Vertical Sided Excavations and Support Structures
Vertical Sided Excavations and Support Structures
Definition
An opened ground is normally called an excavation or trench. A trench is usually a means to an end,
a steep temporary cutting which will be backfilled as soon as a drain, pipeline, sewer or foundation
has been constructed. The structural design of a trench is usually the responsibility of the
construction company that has contracted to do the work, although the client’s engineer will wish to
veto any temporary works that are unsafe. The siting of the trench is normally constrained by its
function.
Excavation
Excavation is an undertaking which is usually on the critical path of a construction programme,
because construction work cannot start until it is completed. The time periods allocated to the
excavation operations must therefore be kept to, or bettered, otherwise delays to the whole
construction programme will ensue. For this reason planning each excavation, large or small, is
important and the figure below shows the principal decisions in the selection of the method of
excavation.
STABILITY/FAILURE OF EXCAVATION
Assessing the stability of an excavation mainly involves estimation of the limiting height/depth of
excavation and checking the possibility against base heave.
(ii) the heaving or softening of the base of the excavation due to high groundwater pressure, which
spoils the foundation for the pipe, etc.
(iii) the heaving of the base of the excavation due to shear failure of the soil, causing local
subsidence outside the trench and spoiling the levels inside,
(iv) the erosive action of the groundwater, washing sand or silt into the trench and causing local
subsidence, and
(v) the consolidation of neighbouring compressible soils due to the local reduction in groundwater
pressure which causes settlement of neighbouring foundations or the opening of sewer joints etc.
Note: The pressure of groundwater in the vicinity of the proposed trench is the KEY to each of the
modes of failure depicted in Figure 1. As seen in 203BE when we discussed the Rankine lateral
earth pressure, the presence of static groundwater behind the face of a retaining wall could double
or treble the thrust on it, perhaps causing the inadequate strutting to break or buckle as a wedge of
soil slides into the trench as shown in (i). If the ground is sandy or silty, high groundwater levels
will be immediately obvious due to influx of water into the trench, which will either flood it or be
successful in drawing down the water table.
Soil type
Vertical cuts in soil can only be supported when soil behaves in an undrained way (with an
undrained strength cu) or in a drained soil where there is some cohesion (c′). Clay therefore could
often be relied on to stand unsupported because of the cohesion. It can be shown theoretically that
an open excavation in normally consolidated clay soil will stand vertically without support provided
the height of the face does not exceed a certain critical depth, called the limiting depth, which
depends on the undrained (cu) or drained (c′) value . This is very useful during temporary works in
fine grained soils (typically clays). The excavation of trial pits/trenches and bored pile construction
techniques are two examples of where this is used in engineering practice.
Dry sands and gravels can stand at slopes equal to their natural angle of repose (Ɵ), depicted in the
figure below, no matter what the depth. With loose sands and gravels where c´ is zero, Ɵ may be
taken to be equal to φ´. Thus a drained cohesionless soil will always fail when the slope angle
reaches φ´, as in the absence of chemical or other bounding between soil particles, c′ = 0. Damp
sand possess some cohesion and can stand vertically for some time.
Ɵ = φ'
Angle of Repose
At ground surface, H = 0
Thus the magnitude of the active lateral pressure at the ground surface is obtained as follows:
Substituting H = 0 in the equation ha K a H 2cu K a and solve for ha we get
ha 2cu K a as the stress at the top of the excavation i.e. ground surface.
It will be seen that negative tensile stresses at the surface exists down to depth z0. The active lateral
stress at the bottom of the excavation is given by ha K a H 2cu K a . The lateral earth pressure
diagram is thus as shown in the figure below.
()2cu K a
z0
H Excav z0
Hc
ation
c u , u sat
K a H 2c u K a
Distribution of active pressure in saturated clay
Tension cracks
A zone of tensile () stresses in the ground implies the formation of tension cracks. The depth z0 is
thus crucial. The theoretical maximum depth of the crack z0 can be determined by recognizing that
at the bottom of the crack, i.e. at depth z0 the lateral earth pressure is zero
ha = 0
Substituting ha = 0 in the equation ha K a H 2cu K a and solve for H = z0 we get
z0
If water is available it can fill up the tension crack and provide additional pressures on the wall. In this
situation the pressure diagram becomes as shown in the figure below
z0 Water
w z 0
Soil
Hc is the upper bound for the vertical cut i.e. plastic deformation occurs, wall is at incipient failure
unsupported.
