ELKHOMRA PROJECT

METHOD OF STATEMENT

Interlock installation

Table of contents
PURPOSE 

SCOPE 

RESPONSIBILITY 

MANPOWER 

TOOL & EQUIPMENT 

METHODS / PROCEDURES 

SAFETY PRECAUTION 

ATTACHMENT 
ELKHOMRA PROJECT

 - PURPOSE
The aim of this method statement is to execute the scope of work, provide and maintain an
effective quality control in compliance with standards and good practices at all stages/
activities for Curbstone .

 - SCOPE

;This Method of Statement applies to the following


Materials for Application
1- Pre-Cast Interlock

 - RESPONSIBILITY

A full and detailed description of roles and responsibilities of all staff is included within
the project quality plan . for the works as covered this method statement , the following
personnel have specific duties

Technical Officer Engineer: Specific responsibilities include:


- Responsible for ensuring that the various submitting are timely undertaken (materials,
method statements, workshop drawings, subcontractor’s issues, technical issues).
- Responsible for quotations as required (materials, subcontractors).

- Responsible for ensuring RFI’s are timely undertaken on behalf of contractor.


- Responsible for the distribution of documents within contractor site personnel.

Site Engineer(s). Specific responsibilities include:


- Ensuring that the project is managed in a safe manner and meets the requirements
Of the project documentation
- Ensuring that subcontractors and suppliers achieve the on-site required
Standards
.
- Ensuring the Client is satisfied with our performance .
ELKHOMRA PROJECT
- Ensuring performance measurable are delivered.

- Shall refer to the QA/QC Department and the HSE Department for advice and
guidance when required.

- Shall ensure that operatives comply with the relevant method statements, Toolbox
Talks and general site briefings.

HSE Site Representative(s). Specific responsibilities include:


- Assisting in the production of any health, safety, and environmental documents.
- Monitoring the implementation of health, safety, and environmental
Requirement
- Undertaking audits and ensuring that corrective and preventive actions are
- Taken where required Liaison with the senior site staff on health, safety, and
Environmental related matters

QA/QC Site Representative(s). Specific responsibilities include:


- Carrying out phased inspections as required.
- Ensuring that completed works are offered for inspection/approval to external

companies within specific dates/programmers.


- Preparation of the ITP.
- Ensuring that all required tests are performed and follow appropriate
specifications etc.
- Reviewing and ensuring that all shop drawings and material submitting are
presented to the appropriate bodies with adequate supporting information.
-Ensuring that materials are inspected when delivered to ensure they comply with the
various specifications

-Maintaining a record of all QA/QC activities on site.


- Controlling and ensuring all measuring and test equipment on site is properly calibrated.
-Controlling all non-conforming products or workmanship and implementing the required
preventive actions.
-Ensuring that corrective and preventive actions are taken when required.
ELKHOMRA PROJECT

-Ensuring that the required testing is undertaken by approved independent laboratories,


and that all test results are reviewed.

-Undertake audits to ensure conformance to agreed Standards, Legislation, and project


specific requirements.
-Ensuring that staffs are aware of their responsibilities in respect of quality issues.

-Assisting and reporting to the QA/QC Manager as required.

Supervisor(s). Specific responsibilities include:


-To ensure that all operatives and appropriate subcontractors have been briefed as to the
content of the method statement and the works.

-To adequately control the works as required.

-To ensure the works are undertaken in a safe manner.


- To ensure all operatives are adequately training in their respective works.

-Reporting any UN-safe practices on site to the site team.

Subcontractors. Specific responsibilities include:


-To undertake their works as specified.

-To work in a safe manner.


-To ensure all operatives are adequately training in their respective works.
-Report any UN-safe practices on site to the site team.
ELKHOMRA PROJECT

 - MANPOWER
The Civil Supervisor shall control the overall activities at site and he will be directly
reporting to the Site Superintendent. The basic manpower under him shall consist
but not limited to the following:
 Lead Pre-Commissioning Engineer
 Testing Engineer
 Civil Lead Man
 Senior Technicians
 Technician
 Vendor Represented (if need)
 QC Engineer / Inspector
 Safety Engineer
 Company Representative

 - Materials :

- Approved Interlock.

-Sand

 - METHODS / PROCEDURES

Preparations

1- After the material samples have been approved, all materials shall be
delivered to site in the manufacturer’s original containers and packages
with seals unbroken and Delivery notes and shall be stored in a dry
place. Materials such as cements, which are partially caked .

2- The work shall be coordinated with other sections of work which adjoins
other materials before installation of the material herein.

3- Before starting the Interlock work , shall be make check for levels

Installation
ELKHOMRA PROJECT

A. Prepare sub grade for the installation of


the interlocking blocks. Any soft soils shall be removed so that it
will not create unstable foundation.
.B. Place aggregate sub base and base as indicated in the plan
Compact by tamping with rubber mallet and screed to depth
required to allow setting of pavers
C. Treat leveling base with soil sterilizer to inhibit growth of grass
.and weeds
D. Using string lines to keep straight lines. Fill gaps between units
not to exceed 20 mm with pieces cut from full size unit pavers.
G. Spread dry sand and fill joints pavers, vibrate pavers and add
.sand until joints are completely filled, remove excess sand
H. Do not allow traffic on installed pavers until sand has been
.vibrated into joints
. I . Levels and slope shall be according to approved shop drawings

SAFETY PRECAUTION

-Safety requirements will be addressed in accordance with the project General


safety plan .

-Tools and equipment will be inspected periodic.

 Attachements : (Checklist & ITP )