLE Summer working Management plan
All workers and staff must bring insulated bottled water
No outside work (Under direct sunlight) shall be allowed between 10:00
Heat Stress AM to 3:30 PM.
Rest shelters shall be provided near to the work place
Adequate cold drinking water along with electrolyte supplementary
fluids shall be made available during working hours by Castle
Infrastructure
Use proper dust mask
Use Safety Glass
Water suppression
Dust Hazard
Work shall be stopped during adverse weather condition.
Regular cleanliness shall be done.

Ensure that hand safety briefing has been given prior to the activity
Proper tools to be used
Proper PPE must be worn during the activity
Hand injury
Appropriate hand gloves shall be used
Minimize manual handling by providing mechanical aids
Provide good housekeeping at all times
Proper stacking of materials
Secure materials when stacked
Slip, Trip and Fall
Material should not block access\egress

Slip, trip and falls Injury to workers Proper access/egress shall be provided to gain access to work area. Construction
Fall from height site staff and visitors Staircase or proper ladder access with handrails shall be provided. manager,
4, Access/Egress No Access Identify the Access by barricade the area with walkway sign and ensure Site
Poor Housekeeping it’s always free from obstruction. Engineer,
Use the roller to levelling the surface and ensure no stone or excavated Site
materials scattered on the way. Supervisor,
Provide safe access and egress for easy movement of operatives to HSE officer
work location and to access assembly point in event of emergency
situation.
Avoid all tripping and projecting hazards in walkway/ Inspect work area,
move material that may cause trips prior to performing work.
All the access to be cleared for any material, tools and equipments.
Access direction signs will be placed.
Housekeeping will maintain regular basis.
No running is allowed on site at any time.
Always use mandatory PPE.
TBT Shall be conducted including Emergency procedures to be
explained to visitors during site induction.
Access for Access will be cleared from material, tools, and equipment' s to ensure Construction
pedestrian and Injury the work area is safe and ready, should case of emergency there would manager,
5 vehicles to workers, staff not be any obstruction for the emergency vehicles and evacuation of Work site
transportation and visitors people. engineer, site
Incompetent drivers or
Operators Only existing roads and pedestrian access would be used. supervisor/
operators
Damage to The driver and operators must have a valid Qatari Driver’s license safety officer
Defective vehicle or
equipment & property All the road signs must be followed (speed limits signs, No entry sign,
equipment.
Vehicle collision etc).
Over speed, over load,
Work area would be barricaded appropriately.
Vehicle/ Equipment
All loose and light weight material to be properly secured to prevent
reversing
from falling during transportation.
Uneven or congested
Vehicles will be parked only at the designated areas.
access.
Vehicle to be refueled only at petrol station.
Lack of traffic control
Stepping/driving over electrical cables, trays and equipment's would be
system/Unauthorize d
strictly prohibited.
entry.
Banks man will be provided as required.
Weather
Unauthorized entry will be strictly prohibited at work areas.
If required access sign will be posted.
Smoking will be strictly prohibited at work areas.
Care to be taken for any overhead obstructions.
Vehicle would be driven only at designated road areas.
Fire extinguisher must be available at site and the employees should
train how to use it.
Mandatory PPE should be used.
Close coordination will be maintained throughout the
execution of work with QatarEnergy/RLC.
Visual and atmospheric inspection/tests would be done by Castle and
concerned parties if required.
QatarEnergy/RLC Heat Stress Guidelines to be implemented during
summer season.
During the heavy wind, Fog or Rain work would be
immediately stopped.
If the noise is higher than 85 DB, adequate ear protection should be
used.
Close coordination with concerned party's supervisors and safety
officers will be maintained.
Topographical • Personnel • Permit would be secured and any concurrence from other End-uses Construction
Survey work • Clients if required will be obtained. manager,
• Vehicles and Work site
6 GPS Instruments • Existing facilities • Tool box talk will be performed by Surveyor supervisor in the supervisor/
and Survey presence of Castle safety officer before commencement of work. Surveyor
accessories, CAT • Lack of • Only competent personnel will be deployed for the work in order to Supervisor,
(Cable Avoidable competency ensure the work is done safely. Safety officer
Tool)- Underground • Manual Handling • While crossing the main road, maintenance roads, utilities and any
Cable Detector, {Survey Tools) other work areas, care would be taken to prevent any
Total Station • Weather condition traffic/pedestrian accidents.
Equipment with {Heat stress Dust
accessories Dumpy Fog etc). • All the work force would be informed to use proper accesses.
leveling instrument • Heavy road traffic • Only medically fit and certified surveyor would be deployed for
with accessories. • Damage to nearby survey works.
and underground • While placing survey point or survey equipment, care would be
services. {Electrical taken not to damage the existing underground and above ground
cables, telecom services e.g. (LV/HV electrical cables, Pipe lines, telecom pipes &
cables, various other service).
types of pipelines
• Good communication with concerned personnel would be
etc).
maintained while doing survey activities.
