NOTES :
4.1 Rates include :-
(a) All leads and lifts of matrerials unless otherwise specified.
(b) The cost of materials in which water includes.
(c) The cost of mixing motor, curing and scaffolding etc
4.2 Rates do not include centring, shuttering or form work unless otherwise specified.
4.4 Form work of RCC will be provided by the contractor and shall be removed by him. No
lead and lift of form work will be payable.
4.5 For RCC work the rates includes all finishing on all exposed surface, projections etc. as
per design. The resulting surface should be smooth and plain. Bottom faces of RCC slabs,
lintels and chajjas etc. shall be finished with suitable thickness of 1:3 cement mortar to make
surface smooth and even, where ever required. Ceiling plaster shall not be paid separately in
any case.
4.6 The rate includes for centring for providing fan hooks etc. For drip course where ever
required the seperate rates will be paid.
4.7 For plum concrete the plum used shall be of 150 mm maximum size rubble.
4.8 For fine and coarse aggregates IS 383 - 1970 may be referred, for plain and reinforced
concrete IS 456 - 2000 may be referred.
4.9 No seperate payment for lead and lift shall be permissible unless otherwise specified.
4.10 The proportion of various size of coarse aggregates in concrete is detailed below.
(This quantities are for 1 cum of concrete)
………………………………………………………………………………………
Concrete Max size of Metal or single Size and qty Total
Mix. Graded metal in cum.
………………………………….
40 mm 20 mm 10 mm
………………………………………………………………………………………
C.C. 1:2:4 20 mm - 0.67 cum 0.22 cum. 0.89cum
Page 17
4.11 Items of R.C.C. includes formworks, centering, shuttering, proping, finishing and
curing etc.
4.12 Rates of centering and shuttering should be paid only for the item in which rates
excluding cost of formwork is mentioned.
0401 Filling available excavated earth (excluding rock) in trenches, plinth, cum 64.8
sides of foundation etc. in layers not exceeding 20cm in depth
consolidating each deposited layers by ramming and watering lead upto
50m and lift upto 1.5m
0402 Filling foundation, around masonry work, plinth, sides of foundation etc. cum 247.9
with moorum I/c ramming layers not exceeding 20cm in depth
consolidating each deposited layers by ramming and watering lead upto
50m and lift upto 1.5m.
0403 Labour only for item no.0402 cum 64.8
0404 Filling in plinth with sand under floors including watering, ramming, cum 276.6
consolidating and dressing complete.
0405 Labour only for item no. 0404 cum 53.9
0406 Filling foundation or under floor with 40mm gauge graded metal and cum 1294.9
moorum including ramming in layers and watering.
0407 Labour only for item no.0406 cum 775.9
0408 Providing and laying in foundation, plinth and under floors lime
concrete with 40mm nominal size graded stone aggregates (metal) and
40% lime mortar. i/c ramming in layers and curing complete excluding
cost of form work.
(a) Lime mortar 1:2 (1lime putty, 2sand) cum 1993.8
(b) Lime mortar 1:3 (1lime putty, 3sand) cum 1910.4
(c) Lime mortar 1:1:1 (1lime putty, 1surkhi, 1sand) cum 1946.8
(d) Lime mortar 1:2 (1lime putty, 2surkhi) cum 1899.7
0409 Labour only for item no. 0408 (for any proportion of lime mortar used) cum 849.0
0410 Deduct from item No. 0408 if shingles (pebbles) are used in place of cum 261.7
40mm nominal metal.
0411 Providing and laying on terrace upto floor two level lime concrete with cum 1798.9
graded brick aggregate 25mm nominal size and 50% mortar comprising
of 1 lime putty and 2 surkhi and curing etc. complete.
