Permit To Work Self Assesment Checklist
Permit To Work Self Assesment Checklist
CORPORATION
TRAIN 3 OF WARA PRESSURE MAINTENANCE
PROJECT (NSK) Project-EF/1945
COMPANY EPC CONTRACTOR
Check List Number Check List Title Page 1 of 2
Rev 0
Permit to Work Self-Assessment Checklist
Date
4.5 Have all isolations been entered and endorsed in relevant section of the Permit?
Have isolations been carried out by nominated & authorized personnel only
4.6
(from KOC or Service Contractor)?
Section 5 - Authorization & Distribution Yes No N/A
Has the permit been duly signed by Permit Applicant, Permit Issuer and
5.1
Worksite Supervisor?
5.2 Have copies of Work Permit been distributed as per requirement?
Section 6 - Site Gas Test Yes No N/A
Has the gas test been carried out in line with requirements of sub-clause 5.15 of
6.1
KOC.SA.004 procedure and relevant section in the Permit duly filled-up?
Section 7 - Permit Registry Yes No N/A
Has the Permit Issuer inspected the worksite and ensured that area is
10.3
acceptable prior to signing to accept the hand-over of the area & equipment?
10.4 Have all supplementary certificates been collected?
10.5 Have all control measures been removed?
If the isolations at worksite continue beyond work completion or validity of
10.6 permit, are such long term isolations indicated in the permit and recorded in
Override Record Register?
Note: N/A means ‘Not Applicable’
Critical Findings