• Damage tool and
equipment. • Surveyor would not be allowed to place survey equipment's vary
near to the roads, excavated areas and other existing services.
• Markings on existing live pipe lines or any other services would not
be allowed.
• Smoking, naked flame and any sparks would be strictly prohibited
• Mushroom protection on fixing pin(rebar)
• Warning signs, warning lights, VBUs safety cone would be
• provided as required.
• Suitable fire extinguisher would be placed.
• Any instruction given by client or concurring parties' representative
would be strictly adhered to make the work area safe.
• Mandatory PPE will be used at site.
• During any emergency QatarEnergy/RLC control room will be
contacted 135.
Use of mobile • Workers. • Periodic inspection schedule/certification shall be made available Construction
crane /crane • Client. for verification. manager,
7 mounted pickup • Visitors and Site
and their nearby workers. • Driver and operator must have valid Qatari Driving License and Engineer,
accessories for • Nearby Existing third party certificate. Site
lifting of Facilities • Doily checklist to be OK before operating of crane and or crane Supervisor,
Portacabins. mounted pickup.
containers. site • Lack of
toilet. empty sewage competency • Visual inspection of cranes also would be performed to make sure
holding tank, • Fall of material free of any leakage e.g. (Hydraulic from pipes. diesel/ petrol and oil
etc).
portable water tank. • Vehicle occident.
DG set. & small • Nearby Heavy • Crane/crane mounted pickup would be made sure in sound
equipment etc.). road traffic condition.
• Environment. • Third party certificate of Rigger. Rigging gears & Crane with
• Crane failure QatarEnergy Stamp should be available at all times during any
• Damage to lifting activities.
material
• Visible jacket for Rigger will be provided.
• Fall/load slipped
hazards • Competent/ trained and certified operator, lifting supervisor would
• Deviation from be deployed to the crane operations.
approved method • Appropriate spreader- pads would be used.
statement and
supplier's • Lifts would not be left suspended.
instructions. • All lifts would be completed under direction of competent
• Falling objects personnel/Rigger.
and Materials • Work area would be restricted by barriers. guards and warning
• signs.
• Make sure the area must be well compacted.
• Work area will be made sure free from any overhead and nearby
obstruction like buildings, excavation, electrical wires. fences. pipe
line building etc.)
• Inspect the slings and other lifting accessories for its conditions.
• Centre of gravity to be monitor properly.
• Good communication between the crew members to be maintained
throughout the work.
• Angles of the slings would be tried not to exceed more than 45°.
• During heavy wind (25 KT) work would be slopped immediately .
• Loading or offloading will be properly controlled/supervised at all
times.
• While transporting the mentioned things would be proper tightening
with proper belts or chain and security escort would be requested
well in advanced for the same.
Manual Handling • Workers, • Manual handling will be discouraged and avoided as much as Construction
8 • Client, possible manager,
• Visitors and • Carry out manual handling assessment, adopting a correct Site engineer
nearby workers posture to lift the load. Site
• Improper lifting • Using the proper method of lifting techniques or arrange for supervisor
• Slip Trips & fall team lifting.
• Improper tools • Any broken or unsuitable tool will be removed from the work
• No work breaks site. (ie, Homemade, Modified, Incorrect for task etc)
• Pinch Point • Work area kept clean & Tidy Providing work breaks or works
sharing to reduce exposure time.
• Reducing the exposure by job rotation & changing of task
• PPE will be used, this will consist of safety boots, Hi Viz coverall
safety glasses, safety helmet& hand gloves.
Cleaning, • Workers. • HSE Induction of all personnel including emergency procedures. Construction
Leveling. Grading& • Client. Location of escape route. Location of fire extinguisher and manager,
backfilling • Visitors and emergency numbers et c. Site engineer
nearby workers • Ensure that operators are competent and having Qatar driving Site
9 • Lock of • Existing nearby license & third party certificates. supervisor
competency • facilities • Vehicle movement is to be controlled by certified banksman.
• Un-authorized • Reverse alarm must be installed for all the moving equipment.
operation • Follow RLIC standard speed limits as applicable. (e.g.
• Faulty Equipment Excavator I Backhoe.
• Dust • Ensure that all equipment Grader, etc) have valid third party
• Noise certificates and inspected as per QatarEnergy/RLIC procedure.
• Struck • Deploy water truck to sprinkle water at frequent intervals for the
dust suppression.
• Dispose top soil and other unusable excavated materials as per
QatarEnergy/RLIC approved dumping procedures.
• Avoid equipment oil change/repair works on site.
Working at • Workers. s taff • RLIC e-Permit would be obtained prior to start any activities Construction
Height and Nearby • Competent workers will deploy for the task. manager,
workers Work site
• Continuous monitoring by a competent supervisor and Safety
• Properties. Officer.
