Concrete SW Design Guide 2009 IBC
Concrete SW Design Guide 2009 IBC
Concrete SW Design Guide 2009 IBC
D E S I G N G U I D E
The information contained in this design guide is based upon the relevant building design codes, experience, and
discussion. It is not intended to be either absolute or all-inclusive. Rational thought and creativity are always the
responsibility of every engineer.
1. ETABS Modeling
1.1.2 Walls should be modeled as shell elements and assigned a specific concrete strength (note that the concrete
strength and unit weights should be defined in the “Material Properties” menu).
1.1.3 Allow ETABS to calculate the self weight of above grade shear walls by defining the unit weight in the
“Material Properties” menu.
1.1.4 The stiffness shall be adjusted to account for cracked sections.
a) Per ACI 318-08, section 8.5.1: Ec=57,000(f’c)1/2.
b) Wall stiffness is adjusted to 70% of gross section properties by setting Ie=0.7Ig.
c) If a more refined analysis is required or if there are significant tension forces due to coupling beams then
the text “Cast-in-Place Concrete in Tall Building Design and Construction” recommends using the
following equation: Ie = [0.6+Pe/(Ag x f’c)] Ig ≤ Ig.
1.1.5 Reference the screen shot below for an example of how to adjust the wall stiffness modifiers:
1
S H E A R W A L L
D E S I G N G U I D E
1.1.6 The corners of individual wall elements should always intersect the corners of adjacent elements (i.e., adjacent
walls and diaphragms should all be connected at the same node). Otherwise the elements will not be connected.
1.1.7 Reference the following for recommended pier labeling:
a) Straight walls with no flanges should be labeled as one pier for their full height to track seismic shears and
moments.
b) The individual segments of C-Shaped, L-Shaped, T-Shaped and I-Shaped walls each need to have separate
pier labels to track shear. To track moments all of the individual segments need to have the same pier label,
which should be done in a separate model. See below for an example:
P1A P1
P1C P1
P1B P1
c) Coupled shear walls should be labeled similar to how flangeless and flanged walls are labeled. The
coupled portions should not be labeled the same.
d) Coupling beams will cause seismic axial forces (compression and tension) to develop in the walls. ETABS
will determine and output these forces, but the user must be sure that these forces have been considered in
the design of the shear wall segments.
2
S H E A R W A L L
D E S I G N G U I D E
1.2.5 Reference section 4.3 for a discussion about coupling beam shear force redistribution.
3
S H E A R W A L L
D E S I G N G U I D E
4
S H E A R W A L L
D E S I G N G U I D E
1.7.4 The response modification coefficient is determined from ASCE 7-05, Table 12.2-1. A building frame system
with an R value equal to 6 is used where tied column elements are detailed at the ends of the shear walls,
capable of carrying the gravity loads. Note that the slab system and/or beams and girders must be capable of
spanning between these elements.
1.7.5 A bearing wall system with an R equal to 5 should only be used where boundary elements are not required or
where tied column elements are not provided at the ends of the wall.
1.7.6 Verify the building system and resulting R-factor with the PM/PIC prior to starting design.
1.7.7 The period of the structure, T, is determined by ASCE 7-05, section 12.8.2. Reference section 1.9 for building
period limitations and requirements.
5
S H E A R W A L L
D E S I G N G U I D E
1.9.3 ETABS will determine the structure’s actual fundamental period through a more complex analysis. Reference
1997 UBC, section 1630.2.2, Item 2 for the equation.
1.9.4 Per ASCE 7-05, section 12.8.2 the upper limit on the structure’s period is Cu x Ta, where Cu is a coefficient
taken from ASCE 7-05, Table 12.8-1. ETABS applies this factor automatically when determining static base
shears.
1.11 Determination
1.11.1 The redundancy factor is determined from ASCE 7-05, section 12.3.4.
1.11.2 can be taken as either 1.0 or 1.3 depending on the requirements of ASCE 7-05, sections 12.3.4.1 and 12.3.4.2.
1.11.3 must be determined for the entire building height, not just the lower 2/3 as in previous codes.
1.11.4 may be taken as 1.0 for drift calculations, anchorage and collector design, and design of architectural
components.
1.11.5 The IBC is silent on the issue of using for foundation design. should be used for the design of spread
footings, mat slabs, or pile caps supporting shear walls. may be taken as 1.0 for checking soil bearing or pile
capacities.
1.11.6 See DCI Design Advisory C-1 for a discussion of determination for a punched/coupled shear wall system.
1.12 Irregularities
1.12.1 ASCE 7-05, Table 12.3-1 describes the horizontal structural irregularities, lists the applicable seismic design
categories, and indicates the reference sections for each irregularity.
1.12.2 ASCE 7-05, Table 12.3-2 describes the vertical structural irregularities, lists the applicable seismic design
categories, and indicates the reference sections for each irregularity.
1.12.3 In most cases, buildings with torsional irregularities are acceptable as long as the diaphragm – to – shear wall
connections have been designed for increased forces according to ASCE 7-05, section 12.3.3.4.
