Press Information Bureau
Government of India

Ministry of Road Transport & Highways



10- June- 2016 12:15 IST
Status of National Highway Projects in Uttar Pradesh
·      In the State of Uttar Pradesh there are 60 National Highways
with total length of 8483 Kms, out of which
with NHAI and
3143 Kms with State PWD. NOC is awaited for 10 Nos NHs with 811 Kms.

·      8 Major Projects having a length of 865 Kms amounting to  Rs. 6218 Crs were completed in the past 2 years.

·      31 Major Projects are ongoing with a total length of 2156 Kms with
total TPC of Rs. 19,436 Crs.

·      24 Major Projects were awarded during 2014- 15 & 2015- 16, with a
total length of 1293 Kms and total TPC of

·      15 projects are likely to be awarded in the next 12 months with a


length of 840 Kms with TPC of Rs.6790 Crs.

·      1400 Kms of National Highways are under DPR and Civil construction
work likely to be awarded in the next 
approx cost of Rs. 14,000
Crs.

·      Under CRF and ISC Schemes a total number of 79 Projects have been
sanctioned amounting to Rs. 3035 Cr
16 & 2016- 17.

·      10 Number of new National Highways in the Uttar Pradesh state have
been declared with a length of 811 Km
by the Ministry)

·      35 Nos of NHs with 2591 Kms length have been approved ‘ in- principle
’, MORTH shall invest an amount of
Rs. 25,910 Crs to develop
these National Highways, subject to the outcome of DPR / receipt of NOC from
th

·      In totality, MORTH, through NHAI and State PWD, shall invest
approximately an amount of Rs. 74,794 Crs  
next two
years.

The details of the above projects can be seen in the 13 tables that
follow

Table 1 :
Details of NHS in Uttar Pradesh

S. No. Details
of  NH Length
(Km)
i. Total NH length (60 nos including newly
declared NH) 8483
 
ii. NH length entrusted to NHAI 4529
 
iii. NH length entrusted to PWD 3143
 
iv. Length of newly declared NHs but NOC from
State PWD yet to 811
be received (10 nos )  
 
v. Length of ‘In Principle’ approved National Highways. (35 nos) 2591
 
vi Total length 11,074 Km

Table 2: Density of NHs

Sl. NH density in respec t of NH density


No. population and
area
Uttar Pradesh All India

(i) Length (in Km./1000 Sq Km 34.87            28.25                


of area)      (Area=243286 Sq Km) (Area=3287263 Sq
Km)

(ii) Length (in Km./Lakh of 4.25                 7.67                


population) (As per 2011 (Population=1996
Lakh) (Population=12102
Lakh)
Census)

Table 3: Lane
distribution of entrusted NHs [7672 Km = 8483 – 811]

S.no Lane Distribution % age

i. 4 Lane and above 28%


 
ii. 2 Lane 69%
 
iii. Less than 2 Lane 3%
 
 

Table 4: Details
Of NH Works In The State Of Uttar Pradesh

S No Programme / Plan Total No of Projec ts Length in Km


2 Projects completed during last 2 years 8 864.97

  Ongoing Major Projects 31 2156.87

2 Projects in pipeline 15 839.72

3 DPR under preparation 1400

4 CRF & ISC likely to be awarded during 2016- 17 79 1706.65

5 New National Highways Declared 10 811

6 National Highways declared  “In Principle” 35 2591

Total Estimated / Projected investment in UP since


May 2014.   8641.66

Table 5: Major projec ts


c ompleted during last 2 years. Major Projec ts c osting > Rs.100 Crs.

