Semegne Woldeyohannes Excavation

Download as pdf or txt
Download as pdf or txt
You are on page 1of 121

ADDIS ABABA INSTITUTE OF TECHNOLOGY

SCHOOL OF CIVIL AND ENVIRONMENTAL ENGINEERING

EXECUTION MANAGEMENT OF DEEP EXCAVATION IN ADDIS


ABABA CONSTRUCTION PROJECTS

BY SEMEGN W/YOHANNES

A Thesis Submitted to the School of Graduate Studies of


Addis Ababa University, Faculty of Technology

In partial fulfillment of the requirement for the Degree of


Master of Science in Civil Engineering
(Construction Technology and Management)

June, 2016
ADDIS ABABA UNIVERSITY
SCHOOL OF GRADUATE STUDIES
FACULTY OF TECHNOLOGY
DEPARTMENT OF CIVIL & ENVIRONMENTAL ENGINEERING

EXECUTION MANAGEMENT OF DEEP EXCAVATION IN ADDIS


ABABA CONSTRUCTION PROJECTS

BY

SEMEGN W/YOHANNES

June 2016

Approved by Board of Examiners

Wubishet Jekale (Dr. Ing)_ _____________________ _________________

Advisor Signature Date

_________________________ _____________________ _________________

External Examiner Signature Date

_________________________ _____________________ _________________

Internal Examiner Signature Date

_________________________ _____________________ _________________

Chairman Signature Date


Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

Acknowledgements

First of all I would like to thank the Almighty GOD who gave me the strength and tolerance to
pass various obstacles and come up to the accomplishment of this thesis.

I would like to express my deepest gratitude to my advisor, Dr. Ing Wubishet Jekale, for his
guidance, comments, supervision, and excellent advice provides to me from the beginning of the
research. And also, for spending his precious time for improving the quality of this research
throughout the preparation period. All my postgraduate instructors deserve great thanks since
their inputs are worthwhile.

I would like to express my appreciation to all organizations and individuals who contributed
directly or indirectly to this thesis and provided the necessary documents and support for
realization of this thesis. Especial thanks are forwarded to contractors, consultants and clients
(project owners) who sacrificed their time in filling the questionnaires. I would particularly like to
thank experts of Addis Ababa City Road Authority (AACRA) for their willingness and
cooperation to provide all the necessary data. I am deeply grateful to all my friends who have
been very supportive in this research.

In addition, I would like to express my appreciation to ERA who offers me the opportunity to
study the post graduate program.

Finally, I would like to extend my deepest gratitude to my dearest family.

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management i
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

Table of Contents
Acknowledgements ..................................................................................................................................................... i
Abstract ..................................................................................................................................................................... iv
List of Figure .............................................................................................................................................................. v
List of Tables ............................................................................................................................................................ vii
Acronyms ................................................................................................................................................................ viii
1. Introduction ........................................................................................................................................................ 1
1.1. Background................................................................................................................................................ 1

1.2. Statement of the Problem .......................................................................................................................... 2

1.3. Objective of the Study ............................................................................................................................... 2

1.4. Research Questions ................................................................................................................................... 3

1.5. Scope and Limitation of the Study ............................................................................................................ 3

1.6. Significance of the Study........................................................................................................................... 3

1.7. Structure of the Thesis ............................................................................................................................... 4

2. LITERATURE REVIEW .................................................................................................................................. 6


2.1. General ...................................................................................................................................................... 6

2.2. Process in Construction of Deep Excavation ............................................................................................ 7

2.1.1. Planning .............................................................................................................................................. 7


2.1.2. Execution .......................................................................................................................................... 12
2.1.3. Monitoring & Evaluation.................................................................................................................. 18
2.3. Challenges in Deep Excavation ................................................................................................................ 22

2.4. Remedial measures for Deep Excavation ................................................................................................. 33

3. METHODOLOGY ........................................................................................................................................... 37
3.1. Approach and Research Type ................................................................................................................... 37

3.2. Data source ............................................................................................................................................... 38

3.3. Data collection .......................................................................................................................................... 38

3.3.1. Questionnaire .................................................................................................................................... 38


3.3.2. Interview ........................................................................................................................................... 39
3.3.3. Observation....................................................................................................................................... 39
3.3.4. Secondary Data Sources ................................................................................................................... 39

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management ii
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

3.3.1. Questionnaire .......................................................................................................... 38


3.3.2. Interview ................................................................................................................. 39
3.3.3. Observation ............................................................................................................. 39
3.3.4. Secondary Data Sources ......................................................................................... 39
3.4. Data Analysis ................................................................................................................. 40

4. ANALYSIS OF FINDINGS AND DISCUSSION ................................................................42

4.1. Introduction .................................................................................................................... 42

4.2. Responses to Survey....................................................................................................... 42

4.3. Deep Excavation Works Execution Management Practices .......................................... 44

4.4. Problems and Challenges in the Execution of Deep Excavation ................................... 55

4.5. Improving the methodologies for better execution management ................................... 65

5. CONCLUSIONS AND RECOMMENDATIONS .................................................................70

5.1. Conclusions .................................................................................................................... 70

5.2. Recommendations .......................................................................................................... 72

REFERENCE .................................................................................................................................75

Appendix A: Research Proposal ....................................................................................................79

Appendix B: Questionnaire............................................................................................................92

Appendix C: Questionnaire Analysis...........................................................................................103

Appendix D: Observation Guideline ...........................................................................................109

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management iii
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

Abstract

To alleviate the traffic congestion of the A.A city, it is vital and crucial to allocate underpass and
overpass transportation means for the expansion of roads and construction of supportive infrastructure.
Although, the construction of high rise building are significantly increasing, especially by financial and
commercial institutions as well as by other individual investors for hotel and real state purposes. Those
buildings require large parking area, stores and other facilities that can only be alleviated by constructing
basements. To construct basements and underground transportation means deep excavation is a must.
Deep excavation is an important component of construction which relieves shortage of space and allows
usage of underground spaces for different structures. Thus, this thesis is prepared to study practice of
deep excavation in scientific way and to develop a better ways for execution of deep excavation in urban
areas.
The research was undertaken to assess the practices in planning, quality assurance services and
execution, identify challenges that need to be addressed and to recommend interventions in order to
improve execution management of deep excavation in A.A. civil work projects. Accordingly, a literature
review was conducted on related topics, through which numerous variables challenge was identified. In
the matter of fact, detailed analyses were accomplished with primary data collected through
questionnaire, interviews and by physical observation of projects.

The response are found from different professional found in employers, consultants and contractors side
and which are engaged on the three civil work construction projects (i.e. building, road & railway). The
responses are calculated by using a weight average technique of all groups as per each variable ranked.
Based on the findings it is observed that, challenges as safety and health management, lack of recording
construction events, wrong calculation of earth pressure and lack of well qualified and experienced
professionals found to be the most common outstanding once. Failures encountered and observed from
respondents are differential settlement, subsidence of ground, cracks on nearby structures and collapse
on adjacent structures including small injuries up to loss of lives of workers and also neighboring
community living on adjacent have been recorded & investigated.

Recommendations are forwarded by pointing out the responses & expectations from clients, consultants
and contractors. Those recommendations cultivate us to adopt quality assurance by implementing
recording and analyzing construction events with close supervision. During construction, monitoring
execution compliance by regulatory bodies and upgrading professionals experience through continuous
professional development trainings are deemed as remedial measure to execute fatal and hazard free
deep excavation in A.A.

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management iv
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

List of Figure

Figure1.1: - Flow chart of the Research

Figure 2.1: - Tripod

Figure 2.2:- Flow diagram of the third-party risk management strategy

Figure 2.3:- Structure to identify measurement techniques

Figure 2.4:- Response of nearby structures to deep excavation

Figure 2.5:- Failure of Open cut Excavation that Lead to Driven Pile Foundation Failures- North

Jakarta-2005

Figure 2.6:- Kick in Failure of Sheet Pile-Surabaya-2007

Figure 2.7:- Failure of Sheet Pile Walls; Further Soil Movement was tried to be stopped by Soldier

Pipe Failed-West Jakarta 1995.

Figure 2.8:- Ignorance Open cut excavation led to a building collapse - China

Figure 2.9:- Mass Rapid Transit cut and cover excavation failure – Singapore

Figure 2.10:- Ground water seepage through impervious wall; Unbalance water pressure and

Impermeable layer at base

Figure 2.11:- Artesian water pressure

Figure 2.12:- Squeezing or Flow of Soft Soil through the Gaps within Soldier piles.

Figure 2.13:- Heaving Mode of Failure

Figure 2.14:- Focus of possible measures to improve performance

Figure 4.1:- Frequency and percent of response by type of project

Figure 4.2:- Result of questionnaire using RII

Figure 4.3:- Lack of proper usage of Safety & Health cloths

Figure 4.4:- Unsafe & inappropriate working condition; poor reinforcement placement

Figure 4.5:- Shoring pile for the support of natural ground

Figure 4.6:- On site slump test of concrete

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management v
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

Figure 4.7:- Lack of protection wall & sliding of the ground results collapse of the fence

Figure 4.8:- Addis Ababa light railway project

Figure 4.9:- Wrong calculation of soil pressure results sliding & failure of foundation

Figure 4.10:- (A) Sliding of ground due to wrong calculation of earth pressure

Figure 4.10:- (B) Sliding& collapse of structure due to wrong calculation of earth pressure

Figure 4.11:- Sliding effect on utility lines and the sliding results unsafety environment neghborings

Figure 4.12:- Construction of retaining wall

Figure 4.13:- Occurrence of Challenges remark from respondents

Figure 4.14:- Deformation of re-bars due to sliding of the ground & presence of ground water

Figure 4.15:- Effect on neighboring structure

Figure 4.16:- Occurrence of Failures remark from respondents

Figure 4.17:- Failure of temporary supporting piles including the anchor

Figure 4.18: Effect on neighboring structure; collapse of feeder road

Figure 4.19:- Poor quality of concrete retaining wall, improper erection of formwork results

deformed structure

Figure 4.20:- Occurrence of Remedial measures remark from respondents

Figure 4.21:- Collecting ground water through perforated pipes & pump out the collected water

Figure 4.22:- Construction of protection wall to avoid future sliding & protect the neighbor structure

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management vi
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

List of Tables

Table 2.1:- Comparison of approaches for deep excavation construction

Table 2.2:- Monitoring Instruments for deep excavation.

Table 4.1:- Frequency and percent type of organization

Table 4.2:- Top ten factors of deep excavation

Table 4.3:- Technical & Non-Technical challenges in deep excavation

Table 4.4:- Factors of challenges

Table 4.5:- Failures or Damages mentioned from respondents

Table 4.6:- Remedial measures mentioned by respondents

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management vii
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

Acronyms

A.A. Addis Ababa

AACRA Addis Ababa City Road Authority

AALRT Addis Ababa Light Railway Transit

ACI American Concrete Institute

BS British Standard

DIN Deutsche Industrie Norm

ES European Standard

TSC Traffic and Safety Coordinator

BATCODA Ethiopian Building and Transport Construction Design Authority

ERA Ethiopian Roads Authority

FHWA Federal Highway Agency

FIDIC Federation Internationale des Ingenieurs – Conseils,


a French acronym with its English equivalent of
“International Federation of Consulting Engineers”

RII Relative Importance Index

WBS Work Breakdown Structure

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management viii
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

1. Introduction

1.1. Background

A rapid development of economy leads for further construction of infrastructures while the available
construction areas are limited. Thus the construction requires much excavation for basement and
underpass road provision that embrace difficult design, complicated construction technology,
vulnerability to circumstance and other complex characteristics. [23]

Deep excavation into the ground is indispensable to create additional floor space and roads to meet
increasing space requirements for parking and other functions in multi-story buildings and for underpass
ways at the city centers. Numbers of deep excavation pits in city centers are increasing every year.
Structures in the immediate vicinity of excavations, dense traffic scenario, presence of underground
obstructions and utilities have made excavations a difficult task to execute. An excavation is basic phase
in the construction of basement and underpass infrastructures. The process of an excavation may encounter
different kinds of soils underneath the same excavation site from soft clay to hard rocks. During
excavation, some soil types pose greater problems than the others. [1,7]

No matter how many trenching, shoring, and back filling have been done in the past, as we all understand
every project have its own unique characteristics, though it is important to approach each new project with
the utmost care and preparation. Many on site accidents result directly from inadequate initial planning.
Waiting until the work has started to correct mistakes in shoring or sloping slows down the operation,
adds to the cost, and increases the possibility of other excavation failure. Determination of site condition
through site observation, test borings for soil type or conditions, and consultations with local officials and
utility companies is important and should be the primary activities to manage difficulties related to deep
excavation. [1,5,6]

The goal of monitoring data management is to provide useful scientific information about the status and
trends of various factors affecting the environmental impact of a project. Comprehensive data
management functionality is thus essential for achieving this goal, particularly for urban deep excavations.
[14]

But, it is not to be denied that design and construction of deep excavation becomes more difficult as
excavation depth is deeper and surrounding environment becomes more complicated. Therefore, the
construction project team must consider a wide variety of information to assess environment impact when
managing risks and making project decisions. [21]

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 1
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

The thesis was originally undertaken to assess the practices in planning, execution with quality assurance
services management, identify challenges that need to be addressed in recently constructed deep
excavation projects in A.A. After analyzing the gathered information, remedial means have been included
through conclusion and recommendations in order to improve execution management of deep excavation
for the construction of basement and underpass roads in Addis Ababa construction projects.

1.2. Statement of the Problem

In our country cities develop rapidly with construction which makes the space above ground to become
more & more precious. Due to this, underground space is developed with greater speed followed by deeper
excavation although the existence of nearby structures makes the excavation work more challenging.
Consequently, this part of construction requires special attention and management to avoid unplanned and
unwanted result.

In most of local construction sites, during the execution of deep excavation sliding of the ground, getting
unexpected substructure which have contrary characteristic to the geotechnical results, presence of
unexpected water table, striking unknown utilities and so on makes the excavation more difficult. Also,
because of negligence and less attention to safety and health, many accidents and injuries of workers can
be incurred during deep excavation. This usually occurs due to less attention given to the execution
management of deep excavation in construction.

Therefore, studying the current practice of deep excavation in local construction especially in Addis Ababa
which leads to the above mentioned drawbacks and reviewing of regulations related to this issue is
important to attain improved construction means.

1.3. Objective of the Study

The objectives for this research are:

 assessing local practices in planning, quality assurance services and execution of deep excavation
for the construction of basement and underpass road works.

 identifying problems, challenges, unwanted effects and gaps that need to be addressed to improve
the planning, quality assurance services and execution of deep excavation for the construction of
basement and underpass road works.

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 2
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

 recommending interventions in order to improve the planning, quality assurance services and
execution methodologies of deep excavations for the construction of basement and underpass road
works based on the findings of the study.

1.4. Research Questions

This thesis will be guided by the following questions as major benchmarks:

1. What is the practice of Addis Ababa construction projects in the execution management of deep
excavation work?

2. What are the problems and challenges incurred with regard to execution management of deep
excavation?

3. How the gaps can be filled and improved methodologies can be achieve in order to have better
execution management means?

1.5. Scope and Limitation of the Study

The scope of the study has been limited to projects which engage deep excavation and have been
constructed in recent years. The projects are from the three type i.e. building, road and railway sectors.
From the research building projects which there were three and more basement floors with underpass road
and railway projects in Addis Ababa have been considered.

The data collection were limited to primary data i.e. observation, interviews & questioner mainly for the
building & road sectors. There were difficulties to find relevant written and organized documents in every
sector where deep excavation was implemented. Especially in railway project it was difficult to find even
primary data through interviews & questioner since the companies weren’t willing to give any kind of
data. Thus, the availability of limited data precludes the researcher from further in-depth studying on the
topic.

1.6. Significance of the Study

The expected outcomes of the study are:

 to contribute towards the improvement of deep excavation management;

 to contribute improvement mechanism of execution practice of deep excavation;

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 3
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

 to provide an input for contractors to have better execution mechanism

 to provide an input for controlling & supervision to regulatory bodies and consultants

 to show the challenges and failures that could occur due to poor execution and provide better
mechanisms to alleviate them.

Therefore, the stakeholders who involve in the construction of deep excavation shall benefit from the
outcomes of the thesis. It is also hoped that the findings of the research may simulate other researchers to
conduct further studies.

1.7. Structure of the Thesis

This study has been organized into six chapters that discuss various aspects of the construction of deep
excavation work that focuses on the main aspects which are of relevance to this thesis. Chapter one
explains the background of the research and spells out what the research intends to achieve. It is followed
by chapter two which is literature review of the thesis that provides a general understanding of
international practice on the management of deep excavation and the challenges with the remedial
measures are presented. This will also provide bases for the analysis of the main topics. In chapter three,
the methodology used for the research are discussed and highlights of the primary and secondary data
collection methods are given. Chapter four is dedicated to the analysis and discussion of the results
obtained from the study. The last chapter draws conclusions of the research and provides some
recommendations for improvement. Further recommendations for future studies are also included in this
chapter. The following figure shows the organization and structure of the paper.

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 4
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

1. INTRODUCTION

Publications

2. LITERATURE Journals
Tools Used
REVIEW
Books

3. METHODOLOGY

Observation
4. DATA ANALYSIS
Tools Used Interview
AND DISCUSSION

Questioner

5. CONCLUSIONS AND
RECOMMENDATIONS

Figure 1.1:- Flow chart of the Research

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 5
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

2. LITERATURE REVIEW

2.1. General
In the construction industry, deep excavation works are becoming very popular as high rise buildings
constructed and the creation of underground transportation increases. A deep excavation into the ground is
indispensable to create additional space to meet increasing space requirements for parking of multi-story
buildings and for underpass roads at the city centers. Numbers of deep excavation pits in city centers are
increasing every year. Structures in the immediate vicinity of excavations, dense traffic scenario, presence
of underground obstructions and utilities have made excavations a difficult task to execute. An excavation
is basic phase in the construction of foundations, basements or underpass way. The process of an excavation
may encounter different kinds of soils underneath the same excavation site from soft clay to hard rocks.
During excavation, some soil types pose greater problems than the others. [1, 7]

It is not to be denied that design and construction of deep excavation becomes more difficult as excavation
depth is deeper and surrounding environment becomes more complicated. Therefore, the construction
project team must consider a wide variety of information to assess environment impact when managing
risks and making project decisions. The goal of monitoring data management is to provide useful scientific
information about the status and trends of various factors affecting the environmental impact of a project.
Comprehensive data management functionality is thus essential for achieving this goal, particularly for
urban deep excavations. [14, 21]

New construction with multi-story basements for parking and storage facilities calls for deep open
excavation accompanied by the risk of damage to adjacent buildings. The drilling of the tiebacks supporting
the structure, large displacement of the supporting wall due to unexpected high loads or driving of piles in
the excavation and piping might create settlement and tilting of neighboring structures. [15]

Urban regeneration calls for travel to work and play, to offer and access services. However, the recent rate
of growth in car travel is unsustainable. In order to reduce carbon dioxide emissions, other pollutants, traffic
congestion and noise, car travel must be replaced by mass rapid transit systems. Cities around the world
are attempting to regenerate or expand by building subways.

