4 Crashing of Project Networks
4 Crashing of Project Networks
(Time-Cost Trade-Off)
Time-Cost Trade-Off
The basic assumption in minimum-cost scheduling is that there is a relationship
between activity completion time and the cost of projects.
• it costs money to expedite an activity;
• it costs money to sustain (or lengthen) the project
The costs associated with expediting activities are termed activity direct costs,
and add to the project direct cost.
The terminology relevant to expediting activities is called crashing
Crushing is a schedule compression technique used to reduce or shorten the
project schedule.
Time-Cost Trade-Off
Activity Normal Normal Cost ($) Crash Time Crash Cost ($)
Time (Weeks)
(Weeks)
1-2 7 700 4 850
1 7
5
3
6
8 6 3
4
7
Find the Critical Path
The critical path is the longest path through the network
Find the least slope value for the two critical paths
Crush activity 1-2 by one week
4-6 by one week
2nd Iteration Network Diagram
9
2 5
6 2
5
1 7
5
3
6
8 6 3
4
6
New Critical Paths
The new critical paths are: Total cost =10,100 + (50+125) -200
1-2-5-7= 6+9+2 =17weeks = $10,075
1-3-5-7=5+5+2 = 12weeks
1-3-6-7 =5+6+3 = 14weeks
Critical Path Critical Activities Critical Limit Slope
1-4-6-7 = 8+6+3 = 17weeks
1-2-5-7 1-2 2 50*
Therefore critical paths are: 2-5 2 225
1-2-5-7 = 17 weeks 5-7 1 100
1-4-6-7 = 17 weeks 1-4-6-7 1-4 3 200
4-6 1 125*
Project completion time Is 17weeks 6-7 1 350
3rd Iteration Network Diagram
9
2 5
5 2
5
1 7
5
3
6
8 6 3
4
5
New Critical Paths
The new critical paths are: Total cost =10,075 + (50+125) -200
1-2-5-7= 5+9+2 =16weeks = $10,050
1-3-5-7=5+5+2 = 12weeks
1-3-6-7 =5+6+3 = 14weeks
Critical Path Critical Activities Critical Limit Slope
1-4-6-7 = 8+5+3 = 16weeks
1-2-5-7 1-2 1 50*
Therefore critical paths are: 2-5 2 225
1-2-5-7 = 16 weeks 5-7 1 100
1-4-6-7 = 16 weeks 1-4-6-7 1-4 3 200*
4-6 0 125
Project completion time Is 16weeks 6-7 1 350
4th Iteration Network Diagram
9
2 5
4 2
5
1 7
5
3
6
7 6 3
4
5
New Critical Paths
The new critical paths are: Total cost =10,050 + (50+200) -200
1-2-5-7= 4+9+2 =15weeks = $10,100
1-3-5-7=5+5+2 = 12weeks
1-3-6-7 =5+6+3 = 14weeks Since the total cost of this 4th iteration is more that the previous iteration, we
1-4-6-7 = 7+5+3 = 15weeks have reached an optimal solution.
The final crashed project completion time is 16weeks and the corresponding critical
Therefore critical paths are: paths are 1-2-5-7 and 1-4-6-7.
1-2-5-7 = 15 weeks
1-4-6-7 = 15 weeks