TPC/ Civil
Sl. Length Remark/Subs
NH Work Mode Cost (Rs. In
No. (in km) c ompletio
Cr)
4- laning of
Lucknow- Raebareilly BOT
1 24B 70 635 Completed in Ja
section (Annuity)
2 Laning with Paved
Shoulder of COD for 81.4 km
2 93 BOT (Toll) 81.4 250
Agra - Aligarh Section in Aug, 2015
COD for 118
3 24 4 laning of Moradabad -
Bareilly BOT (Toll) 121 1267
issued
in Nov, 20
COD for 103
4 93 4/6 laning of Ghaziabad
– Aligarh BOT (Toll) 126.3 1141
issued in June, 2
ROB complete
Unnao ROB and
approaches of
5 25 EPC 16.2 53.52 opened for tra
Lucknow Kanpur section
23, June, 2015
2 laning with paved
shoulder of COD for 123
6 86 BOT (Toll) 123.86 373.47
Kanpur – Kabrai Section issued in July, 20
6- laning of Etawah – Chakeri 160.21 1928 6- laning comple
7 2 BOT (Toll)
section BOT (Toll)
mode 159.71 km in Se
2laning with PS of Raebareilly – BOT 166 569.4
8 231 Completed in Fe
Jaunpur on BOT
Annuity mode. (Annuity)
    Total 864.97 6217.39
TPC : Total Project Cost
COD : Commercial Operation Date.
 
Table 6 : Ongoing Major Projec ts: Physic al and
Financ ial progress
(a)          Projec ts under NHAI

TPC/ Civil Date of Start Statu



Stipulated
NH Length Cost (Present p
Sl. Work Date of
No. (km) (Rs. progres
No. Completion
Crore)
1 25 Jajmau Ganga 5.46 201.66 Dec, 05 Dec, 08 94% in Progre
Bridge to Rama
Devi Crossing
2 2&3 Construction of 32.2 465.5 Jul, 11 Jul, 14 85% in progre
new 4 Lane
Agra
Bypass(EPC)
3 24 4- laining of 121 1267 Dec,10 June,13 98.6% in p
(PCOD issu
Moradabad –
length of

Bareilly Section km.) Only


on BOT (Toll) remains t
mode completed. D
TPC/ Civil Date of Start Statu

Stipulated
NH Length Cost (Present p
Sl. Work Date of
No. (km) (Rs. progres
No. Completion
Crore)
4 24 4- laning of 151.2 1046 March, 11 Aug, 13 44% in Progre
Bareilly –
Sitapur sec on
BOT (Toll)
mode
5 2 6- laning of 160.21 1573 Mar, 13 Sep, 15 99% (6- lanin
is complete
Etawah –
balance wo
Chakeri
section service road
BOT (Toll) etc at few lo
mode left due to
progress
award)
6 91 Ghaziabad to 126.30 1141 Feb, 11 Aug, 13 96%(PCOD
for length 10
Aligarh (Km
on 23.06.15
23.600 to Km
140.200) BOT
(Toll) mode
7 24B 2- laning with PS 106.6 291.4 Jul, 12 Jan, 14 58% in progre
of Rbly –
Allahabad
section on BOT
(Toll) mode
8 2 6- laning of Delhi 179.5 1928 Oct, 12 Apr, 15 51% in progre
– Agra
section
on BOT (Toll)
mode
9 232 2laning with PS 155 636 Apr, 14 Oct, 16 70% in progre
of Tanda -
Raebareilly on
EPC Mode.
10 232 2laning with PS 133 429 Apr, 14 Oct, 16 58% in progre
of
Raebareilly -
Banda on EPC
Mode.
11 56,29 4- lane
Varanasi 16.55 261.00 May, 15 May, 17 20% in progre
Bypass (Phase-  
I) on EPC Mode.
12 233 4- laning of 58.64 674.34 Dec,15 May, 18 The contra
Ghaghra Bridge mobilizing

to Varanasi site and esta


section from camps and
km 121.800 to infrastructur
km 180.420 undertake

[Package- I] on project.
EPC mode.
13 233 4- laning of 59.95 741 Jan, 16 June, 18 The contra
Ghaghra Bridge
mobilizing

to Varanasi
section of
NH- site and esta
233 from km camps and
180.420 to km infrastructur
240.340
[Package- II on undertake

EPC mode. project.