Engineer/
• Falling objects and Equipment Supervisor,
Materials • Tool box talk will be conducted prior to start any working at
10 • Existing nearby height by a competent supervisor in the presence of CASTLE
Safety officer
• Fall from Height facilities
• Slip. Trip and Fall Safety Officer.
• Safety Harness with double lanyard and other mandatory PPE's
will be use while working at height at all times.
• Secured and proper access and egress will be arranged prior to
start any working at height.
• Workers. s taff • RLIC e- Permit would be secured and any concurrence will Construction
and Nearby be obtained. manager,
11 workers Site engineer
Excavation for • Properties. • HSE checklist and required activities shall be performed. Site
installation of site Equipment • Strict compliance with supplier's instructions I method supervisor
hoardings, • Existing nearby statements.
plumbing works, facilities • Review the available drawings and mark potential hazards
Electrical works and
on the site.
gates
• Extreme care will be taken to prevent any unintentional
• Lack of competency damage to the existing underground and nearby services
• Deviation of (Warning tape, loose soil) present special tools like plastic
approved Method shovel etc would be used.
Statement • Concurrence from the concerned parties will be obtained as
• Slip, trip & fall required by QatarEnergy/RLIC.
• Soil collapse • Area will be scanned before commencing of the excavation
• Electrocution works.
• Fire hazard
• Tool box talk will be performed by site engineer in the
• Noise presence of CASTLE safety officer prior start of work.
• Vibration • Hand tools and equipment to be inspected daily & calibration
• Dust certificates & Insurance to available at site.
• Nearby road traffic
• Underground • Proper shoring will be provided if required.
service damage • To control dust at site water will be sprayed wherever as
required.
• Supervisor to be available full time during the excavation
works.
• All the area around the excavations would be barricaded with
warning tap, safety cones. proper sign boards and wherever
required blinking lights would be provided
• Flagman would be provided.
• No mechanical works within 3 meters to the existing services.
Painting work if • Painters. Staff • Only experienced painters will be deployed for all the paint- Construction
required and nearby related works. manager,
workers Site engineer
• Good ventilation will be provided if required. Site
12 • Ignition source will be kept away from the working areas. supervisor
• No smoking sign will be provided.
• Workers will be advised to wash their hands before eating.
• Irritation to eye
and skin • The container will be seal when not in use and will be stored
• May cause separately at flammable storage area.
ensitization/ • Work area will be barricaded withwarning tapes. Caution
irreversible by skin boards.
contact • Cleaning or washing of paint to the drainage system or
• Harmful for sewage lank would be prohibited
inhalation (toxic
fumes) • After completion of the paint marking/water proofing works
• Fire and explosion the entire west will be disposed as per QatarEnergy/RLIC
hazard. waste management plan.
• Breaks for the work force would be provided.
• Proper supervision would be obtained.
• Proper fire extinguishers as mentioned in the SDS would be
provided. First Aid Kit will be available at site.
• SDS instruction will be followed.
• Adequate and suitable PPE will be used at site.
Carpentry and • Carpenters, • Deploy water truck to sprinkle water at frequent intervals for Construction
Masonry works, • Mason, staff the dust suppression. manager,
Erection of car and Nearby Site engineer
13 shade etc . • Tool box meeting will be conducted. Site
workers
(Block work. • Dust (cement. • Properties. • Only experience masons would be deployed for the work. supervisor
Plastering, Sand) Equipment • Minimize carrying of loads by hand. Mechanical assistance
blinding concrete • Sharp edges • Existing nearby such as hoist, trolleys, and lifts shall be use.
etc.) • Hit by flying object facilities
• Falling objects • While working on scaffolding harness would be used.
and materials • Presence of site supervisor is must.
• Chemical Hazard
• Carry out manual handling assessment
• Fall hazards {while
working on height) • Construction and working area would be properly barricaded.
• Manual Handling • Good housekeeping to be maintained.
• While working on height underneath area would be
barricaded.
• Mandatory PPE would be used.
Electrical works for • Electrician and • Trained electrical personnel to do the job. Construction
the Provision of nearby workers manager,
14 Temporary • Isolation of the area and ensure disconnection from power Site engineer
power Supply. supply with coordination of QatarEnergy/RLIC electrical focal Site
point. supervisor
• Non-conducting tools will be using during the electrical war.
• Bothe ends of the cables will be monitored.
• Static discharge /
Electrical shock, • Coble should be handled with care because of the presence
• Fire of electrical hazards.
• Warning signs indication 'Voltage' and 'Danger' testing in
progress shall be displayed.
• Suitable PPE to be worn
• Electrical Distribution board and Junction box would be
inspected frequently and color coding system would be apply
for all electrical power tools and cables as well as hand tool.