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 6
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

Increasing transportation needs the enlargement of existing railway or subway stations, underpinning and
new construction works. In urban areas new public or private roads can be built underground and
heterogeneous soils and nearby foundations of existing buildings may be encountered.

Concerning ground conditions, there is always an element of uncertainty; the ground is a natural product
and can be investigated only in a limited number of drill-holes. On the other hand, the engineer must take
into account these risks considering the characteristics of the subsoil and, without compromising cost. [15]

2.2. Process in Construction of Deep Excavation


As roots are base for the lives of trees, deep excavation construction is also the base for high rise buildings
and underpass structures. In deep excavation construction work, there are various procedures, as per the
literatures used and reviewed for the purpose of this research the main procedures can be categorized into
three which are:
1. Planning,

2. Execution, and

3. Monitoring and Evaluation.

2.1.1. Planning
Excavation work should be carefully planned before work starts so that quality and safety can be assured
and also efficient and effective utilization of resources within the schedule can be attained. It is imperative
that preliminary analyses be carried out for many options of the walls, support systems and construction
methods to assess on the cost and time of construction together with the technical requirements on the
quality, safety and its influence on the adjacent structures before proceeding to the execution. [20]

In order to maintain quality for deep excavation work in urban area, planning of construction procedure,
arrangement of site, locating of mobile equipment, stability of adjacent structures and similar issues shall
be studied well. Thus, in the construction of deep excavation, planning shall focus the major concepts like
design, quality assurance, presence and protection of nearby structure, safety and risks of the construction
work, etc.

Planning involves identifying the hazards, assessing the risks and determining appropriate control measures
in consultation with all relevant persons involved in the work, including the principal contractor, excavation
contractor, designers and mobile plant operators. Structural or geotechnical engineers may also need to be

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 7
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

consulted at this stage. Professional engineers must include a way for workers to enter and exit deep
foundation excavations in their designs. [15, 16]

Excavation work is usually related to risk and the degree of risk increases as the excavation becomes deeper
and as it is performed adjacent to existing structure so that risk management is mandatory. As Deltares
developed the GeoQ method (Van Staveren, 2006) which is used to structure on ground related risk
management. GeoQ is based on six generally accepted risk management steps:

1. Determination of objectives and data collection: it involves gathering of all relevant project
information. It used to provide clarity about the project objectives which allows to define the risks
as obstructions that prevent meeting objectives.

2. Risk identification: is an important step, and determines anything foreseeable that might obstruct
the project objectives as a risk by giving a name and identity. However, large damage unfortunately
result from unforeseen risks which remain as unforeseen. Thus our challenges remain to arrive at a
maximum number of foreseeable risks and use different tools to identify them.

3. Risk classification and quantification: here risks are classified in terms of probability and
consequences as the risk seriousness can be expressed in the likelihood or probability of occurrence
and the likely effect or consequences of the risk. The classification can be as qualitative, semi-
qualitative and quantitative.

4. Risk remediation: concerned with selection & application of remedial measures. Before engaging
in the remedial action it is required to further breakdown and analyzing the risks by risk structuring
and risk analysis. Then risk response strategies or remediation will be implemented.

5. Risk evaluation: in this step the objective is to verify whether the remaining risk profile is
acceptable to the responsible and affected parties, or not. Means the risk response made needs to be
checked and balanced with the risk tolerance of the affected parties.

6. Transfer of risk information to next project phase: all gathered and analyzed risk management
information needs to be properly filled to transfer to the next project phase so that they can be used
as basis for the risk management process of the next project. [4,23]

Therefore, in general terms for the management of deep excavation construction could encompass three
main stages as risk identification, risk analysis, risk control and contingency plans of action, where the first
stage presented in the planning category as follows.

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 8
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

Risk Identification

Many sources of risks in construction are associated with the construction of deep excavations. Ground
movements, ground water control, and poor quality of construction are always main sources of risks in
executing deep excavations.

Unavoidable induced ground movements are always associated with the stress release from the earthwork
excavation within the site and this can result settlement of the ground. Other source of settlement could
also occur due to the increases in the effective overburden pressure during lowering groundwater table in
case of dewatering outside the excavation boundary. These ground movements could be predicted and
controlled during the design process by adopting a finite element model by which the construction sequence
is modeled and the ground movements are predicted. [22]

In another scenario, deep excavations must be designed in such a way that the elements of bracing system
and neighboring structures meet both ultimate and serviceability limit state requirements. Also design and
construction should be handled to avoid damage to neighboring structure that needs to consider legal
requirements and necessary determination of impact zones and their environmental influence during
execution and operation. [19]

Site investigation studies the presence of soil characterization, ground water conditions, underground
utilities and other subsurface conditions. In the study of ground water conditions frequently report water in
borehole logs but sometimes it may not be clear whether it is a water table, a perched level, a significant
source of water, leakage from a water main, surface water infiltration or due to granular pockets and lenses.
If there is plenty of water a watertight type of wall has to be selected otherwise water seeping through the
wall is drained off. [18]

Technical data related to existing groundwater conditions should be investigated, and the need for
groundwater control in making the excavation, planning a dewatering system to meet the job requirements
and its effect on adjacent structures, specifications, monitoring and the necessity for recharge of the exterior
water table should be assessed. Soil investigations generally includes determination of piezometric levels,
presence of perched, depressed or artesian water levels, detailed description of soil layers, grain size
analyses of aquifer soils. Depending on the project more detailed investigations may be made like borehole
permeability tests, water pressure tests, well pumping tests and observation wells. Local studies on
groundwater regime are also helpful if available. [18]

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 9
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

Every time workers must wear a full body harness inside a deep excavation attached to a secured lifeline
that meets the requirements of the Workplace Safety and Health Regulation (relating to fall protection).
The lifeline must extend to the top of the excavation and be secured to an anchor, as required by the
regulation. A worker must be in place continuously to monitor the worker that is in the deep foundation
excavation.

A tripod or similar type of hoist must be used to raise or lower workers into or out of deep foundation
excavations. The hoist and all cables, hooks (equipped with positive means of securement) and components
must be:

 designed and certified by a professional engineer


 inspected regularly to ensure safe operating condition
 a sufficient height to safely raise the worker completely above the ground surface
 equipped with a brake capable of supporting at least four times the maximum load that may be
applied to it. [15]

Figure: - 2.1 Tripod [15]


Concerning safety management of deep excavation safety and health regulation especially with respect to
confined spaces must be followed. With respect to this, when workers are required to enter deep foundation
excavations, support structures must be installed; that must be designed and certified by a professional

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 10
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

engineer. The support structure must extend 300 millimeters (12 Inches) above the ground level and
continue to the point where the work is being carried out. The support structure must be at least 700
millimeters (28 inches) in diameter and be secured against any movement.[15]

When one considers performing excavation of specific site conditions such safety checklist shall be well
thought which are:
• Traffic,
• Proximity and physical conditions of nearby structures,
• Soil type,
• Surface and ground water,
• Location of the water table,
• Overhead and underground utilities, and
• Weather and so on.
These conditions can be determined through jobsite studies, observations, test borings for soil type or
conditions, and consultations with local officials and utility companies to determine the approximate
locations of utility installations. [1]

The other thing that must be studied before construction ahead is supporting wall. There are several types
of in-situ walls are used to support excavations. The criteria for the selection of type of wall are size of
excavation, ground conditions, groundwater level, vertical and horizontal displacements of adjacent ground
and limitations of various structures, availability of construction cost, speed of work and others. One of the
main decisions for the selection of supporting walls is the water-tightness. [1]

Major concern during the planning of deep excavation is the impact of construction related to ground
movements on the adjacent properties and utilities. During excavation, the state stresses in the retained
side are the stress relieve on the excavation face resulting in horizontal ground movement and follows by
vertical movement for equilibrium and increase in vertical stress due to lowering of water table resulting
in both immediate and consolidation settlement of the ground. These ground movements that vary away
from the excavation can cause buildings, especially those on shallow foundation, to translate, rotate,
deform, distort and finally sustain damage if the magnitude exceeded the tolerable limits. [20]

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 11
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

2.1.2. Execution
In particular in most modern development projects, the scale of construction tends to be growing bigger
and bigger, that makes planning and construction of deep excavation become much more difficult and
complex. The elements of a deep excavation are identified by means of a work-break-down-structure
(WBS). For every element a list of unwanted events has been made. These unwanted events are described
to show the relevance. In order to keep an overview, a differentiation has been made for unwanted events
affecting
 Single elements of the deep excavation. e.g. instability of trench of cemented bentonite wall

 deep excavation as a whole, a combination of those single elements e.g. bursting/heave of a


submerged concrete floor
 Surroundings of the deep excavation e.g. cracks in surrounding buildings caused by vibrating piles[4]

For a complete outline of all measurement techniques a risk based overview of a deep excavation is
developed. This overview has the structure as shown below

Figure 2.3:- Structure to identify measurement techniques [4]

For each unwanted event the parameters have been identified which should be taken into account
for possible development of the unwanted event. With these parameters it is possible to find a list of
specific measurement techniques. Each parameter and technique is described using standard. [6]

Deep excavation or basement or similar underground structures can be constructed using the following
approaches:

1. Open cut arrangement


2. Bottom-up arrangement
3. Top-down arrangement

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 12
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

Table 2.1:- Comparison of approaches for deep excavation construction [17]

Open cut Bottom-up Top-down


Size of Site Very large open site Small sized site Large sized site
Site Environment Unobstructed Adoptable to most Adoptable to most
environment complex environment
Protection Simplest protection Complex lateral Limited shoring support
support required where required
Special Provision Not much Not much Temporary vertical
support required
Machinery Suitability Large machine Small machine Large machine
Spoil Removal Using ramp Staged platform or Ramp vertical shaft or
bucket bucket required
In addition to what is explained in the table when certain jobs are simpler in nature the relative economical
and effective way is cut & fill or bottom up methods, on the other side excavation is going deeper and the
surrounding environment getting more complex and sensitive, top-down or combined method may be a
more appropriate option to construct.[17]

It is important to carry out analyses to estimate the magnitude and distribution of the ground movements
due to the proposed excavation of the nearby structure. Piled buildings adjacent to deep excavations have
to be assessed differently from buildings with shallow foundations. Piled buildings settle an amount
between the surface settlement (for friction piles in failure) and tip level settlement (for end bearing piles
with sufficient capacity to take full negative skin friction). The precise soil-pile interaction can be estimated
based on the pile load, the pile capacity and the shaft friction development. Based on measurements of
timber pile foundations, the pile settlement is equal to the soil settlement at a depth of 0.3 – 0.8 times the
pile length for most original timber pile foundations and 0.8-1.0 times the pile length for most renewed
foundations in the first sand layer. Most of the modern buildings settle not more than the pile tip level. [13]

The other impact related to this construction work is environmental impact, which is usually related to
displacements and strains caused by deep excavations. The most common are displacements of retaining
structures and settlements of the adjacent buildings together with zones where they occurred. We can
distinguish two types of environmental impact: natural influences (unloading, reloading and additional
loading) and technological influences (related to technology applied and solutions). [19]

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 13
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

Natural impact: that includes changes of stress state in subsoil as a result of unloading process, and then
loading by the structure. These influences are basically irrelevant to solutions used and technology of works
applied.

Technological impact: depends on assumed solutions which influence the changes of stress state such as:

- type and technology of bracing system which define its stiffness,


- execution method of bracing,
- changes of stress state during the deepening process for diaphragm wall;
- type of support or anchoring (initial prestressing or strutting);
- vibrations during driving/vibrating of sheet pile wall;
- technology of excavation deepening;
- influence of excavation dewatering,
- disturbance of groundwater flow,
- soil improvement under neighboring structures,
- influence of vehicular traffic. [19]
While analyzing these specific situations one should take into consideration individual influences, which
can occur, as well as corresponding to the impact zones. These zones must consider all the limitations
resulting from:
- conditions of serviceability limit state for bracing
- system with supports and neighboring structures,
- character of nearby urban infrastructure and the impact on inhabitants and installations:
- vibrations (rate, frequency amplitudes),
- vertical displacements,
- horizontal displacements,
- difficulties for inhabitants.
Defining the range of impact zones as well as possible ground surface displacements behind the wall
(especially positive displacements) one should take into account individual influences such as local
conditions and experience. Since the methods defining range of impact zones and values of displacements
are mainly based on measurements of various specific structures, it is appropriate to carry out back analyses
together with the analysis of measurement results for existing structures. [19]
Three stage risk analysis procedure was established which is a common approach in large projects. For the
preliminary and standard analysis stages soil movements behind the excavation were estimated from the

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 14
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

deflected shape of the retaining wall. The relation between wall deflection and surface settlements was
established using an empirical method. At the preliminary analysis stage the risk criteria were simply
specified. Areas with settlement estimates below 10mm and settlement slope below 1/750 were deemed
safe without the need of further analysis. The values selected are in agreement with well-known empirical
criteria. [12]

Figure 2.2:- Flow diagram of the third-party risk management strategy [12]

For deep excavation, dilapidation survey of adjacent structures is necessary to prevent unnecessary
contractual conflict or even lawsuit. Dilapidation survey also deforms part of the requirements by the local
authorities and should be carried out prior to any construction activities at the site. [20]

Normally some of the adjacent structures, especially old buildings, may have already suffered from some
cracks prior to construction activities at the site. Therefore, by carrying out dilapidation survey, the
developer, consultants, contractor and even the owners of adjacent structures will have a clear picture of

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 15
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

the conditions of the structures adjacent to the site. The dilapidation survey report also serves as a reference
for any claims by the owner of the adjacent properties on the damages caused by the excavation (if any).

In most of the deep excavation, some movements of the retained ground are commonly expected. The
dilapidation survey should cover the area within and beyond the influence zone of the excavation. It should
be thorough and with approval of the adjacent owners. The survey should also include the interior of the
adjacent structures and settlement of ground especially between suspended and non-suspended structures.
If there are cracks on the adjacent structures, the direction of the cracks, the dimension of the cracks like
length, width of the cracks should be measured and reported. Photographs should also be taken together
with the measuring equipment (measurement tape or ruler) and included in the report [20].

Figure 2.4:- Response of nearby structures to deep excavation [3]

Urban deep excavations in cities quite often cause ground surface settlement which can occur during three
construction stages:

(1) Retaining wall construction: - as studies show after the completion of the diaphragm walls
and before the main excavation, the accumulated deformation was found to be 40-50% of the total
deformation after the completion of the main excavation. And the ratio of the maximum settlement induced
by the construction of diaphragm walls to the depth of the trench was 0.15% according to in situ monitoring
results.

(2) Ground water pumping: - most problems encountered in deep excavations have a direct or
indirect relationship with ground water. Groundwater induced problems in an excavation may arise from
insufficient investigation of groundwater or geological conditions. Thus, it is necessary to perform detailed
investigations of groundwater and its influences on soil or structures during excavations. [14]

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 16
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

(3) Main excavation: - from observation of the shapes or types of ground surface settlement it can
be observed that the soil at the back of a retaining wall moves forward and down as the retaining wall
deforms under normal conditions, producing ground settlement. The zone of influence of a settlement
should be two or three times that of the excavation depth and in excavation of sandy soils might induce a
zone of influence of settlement about twice that of the excavation depth.

In relation to deep excavation work, any associated accidents can easily result in serious damage to adjacent
structures or cause human casualties. Ground settlement is especial thought to have the greatest impact on
the nearby environment as a result numerical analysis methods and field monitoring are two commonly
used tools to predict and assess the ground settlement induced by an excavation. [14]

Numerical analysis methods performed through collection and evaluation of data of surface settlement
from underground construction in various locations of the construction site while field monitoring done by
accurate and on-time reporting of key measurements of monitoring data obtained from field. Professional
engineering knowledge and experience can be used to interpret the monitoring data results to avoid and
reduce accidents from occurring. [14]
The other point is to consider risk management, as discussed above defining sources and identifying risk
is done in the planning phase then when execution start implementation of the plan is mandatory. Thus in
the execution phase risk management should be implemented to improve quantitative risk analyses, which
form part of good risk management, improvements are needed to methods that can be used to indicate
whether or not and to what extent buildings will be influenced by construction activities. Based on these
analyses, relevant measures can be taken in a cost-effective way. [19]

The need for explicit and clear risk management strategies for large infrastructural works is now largely
recognized. The risks that have more serious consequences and require more careful management are those
inflicted on third parties. The societal tolerance to this kind of risk exposure is quickly decreasing. Third
parties at risk might be largely insensible to the eventual medium and large term benefits of the proposed
infrastructure. Loss of good will associated to third party damage might jeopardize the success of a project
or even its continuation.

Adequate risk management during construction is dependent on accurate and on-time reporting of key
measures from the intensive monitoring system. The system can evaluate the probable environmental
impacts from the critical monitoring data.