TPC/ Civil Date of Start Statu

Stipulated
NH Length Cost (Present p
Sl. Work Date of
No. (km) (Rs. progres
No. Completion
Crore)
14 233 4- laning of 59.07 785 Jan, 16 June, 18 The contra
Ghaghra Bridge
mobilizing

to Varanasi
section of
NH- site and esta
233 from km camps and
240.340 to km infrastructur
299.350
[Package- III] on undertake

EPC mode. project.


15 56 4- laning of 74.53 986 Jan, 16 June, 18 The contra
Sultanpur to
mobilizing

Varanasi
section of
NH- site and esta
56 from km camps and
134.700 (design infrastructur
chainage km
134.700) to km undertake

205.000 (desing project.


chainage km
209.230)
[Pac kage-I] on
EPC mode.
16 56 4- laning of 63.36 806 Jan, 16 June, 18 The contra
Sultanpur to
mobilizing

Varanasi
section of
NH- site and esta
56 from km camps and
205.000 (desing infrastructur
chainage km
209.230) to km undertake

263.000 (design project.


chainage
272.590)
[Pac kage-II] on
EPC mode.
    Total 1502.57 13231.9      

(b)          Projec ts under NHDP IV Zone of MORT&H

Sl. NH. Name of Length Agreement TPC in Date Length Stipulated Status
No. No. Projec t (Km) amount    Crs of    Completed Date of (Present
(Rs. In c r.) start till Marc h Completion physic al
2016 (km) progress)
1 29E Gorakhpur- 81.41 441.00 569.34 19.03.15 45 Mar, 2017 50%
Ferenda-
Nautanwa-
Sonouli
section 
2 28C Barabanki 43.00 272.70 358.47 19.03.15 31 Mar, 2017 68%
to junction
with
MDR-
13 near
Jarwal
section  
3 28C Junction 50.00 261.00 337.58 28.10.14 50 April, 2016 99%
with MDR-
13 near
Jarwal
to
Bahraich
bypass
section 
4 28C Bahraich 51.00 328.45 437.92 30.10.14 50 June, 2016 90%
bypass to
Rupaidiha
section  
5 233 Indo- Nepal 65.87 393.08 551.48 26.06.15 0 June, 2017 5%
Border to
Rudhauli
section
Bridge
section 
7 27 Allahabad 41.72 400.05 774.57 Yet to 0 - -
to UP/MP start
Border
section   
8 29E Gorakhpur 18.25 531.00 531.00 Yet to 0 - -
bypass start
from
existing
km 79.670
of NH- 29E
to existing
km
251.700 of
NH- 28
407.65 3024.78 4111.29 206

(c )           Projec ts under Uttar Pradesh PWD &


PIU of MORT&H

Sl. NH
No. Name
of work Length Sanc tion Date of Start Stipulated Sta
No (km.) Cost       ( Date of (Phy
Rs. Cr.) Completion c omple
lik
c omple
)

1 96 Strengthening 46.47 227.74 23- 2- 13 May, 2016 92% /


O
with provision of 2016
paved shoulder in
km.
0.00 to
46.470 of NH-
96(330) EPC
MODE
2 730 Widening & 33.00 207.88 29- 2- 16 Aug, 2017 Agreem
strengthening signed o
from km. 505.00 15, Ap
to 538.00 of
NH- date 29-
730 (EPC MODE).