Scaffolding works • Scaffolders, • Only competent and certified scaffolders would be deployed Construction
for installation of Staff and for all the scaffold related works. manager,
15 overhead water nearby workers Site engineer
• All the Scaff old lubes couplers planks and ladders provided,
tank, sheeting work • Existing nearby Site
and other related would be made sure in good working condition (free of supervisor
facilities
works above damage, crocks, bends, ladders in good condition. Coupler Scaffold
required height. and planks free of crocks, bend etc). supervisor
• Scaffolding • Scaffold would not be allowed near to excavated or Firm
collapse base for scaffolding would be provided.
• Hit by falling
materials. • Avoid uncompleted areas which may lead to settlement later
• Fall of person due to weight or rain etc.
• Falling objects • Scaffold would be tied with proper support from all the
and materials. angles, toe board, handrail. proper ladder with one meter
• Damage scaffold above from the landing point would be provided.
material • The scaffold area would be barricaded with warning tope
• Working at safety cone and with proper sign board.
height
• Only certified scaffolding inspector will be allowed to sign on
the scaffolding tog.
• Do not remove or alternate the scaffold unless approved by
scaffolding inspector.
• Mandatory PPE will be used.
• Make sure material are properly rigged and secured prior to
hosting them.
• No other work will be carried out nearby the scaffolding works
• Movement of unauthorized persons will be prohibited.
• Good communication would be maintained.
• Work area will be cleaned from excess materials to reduce
the tripping & other related hazard.
• Frequent breaks wilt be provided for the workforce.
• Closed coordination will be maintained with
QatarEnergy/RLIC safety representative.
Electrical & Loss • Workers • Competent person shall be used in installing firefighting materials Construction
Prevention • Technician/electri such as, smoke detectors, heat detector, DCP fire extinguishers, manager,
16 cians fire alarm sounder with flasher, fire blanket, exit light and manual Work site
• Electrocution
• Staff and nearby call point are as per QatarEnergy/RLIC standards and approved by Engineer/
• Use of untrained QatarEnergy representative. Supervisor,
employees
electricians for • Information boards like, NO SMOKING, EXIT, CAUTION, FIRE Safety officer
electrical works EXIT, DANGER, etc. are to be posted and fixed as per HSE rules
• Use of substandard and regulations.
electrical fixtures • Closed supervision will be implemented.
and fittings
• Proper access and egress will be provided during installation of fire
• Use of substandard alarm and detection system.
connections
• All electricians to be suitably trained and experienced in the works.
• Non-adherence to
• All wiring, connections and terminations inspected prior to
colour coding of
connection to live supply.
wiring
• All wiring to follow colour coding standards; All fuses shall be to
• Incorrect earthing
correct rating for electrical system or equipment.
• Tripping hazard
• All junction boxes and sockets fixed securely to structure.
• Damage to
• All electrical junction boxes, sockets and fittings to be of suitable
unprotected cables
quality as per QatarEnergy standard.
• Use of incorrectly
• Insulation tape shall not be used for cable connections, correct
rated fuse
junction boxes to be used as per QatarEnergy standard.
• All earth connections shall be to as per QatarEnergy standard.
• No cables shall trail on the floor; all securely clipped clear of
damage or posing a trip hazard;
Use of Power Tools • Electrocution due to • Workers, staff, • Ensure workforces understand the hazard/risk and control Construction
Drilling Machine, electric shock and Nearby measures through TBT meeting. manager,
Cable Tester, Power • Crushing and cut workers. • The area must be free from any combustible materials before start Site engineer
17 meter, multimeter, injury • Properties, work. Site
electrician fitter • Sharpe edges, nip • Equipment • Ensure Adequate access and egress, supervisor
tools, Bending point and trap. • Existing nearby • All tools and machines must be inspected /certified.
Machine, Gas • Entanglement facilities • Only diesel operated Generator to be used and make sure earthing
Cylinder • Back pain and spinal is done before start.
injury due to
improper manual • Power tools must be double insulator and dead man switch fitted
handling. with.
• Rotating parts of the • Tools would not be altered, maintained or repaired without
machinery authorization.
• Dust/noise. • All the rotating parts should be covered by using guard system
• Use of faulty/ • Provide drip tray for generator
uncertified • All electrical connection should be inspecting prior to start the work
equipment. and provide good earthing.
• Fall, trip and slip • Provide adequate fire extinguisher at site
Hazards • Availability of fire blanket and fire watcher
• Miscommunication/ • Adequate illumination. Required ventilation.
lack of supervision • Always ensure that the power supply is maintained in an
• Electrocution due to appropriate condition and that all live cables are suitable protected.
faulty power • Units which are damaged in any way must not be used as they
tools/electromagneti represent a significant shock risk.
c interference. • Electrical cables should keep away from the hot surfaces.
• Fire/Explosion • Minimize the workers from the area
• Deviation from • Maintain adequate body ergonomics.
approved • Power tools should be inspected and color coded before starting
procedures. the work
• Cord appears fully insulated with no splits or pinches
• Socket and appliance are not wet.