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 17
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

2.1.3. Monitoring & Evaluation


Monitoring and quality control are measurements which should create the possibility to foresee unwanted
events and facilitate an incentive to take appropriate measures in order to prevent negative consequences.
Measurements for quality control are usually performed only once and are usually not part of a monitoring
plan while quality control should be part of monitoring for deep excavation. [6]

In urban areas, deep excavations are surrounded with all sides either by roads, buildings or services. It is
very important to have an effective instrumentation and monitoring scheme to make sure that during
excavation and construction of the underground structures, the safety of the surrounding properties can be
secured. The instrumentation and monitoring scheme also allows the design engineer to validate the
design and to identify the need for remedial measures or alterations to the construction sequence before
the serviceability of the retaining structures or the surrounding buildings and services are affected. [20]

In general there are four types of objectives for measuring and monitoring identified which proposed as:

1. Operational/qualitative goals: Decision making with regard to possible occurrence of risks is


improved by measuring failure mechanism development. The progress of construction of the deep
excavation is controlled and checks are performed on the assumptions made for the design of the
deep excavation. Construction safety of deep excavation and surroundings is also guaranteed. The
aim is to reduce uncertainty and gain reliability. In addition, quality control of constructional
elements is an operational goal. Examples are load tests on anchors or piles, or torque measurements
while installing drilled piles. [4]

2. Communicative goals: Deep excavations are often constructed in densely populate areas.
Therefore sound understanding between professionals whom participate in the design and
construction process is very essential. Also it is very important to get the public’s support in order
to prevent complaints that can slow down the construction process. Monitoring can be efficiently
used to demonstrate the construction process is under control. [4]

3. Legal goals: Monitoring can be used to answer questions about liability of building damage.
Monitoring can also be a requirement or boundary condition to authorities’ permission for deep
excavation construction. [4]

4. Scientific goals: Monitoring can provide excellent data for scientific research to improve
understanding of deep excavation (and soil) behavior.[4]

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 18
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

For monitoring and quality control measurement of deep excavation work, the commonly used
instruments are described hereunder:
Table 2.2:- Monitoring Instruments for deep excavation. [20]
Type of Instrument Description
Inclinometers Measures the deformation of wall with depth and the access
tubes are usually installed in the retaining wall
Piezometers or Standpipe Monitors the change of the ground water level that should be
Piezometers located in lines perpendicular to wall to establish profile and
also allows sudden change of pore water pressure
Settlement Markers / Installed on the ground in lines perpendicular to measures the
Displacement Markers settlement of the ground surface profile using levelling
Deep Extensometers Measures the settlement or heave of the subsoil at different
depth and can be installed in the site to monitor the heaving of
the subsoil due to excavation.
Load Cells Installed at the struts or anchors to measure the change of load
at each stage of excavation
Tilt meters Are used to monitor the change in inclination (rotation) of
structural element.

Practical monitoring program is essential to the success of the instrumentation and monitoring scheme.
For deep excavation, usually the monitoring of all instrument are carried out weekly. In the area where
activities like construction of the wall, bulk excavation in front of the wall, drilling of ground anchor etc.,
the frequency of monitoring for the instruments at the affected area should be increased to daily. If there
is any sign of increasing wall movement, strut or ground anchor load above the values designed, the
frequency of monitor should be intensified to daily until the causes identified and remedial measures
carried out. [20]

In order to ensure the quality of works and safety of the supporting wall for deep excavation, the
construction and workmanship shall be closely supervised. The submitting person or his representatives
shall supervise the construction ensuring it complies with drawings, specification and use of the approved
method. Some of the commonly encountered problems at site that requires close supervision and
construction control are:

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 19
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

 During the excavation or drilling of the wall, the construction records should clearly highlight
types of soils encountered, rock level (if any), any abnormalities like sudden drop of drilling fluid
or water gushing out (artesian). Design engineer has to review the records and confirm the validity
of the design assumptions like subsoil types, rock levels and water conditions

 Design engineer should review monitoring records of the instruments and carry back-analysis to
validate the design and also to check the performance of the wall.

 During each stage of bulk excavation in front of the wall, the supervising engineer should make
sure that the Contractor follows the predetermined design level to prevent over excavation deeper
than the design level. Over-excavation increases additional stresses resulting in the increase in
wall movement and deformation of the retained soil. Unnecessary over-excavation might even
cause catastrophic failure of the wall.

 Surcharging at the retained side of the wall should also be closely monitored. Extra surcharge
above the design value increases the soil pressure on the retained soils and may cause increase in
wall movement and even failures.

 The drainage system of the excavated platform in front of the wall is very important because bad
surface drainage would cause soaking and softening of the soil in front of the wall and reduces the
passive resistance supporting the wall.

 If prestressed ground anchors are being used as support for the retaining wall, prestressing and
locking off anchors should be carefully carried out at the site. Overstressing of the anchors or
locking off the anchors at loads higher than predetermined design values can sometimes cause
increase in the anchor load and even to failure. On the other hand, the wall would experience
larger movements if the anchors are understressed. Thus prestresssed ground shall be carefully
examined & overstressing and understressing of anchor should be avoided to prevent over load
and movement of anchor which leads to failure.

 Special care in sealing the anchor holes for temporary ground anchors during construction and
after construction is very important to prevent further lowering of the ground water level on the
retained ground.

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 20
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

 The drilling technique of ground anchors proposed by the Contractor in the method statement
should also be reviewed by the Consultant. For loose soil that is sensitive to loss of materials
through the anchor holes, double acting drilling method with temporary casing should be used.

 If internal struts are used, the connections between the waller beam and truts should be in full
contact and ensure that the required prestress are applied when specified to reduce wall movement.
[20]

On the other hand, vulnerability indexes that have a long tradition for seismic risk analysis are used to
building damage assessments. A vulnerability index allows to explicitly account for aspects overlooked or
poorly modeled in the methods employed to assess induced building damage. Here, four categories of items
were considered in each building to assess its vulnerability to induced movements. These categories were
the following:

a. structural aspects (type of vertical bearing elements, type of horizontal linkages, information
on foundations & so on)
b. relative location and 3D orientation of the building with respect to the construction site
c. functional and esthetical characteristics and
d. state of repair. [12]
Besides the points described above, risks related problems have to be considered in monitoring for deep
excavation work. In the planning phase the sources are identified and in the execution phase the risk
analysis were implemented to get improved method of construction then in this phase risk control and
contingency plans of action will be presented.

Risk Control

Risk control during the construction stages is insured by periodically reviewing the monitoring report of
different variables. The readings are to be compared with the limits set during the design stage. It could be
always ensured through the following:

 Incorporating a design with adequate safety factor and reasonable ground movements that could
be safely tolerated by the surrounding structures.

 Incorporating an inclusive quality control program during construction.

 Performing a pre-construction dilapidation survey to verify the conditions of the surrounding


structures and their safety conditions when subjected to the predicted ground movements.

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 21
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

 Adopting an elaborate monitoring system that suit the risk sources associated with the execution
of the deep excavation. [22]

Contingency Plans of Action


Contingency plans are used in the event of emergency response, back-up operations, and disaster recovery
for construction projects which carry a large element of risk. The contingency plan shall therefore focus
upon ways in which certain events identified through completion of project.
Risk assessments can be militated against using a set of pre-identified procedures. The plan shall be fit-for-
purpose and undergo the following key tests prior to its release:

- Is the plan achievable in reality, should this be required?


- Are the trigger mechanisms for actual activation of the plan clear and realistic?
- Does the plan address anticipated situations in a timely, affordable, effective, consistent manner? [22]
Thus the goal of monitoring is to provide useful scientific information about the status and trends of
various factors affecting the environmental impact of a project, particularly for urban deep
excavations.[14]

2.3. Challenges in Deep Excavation


Numerous engineering problems are likely to be encountered as construction works are going deeper and
deeper down into the ground. Engineers and builders have to face a lot of problems such as the existence
of complicated sub-soil, overcoming of tremendous soil pressure, the provision of complicated temporary
support works and working in congested underground or sensitive nearby environment. [17]

Problems and failure costs related to underground construction (e.g. for underground parking facilities,
basements, infrastructure) are increasingly acknowledged, since it has become clear that they have a large
influence on the image of the sector and the results in terms of money 5-10% loss of effectiveness due to
failure costs compared to 2-3% net profit. [4]

The construction of deep excavation is technically challenging task which requires serious attention and
follow up to avoid any associated accidents which can easily result in serious damage to adjacent structures
or cause human casualties. Mostly these difficulties are ignored and left carelessly but lately could develop
to failures.

Here some cases of the failures observed in deep excavation are presented; primarily the possible technical

issues are described below:

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 22
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

a) Inadequate instability analysis of an open cut excavation can lead to a slope failure which in turn
causing driven piles that had been put into place were subjected to large lateral force that lead to
the piles. The consequence of such a failure in a building foundation, new piles have to be
reconstructed. [9]

Figure 2.5:- Failure of Open cut Excavation that Lead to Driven Pile Foundation Failures- North
Jakarta-2005 [9]
b) Insufficient toe penetration of steel sheet piles, would lead to excessive movement of the sheet pile
would lead to excessive movement of the sheet piles toe, which often lead to kick in failure. This
kick in failure would then lead to large and often sudden sagging of the ground behind the wall. If
this event were to take place near adjacent buildings and utilities, the buildings and utilities would
have had collapse. [9]

Figure 2.6:- Kick in Failure of Sheet Pile-Surabaya-2007

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 23
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

c) The earth pressure induced by soft clay was often wrongly calculated, as a result, a cantilever sheet
piles wall system was in total failure causing the seven to collapse and traffics were severely
interrupted. Further lateral movement of the soft soils was tried to be stopped by installing 60cm
diameter soldier pipe piles. The pipes were also casted with concrete, but it was not successful. The
pipes were eventually slanted to almost 30 degrees. One must understood that once the soil
movement exceeds their yield stresses, it will be very difficult to stop further movement. [9]

Figure 2.7:- Failure of Sheet Pile Walls; Further Soil Movement was tried to be stopped by Soldier
Pipe Failed-West Jakarta 1995. [9]

The above cases shows the failure of retaining wall for very soft to soft gray to black clay, but for strong,
medium to stiff clays the failure of retaining walls with inadequate provision of soldier piles, the capping
beam and the soldier piles moved excessively and broken which is shown below; and due to careless open
cut excavation collapse of a Thirteen stories building in China. Similar problem were observed in Indonesia
whereas nine story building tilted severely and it was totally destroyed. A serious incident of excavation
failure had caused the loss of four lives in Singapore, the collapse of pedestrian bridge and the total cut off
of a major highway. [9]

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 24
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

Figure 2.8:- Ignorance of Open cut excavation led to a building collapse – China [9]

Figure 2.9:- Mass Rapid Transit cut and cover excavation failure – Singapore [9]

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 25
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

There are also technical issues that can lead to failures which can often be ignored or forgotten or wrongly
calculated in the design stage and in the execution phase; some of them are:

a) Water pressures

Fluctuation of ground water tables must be investigated. In area where rain intensity is high, the
difference within the rainy and dry season can be of several meters. When excavation is executed near
a river or sea shore, the influence of high and low tides to the ground water table also need to be
investigated. Failure in estimating the ground water tables shall lead to the wrong calculation of water
pressures acting on the retaining walls, and it can contribute to excessive movement of the retaining
wall. In an adverse condition may also cause failure. Observation of ground water table through soil
investigation boreholes only is inadequate. The proper measures should be performed by installing
observation wells and piezometers, best installed in every significant layer of soil. The measurement
should span over the rainy and dry season. By employing this method, the correct water table during
the dry and rainy season can be identified. The existence of artesian water pressure, if any, can also be
identified. [9]

b) Seepage force

Seepage of ground water toward the excavated area is often forgotten in analyzing the stability of earth
retaining structure. The mode of the seepage depends on whether water can pass through the retaining
wall or not. For open cut excavation and retaining wall systems where water can seep or flow through
the wall. Therefore, it is very important to prevent the ground water to flow out from the slope of the
open cut excavations or through the walls of the retaining wall system. For that it is advisable to install
dewatering wells at the perimeter of the excavation area. For an excavation with impervious retaining
walls like diaphragm walls or secants piles, where the toe of the walls is located in a permeable soil
layer, then it will not act as a water cut-off system. Means water can seep from outside into the
excavation area through the permeable soil layer below the walls toe, which creates seepage force that
increases the effective overburden pressure in the active side of the walls and on the other side reduces
the effective stress in the passive side of the walls. This means the seepage force increases the lateral
pressure to the walls and decreases the passive pressure. A large seepage force may significantly reduce
the effective overburden pressure and subsequently will induce piping and boiling. This effect of
seepage force is often forgotten by inexperience design engineers and contractors. If the retaining wall
is embedded into an impermeable layer, there will be unbalance water pressure within the active and

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 26
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

passive sides. When the base of an excavation is impermeable, say by jet grouting a layer at the base
of the excavation, the base of the excavation is then subjected to an uplifting force. Therefore, to
withstand this uplift force, thickness of the base has to be calculated. Ignorance in calculating this
uplifting force can cause failure. [9]

Ground water seepage through solider piles

Figure 2.10:- Ground water seepage through impervious wall; Unbalance water pressure and
Impermeable layer at base [9]

c) Artesian water pressure

The existence of artesian water pressure can greatly affects the stability of an excavation. The weight
of the soil from the excavation level to the top of the aquifer layer and the friction of the soil wall
system should be able to withstand the artesian pressure; otherwise the base of the excavation shall
fail. This type of failure is known as bursting or boiling. In a smaller scale, the seepage of the artesian

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 27
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

water reduces the passive resistance of the soil. Undetected artesian water pressure beneath an
excavation may lead to unsafe excavation. [9]

Figure 2.11:- Artesian water pressure [9]

d) Squeezing/soil flow and heaving

When soldier piles system is used as retaining structures for soft soils, soil squeezing or soil flow
through the gaps within the soldier piles may the place. This phenomenon may affect the stability of
the structures/facilities adjacent to the excavation area. Therefore, it should be noted that the gaps
within the soldier piles must be close enough to ensure the formation of arching (arching effect) where
the soft soils couldn’t penetrate or squeeze out of the gaps.

Figure 2.12:- Squeezing or Flow of Soft Soil through the Gaps within Soldier piles. [9]

e) Heaving

For braced excavation system, it is quite common that the design engineer forget to take into account
the heaving mode of failure. This mode of failure can take place due to the weight of the soil columns,
of 0.7 excavation width, at the sides of the excavation pushing inward from the bottom of the excavated

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 28
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

area. If the bearing capacity of the soil beneath the excavation area is unable to withstand the soil
column weight, then heaving failure can take place. [9]

Figure 2.13:- Heaving Mode of Failure [9]

In the execution of deep excavation different challenges observe due to a number of causes, such that some
of the cases will be reviewed hereunder:

In Netherland 50 deep excavations were studied while in 61% of the cases the wall of the deep excavation
caused damage. In a quarter of these cases, the installation of the wall played a major role and in another
quarter excessive deformation occurred due to problems with the stiffness (mostly cantilever types) or
strength of the wall. The function of the deep excavation wall is to retain ground and ground water, its
stiffness and strength must keep the wall deformation within acceptable limits. In half of the cases the water
retaining function was compromised, so that leakage from a steel sheet pile wall, secant pile wall,
diaphragm wall or jet grouted wall took place. Damage to the adjacent buildings is mainly caused by
inadequate performance of the wall (including the anchoring system) or by damage during the installation
of the wall. [7]

When failure occurs in deep excavation an important question usually is whether the problem is caused by
the design or the execution of the project. In most of the cases where the study addresses, the design played
a crucial role in the origin of the failures. The designer of the wall (which can either be an engineering firm
or a contractor in an integrated contract) often disregards the installation effects of retaining walls and
foundations. A lot of effort is put into the design of the wall stiffness and related assessment of possible
damage to properties, but the installation and the associated deformations are often excluded. The
reluctance of designers to take issues of constructability into account is often due to perceived liability
issues. [7]

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 29
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

Sometimes the deformations caused by the excavation were not larger than foreseen, but an incorrect
assumption was made about the type, dimensions or quality of the foundation of the adjacent buildings.
This was the major cause of failure in 10% of the total number of projects.

Occasionally the naturally available sealing layer in the soil was absent locally, which had not been
identified before construction due to insufficient ground investigations.

In urban areas, it is not always possible to perform ground investigations as buildings to be relocated in a
later stage are still present. In such a case, it is known in advance that there is an increased risk that the soil
profile might deviate locally. In several cases, the excavation was deeper than designed for, usually for
local elevator pits. Sometimes even the vertical equilibrium, including all the 3D effects was not sufficient
to prevent uplift. Artificial seals such as injection layers are commonly known to be sensitive to
construction practice and might not be water proof, but merely water resistant to a certain degree. If this is
taken into account in the design, this need not be a problem. [7]

Foundation piles in or adjacent to deep excavations may be damaged during the excavation. This can be
caused by horizontal deformation, especially in very soft soil or by swelling. Damage due to the latter can
generally be prevented by adequate pile reinforcement. Other failures are related to anchored concrete
floors. Many floors are anchored with micro piles, which are very sensitive to installation procedures.
Relatively few accidents have occurred, mainly due to the increasing awareness of the sensitivity and the
subsequent implementation of test programs and pile tests.

As per the study, it had been concluded that in 77% of the cases failure could have been avoided if proper
risk management had been applied during the preparation of the project. Risk management also may have
identified the lack of knowledge of the staff working on the project. [7]
During construction of such projects, problem such as settlement of foundation of neighboring buildings
and collapse of earth retaining wall sometimes occurs. The most frequent problem concern dewatering,
temporary earth retaining structures and workmanship. While excessive water pressure often triggers
leakage of water from ruptured part of foundation base leading to base settlement and deposition muck. [8]

On the other hand, when we come to Indian practice there are four major points where problems observed
in relation to foundation construction of deep excavation projects which are discussed below.
a. Excessive Water Pressure

The failure of foundation occurs due to high uplift pressure by water. This force causes uneven settlement
of foundation. This force during construction phase causes complication for laying of foundation concrete
AAU, AAIT, School of Civil And Environmental Engineering
MSc in Construction Technology & Management 30
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

in such a way that it raptures the base of foundation over which steel has to be placed. The uplift pressure
of water can cause seepage of water from ruptured base leading to creation of muck which makes conditions
unworkable and also leads to formation of small ponds where soil has settled. [8]

Thus, investigation revealed improper or less efficient dewatering system which leads to such
complications and if not controlled all these factors have potential to cause catastrophe and delay the project
to a large extent.

b. Improper Dewatering Procedures

Inadequate dewatering procedure for deep foundation construction project cause many undesirable
consequences which include settlement of existing buildings, cracks in walls and slabs of existing nearby
buildings and improper working conditions, collapsing of soil from earth brims /shores. Particularly, if
improper dewatering procedures are followed improper working conditions and collapsing of soil from
earth brims are far most common problems. [8]

The most frequent problem concern dewatering, temporary earth retaining structures and workmanship;
while excessive water pressure often triggers leakage of water from ruptured part of foundation base
leading to base settlement and deposition muck. When dewatering is performed without adequate water-
table monitoring procedures, settlement of the soil surrounding the excavated area can occur.

c. Poor Workmanship Steel Placement and Binding

As, for any structure to gain strength, the reinforcing steel bars need to be placed with great precision,
proper cover and avoiding contact with water, prior to concreting is important. Often the steel gets exposed
to water in these kinds of construction projects prior to concreting.

d. Improper Soil Nailing and Shotcreting

In one project, soil nails were driven and left as shotcreting was delayed. Because of delayed shotcrete the
soil of earth brim started to erode and fall in excavated area. It also added to formation of muck in excavated
area. [8]

In another way one of the major issues with respect to deep excavation management is the bidding system,
where the “lowest bidder wins” system with the intention is to achieve cost efficiency. However, it also
carries the negative side effect that is the tender participants will try to cut cost here and there, very often,
by sacrificing quality and safety. The participants that lost in one tender would bid lower in the next tender,
then the ones lost in this tender will also bid lower in subsequent tenders and the trend goes on until it

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 31
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

reaches unhealthy state where the consultants, contractors and subcontractors don’t have enough profit
margins. The effects of this are:

 Consultants can’t pay qualified engineer in a reasonable manner, they don’t have enough budget to
enhance the knowledge of their engineers; very often they even don’t have money to upgrade
themselves. Unable to attend good seminar and courses, unable to by licensed software, not to say
to develop research and development department. Low and inadequate income make good
engineers seek for other professions. The effect as example the soil investigation report and the
design quality will be lower and lower.

