Exercise 8 - PM
Exercise 8 - PM
Exercise 8 - PM
finish time 4 3 5 8 9 10 13 11
Latest 0+4 = 1+3 = 8+1 = 5+4 = 4+5 = 11+2 = 9+4 = 11+2 =
finish time 4 4 9 9 9 13 13 13
Total Float 4–4 = 4–3 = 9–5 = 9–8 = 9–9 = 13–10= 13–13= 13–11=
0 1 4 1 0 3 0 2
EFFi = max{ESF + dF; ESG + dG; ESH + dH} = max{EFF; EFG; EFH}= max{10; 13; 11} = 13.
mpd = EFFi – ESIn = 13 – 0 = 13.
deadline = mpd ➔ LFFi = EFFi ➔ TFFi = LFFi – EFFi = 0.
Critical activities (TFk = TFFi = 0): A, E and G.
mpd = dA + dE + dG = 4 + 5 + 4 = 13.
Critical path: A → E → G.
Fk = ESk + dk = EFk
SE = (FA, FB, FC, FD, FE, FF, FG, FH) = (EFA, EFB, EFC, EFD, EFE, EFF, EFG, EFH) =
= (4, 3, 5, 8, 9, 10, 13, 11)
SL is the schedule on which all activities start on their later start date without
compromising the mpd.
Fk = LSk + dk – (deadline – mpd) = LSk + dk – (13 – 13) = LSk + dk – 0 = LSk + dk = LFk.
SL = (FA, FB, FC, FD, FE, FF, FG, FH) = (LFA, LFB, LFC, LFD, LFE, LFF, LFG, LFH) =
= (4, 4, 9, 9, 9, 13, 13, 13)
Activities Resources
8
H 2 2
7
G 4 4 4 4
6
F 2 2
5
E 3 3 3 3 3
4
D 2 2 2 2
3
C 2
2
B 3 3 3
1
A 2 2 2 2
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 (time) 0 1 2 3 4 5
Resources
8
2 2
7
4 4 4 4
6
2 2
5
3
4
2
3
2
2
0
8 9 10 11 12 13 (time) 0 1 2 3 4 5 6 7 8 9 10 11 12 13 (time)
Schedule Effective Ideal Usage Maximum Variance of resource
usage ratio utilization
usage float
SE 66 104 0.63 6 1.92
SL 66 104 0.63 6 2.84
• Effective usage: The Effective usage is the total amount of resources needed, that is
∑𝐻
𝒋=𝑨 𝒅𝒋 𝒓𝒋 .
(The Effective usage does not depend on the schedule being considering.)
Effective usage (in SE) = Effective usage (in SL) =
= 4×2+3×3+1×2+4×2+5×3+2×2+4×4+2×2=66.
• Ideal usage: The Ideal usage is equal to the area of the rectangle whose basis
corresponds to the duration of the project (T) and whose height is equal to the
𝐦𝐚𝐱 𝑹(𝒕)] × 𝑻.
maximum amount of resources needed, that is, [𝟎≤𝒕≤𝑻
• Usage ratio: The usage ratio is defined as the ratio between the effective usage and the
ideal usage, that is
𝑬𝒇𝒇𝒆𝒄𝒕𝒊𝒗𝒆 𝒖𝒔𝒂𝒈𝒆
𝝆= ∙
𝑰𝒅𝒆𝒂𝒍 𝒖𝒔𝒂𝒈𝒆
(The Usage ratio lies in the range [0,1]. This measure is used to compare schedules, because
the higher it is the more efficient is the use of resources. Unfortunately, the most efficient
schedule (the one with 𝜌 = 1) may be impossible to obtain.)
(The best schedule is the one that has the lesser maximum float.)
𝒕𝒊 −𝒕𝒊−𝟏
• Variance of resource utilization: 𝝈𝟐 = ∑𝒌𝒊=𝟏 × (𝑹𝒊 − 𝝁)𝟐, where:
𝒕𝒌 −𝒕𝟎
𝑬𝒇𝒇𝒆𝒄𝒕𝒊𝒗𝒆 𝒖𝒔𝒂𝒈𝒆
❖ 𝜇 = 𝑀𝑒𝑎𝑛 𝑢𝑡𝑖𝑙𝑖𝑧𝑎𝑡𝑖𝑜𝑛 𝑜𝑓 𝑡ℎ𝑒 𝑟𝑒𝑠𝑜𝑢𝑟𝑐𝑒 = ;
𝑻
▪ Temporal segmentation in SE
[0, 3[, [3, 4[, [4, 5[, [5, 9[, [9, 10[, [10, 11[ and [11, 13[ (𝑘 = 7 intervals)
▪ Temporal segmentation in SL
[0, 1[, [1, 4[, [4, 5[, [5, 8[, [8, 9[, [9, 11[ and [11, 13[ (𝑘 = 7 intervals)
[0, 3[, [3, 4[, [4, 9[, and [9, 13[ (𝑘 = 4 intervals)