1.12.4 Per ASCE 7-05, section 12.3.3.1, structures with extreme torsional irregularities, extreme soft stories, or weak
stories are not permitted in Seismic Design Categories E and F.
1.12.5 Shear wall structures over 160ft in Seismic Design Categories D and E must meet some additional regularity
requirements per ASCE 7-05, section 12.2.5.4.
6
S H E A R W A L L
D E S I G N G U I D E
a) Another option is to create a separate ETABS model for each mass offset direction. The above grade floor
plates are physically moved the 5% offset dimension in each model. Rigid diaphragms need to be re-
assigned and the dynamic forces need to be re-scaled for each model.
b) A third option, when rigid diaphragms are used, is to apply an externally applied moment or force couple
to each story to account for accidental torsion. If this method is used it is possible to define different load
combinations for each offset direction and have ETABS provide an envelope solution for the shear wall
design forces, all within the same model.
7
S H E A R W A L L
D E S I G N G U I D E
Where c is 3.0 for hw/lw ≤ 1.5, is 2.0 for hw/lw ≥ 2.0, and varies linearly 3.0 and 2.0 for hw/lw
between 1.5 and 2.0.
Where is 1.0 for normal weight concrete (reference ACI 318-08, section 8.6.1 for other
conditions).
c) Vu/ ≤ 8 Acv√f’c (For all wall piers sharing a common lateral force) per ACI 318-08, section 21.9.4.4.
Where Acv is the gross area of concrete bounded by web thickness and length of section.
d) Vu/ ≤ 10 Acw√f’c (For any one of the individual wall piers in a group) per ACI 318-08, section 21.9.4.4.
Where Acw is the area of concrete section of the individual pier considered.
8
S H E A R W A L L
D E S I G N G U I D E
For seismic design categories (SDC) C thru F all structures with horizontal plan irregularity Type
5 need to be designed for 100% of the load in one direction combined with 30% of the load from
the other direction.
For SDC D thru F structures with intersecting shear walls that are subjected to axial forces greater
than 20% of the axial design strength also needs to be designed for 100% / 30%. This requirement
should not be applied to straight walls.
The SRSS load combination can also be used in place of the 100%/30% requirement.
d) Note that in low seismic regions and for high-rise flexible buildings the load combinations including wind
loads need to be checked as well.
9
S H E A R W A L L
D E S I G N G U I D E
b) Option 2 (most common) considers that the wall is acted on by gravity loads along with the maximum
shear and moment induced by earthquake loading in a given direction. Therefore, the compressed
boundary resists the tributary gravity load plus the compressive resultant associated with the bending
moment.
In this case, boundary elements are required where the maximum extreme fiber compressive stress
(corresponding to load combinations that include earthquake effects, E) exceeds 0.2f’ c as per ACI
318-08, section 21.9.6.3.
2.6.2 Reference ACI 318-08, section 21.9.6.4 where special boundary elements are required by either option 1 or 2
(above):
a) The length of boundary elements shall be no less than c – 0.1lw or c/2 per ACI 318-08, section 21.9.6.4(a).
b) Boundary elements in flanged sections shall extend a minimum of 12 inches into the web per ACI 318-8,
section 21.9.6.4(b).
c) Transverse reinforcement for boundary elements shall meet the requirements of ACI 318-08, sections
21.6.4.2 through 21.6.4.4, except Eqn. (21-4) need not be satisfied and the transverse reinforcement spacing
limit of 21.6.4.3(a) shall be one-third of the least dimension of the boundary element per ACI 318-08,
section 21.9.6.4(c).
d) Extend special boundary element transverse reinforcement at minimum of 12” into the foundation per ACI
318-08, section 21.9.6.4(d).
2.6.3 Reference ACI 318-08, section 21.9.6.5 where special boundary elements are not required by either option 1 or
2 (above):
a) Note that shear walls in a building frame system (i.e., R = 6) will require boundary elements regardless of
lateral forces. However, the boundary elements in these cases are designed as “column elements” that have
been designed to resist any combination of both gravity and lateral forces.
2.6.4 If boundary elements are required consider using a minimum wall thickness of 12” for constructability.
2.6.5 DCI’s “Shear Wall Reinforcing Lap Splice Schedule” decreases the required lap lengths based on a minimum of
1.5” of clear cover and does not increase it by 1.25 in accordance with ACI 318-08, section 21.9.2.3
requirements. Consider including this schedule on each shear wall elevation sheet. The 1.5” of clear should be
specified for all shear wall reinforcing and not just to the ties in a boundary element. For shear walls designed
without boundary elements the designer should only use the “Shear Wall Reinforcing Lap Splice Schedule” if
1.5” clear has been specified on the drawings.
2.6.6 In boundary elements where #14 or #18 bars are used, consider spacing these bars at 8” o.c. with the distance
from edge of concrete to center of bar equaling 4”. This is to ensure that the boundary remains constructible as
these bars require large couplers. The couplers shall be staggered a minimum of 24” to avoid congestion. All
other bar sizes shall be spaced at no less than 6” o.c.