• Isolate the sockets after use
• Ensure good standard house keeping
• Provide adequate PPEs such as heat resistance gloves,
• dust mask, face shield, (double eye protection) ...etc
Use of Hand Tool • Personnel • Tools would be use by the competent and experience personnel Construction
Screw driver, • Congested areas • Client's only. manager,
18 Spanner etc. • Damage tools, • Equipment's • All the involve personnel would be informed about the associated Site engineer
equipment's and • (new & existing) hazards. Site
materials. • Only competent personnel will be deployed for the task. supervisor
• Roll over • Proper and suitable tool would be used during the execution of the
• Hit by flying object task.
• Falling objects and • Homemade tools would be strictly prohibited at site.
materials • Monthly inspection and color coding with inspection sticker in power
• Health effect due to tools will be implemented.
inhalation of dust • Tools would be made sure free of any wet condition, grease, oil or
• Sharp edges any other chemical which can lead to danger situations.
• Pinch Point • Tools would not be altered or repaired without authorization.
• Electrocution
Access and egress • Workers • Alternative proper access to be provided for workers. Construction
• Lack of adequate
into the excavation
access/exit way • Co-workers • All the Access shall be well secured and conduct periodic manager,
and across
• Equipment ramp, • Public inspection Site Engineer
19 excavation
access resulting to • Vehicles • Proper barrication with signage will be provided prior to start Safety Officer
• Existing any excavation works. Site
personnel Slip,
Trip & Fall. services • Provide access route with proper landing area supervisor
• • Provide enough signages regards to the access and egress. Scaffold
Short cuts resulting • Foot crossing access shall be prepared by a competent scaffolder inspection
to the personnel (If required).
falling into deep
• The same access shall be inspected by the scaffolding inspector
excavation.
and green tagged to ensure safe access .
Use of equipment • Workers • Equipment shall be third party certified and approved by the Construction
for excavation • Co-Workers QatarEnergy prior to use. manager,
20 (Hand tools, Power
• Lack of competency • Existing services • Excavation checklist and mandatory activities shall be Site Engineer
Tools, Hilt, shovel.
• Damage to • Public performed. Safety Officer
pickaxe, Chisel.
underground • Strict compliance with supplier 's instructions I method Site supervisor
Hammer, plate statements.
services
compactor,
• Damage equipment • Only authorized and experienced person will be deployed for the
Wheel Borrow, job.
Diesel Generator). • Fatigue
• Contact with live electrical cables can lead to electrocution and
• Fire and explosion
fire hazard.
• Electrocution.
• Dip tray will be provided.
• Noise
• Proper cable management will be implemented.
• Dust
• Personnel involved with the equipment must maintain safe
• Vibration
distance from the equipment as much as possible.
• Impact, crash etc.
• To control dust at site water will be sprayed wherever required.
• Cave-in
• Fire extinguisher will be placed in the equipment and employees
will be trained for the correct use of the same by the competent
supervisor. Mandatory PPE will be used at site.
Excavation, • Lack of • Workers • Ensure is conformed, carry out survey works and identified Construction
compaction, and competency • Co-Workers underground services, carry out underground service scanning manager,
21 backfilling by hand • Deviation from • Existing services and trial pit. Site engineer
and equipment. approved Method • Public • HSE checklist and mandatory activities shall be performed. Site
statement. • Strict compliance with supplier 's instructions/method supervisor
• Slip, Trip, fall statements.
hazards. • Review the available drawings and mark potential hazards on
• Soil collapse the site.
• Electrocution. • Extreme care will be taken to prevent any unintentional damage
• Fire hazards to the existing underground and nearby services. (Warning tape,
• Noise loose soil) present special tools like plastic shovel etc would be
• Vibration used.
• Dust • Area will be scanned before commencing the excavation work.
• Heavy nearby • All electrical cables will be taken as live unless declared dead by
road traffic. authorized QatarEnergy/RLIC personnel.
• Underground • Tool box talk will be performed by site engineer in the presence
service can be of Castle safety officer prior start of work.
damage. • Work area will be cleaned on regular bases.
• Proper manual handling techniques will be explained to the
workers to prevent any injuries while handling the mentioned
activities.
• While crossing the street road, maintenance road, utilities and
any other work areas care would be taken to prevent any
traffic/pedestrian accidents.
• All the work force would be informed to use proper accesses.
• Hand tools and equipment to be inspected daily & calibration
certificates, TPC& Insurance to be present onsite.
• Proper shoring will be provided if required.
• Special tools like plastic shovel etc would be used.
• Excavated material will be placed minimum one meter away
from the edge of excavation.
• To control dust at site water will be sprayed wherever
• required.
• Supervisor to be available full time during the excavation work.
• All the area around the excavations would be barricaded with
warning tap, safety cones, proper sign boards and wherever
required blinking lights would be provided
• Good communication with concerned personnel would be
maintained while doing survey activities.
• Suitable fire extinguisher would be placed.