 The main contractors shall press subcontractor pricing, then who will the subcontractor press? The
clear facts are everyone will cut cost here and there. The first stage is trying to cut construction
temporary supporting elements (temporary work), for examples: omit the capping beam that tie
diaphragm walls panels/soldier piles into one system, omit some waller beams in a strutting or
ground anchoring system, reducing the number of struts, cut cost on the dewatering system. When
cutting is successful in one project, the contractors are getting daring from one project to another.
They forgot that the soil condition varies from one place to another. This kind of cost cutting on
temporary work which is often take place in the execution of deep excavation, can lead to fatal
failure. One of the causes of the failure on the cut and cover Mass Rapid Transit excavation of
Singapore mentioned above was improper strutting system.

 The next effect of unreasonably low cost is the consultants/ contractors try to cut overhead. They
don’t have budget to hire qualified engineers, especially good geotechnical engineers. The
consequence is they are unable to see the danger that may take place. Despite the fact that the
engineers very often have to work overtime with no compensation at all, the salaries of the engineer
are inadequate. While the cost of living increases year by year, the engineers’ salary hardly moves
up, sometime they even get reduced salary under the reason of economic crisis. Compared to their
peers in the financial world their salary are way too low, therefore, the capable engineers start to
seek for another professions that give much better compensation. Of course the scarcity of good
and qualified engineers leads to lower quality of construction work.

 The saddest thing of all is the engineers that pressure engineers, just merely to follow the instruction
of the owners. The engineers that act as a quantity surveyor often carry out the “price negotiation”
with very shallow basis. They collected lowest pricing of every items from every contractors, the

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 32
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

quantity surveyor doesn’t (and doesn’t want to) understand geotechnical work. They couldn’t see
the potential problems of low costs and they don’t want to understand what they are negotiating at.
Their attitude shows that they aren’t qualified to be named quantity surveyor. Ones don’t need an
engineer for doing that way of negotiation. Good quantity surveyor must understand what he is
negotiating at, how to carry out the construction work, want to understand and want to seek and to
survey for proper pricing of every item he is negotiating at. He must give feedbacks to the owner
on the proper price level and not only pressing the pricing of the consultants/ contractors/
subcontractors. [9]

2.4. Remedial measures for Deep Excavation


In deep excavation, quality and safety of the construction are key factors so that suitable construction
method, supervision and monitoring system must be adopted. The design assumption must be clearly stated
in the design report and it has to be explained to the contractor. The contractor must pay attention to all the
design assumptions, if there is any discrepancies in the field, the contractor must report and carry out
coordination with the designer. So that problems and unwanted effects can be minimized and eliminated.

Moreover, strict quality control measures should start early during the prequalification of the foundation
contractors. Qualified foundation contractors should have adequate knowledge about the soil conditions of
the excavated area.

When ground water exists that results water pressure proper, dewatering is necessary. As dewatering is the
process to remove the over saturated water in ground and keep the subsoil within a non-saturated condition.
When it is performed without adequate water-table monitoring procedures, settlement of the soil
surrounding the excavated area can occur. It is recommended that planning of a dewatering system should
refer to the original design data, boring logs, and the instrument system data. Due to non-homogeneous and
non-isotropic soil properties, monitoring and, if necessary, modifying construction operations before each
stage of excavation should be performed. Survey and evaluation of the neighboring structures and facilities
before, during, and after the excavation are extremely important. If observations of a neighboring structure
or facility indicate an inadequate foundation, underpinning or grouting of the existing foundation also
should be performed. [8]

The other common problem in the construction of deep foundation is poor reinforcing steel placement.
Such placement requires accuracy, particularly when the foundation is deep. Often the steel gets exposed
to water in these kind of construction projects prior to concreting. The effect of exposure of steel can be

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 33
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

diminished by coating steel with cement slurry coating. This will make a protective layer around
reinforcement bars and will diminish rusting of reinforcement bars. [8]

Whereas, the problem of soil erosion from earth brim is concerned, it can be prevented by carefully and
properly monitoring soil nailing and shotcreting process. One thing should be taken care of that after the
nails are driven into soil, after that they should be locked with the help of mesh of desirable size and a
bearing plate mostly of size ranging from150 sq. m to 250 sq. m, followed by shotcreting. Iron nails should
not be left exposed for a longer period of time and stricter quality control measures should be adopted. [8]

In the presence of utility lines in the construction line the contractor or professionals assigned on the site
required to protect their safety therefore, before starting work its mandatory to determine the approximate
location of utility installations like sewer, telephone, fuel, electric, and water lines or other underground
installations; Contact the utility companies or owners involved to Inform and ask the utility companies or
owners to find the exact location of underground installations. Else if the excavation work exposes
underground installations, the contractor required to protect, properly support or remove them. [1]

Besides, to prevent or minimize the risk of failures and problems in deep excavation the succeeding
procedures are forwarded as remedial measure;

 Appoint a capable geotechnical engineer or expert to assess the problem at hand.

 Carry out an adequate, proper and systematical soil investigation as pointed out by the
geotechnical engineer

 Analyze, interpret and derive the geotechnical design parameters based on the available soil
data. Whenever necessary carry out additional soil investigation. In a large and/or important
construction, geological and seismicity of the area need to be investigated as well.

 Asses and understand the type of construction to be built and also the possible loading imposed
to foundation/ground.

 Carry out the short term and long term stability and the possible deformation of the planned
structure.

 While building the structures, install instrumentation systems, examples: piezometer,


inclinometer, pressure cells, etc. Carry out proper and systematical monitoring based on the
installed instrumentation. Interpret the data properly where independent institution is highly
recommended for this aspect.

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 34
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

 Compared the monitoring measurement taken in the above step with the design (prediction)
made prior to construction. Carry outback analysis and do the necessary correction. Admit the
error when one, as an engineer, made an error in our prediction or calculation and immediately
seek for remedies. If necessary ask for help from a more experience engineer.

 Whenever necessary carry out quality control testing for examples carryout sonic logging test
to check the soundness of piles, perform static loading test to check the capacity of piles, etc.

 In handling a new type of problem which is complex and difficult, it is better to seek an advice
from fellow capable engineers.

 Professionals engaged in the specific work should be honest to their capability and should never
pretend to be clever on everything. Even in the field of geotechnical engineering, the
geotechnical expert will not master every aspect of geotechnical engineering and geotechnical
construction so that this should be considered in mind.[9]

Distribution of earth pressure influences stability, stress, and deformation analysis of the deep excavation.
For problems of excavation, considering that the active earth pressure is usually the main force leading to
the failure of the excavation supporting systems. The passive earth pressure is usually the force resisting
the failure. The pressure distribution shall depend on the nature of backfill.

Stability of excavation is the major design criterion in order to avoid collapse of excavations. Stability
analysis involves the distribution of earth pressures such that provision of support system such as shoring,
bracing or underpinning to ensure that adjacent structures. The professional should be responsible for
maintaining materials and equipment used for protective systems. Defective and damaged materials and
equipment can cause failure of a protective system and other excavation hazards. Thus a registered
professional engineer should evaluate and approves these materials for use. [1]

Besides the remedial measures discussed above the possible focus area to eliminate the problems and
challenges is summarized with pie chart in Figure 14 below. The major areas that require emphasis are
education in design review the failure cases could have been avoided with a proper training and education
of the geotechnical staff and risk analysis that is proper risk management or implement improved method.
Then performing new researches that can address those challenges and failures comes in the third place.
Site investigation is also the other major issue which requires high focus and the base to solve most
problems related to technical subjects; lack of information regarding the adjacent foundations and related
data can however be managed by carefully analyzing all possible consequences. This may be achieved by
AAU, AAIT, School of Civil And Environmental Engineering
MSc in Construction Technology & Management 35
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

identifying possible events, assessing the importance of the event and defining the necessary
countermeasures (and related costs) that eventually should be taken. The same applies for the lack of
ground information. In many cases, it is impossible to do proper soil investigation because existing
buildings are still present on the jobsite. Then just at the start of the project the existing buildings are
demolished and borings are performed often leading to surprises and additional costs. In addition, these
surprises can be avoided with a proper risk assessment during the design process of the project. Monitoring
is the last but not the least subject which requires attention and implementation.

Therefore, it can be concluded that in 77% of the cases failure could have been avoided if proper risk
management had been applied during the preparation of the project. Risk management also may have
identified the lack of knowledge of the staff working on the project. Therefore, the challenge for the
education of geotechnical engineering is to not only teach a good theoretical base but also to convince the
students to apply risk management during the entire design process. Especially the young geotechnical
engineers without experience should be familiar with a risk-based approach for the field of geotechnical
engineering in which practice and experience play a major role. [7]

Figure 2.14:- Focus of possible measures to improve performance [7]

In general, for deep excavation execution prediction of deep excavation performance involving both
stability and limitation of deformation is very important. While stability tells that the excavated wall isn’t
endanger of collapse and whose base doesn’t heave uncontrollably and although the Limit of ground
deformations let’s to know the adjacent buildings, streets and utilities around excavations can be damaged
or not.

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 36
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

3. METHODOLOGY
In this part, the methodology adopted for this research will be discussed. The research approach and the
demarcations are coupled with data collection methods and how the analysis was made.

3.1. Approach and Research Type

There are two types of researches i.e. qualitative and quantitative researches where the division bases on
the way in which the research objectives can be questioned. A qualitative research is a “subjective”
assessment of a problem and takes the form of an opinion, view, perception or attitude towards objects
(that are referred to as an attribute, variable, factor or question). Quantitative research, on the other hand,
is an objective measurement of the problem that investigates facts and tries to establish relationships using
statistical tools. This research is basically of a mixed research type where both qualitative and quantitative
methods are employed. [25].

The research strategy adopted can be categorized as exploratory and descriptive type. It is exploratory
because the research was initiated to identify practical problems and attempts to find present challenge,
factors of challenges and remedial measures in execution of deep excavation. It is also descriptive because
it tries to describe the overall practice of execution management in A.A. construction projects.

In this study, interviews, structured questionnaire and site visits were used in the gathering of data. The
interviews were adapted to collect detailed information about respondent’s experiences and impressions
about Construction of deep excavation in urban and congested area. It was also used to collect preliminary
information to help in structuring questionnaires.

The questionnaire survey was also adapted to get feedback on views of respondents towards deep
excavation work in Addis Ababa construction industry. The site visits involved observations where the
researcher sought to find out how is deep excavation deployed on site with the execution management and
quality assurance practice. The researcher spent time seven (7) months on seven (7) building construction
sites, one (1) from road & one (1) railway by observing the execution of deep excavation work.

The questionnaire survey focuses on the three main procedures and challenges with their remedial measures
to be followed in the construction of deep excavation. Photos were taken during the site visit to support the
data collection.

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 37
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

3.2. Data source

The research data was collected based on the stepping points found in the literature review on the
execution management of deep excavation. The sample were drawn from Clients, Addis Ababa City Road
Authority and Addis Ababa Light Railway Transit (AALRT) for underpass road and railway projects
respectively. For building projects in A.A. under construction clients, consultants and contractors
involved in deep excavation and skilled professionals in related construction work were taken. Those
elements were selected without limitation except their professional skill and experience in the specific
work.

3.3. Data collection

The data collection approach adopted for conducting this research includes both primary and secondary
sources. Questionnaire, interview, and observation provide the primary data for this study while the
secondary data sources include journals, internet sources, as well as reviewing related archived documents
on execution of deep excavation. These different methods of data collection have been used in order that
the data or information obtained from one can be supplemented by the others whereby the collected data
will give multiple evidences.

3.3.1. Questionnaire

Questionnaire provides firsthand information for the subject matter of a research as it is focused on issues
which further serves as a survey to understand the main concerns and attitudes of respondents towards the
problems. In this study, questionnaire was administered to some randomly selected stakeholders in the
construction of deep excavation. [25]

The study has used the data sources to produce the following basic documents: respondents’ documents
and site observation. The respondents’ documents were collected using questionnaires from clients
(project owners), contractors and consultants. The two basic types of survey questions which are:
questionnaire have been used in this research.

The questionnaire have been categorized into two; open-ended and closed-ended groups in which the first
group contains four part where part I raises general questions related to the planning of deep excavation
work that involves the design, construction planning and health & safety planning. Part II contains
questions related to execution practices on construction and health & safety implementation. In Part III

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 38
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

the respondents were asked how they perceive the practice of monitoring and evaluation in deep
excavation work. And Part IV deals with questions related to technical and non-technical challenges.
Finally, in the second group respondents were asked to give their experience of challenges with the
remedial practices in execution management other than mentioned in the first group.

3.3.2. Interview

Interview is one of the primary data collection methods which is flexible and adaptive way of investigating
underlying motives of a subject in a way that self-administered questionnaires cannot [26].

The interview undertaken for this thesis was based on semi- structured style. This type of interview has a
predetermined set of questions (generalized form of questionnaire) with a flexible order depending on
what the interviewer perceives the subject matter by looking at the respondent capability and exposure or
experience. The interview for this thesis was done with eleven reputed professionals of the sector, who
have strong expertise with regard to the deep excavation work in focus. From these interviewed
professionals, two from client, four from consultants and the rest five were from contractors.

3.3.3. Observation

Observation to some selected projects were used in this research to support or supplement responses and
arguments found through questionnaire and interview. Nine undergoing construction projects who
engaged in deep excavation work were observed to find out how deep excavation is implemented and
managed in local construction projects. Photographs were taken as supportive & descriptive data.

3.3.4. Secondary Data Sources

The secondary data were obtained from relevant books, journals, magazines and research papers which
have been used to perceive the practice of deep excavation management. These secondary sources provide
a general understanding of the subject area by presenting a wide range of ideas in the field which help to
supplement other specific information obtained from the primary data sources.

The data collection was the most tiresome part in this research. The major difficulty was the respondents’
unwillingness to respond and reluctance to react as per their promised schedule that made the research
stressful for the period of data collection.

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 39
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

The responses for the structured part of the questionnaire are organized based on Likert’s-scale of five
ordinal measures of agreement towards each statement (from 0 to 4) as shown below, which are Likert
scale’s intervention that is attributed by Dr. Rensis Likert (1932), who described the technique for
measurement of attitudes in scientific way. The reasons for adopting this simple scale are:

• to provide simplicity for the respondent to answer, and

• to make evaluation of collected data easier

Likert’s-scale is important to know respondents' feelings or attitudes about something. The respondents
must indicate how closely their feelings match with the question or statement on a rating scale. [26, 27]

After identifying the factors that have impact on the management of execution of deep excavation,
respondents were asked about the impacts of each factors of deep excavation based on the following
choices.

0- No significance

1- Minor significance

2- Average significance

3- High significance

4- Extreme significance

3.4. Data Analysis


Since Likert type of questionnaire used, the analysis have been performed by identifying the Relative
Importance Index (RII) method. The relative importance index method is used to determine the relative
effect of the factors affecting the performance of the construction of deep excavation. The clients,
consultants and contractors experience on the effects of the factors are used as an input in the formula. The
relative importance index is computed as follows. [28, 29]

Weighted average

RII = ∑W

AxN

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 40
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

Where:
W is the weight given to each factor by the respondents and ranges from 0 to 4
A = the highest weight = 4
N = the total number of respondents
N n1 n2 n3 n4 n5
5(0-4) ES VS MS SS NS

RII = 4n1+3n2+2n1+1n4+0n5
4N

Subsequently, the statistical tools for data analysis and the background, statistical results obtained from
the data are discussed in chapter four.

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 41
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

4. ANALYSIS OF FINDINGS AND DISCUSSION

4.1. Introduction
This chapter deals with the analysis of gathered data and presents discussion from the result of analysis on
the major issues by combining with literature review. The data collection was carried out through interview,
questionnaire and observation in randomly selected construction projects. Also for the purpose of this
research, site visit of undergoing projects was accomplished.

The aim of this research is to assess the practice in planning, quality assurance services and execution
management, identify the problems and deals with the gaps that need to be improved in planning, quality
assurance and execution of deep excavation.

The procedure applied to analyze the result of the questionnaire is by forming the Relative Important Index
(RII) for the factors of challenges and unwanted effects. The question presents opportunities of responses
as Extreme Significant (ES), Very Significant (VS), Moderately Significant (MS), Slightly Significant (SS)
and Not Significant (NS), to identify the factors as the frequency of occurrence of the variable and the
percentage of respondents’ answer were ranked for the analysis purpose. Through this ranking it was
possible to identify the major causes for the challenges and unwanted effects that have impact in the
management of deep excavation construction.