This surcharge load may exceed the bearing capacity of the soft, normally consolidated soil, resulting
in heaving. The term heave refers to a condition where clay soil flows into the excavation giving rise
to the base elevation. The figure shows the generally assumed mechanism of base failure in a cohesive
soil. The slope of the straight portion of the slip surface is at 45° to the horizontal and the curved
portion is a circular arc with its centre at the base corner of the vertical side. From geometry of the
figure, the radius of this arc R = Btsin45° = 0.7Bt.
Surface or level c – d may be regarded as the base of the footing with width B carrying the weight of
the column of the soil abcd above it plus any surcharge qs on the surface a – b.
The downward movement is resisted by the shearing resistance T along the surface b – c.
T = H0 for undrained clay = cu
Therefore T = cuH0
v is the net vertical stress on plane c – d and the net load is Bv
If the bearing capacity of the clay along plane c – d is just adequate to avoid foundation failure then the
Ultimate bearing capacity qult of the soil is calculated in the same way as for a footing using
appropriate bearing capacity factors:
Factor of safety against heave is given by the ratio of net bearing capacity to net stress. Add
surcharge stress to the net stress if applicable.
cu
( F S ) heave N c substituting for v
v qs
cu
( F S ) heave N c
c
H 0 ( u ) q s
B
NOTE: The above equation best suits conditions where H0/B > 1. If H0/B <1 the shear resistance
along b – c is ignored making the design more pessimistic (worse case scenario). Bjerrum and Eide
(1956) showed that the factor of safety against bottom heave in this case is basically the ratio of
bearing capacity of undrained clay to the overburden pressure (+ any surcharge)
cu cu
( F S ) heave N c or ( F S ) heave N c
v qs H 0 q s
where Nc is a bearing capacity coefficient or factor which can be obtained from several charts e.g.
Skempton (1951). For practical purposes coefficient Nc can be approximated by
H H H
N c 61 0.2 0 for 0 2.5 and N c 9 for 0 2.5
B B B
If (FS)heave < 1.5, the sheeting should be extended below the base of the excavation for stability.
These may be used as either temporary or permanent supports for excavations in granular soil and
perhaps short-term ones to clays and silts. The supported height is comparatively small due to the
8
Stability
For a cantilever wall the stresses acting at failure can be as shown in the figure below. Cantilever sheet
pile walls are analysed by assuming that rotation occurs at some point just above the base (toe) of the
wall. The consequence of assuming rotation above the base is that, below the point of rotation, the
lateral pressure is passive behind the wall and active in front of the wall, thus the rotation is resisted by
two passive forces Pp1 and Pp2.
x Active
d Passive
C
z Passive
C, Point of Rotation
(a) Actual wall (b) Actual Pressure distribution
(a) Geometry and (b) Pressure diagram on Cantilever Sheet Pile Wall
For design we need to determine the required depth of penetration d for stability and then to size the
wall to resist the maximum moment. To determine d required for a given height H we need to consider
both moment and force equilibrium:
F x= 0 M=0
If the soil is dry (γ) and the soil type is cohesionless or frictional, i.e. -soils, the pressures and
forces are as shown in the figure below
Pressures Forces
Pa1
K x K ( x H )
h p h a Pp1 ya =(H + x)/3
K ( x H )
h p
yp = x/3
Pp2
K (d H )
h p
Approximation of Pressure and Force Quantities
9
z = 0.2x
d=x+z
Thus d = 1.2x
Also the passive resistance is decreased by a factor of safety FSp.
Note: If moment of forces are taken about the centre if rotation, then Pp2 can be eliminated, thus it
need not be taken into consideration any more.
M C PP1 y p Pa1 y a 0
1 x 1 (x H )
K p x 2 K a ( x H ) 2 0
2 3 2 3
K px 3 K a ( x H )3 0
K a (x H )3 K p x3
xH
3
Kp
x Ka
H Kp
1 3
x Ka
H Kp
3 1
x Ka
H
From which x
Kp
3 1
Ka
10
Factor of safety
Before the above formulae can be applied, the value of Kp has to be calculated so that it includes a
factor of safety. Two methods are introduced below:
The application of these mobilisation factors results in a higher active pressure and lower passive
pressure than the unfactored soil strength parameters.