• Flagman would be provided.
• Good housekeeping will be maintained.
• Emergency evacuation procedure would be followed during any
emergency e.g. (water Pipe damage, Gas leakage, Fire or any
other dangerous situations and RLIC control room would be
contacted on 135).
• Removal and replanting of any trees, plants & shrubs encountered
in the cable routes will be done only after getting the required
permissions and approval from the concerned QatarEnergy/RLIC
departments.
Soil removal • Movement of • Co-workers, • Workers should be made aware of the hazards of working near Construction
workers during • Local public and such equipment through toolbox meeting. manager, Site
22 excavation and equipment • Workers should not be allowed to work in proximity of Engineer,
soil handling may equipment. Work site
hit workers in the • Proper coordination at all times will be maintained. supervisor
operating radius
and lading severe • Dust suppression shall be done by sprinkling water in the
injury and fatality. premises.
• Dust pollution • Workers in the vicinity should be provided with dust mask

• Workers • All electrical equipment, drills, grinders, cutters etc., to be Construction


• Co-Workers tested, inspected and sound, no damaged leads, connectors manager,
• Existing services etc. removed from service and quarantined if damaged; Site engineer
• Public • No guards to be removed from grinders or cutting equipment at Site
23 any time; supervisor
• No handles shall be removed from electrical hand tools at any
time;
• No electrical hand tools shall be adapted for use other than as
designed by the manufacturer;
• Manufacturers power tool speed rating and cutting disc max
speed to be matched to prevent bursting of wheels;
• Grinding / cutting wheels shall only be changed by trained
personnel;
Office installation • 110v tools to be used, unless exempted by risk assessment;
• Electrical equipment
and Dismantling • Splitter boxes shall not be used for multiple connections;
– grinders, cutters,
using hand tools and
drills etc. • All Emergency Stop buttons to be present and working on all
power tools. machinery, if not, machine will be quarantined until repaired to
standards;
• Equipment to be subject to regular electrical inspection regime,
and especially when returned to the stores;
• Hot works permit required if cutting through steel, aluminium etc.
where a spark can be formed, fire extinguishers and fire watch
in place as per permit requirement;
• Ear protection and face mask to be worn by all workers in area,
not just tool operators. Eye protection to be worn;
• When using vibrating tools such a jack-hammers etc., workers
shall be rotated to avoid Hand Arm Vibration. Refer to chart for
recommended use in 8hour period;
• Workers shall be advised of the symptoms of HAV via briefings,
toolbox talks etc.
• Personnel • Offices to be fitted with smoke detectors. Construction
• Client's • Hose reels to be installed before personnel allowed to occupy, manager,
Site offices
• Fire • Equipment's fire pumps subject to inspection regime. Site
• Muster points • (new & existing) • Extinguishers to be placed in clear areas and subject to weekly Engineer,
24 Fire prevention and Site
relocated due to site inspections.
emergency
procedures
development • Emergency exits to be established and clearly marked with Supervisor,
signage. To be communicated at Induction. Safety office.
• Fire drills to be routinely undertaken, at least every 6 months.
• Muster points also clearly identified at induction, and kept clear
of storage areas.
• Reverse parking deployed in parking areas.
• Designated smoking areas established, clear of the offices, with
sand trays and fire extinguishers.
• Waste skips to be at least 10m from offices, and not allowed to
overflow. Regular removal from site by licensed contractor.
• Double stacked offices to be fitted with steel emergency exit
stairs, at least 2 at opposing ends.
• Flammable liquids, fuel, paints, chemicals shall not be stored in
offices.
• No gas cylinders to be stored inside offices, but in area clear of
offices in signed cages;
• Waste paper etc. to be removed daily and not allowed to build
up.
• New muster points to be effectively communicated to site staff.
• Workers • Edge protection to be erected at all work areas where the potential Construction
• Co-Workers of injury from fall exists, regardless of height but compulsory above manager,
• Existing services 1m. Site
• Public • Where due to the constraints of the work area fall protection is not Engineer,
possible safety harness and lanyard are to be used and hooked off Site
to a secure anchor point. Supervisor,
• Working at height • Avoid overreached practice
• Lost of • Maintain 3 contact point at all times
concentration • Ensure suitable firm base ground and adequate ladder secured
25 • Overreached while • No shock lanyard to be used below 6m on height.
Work at Height
working on ladder • All hand tools to be tied off when working at height.
during
• Lost of 3 contact • Ensure good standard of lighting, at night, for the work area.
(Office cabin set-up)
Use of Ladders and
point/balance. • Supervisors must ensure that all ladders are correctly angled, tied
stepladders • Longtime working on or footed. A suitable base must also be provided for ladders.
ladder • A ladder must extend at least 1 meter above the landing unless a
• Unsuitable suitable handhold is present.
base/Unsecured • All defective ladders are to be removed off site once defect has
ladder. been observed; Painting of ladders is prohibited.