2.6.7 All couplers and mechanical splices shall conform to ACI 318-08, section 21.1.6.
2.6.8 Terminators may be used on #14 and #18 bars at the foundations to decrease the embedment depth required.
2.6.9 Typically Lenton Couplers and Terminators are specified unless a substitution is requested.
10
S H E A R W A L L
D E S I G N G U I D E
b) Conventionally reinforced link beams shall satisfy the requirements of ACI 318-08, section 21.5. This
includes designing the transverse reinforcement for the shear associated with the maximum probable
moment (Mpr) of the member.
c) Vu/ ≤ 6 Acv√f’c – Check that all coupling beams meet this requirement for worst-case load combination
(note that the code allows a coefficient of 10, but it gets very difficult to detail all of the reinforcing once
you get above 6).
2.8.3 The current code gives the engineer the choice of conventional or diagonal link beam when ln/h values fall
between 2 and 4; however, ACI feels strongly that diagonally reinforced coupling beams perform better in
seismic events. However, they are more difficult and expensive to build. Therefore, discuss these options with
PM/ PIC prior to designing link beams.
2.8.4 Diagonally reinforced link beams shall be used if ln/h < 2 and Vu > 4√f’c per ACI 318-08, section 21.9.7.2.
a) The shear strength of diagonally reinforced link beams is determined by Vn = Vu/ = 2Avdfysin and shall
be less than 10 Acp√f’c per ACI 318-08, section 21.9.7.4(a).
b) The horizontal component of the diagonal reinforcing as well as horizontal top, bottom and side bars shall
be assumed to contribute to the moment strength of the coupling beam.
c) ACI provides two options for confining the diagonal reinforcing per sections 21.9.7.4 (c) and (d). DCI
recommends that section (d) be used as it greatly increases the constructability of the beam.
d) Constructing diagonally reinforced beams is extremely difficult in walls 18” wide and narrower. Consider
using 24” wide walls as a minimum with diagonally reinforced coupling beams.
e) To ease in construction, consider using four bars in each group of diagonal bars. To increase capacity,
grade 75 can be specified for the diagonal reinforcing if enough tonnage is used throughout the project.
See advanced topics below for further discussion on grade 75 reinforcing.
f) Terminators may be specified for the diagonal reinforcing bars to ease in construction and where there is
not enough wall length to develop the bars.
g) ACI 318-08 modifies the development length requirements for shear walls and coupling beams by
multiplying the development length of chapter 12 by a factor of 1.25.
11
S H E A R W A L L
D E S I G N G U I D E
d) Drag strut force can be assumed to vary linearly from zero at the diaphragm edge to a maximum at the
shear wall. The length of the drag strut can be cut off where no longer required.
e) The use of post-tensioning to resist drag forces can be considered.
2.9.5 Reference “Concrete Slab Seismic Resisting Collector – Design Examples” by the SEAONC Seismology
Committee for an advanced discussion on slab / shear wall connection design. This document is available on
the DCI Intranet.
12
S H E A R W A L L
D E S I G N G U I D E
The section modulus, S, of the entire pile cap can used (similarly to a mat foundation) to find the
effective bearing pressures. The force in the pile is then found by applying the tributary bearing
pressure to each pile.
The section modulus, S, of the pile group can be used to determine the force in each pile directly.
d) The depth of the pile cap is usually controlled by one-way shear or punching shear of the columns or piles,
however, more depth may be required on occasion to reduce flexural steel quantities to economical levels.
In some cases it may make sense to add shear reinforcing in lieu of increasing the depth of the footing.
e) The pile cap should be designed at critical locations for shear and flexure by applying point loads from the
piles and columns.
13
S H E A R W A L L
D E S I G N G U I D E
3.2.3 Carefully review thick slabs; studrail cost increases dramatically where stud length > 10”. Where thick slabs
are required, consider increasing clear cover to stud rails to decrease stud length.
3.2.4 Standardize the diameter, spacing and total studrail length for each slab depth as much as possible.
3.2.5 Provide a minimum of (3) #5 EW Bot; (6) total over columns. This is a DCI standard and not an explicit code
requirement.
3.2.6 Ram Concept/DECON Analysis
a) Only check gravity condition. Vu may be determine by hand from tributary area or taken from PT design
software. Unbalanced moments should be taken from RAM Concept or PTDATA printout (not available
on computer screen).
b) When a slab edge is within 10d of a column face, either an edge column or corner column condition shall
be used for design.
c) Always use positive values for moments at edge and corner conditions.
d) Verify with PM/PIC if it is appropriate to disregard biaxial moments.
e) Select “ACI 421.1-R92” Design Code
f) Do hand calculation to verify Vs >= 3.5(f’c)1/2 per ACI 318-08, section 21.13.6.
g) Do hand calculation to determine studrail length per ACI 318-08, section 21.13.6.
h) Include openings when located within 10 times the slab thickness from the column face or within column
strip.
4. Advanced Topics
14
S H E A R W A L L
D E S I G N G U I D E
15