B
Pa
h Pp
yp ya
Bending Moment
Applying Method 1:
1
Active force: P a K a (h H ) 2
2
1
Passive force: P p K p h 2
2 FS p
Equating forces: Pa = Pp
1 1
or K a (h H ) 2 K p h 2
2 2 FS p
K ph2
K a (h H )
2
FS p
hH
2
Kp
h K a FS p
H Kp
Re-arranging, 1
h K a FS p
H Kp
From which 1
h K a FS p
H
Hence the position of Mmax is given by: h
Kp
1
K a FS p
For Mmax, take moments about point of zero shear.
hH
Pa is acting at: ya
3
h
Pp is acting at yp
3
max = Ppyp – Paya
1 1
M max K p h 3 K a (h H ) 3
6 FS p 6
12
M max K a (h H ) 3
6 FS p
Surface Loading
Note that as the factor of safety increases the maximum moment also increases.
The factor of safety can be dramatically reduced by surcharge loadings on the supported ground next to
the wall as shown in the figure below. For a uniform surcharge then the effective active pressure can
be increased by Ka s, while for a concentrated load from a footing the Coulomb method of trial
wedges can be used to determine the active force on the wall. In the latter situation allowance must be
made for the fact that the point of application of the load will also change.
s
QL
PA
Ground water
Consideration must also be given to the water pressures acting on the wall.
Water
Table
Water
For economic reasons cantilever walls are usually limited to excavations less than 6 m deep. They are
often used to support low banks of free draining sand and gravel soils. They are not suitable for the
13
Advantages:
1. Reduction in the depth of penetration
2. Increase in the height to be supported
3. Allowing the use of lighter sections, due to the reduction of bending moments and deflections.
Unknowns
a) Depth of penetration (d)
b) Tension (T0 in the tie rods
c) Maximum bending moments (Mmax)
In principle, anchored sheet piles are usually used when the height of the retained soil is in excess of 5
m. With increasing height, a series of anchors, as opposed to single anchor, might be necessary, so as
to limit the deflection and control the bending moments.
Deflected h
position of
Anchor or Prop T
the wall
between sides of
excavation
H
Pa
d
Pp
2 FS p
For d, take moments about the tie rod
2 Pp 2d
M 0 Pa 3 (d H ) h FS 3 H h 0
p
2 Pp 2d
Equating Pa (d H ) h H h
3 FS 3
p
As Pa and Pp are also expressed in terms of d, there is no advantage in deriving a complicated cubic
formula in order to evaluate it. As easier application of the equation above is illustrated by the tutorial
example question.
Anchorage
There are two points to consider in the design of the support to the tie rods.
1. The distance of the anchor from the sheet piles, that is the length of the tie rod.
2. The prevention of bearing failure of soil supporting the anchor.
15
Horizontal bracing
This method of support is applied to vertical cuts, deeper than 1.2 m. These are normally narrow, deep
trenches – excavated to accommodate pipelines etc to prevent collapse prior or during construction.
Timber support
For cohesive soils, one or several poling board may be omitted (open timbering) whilst closed
timbering is appropriate in loose wet soils. At least 1 m high handrail should be constructed on both
sides for safety.
16
1. Whilst the a retaining wall is homogenous, stiff structure, the sheeting is flexible. The
flexibility depends on the positioning of the struts during excavation. Moreover any non-
uniformity in the supported soil can greatly influence the magnitude of force in each strut, but
has no effect on a rigid wall.
2. The development and magnitude of force in the struts depend largely on the sequence of their
installation, hence on the method of excavation.
Notes:
Should one strut fail, then the adjacent members would carry its load. This cannot occur, when the
support is a solid wall.
Because of uncertainties involved, the pressure distribution, in this case ca only be approximated on
the bases of actual measurement of strut loads during and after construction. Terzaghi and peck
suggested the distributions, for cohesionless soils as shown in the figure below.
1 sin
where K a =
1 sin
17
H
The choice of the diagram depends on the stability number of the clay given by the ratio and the
cu
degree of consolidation:
H
If 4 then (c) is to be used and corresponding maximum pressure is calculated by:
cu
pmax = 1.0KAH where KA = 1 – (m4cu/H). Substitute and re-arrange we get pmax = H – 4mcu
where 0.4 m < 1.
For stable sensitive NC clay use m =1, thus pmax = H – 4cu. The lateral earth pressure is less thus
lesser support force is required.
For soft NC clay use m = 0.4, thus pmax = H – 1.6cu. The lateral earth pressure is more thus more
support force is required.
H
If 4 then (b) is to be used and corresponding maximum pressure is calculated by:
cu
pmax = 0.2H to 0.4H The clay is considered to be Over Consolidated (OC).
18