• Ladders should be checked before being put into use and on a
regular basis thereafter.
• Ladders only be used where the duration of the use is short and
where other methods cannot be used due to physical constraints on
site.
• Do not stand on top three rungs of ladders.
Cable Laying • Workers, • Daily Tool Box Talk to be conducted before the start of Construction
• Nearby workers, • work manager,
26 Visitors • Maintain good housekeeping. Site
• Slips, trips and falls
• Clean and remove unwanted materials . Engineer,
• Incorrect manual Site
• Keep fingers away from pinch points.
handling Supervisor,
• Use hand gloves and proper tools.
• Cut injury.
• Clean and remove unwanted materials.
• Slip, trip and fall.
• Appropriate PPE to be worn for the job
• Pinch point
• Use correct manual handling techniques (Explain in TBT).
• crush injury.
• Ensure good coordination and communication between team
• sharp edges.
members.
• Make sure all tools are inspected and color coded.
• Keep all waste cable in one place and barricade the area.
• Place signages temporary waste storage materials.
• Incorrect • Workers, Nearby • Generators to be suitable size and capacity for the task, with Construction
slinging/rigging workers, Visitors maintenance record. manager,
• Inadequate • Generators to have suitable earth rod connected at all time; Site
27 Installation of Diesel maintenance • Fire extinguishers to be located close to generators. Engineer,
Generator at site and • Fuel leakage – • Generators to be fitted with drip tray/ bund wall Site
offices environmental risk; • Diesel tanks to be bunded to 110% capacity, bunds to be sealed Supervisor,
• Noise; with delivery hoses retained inside bund.
• Incorrect earthing • Generators to be subject to regular inspection regime.
• Inadequate electrical • Units monitored for excessive exhaust fumes.
connection
• Workers, Nearby • Ensure to follow safe lifting procedure Construction
workers, Visitors • Ensure proper selection of lifting equipment and manager,
• Electrician • accessories/ free of defect Site
• Incorrect • 3rd party certified rigger; Valid 3rd party certified lifting Engineer,
slinging/rigging • equipment and accessories; Site
• Lifting failure • Ensure to keep within SWL Supervisor,
Install and operate
• Incompetent • Ensure only competent licensed and certified operator
generator
electrician • Ensure all crane safety devices are operational
• Inadequate • Secure generator area.
Maintenance • Only competent person to operate generator.
• Ensure safe refuelling procedure
• Ensure to exclude the area
• Use adequate hearing protection
• Workers, • Barricade the area where pressure test is to be carried out .
• Unauthorized Technician, • Post warning signages.
28
Testing of Drainage
Personnel • Staff and nearby • 48hours pressure tests notification will be given by Castle thru
• Defective tools personnel email to all concerned personnel of QatarEnergy/RLIC.
& Equipment
• Exceeding • Ensure equipment/tools to be used for pressure testing (such as
maximum allowable hose, coupling, pressure gauge, spade, gasket etc) are free from
pressure defect and suitable for the pressure rating of the system.
• Injury to workers • Ensure the pressure relieving device is set at maximum allowable
• Damage to pressure for weakest portion of the segment to be pressure-tested
equipment system • Keep away from the pressurized segment of the system being
• Unattended pressure-tested.
pressurized • Monitor the pressure gauge from a safe distance away from the
tool/Equipment potential source of high pressure jetting (Such as Flange Joint,
• Unsafe Spade, and Coupling etc.)
Depressurization • Never increase the test pressure more than the maximum allowable
pressure for the weakest portion in the segment or pressure rating
of the hose & coupling.
• Do not leave the pressurized hose unattended when the pressure-
test is going on.
• Isolate the equipment from all source of energy when not in use.
• Do not change (exceed/decrease) the duration of pressure test
without permission from Inspection Engineer.
• Ensure the safe depressurization of air at all times.
Material Storage area • Workers, Nearby • Ensure all materials and equipment are stacked in such a way that Construction
workers, Visitors will not constitute a danger to persons in the vicinity during the manager,
29 • course of their daily operations, always stacked in designation Site
storage area. Engineer,
• Ensure all materials are properly stacked in a safe manner and Site
orderliness and stack height should not above allowable storage Supervisor,
• Improper Stack of height 1.5mtrs.
material • Ensure materials are stacked in a suitable pallet to prevent sudden
• Use of unsuitable falling of materials
pallet • Ensure proper manual handling & proper lifting technique.
• Inadequate handling • Avoid lifting heavy loads, get help/ use trolley to lift waterproofing
and storage materials for one place to another.
materials • Establish Fire Point at storage area and ensure fire extinguisher is
• Fire available at work location.
• Ensure the material rolls are properly stacked.
• Ensure materials are properly laid.
• Ensure spread materials are prevented against displacement due
to wind.
• No smoking policy to be enforced at work site
• Ensure provision of First Aid room, Fire Aid and emergency
equipment, Competent First Aider at site always.