0412 Labour only for item no. 0411. cum 757.3
0413 Providing and laying in foundation, plinth and under floors cement
concrete with 40mm nominal size graded stone aggregates (metal) i/c
ramming in layers and curing complete excluding cost of form work
(a) C.C. 1:2:4 (1cement, 2sand, 4metal) cum 3175.9
(b) C.C. 1:3:6 (1cement, 3sand, 6metal) cum 2562.8
(c) C.C. 1:4:8 (1cement, 4sand, 8metal) cum 2169.1
(d) C.C. 1:5:10 (1 cement, 5sand, 10metal) cum 1940.3
0413 Providing and laying in foundation, plinth and under floors cement
concrete with 40mm nominal size graded stone aggregates (metal) i/c
ramming in layers and curing complete excluding cost of form work
(e) C.C. 1:6:12 (1 cement, 6sand, 12metal) cum 1825.8
(f) C.C 1:2.5:5 ( 1cement, 2.5 sand, 5metal) cum 2892.1
0414 Labour only for item no. 0413 (for any proportion of cement concrete) cum 654.0
0415 Add to item No. 0413 for concrete work in super structure upto floor two cum 15 % of item
level for wall independent pillars and like. no. 0414 for
each floor
0416 Add to item No. 0413 and 0415 if in place of 40mm metal.
0417 Extra rate for providing and fixing in position upto floor two level, units cum 1941.5
of precast C.C. work of any mix fixing in cement mortar 1:2 and
finishing with cement plaster 6mm thick in cement mortar 1:3 including
scaffolding .
0418 Extra rate for laying cement concrete in or under water or liquid mud cum 92.8
including cost of pumping and bailing out and removing slush etc.
complete.
0419 Extra rate for providing and mixing water proofing material in cement Bag 50.0
concrete work in the proportions recommended by the manufacturers.
0420 Providing and laying damp proof course 50mm thick with C.C.1:2:4 with sqm. 227.4
20mm size graded stone aggregate. including curing.
0421 Applying one coat of hot bitumen (80/100) or equivalent using 1.7kg. Per sqm. 84.5
sqm On damp proof courses after cleaning the surface with brushes and
finally with a piece of cloth tightly soaked in kerosene oil.
0422 Plum cement concrete 1:2:4 with 75% graded metal of 40mm size and cum 2176.1
25% plums of 150mm size.
0423 Plum cement concrete 1:3:6 with 75% graded metal of 40mm size and cum 1939.8
25% plums of 150mm size.
0424 Plum cement concrete 1:4:8 with 75% graded metal of 40mm size and cum 1748.2
25% plums of 150mm size.
0425 Providing and placing in position RCC for roof, beams, columns column
footing lintels chhajjas, balcony, stairs etc, excluding cost of
reinforcement but including centring, shuttering, proping, finishing &
curing etc.complete.
(a) CC 1:1:2 (1 cement, 1 sand, 2 graded stone aggregate 20mm cum 5770.8
nominal size)
(b) CC 1:1.5:3 (1 cement, 1.5 sand, 3 graded stone aggregate 20mm cum 4916.0
nominal size)
(c) CC 1:2:4 (1 cement, 2 sand, 4 graded stone aggregate 20mm cum 4488.6
nominal size)
0426 Labour only for item 0425. cum 910.8
0427 Add extra for labour only for additional floor or 6.m height and part cum 15 % of item
thereof PCC or RCC work in item no.0426 no. 0426 for
each floor
0428 False work for lintels slabs, columns, walls, sills, chhajjas balconies, sqm. 204.7
beams, stair cases or ornamental moulded work, curved surface etc. cast
in situ including all lead and lift
0429 Labour only for item no. 0428. sqm. 129.4
0430 False work for R.C.C. and P.C.C. work in plinth and foundation sqm. 155.3
0432 Deduct for mixing of cement concrete/ lime concrete without mechanical cum 85.8
mixer in item no. 0408, 0409, 0411 to 0414, 0420, 0422 to 0426 and
0432
0433 Deduct for concrete unvibrated in item no. 0425 cum 85.8
0434 Providing and laying five courses damp proofing treatment sumps, sqm. 550.7
reservoirs, roof etc. consisting of 1st. 3rd and 5th courses of blown type
petroleum bitumen of I. S. grade 85/25 applied @1.6kg/sqm and 2nd and
4th courses of self finished bitumen felt type 3 grade 2 (Hessian Base)
with priming coat of bituminous solution applied hot at the rate of
minimum of 0.25litre per sqm including preparation of surface by
grouting cracks, providing cement concrete fellets rounding of cerlers
etc. wherever required and cleaning and drying of surface before priming
cost is applied, complete as per direction of the engineers-in-charge.
0435 Providing and filling in position blown bitumen in expansion joints RM 9.2
(10cm deep and 1cm Wide)
0436 Deduct from item no 0413 if 63mm graded metal used in place of 40mm cum 37.2
metal
0437 False work for Arches up to 6meter span. sqm. 1045.5