4.2. Responses to Survey


This study has focused on directly participating key professionals of the construction stakeholders who
were engaged in the construction of deep excavation for high rise building, under pass road and railway
projects. For key professionals of randomly selected projects detailed structured questionnaire was
distributed. To make the analysis more comprehensive the questionnaire were dispersed to contractors,
consultants and clients of different projects; a total of 52 questionnaires were distributed out of which 39
(75%) were filled and returned in building, road and railway projects. Table 4.1 and figure 4.1 present the
illustration of response rate in terms of organization and project type. In addition, ten reputed professionals
of the sector (two from client, four from consultants and five from contractors), who have strong expertise
with regard to the deep excavation work in focus, have been interviewed and their responses have been
supplemented with the questionnaire survey.

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 42
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

Table 4.1:- Frequency and percent type of organization


Type of Distribution Response Response
Organization in No. in No. Rate in %
Client 8 7 87.5
Consultant 16 13 81.25
Contractor 28 19 67.86
Total 52 39 75

Figure 4.1:- Frequency and percent of response by type of project

40
35
35

30 27
No. of Questioner

25

20 No. of Distributed
Question
15
11
9 No. of Replied
10 Question
6
5 3

0
Building Road Railway
Type of Project

% Response by Type of % Response by Type of Project


Organization

18%
8%
Client
49% Building
23%
Consultant 33% Road
Contractor 69% Railway

As we can see from the table 4.1 and figure 4.1 the response rate of contractors with respect to the
distributed amount of questionnaire is better than other parties.

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 43
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

With the category of projects railway has the least response as their participation was very much less due
to unwillingness of stakeholders.

On the other hand, nine undergoing construction projects which were engaged in deep excavation work
were observed in detail though the findings from the observation is accompanied in the analysis of data
found from questionnaire and interviews.

4.3. Deep Excavation Works Execution Management Practices


In conducting this research, the primary concern was to identify how deep excavation implemented in
Addis Ababa construction projects. Engaging deep excavation widely, performing geotechnical
investigation and testing of construction materials are appreciative practice. Poor experiences in safety &
health management, less protection of the surrounding environment, accident, and failures found as a result
of instability of excavation and less implementation of quality assurance and construction work
methodologies are deemed as bad experiences in A.A.

As deep excavation requires careful planning to attain the intended quality, effective and efficient
utilization of resources with safe working condition; different mechanisms are applied or adopted but faces
many challenges as it is performed in urban and congested area. In the local construction practice especially
in A.A. deploying deep excavation has its own limitation and challenges. To determine the factors that
influence the execution management and the causes that cultivate problems and unwanted effects, the
hypothesis factors were developed in closed question where the rest practice with the remedial measures
was incorporated with open questioners. Thus the outcomes of the questionnaire discussed further below.

Hereunder the most common practices that occur frequently in the local practice were construction of deep
excavation are presented by pointing out the highly ranked items that have greater values of Relative
Important Index (RII). Whereas the whole analysis result of the questioners is presented in the appendix C.

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 44
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

Questionnaire result by RII


80
75
70
65
60
55
Weighted Average (%)

50
45
40
35
30
25
20
15
10
5
0
18
2b

5b
5e

11

13

16

20
22
24
26

29
31

33

36
38
40

42
44
9
1

12b

15b

17b
17d

28a

28h

32b

34c
34e

41b
41d
17f

28f
Questionnaire No.

RII

Figure 4.2: Result of questionnaire using RII


From the result of the first part of the questionnaire, which is the closed questioner, the most critical factors
that influence management of deep excavation are screened out by rank of their result of relative important
index. As we can see in figure 4.2 the result shows that the factors mentioned in questioner have high
intensity of occurrence as per the RII analysis which describes how much the deep excavation construction
in A.A. lack good execution management practice. More than 90% of the factors get results above 50% or
greater than 0.5 RII which are labeled above the green line. This shows that the local practice in terms of
management of deep excavation in all three phases, i.e. during planning, execution and monitoring and
evaluation stage is facing challenges.

For this research purpose, the factors found above the red line in figure 4.2 are selected for discussion and
they are presented in table below.

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 45
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

Table 4.2:- Top ten factors of deep excavation

Factors in execution of deep excavation RII Rank


Lack of planning to engage safety and health management 0.810 1
Lack of recording construction events that focus on Soil 0.770 2
characteristics
Lack to implement safety and health management plan 0.752 3
Lack of adopting appropriate construction works methodology 0.736 4
Lack to perform monitoring for risk control through incorporating 0.730 5
an inclusive quality control program during construction
Lack of close supervision and construction control 0.721 6
Lack of recording construction events that focus overhead & 0.717 7
underground utilities
Lack of allocating support system for workers 0.708 8
Lack of recording construction events that focus on: Sudden drop
0.702 9
of drill fluid or water gushing out(artesian) if any
Lack of recording the present status of the existing structure 0.700 10

1. The primary factor found to be the lack of planning to engage safety and health management that
comprises identifying the hazards, assessing the risks to the work & staffs and determining
appropriate control measures in consultation with all relevant stakeholders in the work. Thus in
planning phase forecasting of risks is important. The risks are likely to be the presence of ground
water, ground movement due to excavation, sliding of the ground, presence and protection of
underground utilities with their impact on workers and the work itself and so on but they are
neglected. As indicated in the literature review part, for deep excavation safety and health are
forecasted and planned by comprising regulations especially with respect to confined that shall be
designed & certified by professional engineer.
2. Lack of recording construction events that focus on soil characteristics is the other top factor that
results unwanted effect in deploying deep excavations. Sufficient depth soil investigation to know
the correct soil characteristics is mandatory before design that helps the designer to use the correct
geotechnical data for his/her design which makes the design more practical. From the literature
review, it is very important to have an effective instrumentation and monitoring scheme to make sure

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 46
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

that during excavation and construction of the underground structures, the safety of the surrounding
properties can be secured. The instrumentation and monitoring scheme also allows the design
engineer to validate the design and to identify the need for remedial measures or alterations to the
construction sequence before the serviceability of the retaining or the surrounding structures and/or
services are affected.
3. In third stage problem that is found in execution phase, which is lack to analyze the application of
safety and health management system. Even if it is planned to use safety clothes & equipment the
implementation is very rare. Though there is little improvement in implementation of safety
equipment and overall safety management of most our contractors and consultants don’t use safety
clothes and equipment. The attitude of incurring additional cost in using such equipment isn’t purely
changed. Still in our construction industry analyzing of cost for using this equipment and costing for
medicating injuries and rectifying accidents aren’t performed and the out coming benefits aren’t
defined.

Figure 4.3:- Lack of proper usage of safety & health cloths

4. The fourth factor is lack of planning appropriate construction works methodology. The construction
methodology shall be planned in suitable manner for workers. Allocation of machineries and
materials, procedures of activities, how to excavate deeper without disturbing the surrounding
ground, structures and so on must be studied and planned before handing over to execution. However,
the consultant and design engineers do only the design of the structure to be constructed with deep

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 47
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

excavation but the methodology starts to be observed when construction is ahead and problems being
observed. Improper execution brings accident to workers and wastage of resources. As described in
the literature construction works methodology defined in the design stage as one major task so that
planning of construction procedure, arrangement of site, locating of mobile equipment, stability of
adjacent structures and related points have to be done by design engineers & other professionals with
consultation of all responsible personnel. This allows to see the means to define contingency action
plan for problems or failures that might occur.
5. The other cause brings out to be lack to perform monitoring for risk control through incorporating an
inclusive quality control program during construction. One of the major tasks that should be
performed in executing deep excava tion is monitoring risks to attain qualified output with efficient
utilization of resources. By any means especially for underground structures planned quality should
be attained precisely. For this it is important for the designer to communicate full design criteria to
all parties involved in the construction and to monitor the quality of the work throughout the
construction.
6. Lack of close supervision and construction control is factor for unwanted effect in monitoring phase.
The construction and workmanship shall be closely supervised by the consulting engineer to ensure
that the construction attains safety and quality which complies with drawings, specification, standards
and use of the approved method.

Figure 4.4:- Unsafe & inappropriate working condition; poor reinforcement placement

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 48
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

7. Lack of recording construction events that focus on overhead & underground utilities is the seventh
major factor that inhibits well implementation of deep excavation work. The presence of these utilities
affects the construction work by any means. Mostly our cities underground utility lines exact location
is not known. Most of utility providing companies have no plans that show their exact locations. This
makes the designers to have no information of the locations so that they can’t design with the
consideration of protecting the utility lines. Thus the engineers prepare their design by guessing the
locations therefore, as the excavation work begins it becomes difficult to directly interpret the design
to construction, the utilities comes out as obstacle. This can be seen in the figure below (Figure: 4.8).
So that studying of their locations, impact in construction & means of protection should be well
defined. As a result lacking such information may result up to change and rework of design. So that
close supervision with recording of events can results the protection of underground utilities.
8. Lack of allocating support system for workers appears to be the factor for the consequence of injuries
of workers. Mostly supportive (temporary) works are ignored by our contractors for the purpose of
cost reduction and the consulting engineers doesn’t force the contractors to implement as necessary
items. This is because of the attitude of less value given for workers particularly unskilled staffs even
though international safety & health regulations obligate to allocate support systems and to assure
their safeness.
9. Also lack of recording construction events that focus on sudden drop of drill fluid or water gushing
out (artesian) is factor that results challenge. Such monitoring action is not accustom in A.A. deep
excavation work unknowingly or ignorantly. As of this, recording events can lead to forecast damages
as instability of the ground that could come out of artesian pressure and can allows for defining
preventive solution.
10. The last but not the least top ten factor is lack of recording the present status of the existing structure.
It isn’t accustomed to address prediction of the status of bordering structures. Mostly it’s considered
as performing unnecessary work and costing extra amount. Even if it is the responsibility of the
construction party to protect it. But the real fact isn’t this, after accomplishment of excavation work
problems started to appear where that require additional analysis, work and cost to solve existing
problem. Also to protect further challenges.

In addition to interview and site observation the following points are perceived. As of local construction
industry the quality assurance done for construction materials observed in the research is as a good trend.
During the construction of deep excavation it’s usual to construct temporary structures as shoring with pile

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 49
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

for temporary support of the natural ground for projects that cover large area especially in areas where
there is adjacent structure like building and main road.

Figure 4.5: Shoring pile for the support of natural ground


On the other hand, quality of fresh mixed concrete checked with slump test and compressive strength test
also checked with cube tests. This is done in 70% of the observed sites; the slump test done per a truck mix
delivered on site and cube test done per 100m3 of mix of concrete.

Figure 4.6: On site slump test of concrete

In most of road projects usually short period is given for the design stage, whatever kind of project (huge
or small) planned to construct which shows there is no emphasis given for the design. The ‘make it quick’
principle results unsafe design, unsafe structure and unsafe working environment. Correspondingly there
is lack of soil investigation only test pit data are done, no pre design investigation because of poor

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 50
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

understanding about geotechnical investigation output and importance. Specially, for deep excavation that
need to be constructed in urban area proper soil investigation is very important but everyone’s focus is on
the cost incurred to perform the investigation. Most clients require investing less amount of money as much
as possible & the consulting engineers don’t force their clients. Thus, in order to avoid additional cost the
preferable and most practicable way is to ignore it and do the design without having sufficient investigation.
Therefore, the drawback isn’t limited to design but also goes to construction.

The other point is with respect to construction work methodology, it usually comprises the procedure of
tasks, the description of protection means of nearby structures, the limitations of using excavation
machineries, scheduling every task required (w.r.t material, budget, etc...). Most contractors submit their
construction methodology but remains on paper since they aren’t studied well and difficult to be
implemented. Also the consultants doesn’t evaluate and question the practicability of the methodologies.
Even if, the contractors provide work schedule, it’s usual to work by trend which makes the work very
difficult to manage. Besides all mentioned shortcoming, in almost all projects that engage in deep
excavation work face cost over run and time extension as major challenging issues.

Figure 4.7: Lack of protection wall & sliding of the ground results collapse of the fence

In the figure 4.7, the contractor was the owner of the project who have no experience in deep excavation
work. This contractor got high grade construction license but lacks work experience and experienced
professionals for the deep excavation work. So it was very difficult to handle it. The excavation started at

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 51
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

one time then left as it is for months. After that again the excavation started but done without providing
any support to the ground and following proper construction procedure. Whether the excavation doesn’t
preserve the angle of repose of the soil or don’t protect it with bracing or shoring. Thus, the soil slides
down and cover the casted concrete foundation structure, also the sliding collapses the fence. Similarly the
foundation structure covered with water because it’s left ignorantly. While to continue the construction it
is obvious how much it would cost.

As the primary isssue of this research is to investigating the local practice of execution of deep excavation
construction in different projects, the A.A underpass light railway is the other one to consider. During
execution of this infrastructure most of the work is done as per the design and plan. But some challeges
were observed like safety problems, time extension, cost over run and right of way problem.

In most of road construction sites right of way problems which wasn’t considered during design that
requires design revision during execution phase appeared. Also poor site fencing were observed which
leads to falling down of vehicles and pedestrians into the excavated area that results in different accidents
up to death of persons.

During the execution of deep excavation, larger injuries were reported around kality, legahar, mexico &
St.Lideta areas. The problems were related to safety that results death of more than five persons and high
injuries of more than ten individuals recorded. The cases were due to sliding of the excavated soil, poor
construction management corresponding to site fencing, arrangement of construction materials,
arrangement of equipment in the project site and also lack of security & safety of workers.

In most of the assessed projects, geotechnical investigation done with the available professional. While the
contractors ignore to consider and implement the results. Due to this contractros lack to know the specific
type & cohesiveness of the soil that leads to ground related challenges. Sliding of the ground is one of the
challenges, the reason behind this lack of defining cohesiveness of the soil which leads to determine the
angle of repose during excavation. Cutting of the ground without keeping the appropriate angel of repose
results sliding of the ground. From the data found in one of the projects mentioned above where death of
persons recorded, the cause of failure was due to sliding of excavated soil in to workers who were inside
to drill the rock using vibrator of the excavated area.

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 52
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

On the other sites, the failures were due to poor site fencing which leads to falling down of a kid into
collected water of deeply excavated site. Also breaking of pully rope, unsafe rear driving of dump truck
and poor site fencing are found as major reasons. [24]

The other concern is the weather condition, deep excavation of most road project and some of building
projects visited were performed in rainy season, which makes the construction more challenge. In most of
A.A. area the sub surface soil found to be soft clay from the result of geotechnical investigation and
observation during site visits. In projects that were executed in dry season, the instability of the soil wasn’t
as such difficult and easily manageable. While those projects that were being executed in summer season
faced stability problems of excavated ground. Since clay soil loss its strength as it gets wet it requires
additional precaution to prevent the consquence of instability, that could be provision of supporting system
to attain stability of the soil.

During interviewing of professionals engaged in railway project, it’s found that there were big gap in
implementation of safety and health management. More than 70% of the challenges were occured due to
safety and health while this problems observed the assigned professionals engaged in the project were
enforced to assign traffic and safety coordinator (TSC) to secure workers and neighboring society. After
the deployment of TSC related problems and traffic congestion have been minimized. Risk identification
related to the work wasn’t developed during planning by identifying the actual situations.

The other issue in railway project found to be time extensions, as reported by the interviewee the time
extensions were due to right of way and addition of work items. By the time of planning of construction
the right of way issue wasn’t analyzed thus during execution it appears as challenge and forced to incure
additional cost. Extending the project from the initial scope created additional work items that resulted
extension of time which also increased cost of the project. In one construction area of the Light rail way
project that engage deep excavation water leakage found as problem. The ground water was found to be
near more than expected, even if water proofing membrane was used, it wasn’t effective. Thus, the
construction crew use other means of technology as shotcreting of cementious water proofing to prevent
the leakage of the leakage.

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 53
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

Figure 4.8: Practice of AALRT projects; lack of dewatering & protection nearby structure

In the local construction industry in most of the deep excavation projects uses specification and standards
as guideline for quality assurance & construction methodology of overall excavation work and supporting
structure construction presented below.

 BATCODA technical specification & designers specification which gives recommendation of the
steps of excavation and bracing technique
 ERA specification & AACRA manual construction specification
 FHWA (Federal Highway Agency) & British standards
 AASHTO
 DIN
 FIDIC technical specification
 European standards plus software’s like Plaxis & DeepXcav
In addition to these standards, other excavation management standards are used. Also check lists &
construction manuals which are prepared by individual organizations including professional’s experience
are implemented. From the information gathered through interview & observation the trend of using
checklist and quality manuals isn’t as such remarkable. Commonly the checklists are used in 75% of
sampled projects but the construction or quality assurance manual is used in only 40% of the assessed
projects. These manuals are most of general standards which aren’t quietly adopted for the specific work
and condition of the project.

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 54
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

4.4. Problems and Challenges in the Execution of Deep Excavation


In this section the problems and challenges commonly found in A.A. Deep Excavation work will be
discussed. Repeatedly mentioned challenges are found to be safety and health management, lack of
recording construction events, wrong calculation of earth pressure and lack of well qualified and
experienced professional and failures as differential settlement & cracks on bordering structures, collapse
on adjacent structures including small injuries up to loss of lives of workers and neighboring society has
been found as outstanding ones.

Besides the data collected from the questionnaire, other problems & challenges practiced by respondents
that are specified as technical and non-technical challenges are evaluated with RII and ranked below.

Table 4.3:- Technical & Non-Technical challenges in deep excavation

Factors in execution of deep excavation RII Rank


Technical Concerns
Inadequate instability analysis of an open cut excavation 0.616 8
Insufficient toe penetration of sheet piles 0.638 7
Wrong calculation of earth pressure induced by soft soil 0.732 1
Wrong calculation of Water pressure, Seepage force, Artesian water
0.669 6
pressure, Squeezing/soil flow & Heaving
Inadequate performance of the wall (including the anchoring system) 0.592 9
Damage during the installation of the retaining wall 0.444 14
Incorrect assumption type, dimensions or quality of the foundation
0.589 10
of adjacent buildings
Lack of adequate knowledge & experience of working staffs 0.586 11
Lack of proper dewatering procedure 0.533 12
Lack of proper reinforcing steel placement 0.375 15
Inadequate soil nailing and shotcreting 0.476 13
Non-Technical Issue
Lack of proper management of bidding system 0.692 4
Lack of adequate evaluation of technical qualification of bidders 0.710 3
Difficulty to use lowest bidder wins system which results:

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 55
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

 Inability to assign & pay qualified engineer 0.714 2


 cutting overhead cost & ignore cost of temporary works 0.687 5

Similar to the section 4.3, Relative Important Index (RII) of challenging factors calculated and highly
ranked items that have greater values RII are highlighted for detail discussed.