Adverse weather • Personal face • Implement and ensure QatarEnergy Heat stress procedures are Construction
(hot & humid, wind & illness due to followed. manager,
cold) • heat exposure • QatarEnergy Standard for Managing Heat Stress QP-OHH-STD- Work site
30 Without AC • Fatigue rashes 012 supervisor/
Room, Roof Top heat stroke • Implement Ministry of Labor and Social Affairs Ministerial Decree safety officer
Condition. • Vehicle accident No. 16/2007 (Summer Working Hours) and ensure all employees
can occur drive are aware of the decree.
during • Check atmospheric condition prior to work execution
foggy/Rainy • Schedule work shifting to workers exposed to hazardous
weather environment.
• Restrictions of works exposed to sun during summer shall be
enforced. Shift change as per Labor Law work schedules/timings.
• Follow the heat stress awareness trainings through TBT, campaign
• Heat stroke/Heat etc Periodic rest cycle while working.
Cramps/ Heat • Follow the QatarEnergy/RLIC flag system.
exhaust • Monitor heat stress regularly and maintain records.
• Dehydration • Provide enough drinking water and shelter near working area.
• Poor ventilation • HSE personnel we constantly and regularly monitor the heat index
• Hypothermia with the aid of hygrometer and keep record of it..
• To prevent dehydration, rest shelter and cold drinking water shall be
provided always.
• Frequent breaks shall be observed and regulated.
• Workers shall be educated on heat stress management.
• Wear clothing suitable to the conditions and the work.
• Rest and frequently as per heat stress management program.
• Standby A/C bus will be provided.
• Grid reference shall be displayed conspicuously around the site for
reference in case of
• Calibrated temperature device shall be used for monitoring.
(Heat and humidity).
• Adequate drinking water and individual hunter bottle (1 LTR)
• shall be provided to all workforce.
Waste management • Site Operatives • Adequate disposal methods shall be in compliance with Construction
• Environment Qatar/Energy/RLIC standard. manager,
31 • Store the minimum amount, if possible Work site
• Waste should be segregate by category and will be disposed of as supervisor/
• Contamination. per QatarEnergy/RLIC waste management procedures. safety officer
• Biological • Surplus excavated materials will be dumped in the designated area
• Disease as per QatarEnergy/RLIC Approval.
• Provide signage's about the waste.
• Stack them covered & secure always.
• Recycling waste will be disposed through approved recycling
company.
Welfare facilities • Personne l • Adequate welfare facilities shall be provided in compliance Construction
• Client's • with QatarEnergy/RLIC Policy. manager,
32 • Visitors • Approved site and lay down area like rest room, drinking water, Work site
• Environment toilet facilities etc will be provided. supervisor/
• Contamination.
• Insect killer will be installed in Mess Hall/Rest rooms. safety officer
• Biological.
• Pest control, housekeeping/cleaning regime implemented.
• Lack of personnel
• Provide sufficient and suitable toilet facilities for workers.
• hygiene, Disease,
• Ensure provision of suitable temporary rest shelter in the workplace
• Illness.
• Provide trash bins with label.
• Maintain the toilets with cleaning log sheet.
• Ensure the sewage is removed periodically to prevent over flow.
• Ensure daily cleaning by regular inspection.
33 Emergency • Workforce • QatarEnergy Emergency Number:135 display through Notice board Construction
Response • Visitors (if any) to easy identification by all personnel. manager,
• Client • Grid reference shall be displayed conspicuously around the Work site
• Uncontrolled • site for reference in case of emergency supervisor/
emergency • All personnel got awareness training to understand and know how safety officer
responses to act in an emergency.
• Unaware of • Employee should report all the unsafe condition to the supervisor
emergency contact immediately.
numbers by work • In case of emergency all activity should stopped and machinery to
force switch off and proceed to the nearest emergency assembly.
• Delaying in • Displayed Contact Number and picture of Trained Emergency
emergency Response Team at workplace.
response, may • Follow the direction as per emergency response plan.
result in serious • point and wait for further instruction
consequences • Escape route /Emergency route /Emergency Assembly Point,
• Slip, Trip, Fall • Clear/ identified through adequate signage's for easy identifying by
• Inadequate/ all personnel
Congested Access • Site Emergency Contact numbers & Evacuation chart posted.
• Abstraction in • First Aid kit available in first aid station and Certified First
access/escape • Aider name and contact number identified,
routes • Emergency evacuation procedure would be followed during any
emergency e.g. (water Pipe damage, Gas leakage, Fire or any
other dangerous situations and RLC control room would be
contacted on 135
Reinstatement • Proper housekeeping to be maintained. Construction
(Returning site in a • All access shall be free from any obstructions manager,
34 good condition) • After completion of all works all area including the crossing will be Work site
reinstated to its original state. supervisor/
• Debriefing to be conducted. safety officer

You might also like