As it is observed in the table above, the most frequently occurring problem is Wrong calculation of earth
pressure induced by soft soil which is a technical issue that have been discussed in the above section and
can be elaborated with one project which face failure.

Wrong calculation of earth pressure due to soft soil is resulted as factor of failure in deep excavation work.
In designing a retaining structure to support the sides of an excavation, the magnitude and distribution of
the stresses and movements likely to be induced in the structural components must be well estimated. Based
on the geotechnical result identifying the cohesiveness of the soil and checking of angle of repose of the
ground shall be well analyzed before proceeding to excavation. Both temporary and permanent works of
deep excavation should be considered in depth before proceeding to construction. While precise calculation
of earth pressure by the qualified geotechnical engineer allows to determine the suitable support system
that preserves the ground movement.

Figure 4.9: Wrong calculation of soil pressure results in sliding & failure of foundation

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 56
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

As seen in the above figure (Fig. 4.9), which was one of the observed under construction site, faced sliding
& failure of foundation due to wrong calculation of earth pressure. Since they got wrong result they ignored
constructing temporary supporting structure. Thus, the soil of excavated side slides highly and covers the
reinforced concrete footing pads with the reinforcement bars of the foundation columns. Only the top of
reinforcement bars of the foundation columns left uncovered as symbol. Even though ignoring of
supporting structure was done to reduce the construction cost, in actual condition the cost wasn’t reduced
rather increased to rectify the damaged foundation structure and to construct retaining wall to avoid further
collapse.

In the same manner, the other visited site encountered similar challenge as shown in the figure below (Fig.
4.10). Wrong calculation of earth pressure resulted sliding of more than 6m horizontal ground and falling
down of temporarily constructed facility rooms and collapse of foundation structure found.

Figure 4.10: (A) Sliding of ground due to wrong calculation of earth pressure

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 57
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

Figure 4.10: (B) Sliding & collapse of structure due to wrong calculation of earth pressure

In one of the observed site, shown in Figure 4.11 (a), the stakeholders tried to avoid the construction of
temporary support structure since they have wrongly calculated earth pressure result. Meanwhile, it resulted
in high ground sliding & collapse of nearby feeder road occurs. Then to rectify and prevent further failure
they take immediate remedial action, construction of concrete retaining wall, which wasn’t planned &
designed before. Thus they incurred additional cost for this.

(a) (b)
Figure 4.11: Sliding effect on utility lines and the sliding results unsafety environment neghborings
On the other hand, the consequence of avoiding this item of work besides the cost isn’t analyzed well.
Hence many injuries, construction failures and damages observed. The problem started from sliding of

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 58
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

ground which results failure of feeder road, nearby structures, utility lines, and collapse of reinforcement
bars installed for construction of foundation.

The others top five challenges are non-technical issues that are found to be very critical problems in
execution of deep excavation work. The secondly and thirdly ranked factors of challenges are lack of
adequate evaluation of technical qualification of bidders and difficulty to use lowest bidder wins system
which results Inability to assign & pay qualified engineer.

The second mostly observed cause of challenges is found to be difficulty to use lowest bidder wins system
which results inability to assign & pay qualified engineer. In the local construction industry the bidding
system that is being practiced is the “lowest bidder wins” system which has negative consequence in
attaining qualified and well experienced professional. Contractors and consultants can’t pay qualified
engineer in a reasonable manner, they don’t have enough budgets to deploy the knowledge and experienced
of their professionals as they win projects with least bidder. As a result it limits them the accomplishment
of safety and quality of a given project by disbursing available resources effectively & efficiently. The
outcomes turn out to be poor management of safety and health, lack to adopt appropriate construction
works methodology, missing the assessment of hazards, failing to assess the present status of adjacent
structures, presence of overhead & underground utilities & their effect on deep excavation work and so on.
Thus the major means of failures or unwanted effect resulted due to lack of engaging experienced & well
educated professional. Hence, the reason that forces to lack such professional should be well analyzed and
rectified.

The third most frequently practiced challenge found to be lack of adequate evaluation of the technical
qualification of bidders. In most projects technical qualification isn’t considered as the major factor for
evaluation of bidders for deep excavation project. Since deep excavation requires special and well qualified
professionals the technical qualification with respect to professionals, machineries, working methodology
and experience in this specific construction work is very important. Awarding most qualified bidder can
result safety and quality of work with effective utilization of resources, but in the local case this is rarely
practical. Most bid evaluator’s focus on the budget offered for the work before the qualification. However
such evaluations output doesn’t end at awarding stage but the effect shines during execution of the work
by poor management of material, workmanship, schedule, safety and with poor quality assurance method.

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 59
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

The fourth one is lack of proper management of bidding system, poor bidding management system is one
of the major cause of problem and challenge in execution of deep excavation. In almost all local
construction industry less emphasis given for bidding system which results a number of problem in
execution, while the effect exaggerates when we come to deep excavation. As explained earlier deep
excavation implemented for the construction of huge & unique infrastructure that requires special care so
that it requires the engagement of best suitable bidder found from proper bidding system. Once this system
rectified it will solve other causes of challenge even non-technical and technical issues.

The fifth top factor challenge found to be difficulty to use lowest bidder wins system which results cutting
overhead cost & ignore cost of temporary works, since one bidder come out with lowest bid then on the
next it’ll be forced to cut cost of some items to be least bidder, else it’s difficult to include every items of
work with profit. Thus mostly lowest bidders cut the temporary works which is very important item in deep
excavation and also cut the overhead cost since they can’t make their offer the least one. While they can’t
overcome the whole work without profit, so it’s assumed to be engaged without profit though they don’t
work for endowment except to get profit whatever the amount it could be.

From the observation data, one of the challenges was to protect the adjacent structure. As a result of this
collapse of two feeder roads found, in one of this roads the debris of the road demolishes the reinforcement
bar prepared for the construction of foundation. To rectify this damage they went for the construction of
retaining wall as shown in figure 4.12, which wasn’t planned and considered before the collapse.

Figure 4.12: Construction of retaining wall

From the challenges occur during deep excavation work the respondents stated some additional factors
other than mentioned in the questionnaire and presented hereunder:

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 60
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

Table: 4.4:- Factors of challenges


No. Factors of challenges Response
rate
1 Lack of well qualified and experienced professional for the work 6
2 Lack to allocate specialized tools & equipment as per the required need of
3
the project
3 Poor planning of work 3
4 Design problems; incomplete and non-detail design 3
5 Poor capability in performance by the contractor & consultant 3
6 Poor design consideration & poor geotechnical investigation schedule for the
2
projects
7 Poor communication between main & sub-contractors and also with
2
consultant
8 Lack of experience of machine operators & failure of machineries 2
9 Lack of identifying location of utility lines in advance 2
10 Lack to assess the presence & level of the ground water table 2
11 Lack of experience for shoring work and keep shotcrete wall thickness with
2
fixing of reinforcement bars behind the pile
12 Lack of proper site management 1
13 Frequent change of demands from clients after starting of the construction
1
that affect the original design
14 Lack of selecting appropriate type of foundation and deciding foundation
1
depth
15 Lack of monitoring the status of the work & adopting monitoring instrument 1
16 Problem in using design standards & quality assurance manuals 1
17 Lack of deploying sufficient budget for intended works 1
18 Lack of full construction document 1
19 Problem regarding the type of work required for the project 1

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 61
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

Figure 4.14: Deformation of re-bars due to sliding of the ground & presence of ground water
In another scenario, in A.A. construction projects mostly we face very high potential of collapse or
failure of excavation. When the failures first observed the responsible professionals haven’t take any
action to rectify or prevent further damages. Then as we can observe in the above figure (Fig. 4.14) the
sliding of the excavated soil continues and deforms the reinforcement bars placed to cast mat foundation
and beams. Consequently, this challenge poses hazards to workers & equipment. On the other case, lack
of securing the nearby structures during deep excavation resulted settlement of the surrounding ground
that created large cracks on the main joints of nearby building. This creates discomfort to the society to
those who uses the buildings. Such challenges are shown in projects observed in figure below (Fig. 4.15).

Figure 4.15: Effect on neighboring structure


Accordingly these failures occur due to different problems & challenges stated in the questionnaire and
also described by respondents. The challenges described by respondents are presented as follows:

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 62
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

Table: 4.5:- Failures or Damages mentioned from respondents


No. Failures or Damages Response
rate
1 Differential settlement & cracks on bordering structures 5
2 Collapse on adjacent properties; sliding of neighboring road; fail to protect 5
foundation of neighbor building (building holds on air)
3 Structural failure of piles, overturning of some piles due anchoring with 3
unstrengthen temporary structure and with unknown source of water flowing into
the construction site
4 Damage to utility lines, as storm water lines due to losing their support 2
5 Damage of structure due to poor workmanship in constructing retaining structure 2
& its backfill material
6 Failure of support structure 2
7 Sliding of shoring pile due to failure of shotcrete concrete 2
8 Falling down of shotcrete wall due to improper execution that result the surcharge 2
pressure creates further collapse of the structure and accident for workers
9 Sliding of the ground 2
10 Collapse of retaining wall by sliding 2
11 Serviceability failure of nearby structure 1
12 Damage of structure due to unforeseen ground water 1
13 Collapse of building due to shear failure of the foundation soil 1
14 Failure due to sliding of excavated soil 1
15 Horizontal movement of foundation structures 1
16 Settlement due to construction procedure & inappropriate type of retaining wall 1
17 Fall down of HCB fence wall of neighbor during excavation and Sliding of 1
ground
18 Torsional failure of canopies ( cantilevers) 1
19 Failure to protect permeability of water through structures 1

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 63
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

Figure 4.17: Failure of temporary supporting piles including the anchor

As the problems presented in the literature review similar challenges have been recorded. Some of them
where inadequate instability analysis of an open cut excavation which can lead to a slope failure, wrong
calculation of earth pressure that leads to total failure of sheet piles (supporting) and collapse of adjacent
road. Also some technical challenges are occurred in similar manner as inadequate instability analysis of
an open cut excavation, insufficient toe penetration of steel sheet piles, the earth pressure induced by soft
clay that was wrongly calculated, seepage force, artesian water pressure and squeezing/soil flow and
heaving are some of the major factors for failure that are the outcomes of precise analysis of stability of
excavated ground.

Figure 4.18: Effect on neighboring structure; collapse of feeder road

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 64
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

Figure 4.19: Poor quality of concrete retaining wall, improper erection of formwork results deformed
structure

4.5. Improving the methodologies for better execution management


Even in complicated urban settings, deep excavation work have been deployed successfully by overcoming
construction challenges, so that if proper implementation of design with sufficient investigation of the
ground and proper implementation of plan during execution with adequate supervision, the challenges and
failure can be minimized and improved. In the literature review the remedial procedures that shall be
followed are described, in similar manner the remedial measures that can be practiced as minimizing and
avoiding the above discussed problems and failures are gathered.

Thus some of the practiced and forecasted measures are pointed out by participating professional in the
following manner:

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 65
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

Table: 4.6:- Remedial measures mentioned by respondents

No. Remedial measures Frequency


1 Perform adequately study the geotechnical investigation report with full 5
design analysis.
2 Perform close supervision and quality control 5
3 Construct appropriate excavation protection wall or supporting structure 4
4 Commence with an approved & complete design of the excavation 3
5 Before commencing work perform detail assessment of hazards 2
6 Protect adjacent structures avoid risks and damages 2
7 Study the history of the nearby structure which can be used as input for the 2
design
8 Selection proper execution methodology, starting from design to 2
construction
9 Communication with responsible bodies to protect utility line before 2
excavation starts
10 Perform backfill between the pile shoring structure and the permanent 2
retaining wall to avoid further ground movement
11 Use of appropriate construction materials, equipment and qualified 2
workmanship
12 Before starting of excavation protect the existing structure 1
13 Create good communication means between construction parties 1
14 Construct site specific retaining structure 1
15 Adopt the precise and safest construction means to get planned and designed 1
quality of the work
16 Adopt proper planning in risk measurement, identification & mitigation 1
strategy
17 Assign a competent person who must inspect the excavation work 1

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 66
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

Generally, when unforeseen conditions in executing deep excavation appears, seeking immediate &
temporary solution to avoid damage on structures, workers & neighborhood is important. Thus, the
following analysis procedures can be as remedial measures, those are:

 Study the actual situation,

 gather preliminary information,

 perform reconnaissance survey and site investigation,

 then execute design modifications if required and

 adopt new construction method that allows to keep safety and quality of the project.

In relation to this, emergency action plan has to be prepared jointly with the concerned parties. Thus in
such events emergency response, back-up operations, and disaster recovery means shall be implemented.

When problems related to loading the remedy will be stress relieve. As per the information gathered and
described above due to improper loading of excavated materials high failures are recorded up to death of
workers, therefore appropriate management of excavated materials, manpower and equipment is
mandatory. This proper management allows avoiding extra stress which wasn’t considered in designing
stage besides keeping the safety and wellness of workers.

In the case of ground or surface water exists in deep excavation project it requires treatment and the solution
shall be proper dewatering i.e. pumping out the water to avoid mud which affects working efficiency of
machinery & manpower. For the safety of workers, machinery and materials draining of construction site
is important. It also helps to protect and keep the wellness of neighboring structure. As the ground (soil)
becomes wet its resistance to the pressure decreases. Thus the stability of the soil becomes in question
hence it can result failure of the soil and problem to the nearby structure. But this outcomes are understood
lately as the problem exists. Therefore, checking the existence and level of ground water before
construction ahead is the primary factor and allocating appropriate dewatering procedure is a must.

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 67
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

Figure 4.21: Collecting ground water through perforated pipes & pump out the collected water

As sliding of ground occurs immediate action should be taken to avoid further failure and attain safety of
the project so that design re vision and construction of temporary support structure is compulsory. As
shown below in figure 4.22 similar action has been taken & construction of concrete retaining wall is done
to prevent further sliding.

Figure 4.22: Construction of protection wall to avoid future sliding & to protect the neighbor structure

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 68
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

Thus in deep excavation considering construction quality & safety as primary issue the intention of
achieving cost efficiency should come later employers, consultants and contractors should believe in
prioritizing the quality of construction, effective and efficient utilization of resource and then comes to the
budget.

In summary, this part mainly focuses on solution that are practiced in A.A. deep excavation projects and
practicable solutions forwarded from respondents of questioner and interviews. Also response to
unforeseen situations and remedial actions performed are described from observed sites.

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 69
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

5. CONCLUSIONS AND RECOMMENDATIONS


This chapter of the study deals with the conclusions and recommendations which are drawn a result of
findings of the practice, challenges and corrective measures of the problems associated to execution
management of deep excavation in Addis Ababa construction projects.

5.1. Conclusions

Due to congestion of construction area for expansion of roads and parking space of buildings in Addis
Ababa, underground space are required and results deeper excavation which is developed in greater speed
with the existence of bordering structure in either side of the project which makes the excavation work
more challenging.

It is a fact that as we go deeper there is always uncertainty and challenges which could appear in one or
another way. The concern isn’t the existence but the prevention and avoidance of accidents & failures.
Thus, this study aims to address the practice and challenges of deep excavation and to develop remedial
solution. The primary theme is to get full and well studied technical documents & non-technical
information, then forecast the upcoming difficulties of the specific project, which allows to revise the
design and work methodology to achieve better execution management. From the discussions of the
previous sections it appears to suggest that the local construction industry accomplish deep excavation
inefficiently.

Execution management of deep excavation in A.A is implemented with a number of challenges that come
out from lack of knowledge, lack of experience and also negligence to key subjects. As a result of the
findings above, there are some good practice in implementation of design and attaining of quality with
efficient utilization of resources. But mostly there is lack of accomplishing studied work specially with
regard to substructure investigation, safety & health with application of risk management that sacrifices
the quality, budget, time & safety of the work and workers.

One of the major findings is that safety and health management problems. The analysis illustrates that there
is weakness in planning, implementing and monitoring safety and health management in this construction
work. Although there is a bit practice to use safety equipment and protection of ground movement to avoid
related risks, mostly related problems exist and are addressed after their occurrence resulted damages. Since
deep excavation in A.A. is performed in congested area, serious attention is required and calls for
improvement to save consumption of extra resources of the construction including human life.

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 70
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

The research conducted through gathering all reliable secondary data & studying them for literature review
and collect primary data with interview, questioner and observation of A.A. construction projects practice.
Following this analysis of findings with developing conclusions and recommendations accomplished.

It is found that most clients doesn’t understand the output and benefits of geotechnical results and aren’t
willing to cost for the investigation. Since insufficient soil investigation results unexpected ground
condition, it results revision up to change of design & work methodology that leads to incur additional cost
and time for execution. This makes the management of deep excavation more challenging. But if there
were reliable information, risks could be reduced and related problems could be defined ahead with an
alternative corrective approaches. By this most of technical challenges could be address.

For protection of structures, construction of temporary retaining or supporting wall done. In building
projects usually concrete shoring piles are used but in some cases employers push contractors to avoid such
work for budget reduction and lately accidents and failures occur then unexpected cost generated. In
underpass road & railway construction deep excavation implemented in better manner regard to buildings.
But in all the three sectors considering & application of protection of neighboring structure, safety & health
planning with overall management is very poor including information gap that appears between
professionals.

Another major concern is monitoring and evaluation of the construction work with close supervision that
is key procedure in deep excavation execution. Since it is applied to ensure the execution of construction
complies with drawings, specification and approved work method to attain quality output in every aspect,
the implementation requires great emphasis and improvement.

As remedial measure, adopt & perform adequately studied geotechnical investigation report with full
design analysis, adapting close supervision and quality control, constructing appropriate excavation
protection wall or supporting structure, revising working methodology with implementation of immediate
corrective action are taken.

Besides the challenges and failures recorded in the execution, there are also appreciable practices with
respect to assuring quality of construction materials. In almost all projects in road, railway and building
deep excavation construction every construction material used by checking standard quality tests.

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 71
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

5.2. Recommendations

Despite the fact that deep excavation construction in A.A. is being deployed in congested area where there
are structures nearby it needs improvement. Professionals and every participating parties should work to
have better and enhanced means of execution. As per the outcome of the present research analysis and
findings the following recommendations are forwarded:

1. Planning and implementation of safety and health management system to protect workers and the
neighboring society is expected from consultants and contractors.

2. Contractors should plan, prepare and implement achievable work methodology by allocating
relevant time and budget with available workmanship, machineries and other resources.

3. To protect facilities and workers, timely recording of construction events to accurately report key
measures as survey of existence and status of bordering structures, utility and so on before
commencing the excavation work is mandatory.

4. Contractors should plan to perform periodic evaluation of the performance of equipment used
during excavation that allows to minimize and control challenges related to equipment failure.

5. Contractors should perform execution of deep excavation by having detail and approved design
with all relevant information given from the design professionals.

6. Geotechnical engineers should perform detail geotechnical investigation & contractors should
avoid ignoring such investigation reports. Contractors shall interpret the results and other design
analyses with all design professionals. This can allow them to address the possible upcoming
challenges.

7. Every contractor and consultant who are engaged in deep excavation work should perform field
tests for every stage of excavation to ascertain the compliance of geotechnical result that can allow
to revise design and work methodology for best execution.

8. Consultants and Regulatory bodies should prepare advanced controlling scheme aiming reduction
and ultimately avoidance of problems occurring and assurance quality of the execution that allows
to improve and upgrade the overall execution of deep excavation with respect to quality, cost, time
and safety.

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 72
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

9. Regulatory bodies are required to give emphasis to such special and basic construction work and
follow up the design & execution compliance in regard to safety & quality of the project, safety of
neighboring society, protection of nearby structures and similar matters with the existing regulation
and shall develop supportive guidelines or regulation to improve execution management and also
the construction industry.
10. Employers are required to adopt contract documents that shall incorporates detail & clearly stated
special conditions of contract and specifications which includes requirements for deep excavation
to precisely address precaution measures.
11. Employers, consultants and contractors are required to prepare templates for recording data’s of
stability and deformation analysis, the degree of their existence and their effect on bordering
structure and neighboring society and documented for future studies. Also such documentation can
be used for evaluation of the execution management of deep excavation and improving the practice.

12. As many of the geotechnical investigation result and the execution practice shows that most of A.A.
ground soil soft clay which lose its strength as it gets moist though for improved means of
construction adopting deep excavation in dry season could create better condition for executing and
managing deep excavation.

13. Professionals who are engaged in deep excavation shall have adequate knowledge and experience
who can be problem solving in every stage of execution and also shall create good communication
and partnership between all parties of deep excavation to easily address the challenges and cultivate
alternative solutions mutually.

14. Updating professionals with training and education expected from construction companies for those
who involve in design, execution and monitoring phase is more important to develop their skill and
capability of solving problems regarding every aspect to create better execution management
method.

15. Educational institutions shall give emphasis for this basic construction work and provide and
students through project management courses both at the undergraduate and postgraduate levels,
with an emphasis on risk analysis and execution management.

16. In addition to the above, further future in depth study in extension of this research work are
recommended as:

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 73
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

 Assessment of performance of contractors and consultants in executing deep excavation


for building, road and railway projects in A.A.

 Assessment of bidding system and evaluation of qualified bidders for execution and
management of deep excavation construction

 Assessment of the involvement and contribution of regulatory bodies in the controlling


and evaluation of the execution of deep excavation construction.

 Assess the advantage of implementing Building Information Model (BIM)database


technology for risks assessment and management of monitoring data of deep excavation
in urban areas.

17. Since we are compensating many resources up to human lives due to poor management, every
professional who are engaged in the design, execution and monitoring should feel responsible
and shall work to improve the practice. And change of attitudes is the core point that we all
should work on.

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 74
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

REFERENCE

1. Elaine L. Chao, Secretary Occupational Safety and Health Administration; John L. Henshaw,
Assistant Secretary(2002 Revised),Excavations, U.S. Department of Labor; OSHA 2226

2. Ergun M.U.(2008), Deep Excavations, Electronic Journal of Geotechnical Engineering

3. Dinakar K N1 and S K Prasad (May-2014);Behaviour of Tie Back Sheet Pile Wall For Deep
Excavation Using Plaxis; IJRET: International Journal of Research in Engineering and
Technology

4. T.J.Bles, A.Berweij, J.W.M Salema M.Korff; Deltare, Delft, the Netherlands O.Oung,
H.E.Brassina Public works Rottredam, the Netherland T.J.M. de Wit Geomet BV, Alphen a/d
Rijn, the Netherlands(2009);Guideline For Monitoring And Quality Control For Deep
Excavation

5. Venkata Ramasubbarao GODAVARTHI, Dineshbabu MALLAVALLI, Ramya PEDDI, Neelesh


KATRAGADDA, and Prudhvikrishna MULPURU (July-December 2011), Contiguous Pile Wall
as a Deep Excavation Supporting System, Department of Civil Engineering, SRK Institute of
Technology, Leonardo Electronic Journal of Practices and Technologies

6. Wanchai Teparaksa;Performance of Contiguous Pile Wall for Deep Excavation On Chao Phraya
River Bank,Associate Professor, Department of Civil Engineering, Chulalongkorn University,
Thailand,

7. Korff, Mandy, Deltares/Cambridge University, Delft, The Netherlands/Cambridge, UK Tol, A.


Frits van, Deltares/Delft University of Technology, Delft, The Netherlands(2012); Failure cost
analysis of 50 deep excavations in the Netherlands.

8. Jaspreet Singh, Prof. V. Srinivas Raghavan, May 2014; Complications during Multi-Level
Basement / Deep Foundation Construction Projects; International Journal of Science and
Research (IJSR) Volume 3 Issue 5

9. GOUW Tjie-Liong, Ir., M.Eng, ChFC BINUS UNIVERSITY, (June 2012);Deep Excavation
Failures, Can They be Prevented?

10. Nilufer Onder Dept. of Computer Science, Amlan Mukherjee Dept. of Civil and Env.
Engineering, and Pei Tang Dept. of Civil and Env. Engineering, (ICAPS 2010);Construction

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 75
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

Management Applications: Challenges in Developing Execution Control Plans; Proceedings of


the Twentieth International Conference on Automated Planning and Scheduling;Michigan
Technological University

11. Korff M. Deltares and Cambridge University and Mair R.J. Cambridge University(2013);

Response of piled buildings to deep excavations in soft soils; Proceedings of the 18th
International Conference on Soil Mechanics and Geotechnical Engineering, Paris

12. M. Arroyo, A. Di Mariano, A. Gens, E. Alonso;Management of third-party risk in an urban deep


excavation project; Department of Geotechnical Engineering and Geosciences, Technical
University of Catalonia, Barcelona, Spain

13. Manitoba Labour and Immigration Workplace Safety & Health Division (December 2007);
Guideline for Excavation Work; 200 – 401 York Avenue Winnipeg, Manitoba

14. I-Chen Wu, Siang-Rou Lu and Bin-Chen Hsiung(2015);A BIM-based monitoring system for
urban deep excavation projects; Wu et al. Visualization in Engineering

15. A. Thut, U. Raz, D. Naterop, H.-J. Becker; Solexperts AG, Schwerzenbach, Switzerland(March
2002); Monitoring during Construction in Urban Areas; Proc. 2nd Int. Conference on Soil
Structure Interaction in Urban Civil Engineering; Zurich

16. NSW Government work cover(July 2014);Excavation work code of practice; Safe work
Australia

17. Raymond W M Wong(December 2002);The Construction of Deep and Complex Basements and
underground structures within extremely difficult urban environment; presented for International
Conference on Advances in Building Technology Organized by the Faculty of Construction and
land Use, The Hong Kong Polytechnic University Hong Kong,

18. M. Ufuk Ergun; Deep Excavations; Department of Civil Engineering, Middle East Technical
University, Ankara, Turkey

19. G.A. Horodecki & E. Dembicki;Impact of deep excavation on nearby urban area; Department of
Geotechnics and Applied Geology, Gdańsk University of Technology, Poland

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 76
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

20. S.S. Gue & Y.C. Tan, (September 1998);Design & Construction Considerations For Deep
Excavation; SSP Geotechnics Sdn Bhd

21. I-Chen Wu, Siang-Rou Lu and Bin-Chen Hsiung (2007);Applying building information
modelling in environmental impact assessment for urban deep excavation projects;Department
of Civil Engineering, National Kaohsiung University of Applied Sciences, Kaohsiung, Taiwan

22. Ahmed Hosny Abdel-rahman (2007);Associate Prof., Civil Eng. Dept., Engineering Research
Division, National Research Center of Egypt. Construction Risk Management of Deep Braced
Excavations in Cairo; Australian Journal of Basic and Applied Sciences

23. Michael Looby, Director, Byrne Looby Partners; Dr. Mike Long, Senior Lecturer, University
College Dublin, Deep Excavations in Dublin Recent Developments, Engineers Ireland.

24. The Reporter Newspaper:

Vol. 20 no. 1502, Meskerem 11, 2007

25. NAOUM S.G. (1998) Dissertation Research and Writing for Construction Students;Oxford:
Reed Educational and Professional Publishing Ltd

26. Dane Bertram: Likert Scales; CPSC 681 – Topic Report

27. James Dean Brown (University of Hawai‘i at Mānoa)(March 2011);Likert items and scales of
measurement?SHIKEN: JALT Testing & Evaluation SIG Newsletter. 15(1) 10-14.

28. William Kruskal (1984);Concept of Relative Importance;University of Chicago.

29. David J.Bentler;performance of deep excavation support system

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 77
APPENDIXES
Appendix A: Research Proposal
ADDIS ABABA UNIVERSITY
ADDIS ABABA INSTITUTE OF TECHNOLOGY

SCHOOL OF CIVIL AND ENVIRONMENTAL ENGINEERING

MASTER’S THESIS PROPOSAL

IDENTIFICATION

Name: Semegn W/Yohannes (GSR/3921/05)

Faculty: Technology

Department: Civil and Environmental Engineering

Major: Construction Technology and Management

Title of Thesis: EXECUTION MANAGEMENT OF DEEP EXCAVATION IN


ADDIS ABABA CONSTRUCTION PROJECTS

(ERA Regular)

December, 2014
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

Table of Contents
ABSTRACT..................................................................................................................................................... 81

INTRODUCTION ............................................................................................................................... 82

STATEMENT OF PROBLEM ............................................................................................................ 83

LITERATURE REVIEW .................................................................................................................... 84

RESEARCH OBJECTIVE .................................................................................................................. 85

OBJECTIVE.....................................................................................................................................85

RESEARCH QUESTION ..........................................................................................................................85

RESEARCH DESIGN AND METHODOLOGY ...................................................................................... 86

WORK SCHEDULE ........................................................................................................................... 87

BUDGET ............................................................................................................................................. 88

REFERENCE ....................................................................................................................................... 89

BIBILOGRAPHY ................................................................................................................................ 90

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 81
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

Abstract
Deep excavation is an important component of construction for the purpose of foundation and basements
allocation of new buildings in urban areas and other facilities in densely built-up areas of construction.
Presently, shortage of space for parking, public amenities and housing utilities has made necessary to use
underground spaces. Therefore in this paper, it is planned to present the investigation of local practices in
the planning, quality assurance services and execution of deep excavation for the construction of foundation
and basement works.

Deep excavations in urban areas require special measures due to the presence of structures, underground
utilities and other engineering constructions existing in the vicinity.This study will present the problems,
challenges and unwanted effects observed during execution in order to improve the local practice.

Though, it reviews literature in related topics, conduct observation, interviews and case study of projects
which are engaged in such type of construction work. Then with the analysis of gathered data it tries to
develop appropriate guidelines in order to improve the planning, quality assurance services and execution
methodologies of deep excavations for the construction of foundation and basement works.

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 82
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

Introduction
A rapid development of economy leads for further construction of infrastructures while the available
construction areas are limited. Thus the construction requires much excavation for foundations and
basement provision that embrace difficult design, complicated construction technology, vulnerability to
circumstance and other complex characteristics.[3]

The construction of deep excavations in the urban environment is a technically challenging problem that
requires the design, coordination and controlling of site characterization, design of excavation support
systems, specification of responses to construction difficulties, preconstruction surveys of adjacent
properties and utilities, field observations during construction, excavation installation and structure
construction. [2] [6]

Although excavations are regulated by federal, state and local building codes, problems occur in the process
of developing a site due to design errors, construction errors, construction accidents, striking unknown
utilities, differing site conditions, unforeseen natural events, or delays in completion. These problems occur
on many projects; however, in an urban environment, the result is very often. [2] [4]

Adjacent construction may be a nuisance to neighboring property owners (e.g. right of entry agreements,
shoring, underpinning, and/or alterations to operations, dust, noise, felt vibrations, traffic congestion).
Frequently, adjacent property owners claim construction-induced damage. For deep excavations, this
damage may include a combination of building settlement because of a loss of lateral support, loss of use,
business interruption, and structural damage.[2]

On the other hand, even if such construction task requires special attention with regard to safety and health
in working sites, in many cases of local construction it isn’t addressed properly due to less understanding
of the risk and negligence. This leads to the practice of unsafe and health risky working environment. This
problem is mainly due to the lack of proper planning, implementation of the plan and insufficient follow
up. Even though, in complicated urban settings, deep excavation can be deployed successfully by
overcoming construction challenges.

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 83
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

Statement of Problem
In our county cities develop rapidly with construction, while the space above ground are becoming more
& more precious. Due to this underground space is developed with greater speed followed by deeper
excavation although the constraint of land makes the excavation work more challenging. Consequently,
this part of construction requires special attention and management to avoid unplanned and unwanted
result.

In most of local construction sites, during the execution of deep excavation sliding of the ground, getting
unexpected substructure which have contrary characteristic to the geotechnical results, presence of
unexpected water table, striking unknown utilities and so on makes the excavation more difficult. Also,
because of negligence and less attention to safety and health results many accidents and injuries of workers
incurred during deep excavation. This usually occurs due to less attention given to the execution
management of deep excavation in construction.

Therefore, studying the current practice of deep excavation in local construction especially in Addis Ababa
which leads to the above mentioned drawbacks and reviewing of regulations related to this issue is
important to attain improved construction means.

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 84
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

Literature Review
A deep excavation into the ground is indispensable to create additional floor space to meet increasing space
requirements for parking for multi-story buildings and for other structures at the city centers. Numbers of
deep excavation pits in city centers are increasing every year. Structures in the immediate vicinity of
excavations, dense traffic scenario, presence of underground obstructions and utilities have made
excavations a difficult task to execute. An excavation is basic phase in the construction of foundations or
basements. The process of an excavation may encounter different kinds of soils underneath the same
excavation site from soft clay to hard rocks. During excavation, some soil types pose greater problems than
the others. [1][7]

No matter how many trenching, shoring, and back filling have been done in the past, it is important to
approach each new project with the utmost care and preparation. Many on site accidents result directly
from inadequate initial planning. Waiting until the work has started to correct mistakes in shoring or sloping
slows down the operation, adds to the cost, and increases the possibility of other excavation failure.
Determination of site condition through site observation, test borings for soil type or conditions, and
consultations with local officials and utility companies is important and should be the primary activities to
manage difficulties related to deep excavation.[1][5][6]

With this section, it is planned to look for information on related topic from different sources. This includes
studying of previously done researches and scientific journals written in relation to the execution
management of deep excavation in urban construction. That helps to study the subject matter with better
understanding and allows having thoughtful ideas for identifying challenges.

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 85
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

Research Objective
Objective

 Assessinglocal practices in planning, quality assurance services and execution of deep


excavation for the construction of basement and underpass road works.
 Identifying problems, challenges, unwanted effects and gaps that need to be addressed to
improve the planning, quality assurance services and execution of deep excavation for the
construction of basement and underpass road works.
 Recommending interventions in order to improve the planning, quality assurance services and
execution methodologies of deep excavations for the construction of basement and underpass
road works based on the findings of the study.

Research Question

 What is the practice of Addis Ababa construction projects in the execution management of deep
excavation work?
 What are the problems and challenges incurred with regard to execution management of deep
excavation?
 How the gaps can be filled and can achieve improved methodologies in order to have better
execution management means?

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 86
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

Research Design and Methodology


This research focuses on identification of major problems related to the execution management of deep
excavation in urban construction and resulting outcome. Thus the researchmethodologyincludes reviewing
literatures, observation of undergoing construction projects, interviewing and conduct questionnaires for
stake holders who directly participate in deep excavation work.

 Literature Review
This will incorporated reviewing literatures in related topic and surveying researches on risk
management of deep excavation done previously with emphasis given to local practice.

 Population and Sampling


Identify the population size that will be addressed by this research and define sampling or sampling
method of the population.

 Research Identification
This will integrate preparation of questions, case observations, conducting of interview and/or
questionnaires which are targeted to show the critical problems of the local practice in management.

 Data Collection
Data’s will be collected from observed cases, interviews and distributed questionnaires

 Data Analysis
Finally the collected data’s will be analyzed so that the resulting outcomes will be drawn as
conclusion and recommendations.

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 87
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

Work Schedule
2014 2015
Item Activities Duration
No. (Weeks) December January February March April May June

1 Literature Review 4

2 Population and Sampling 3

Preparation of Question for


3 3
Interview and Questionnaire

4 Data Collection 12

Data Analysis and


5 4
Interpretation
Preparation and submission
6 6
of draft thesis
Preparation and submission
7 4
of the final thesis

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 88
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

Budget

The total cost of the thesis is estimated to be13,325.00 birr based on the activity plan. The detail cost
breakdowns are depicted as follows:

A. Expendable Supplies and Documentation:


Unit
Item Total Price
Item Unit Quantity Price
No. (Birr)
(Birr)
1 Stationary Materials Lump Sum 800.00
2 Flash Disk(8gb) No 1 500.00 500.00
3 EVDO No 1 1200.00 1200.00
4 Typing Page 250 3.00 750.00
5 Printing Page 250 1.50 375.00
6 Thesis Binding Pcs 5 70.00 350.00
7 Photocopy Page 1250 1.00 1250.00

SUB TOTAL 5225.00

B. Transportation:

Item Total Price


Item No of Trip
No. (Birr)
1 Research Travel Lump Sum 3000.00

SUB TOTAL 3000.00

C. Communication:

Item Total Price


Item Unit
No. (Birr)
1 Telephone Lump Sum 3000.00
2 Internet Service Lump Sum 2100.00
SUB TOTAL 5100.00

TOTAL (A+B+C) 13,325.00

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 89
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

REFERENCE
1. Elaine L. Chao, Secretary Occupational Safety and Health Administration; John L. Henshaw,
Assistant Secretary (2002 Revised), Excavations, U.S. Department of Labor;OSHA 2226,

2. Deep Excavation & Urban Construction, Exponent Engineering & Scientific Consulting

3. Michael Looby, Director, Byrne Looby Partners; Dr. Mike Long, Senior Lecturer, University
College Dublin, Deep Excavations in Dublin Recent Developments, Engineers Ireland.

4. Ergun M.U.(2008), Deep Excavations, Electronic Journal of Geotechnical Engineering

5. Dinakar K N1 and S K Prasad; Behaviourof Tie Back Sheet Pile Wall For Deep Excavation Using
Plaxis; IJRET: International Journal of Research in Engineering and Technology

6. T.J.Bles, A.Berweij, J.W.M Salema M.Korff; Deltare, Delft, the Netherlands O.Oung, H.E.Brassina
Public works Rottredam, the Netherland T.J.M. de Wit Geomet BV, Alphen a/d Rijn, the
Netherlands; Guideline For Monitoring And Quality Control For Deep Excavation

7. Venkata Ramasubbarao GODAVARTHI, Dineshbabu MALLAVALLI, Ramya PEDDI,Neelesh


KATRAGADDA, and Prudhvikrishna MULPURU, Contiguous Pile Wall as a Deep Excavation
Supporting System, Department of Civil Engineering, SRK Institute of Technology, Leonardo
Electronic Journal of Practices and Technologies

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 90
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

Bibliography

Submitted by

Semegn W/yohannes

Student Signature Date

Approved by

1. Dr. Wubishet Jekale


Advisor Signature Date

2.
Chairman, Dep.’s Signature Date
Graduate Committee

3.
Chairman, Faculty’s Signature Date
Graduate Committee

4.

Dean, Graduate School Signature Date

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 91
Appendix B: Questionnaire
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

ADDIS ABABA UNIVERSITY

SCHOOL OF GRADUATE STUDIES

SCHOOL OF CIVIL AND ENVIRONMENTAL ENGINEERING

Questionnaire Survey for Thesis paper on

Execution Management of Deep Excavation in Addis Ababa Construction Projects

The purpose of this questionnaire is to study practices in planning, quality assurance services and execution
of deep excavations in addition to that to identify the problems and challenges incurred with regard to
execution management of deep excavation in Addis Ababa construction projects. Please answer all
questions as possible. All the information gathered will be kept confidentially and will be used only for
academic research and analysis without mentioning the names of individuals companies involved.

Thank you in advancing for your precious time and kind cooperation!
Sincerely Yours
Semegn W/yohannes
Supervised by: -
Dr. Wubishet Jekale

General Information

1. Type of Organization (Respondents designation)

Client Consultant Contractor

2. Type of Project (Respondents designation)

Building Road Railway

Closed Questioners
The given below are numbers of root causes for the problems, challenges and unwanted effects in deep
excavation for construction projects in Addis Ababa. Please indicate the significance of each factor by

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 93
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

ticking the appropriate boxes and add any remarks relating to each factor as alleviation majors such as the
reasons, the critical factors &/or the solutions.
E.S. = Extremely Significant [4] V.S. = Very Significant [3]
M.S. = Moderately Significant [2] S.S. = Slightly Significant [1]
N.S. = Not Significant [0]

Question Factors for the challenges E.S V.S M.S S.S N.S
[4] [3] [2] [1] [0] Remarks
No. and unwanted effects

Part 1. Planning
Design
1 Lack of design for the supporting
system
2 Lack of selection suitable type of
retaining wall with respect to:
a - Ground condition

b - Limitation of nearby structure

3 Lack of planning assessment of


hazards before design
4 Poor communication between
design professionals;
geotechnical engineer, structural
engineer…
5 Lack of considering ground
related risks in design like:
a - Ground movement

b - Ground water level

c - Change in stress state in


subsoil due to unloading &
loading
d - Vertical & horizontal
displacement of adjacent
ground

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 94
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

Question Factors for the challenges E.S V.S M.S S.S N.S
[4] [3] [2] [1] [0] Remarks
No. and unwanted effects

6 Lack of designer's experience in


construction works methodology
Planning for Construction

7 Lack of allocating site access


(entrance and exit ways to the
site) for workers
8 Lack of allocating of sufficient
construction budget & time
9 Lack of allocating construction
materials, workmanship &
equipment
10 Lack of planning to adopt
appropriate construction works
methodology
11 Lack of planning to perform
dilapidation (destruction) survey
for nearby facilities
12 Lack of planning to analyze the
impact of construction on
adjacent properties due to:
a - Lowering water table

b - Horizontal ground movement


& Surface settlement
c - Displacement of retaining
structures
Health and Safety
13 Lack of planning to engage
safety and health management
14 Lack of planning to identifying
sources of risk related to:
a - Ground water table

b - Ground movement

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 95
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

Question Factors for the challenges E.S V.S M.S S.S N.S
[4] [3] [2] [1] [0] Remarks
No. and unwanted effects

c - Settlement of adjacent
buildings
16 Lack of planning to analyze the
present condition of existing
structure
17 Lack of preparing safety check
list to analyze:
a
- Traffic

b - Proximity and physical


conditions of nearby structures
c - Soil type

d - Surface and ground water

e - Location of the water table

f - Weather condition

g - Overhead and underground


utilities like supply of water,
sewerage, telecommunications
18 Lack of planning to allocate
raising and lowering lifting
machine to lower workers, like
tripod
19 Lack of select appropriate hoist
(lifting machine)that shall be:
designed and certified by a
professional engineer & that have
sufficient height and capable to
support the assumed maximum
load

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 96
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

Question Factors for the challenges E.S V.S M.S S.S N.S
[4] [3] [2] [1] [0] Remarks
No. and unwanted effects

Part 2. Execution

Carry Out Construction


20 Lack to develop outline of
measurement techniques for risk
in execution by defining:
elements of the deep excavation,
unwanted events affecting the
execution, parameter& technique
of measurement
21 Lack of adopting planned
construction works methodology
22 Lack to use prearranged site
access (entrance and exit ways to
the site) for workers
23 Lack to carry out back analysis
of the existing structure with
respect to State of serviceability
of the structure, Appearance of
cracks etc.
24 Lack of recording the present
status of the existing structure
25 Lack of analyzing ground surface
settlement occur due to:
Retaining wall construction,
Ground water pumping & Main
excavation
26 Lack of measuring key functions:
like Surface settlement,
Deflection of retaining wall

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 97
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

Question Factors for the challenges E.S V.S M.S S.S N.S
[4] [3] [2] [1] [0] Remarks
No. and unwanted effects

27 Lack of determining vertical &


horizontal displacement
28 Lack of analyzing impacts which
cause displacements of retaining
structures and settlements of the
adjacent buildings like:
a with change of stress state in
subsoil by loading &unloading
process
b with type and technology of
bracing system which define its
stiffness
c with vibrations during driving/
vibrating of sheet pile wall
d with technology of excavation
deepening
e with influence of dewatering &
disturbance of groundwater flow
f influence of vehicular traffic
29 Lack of analyzing the impact &
difficulties for inhabitants
30 Lack of accurate and on-time
reporting of key measures
Health and Safety
31 Lack of implementing safety and
health management
32 Lack of analyzing the current
condition of risk related to:
a - Ground water table

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 98
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

Question Factors for the challenges E.S V.S M.S S.S N.S
[4] [3] [2] [1] [0] Remarks
No. and unwanted effects

b - Ground movement

c - Settlement of adjacent
buildings

Part 3. Monitoring and Evaluation


Supervision
33 Lack of close supervision and
construction control
34 Lack of recording construction
events that focus on:
a - Soil type

b - Sudden drop of drill fluid or


water gushing out(artesian)
c - Overhead & underground utilities

d - Weather condition

35 Lack to check records of


instruments & carry back analysis
to validate the design &
performance of the wall
36 Lack to check over excavation to
avoid additional stress that
increase wall movement
37 Lack to check the surcharging at
the retained side wall that might
increase soil pressure
38 Lack of examine prestressed
ground anchors & carefully
carryout locking off.
39 Lack to check overstressing &
understressing of anchor to avoid
over load & movement

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 99
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

Question Factors for the challenges E.S V.S M.S S.S N.S
[4] [3] [2] [1] [0] Remarks
No. and unwanted effects

40 - Lack of support system for


workers
41 - Lack to perform monitoring
for risk control through:
a - Incorporating a design with
adequate safety factor
b - Reasonable ground movements
that could be safely tolerated
by the surrounding structures
c - Incorporating an inclusive
quality control program during
construction
d - Performing a pre-construction
destruction survey
e - Weather condition
42 - Lack of adopting contingency
plan for events identified
during execution of the project
- Lack to use contingency plan
43 of action for: emergency
response, back-up operations,
disaster recovery

Part 4. Challenges
Technical Concerns
44 Inadequate instability analysis of
an open cut excavation
45 Insufficient toe penetration of
sheet piles
46 Wrong calculation of earth
pressure induced by soft clay
47 Wrong calculation of Water
pressure, Seepage force, Artesian
water pressure, Squeezing/soil
flow & Heaving

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 100
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

Question Factors for the challenges E.S V.S M.S S.S N.S
[4] [3] [2] [1] [0] Remarks
No. and unwanted effects

48 Inadequate performance of the


wall (including the anchoring
system)
49 Damage during the installation of
the retaining structure
50 Incorrect assumption type,
dimensions or quality of the
foundation of adjacent buildings
51 Lack of adequate knowledge &
experience of working staffs
52 Lack of proper dewatering
procedure
53 Lack of proper reinforcing steel
placement
54 Inadequate soil nailing and
shotcreting

Non-Technical Issue
55 Lack of proper management of
bidding system
56 Lack of adequate evaluation of
technical qualification of bidders
57 Difficulty to use lowest bidder wins
system which results:
a - Inability to assign & pay
qualified engineer
- cut overhead cost & ignore
b
cost of temporary works

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 101
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

Open Questioners

1. Are there any other problems and challenges that you observe in performing such construction work?
If there are please discuss them
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
2. What kinds of failures or damages have you faced to structures?
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
3. What remedial measures do you suggest or take in order to avoid such problems and challenges?
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
4. How do you respond to unforeseen conditions which appear during execution of deep excavation that
might affect the quality of the project?
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
5. How and what kind of specification and/or guideline do you use for the execution of deep excavation?
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________

THANK YOU!

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 102
Appendix C: Questionnaire Analysis
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

Question Factors for the challenges and unwanted effects RII


No.
Part 1. Planning
Design
1 Lack of design for the supporting system 0.658
2 Lack of selection suitable type of supporting structure with respect to:
a Ground condition 0.613
b Limitation of nearby structure 0.538
3 Lack of planning for assessment of hazards before design 0.686
4 Poor communication between design professionals; geotechnical
0.667
engineer, structural engineer…
5 Lack of considering ground related risks in design like:
a Ground movement 0.472
b Ground water level 0.585
c Change in stress state in subsoil due to unloading & loading 0.507
d Vertical & horizontal displacement of adjacent ground 0.600
6 Lack of designer's experience in construction works methodology
0.556

Planning for Construction


7 Lack of allocating site access (entrance and exit ways to the site) for
0.438
workers
8 Lack of allocating of sufficient construction budget & time 0.478
9 Lack to allocating quality construction materials, workmanship &
0.585
equipment
10 Lack of planning to adopt appropriate construction works
0.736
methodology
11 Lack of planning to performing dilapidation (destruction) survey for
0.561
nearby facilities
12 Lack of planning to analyze the impact of construction on adjacent
properties due to:
a Lowering water table 0.595

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 104
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

b Horizontal ground movement & surface settlement 0.610


c Displacement of retaining structures 0.579
Health and Safety
13 Lack of planning to engage safety and health management 0.810

14 Lack of planning to identifying sources of risk related to:

a Ground water table 0.631


b Ground movement 0.584
c Settlement of adjacent buildings 0.642
16 Lack of planning to analyze the present condition of nearby existing
0.648
structure
17 Lack of preparing safety check list to analyze:
a Traffic 0.654
b Proximity and physical conditions of nearby structures 0.659
c Soil type 0.675
d Surface and ground water 0.670
e Level & location of the water table 0.606
f Weather condition 0.561
g Overhead and underground utilities like supply of water, sewerage,
0.574
telecommunications
18 Lack of planning to allocate raising and lowering lifting machine to
0.525
workers, like tripod
19 Lack of select appropriate hoist (lifting machine) that shall be:
designed and certified by a professional engineer that have sufficient
0.486
height and capable to support the assumed maximum load

Part 2. Execution
Carry Out Construction
20 Lack to develop outline of measurement techniques for risk in
0.541
execution by defining: the elements of the deep excavation, unwanted

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 105
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

events affecting the execution, parameter & technique of


measurement
21 Lack of adopting planned construction works methodology 0.689
22 Lack to use prearranged site access (entrance and exit ways to the site)
0.483
for workers
23 Lack to carry out back analysis of the existing structure with respect
0.473
to State of serviceability of the structure, Appearance of cracks, etc.
24 Lack of recording the present status of the existing structure 0.700
25 Lack of analyzing ground surface settlement occur due to Retaining
wall (supporting structure) construction, Ground water pumping, 0.529
Main excavation
26 Lack of measuring key functions like Surface settlement, Deflection
0.524
of retaining wall
27 Lack of determining vertical & horizontal displacement 0.459
28 Lack of analyzing impacts which cause displacements of retaining
structures and settlements of the adjacent buildings like
a with change of stress state in subsoil by loading & unloading process 0.509
b with type and execution method of bracing system which define its
0.643
stiffness
c with vibrations during driving/ vibrating of temporary supporting wall 0.580
d with technology used to deepen the excavation 0.619
e with influence of dewatering & disturbance of groundwater flow 0.621
f influence of vehicular traffic 0.578
29 Lack of analyzing the impact & difficulties for inhabitants 0.564
30 Lack of accurate and on-time reporting of key measures 0.615
Health and Safety
31 Lack to implement safety and health management plan 0.745
32 Lack of analyzing the current condition of risk related to:
a Ground water table 0.639
b Ground movement 0.667
c Settlement of adjacent buildings 0.633

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 106
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

Part 3. Monitoring and Evaluation


Supervision
33 Lack of close supervision and construction control 0.721

34 Lack of recording construction events that focus on:

a Soil characteristics 0.770


b Sudden drop of drill fluid or water gushing out(artesian) if any 0.702
c Overhead & underground utilities 0.717
d Weather condition 0.524
35 Lack to check records of instruments & carry back analysis to validate
0.694
the design & performance of the wall
36 Lack to check over excavation to avoid additional stress that increase
0.583
wall movement
37 Lack to check the surcharging at the retained side wall that might
0.587
increase soil pressure
38 Lack to examine prestressed ground anchors & carefully carryout
0.616
locking off.
39 Lack to check overstressing & understressing of anchor to avoid over
0.617
load & movement
40 Lack of allocating support system for workers 0.708
41 Lack to perform monitoring for risk control through:
a Incorporating a design with adequate safety factor 0.679
b Reasonable ground movements that could be safely tolerated by the
surrounding structures 0.648
c Incorporating an inclusive quality control program during construction 0.730
d Performing a pre-construction destruction survey 0.630
e Recording Weather condition 0.556
42 Lack of adopting contingency plan for events identified during
0.533
execution of the project
43 Lack to use contingency plan of action for emergency response, back-
0.590
up operations, disaster recovery

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 107
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

Part 4. Challenges
Technical Concerns
44 Inadequate instability analysis of an open cut excavation 0.616
45 Insufficient toe penetration of sheet piles 0.638
46 Wrong calculation of earth pressure induced by soft soil 0.732
47 Wrong calculation of Water pressure, Seepage force, Artesian water
0.669
pressure, Squeezing/soil flow & Heaving
48 Inadequate performance of the supporting wall (including the
0.592
anchoring system)
49 Damage during the installation of the retaining structure 0.444
50 Incorrect assumption type, dimensions or quality of the foundation of
0.589
adjacent buildings
51 Lack of adequate knowledge & experience of working staffs 0.586
52 Lack of proper dewatering procedure 0.533
53 Lack of proper reinforcing steel placement 0.375
54 Inadequate soil nailing and shotcreting 0.476
Non-Technical Issue
55 Lack of proper management of bidding system 0.692
56 Lack of adequate evaluation of technical qualification of bidders 0.710
57 Difficulty to use lowest bidder wins system which results:
a Inability to assign & pay qualified engineer 0.714
b cutting overhead cost & ignore cost of temporary works 0.687

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 108
Appendix D: Observation Guideline
Execution Management of Deep Excavation in Addis Ababa Construction Projects 2016

Observation Guideline
Type of project
Building Road Railway

1. What are the issues considered before commencing deep excavation execution?
______________________________________________________________________________________
2. Is there any standard and specific quality assurance manual adopted for the work?
_______________________________________________________________________________________
3. What kind of construction methodology is adopted?
______________________________________________________________________________________
4. Does construction material test performed to assure quality of construction materials?
______________________________________________________________________________________
5. Does they perform periodic evaluation of equipment deployed for the excavation?
______________________________________________________________________________

6. Did they provide temporary support to protect the excavated ground? On what basis?
______________________________________________________________________________________
7. What kind of supporting structure applied?
______________________________________________________________________________________
8. How quality does controlled in deep excavation work and the evaluation is done?
______________________________________________________________________________________
9. Do they protect nearby structures and how?
______________________________________________________________________________________
10. Is there any challenge occurred during execution? What types of challenge and how much was the
damage?
______________________________________________________________________________________
11. How do they handle the challenges and what kind of precautions they adopt?
______________________________________________________________________________________
12. How do they respond to unforeseen conditions?
______________________________________________________________________________________
13. How do they manage unexpected ground conditions?
______________________________________________________________________________________
14. How did they manage the overall execution?
______________________________________________________________________________________

AAU, AAIT, School of Civil And Environmental Engineering


MSc in Construction Technology & Management 110
DECLARATION

I, the undersigned, declare that this thesis is my original work and has not been presented
for a degree in any other university, and that all sources of materials used for the thesis have been
duly acknowledged.

Name Semegn W/yohannes

Signature ________________

Place Addis Ababa University, Addis Ababa

Faculty of Technology

Date of submission June, 2016

You might also like