3 730 Widening & 26.90 138.44 03- 2- 16 Feb, 2018 Agreem


strengthening signed o
from km. 454.00 15, Ap
to 470.90,
474.00 date 03
to 484.00 of NH-
730 EPC MODE

4 730A Widening to two 50.675 164.54 28- 2- 14 Dec, 2016 35%/ De


lane carriageway – Not
with paved imposin
shoulder and issued.
strengthening
from Km.0.00 to
50.675 of NH-
730A (EPC mode)

5 Eastern Construction
of 17.93 302.73 04.03.2014 July,2017 The
co
side
of Ring Road for has p
NH- 24B Raebareli city to co
(Phase- I) on the w
Eastern Side of 31.07.20
NH- 24B

6 56 Four laning
of 17.25 753.57 15- 9- 15 Sept, 2017 Physica
Babatpur- progres
Varanasi section 11.25%.
of NH- 56 (231) date
Km 263.00 to complet
280.25 (EPC Septem
MODE) 2017.
(50.675) to to be
105.500 of NH- and ap
730A on EPC date
mode notified
    Total 246.655 2093.23      

Table 7 :
Projec ts awarded in 2014-15 & 2015-16:

Sl
Name of the Projec t
No

NH(O)
Projec ts exec uted by State PWD

1
Widening with Paved
shoulders & Strengthening from Km.0.00 to 50.675 of NH- 730A EPC MODE

2
Strengthening with
provision of paved shoulder in km. 0.00 to 46.470 of NH- 96(330) EPC MODE

3
Widening &
strengthening from km.505.00 to 538.00 of NH- 730 (EPC MODE)

4
Widening &
strengthening from km. 454.00 to 470.90, 474.00 to 484.00 of NH- 730 EPC
MODE

5 Constn. for four laning of


Babatpur- Varanasi section of NH- 56 (231) Km 263.00 to 280.25 (EPC MODE)
6
Construction
of Ring Road for  Raebareli City (Phase - I) on Eastern side of NH 24B
7
Widening to
two lane with paved shoulder from Km.51.000 (50.675) to 105.500 of NH- 730A on
EPC mode
   Sub- total
A

NHDP-IV
exec uted by state PWD

8 Barabanki to junction with


MDR 13 near Jarwal section of NH- 28C in Uttar Pradesh km 0 to 43
9 Junction with MDR- 13 near
Jarwal to Bahraich section of NH- 28C in Uttar Pradesh km 43 to 93
10 Bahraich bypass to Rupaidha
section NH- 28C in Uttar Pradesh km 99 to150
11 Sonouli to Gorakhpur
section of NH- 29E in Uttar Pradesh km 0/0 to 80/0
12 Indo- Nepal Border to
Rudhauli section of NH- 233 in Uttar Pradesh km 0/0 to 65/870
13 Rudhauli to Ghagra Bridge
section of NH- 233 in Uttar Pradesh km 65/870 to 122/270
14
Four laning of Allahabad
to UP/MP Border section of NH- 27  
15
Gorakhpur bypass from
existing km 79.670 of NH- 29E to existing km 251.700 of NH- 28
  Sub- total B

NHDP-IV exec uted by NHAI


16 Construction
of 4- lane Varanasi Bypass connecting NH- 29 and NH- 56 (Phase- I) on EPC Mode.

17 4- laning of
Ghaghara Bridge to Varanasi section from km 121.800 to km 180.420 (Pkg- I) on
EPC Mode.

18 4- laning of
Ghaghara Bridge to Varanasi section from km 180.420 to km 240.340 (Pkg- II) on
EPC Mode.

19 4- laning of
Ghaghara Bridge to Varanasi section from km 240.340 to km 299.350 (Pkg- III)
on EPC Mode.

20 6
laning of Agra to Etawah Bypass section from km 199.660 to km 323.525 on BOT
(Toll)
21 4- laning
of Sultanpur to Varanasi section of NH- 56 from km 134.700 to km 205.000
(Design Ch. 209.230)
22 4- laning
of Sultanpur to Varanasi section of NH- 56 from km km 205.000 to km 263.000
(Design Ch. 272.5
23 6- lane
Eastern Peripheral Expressway around Delhi
24 Construction
of Delhi – Meerut Expressway
  Sub- total C

  Total (A+B+C)

Table 8:
Projec ts in pipeline:
NH(O)
Projec ts exec uted by State PWD

Widening of existing single lane


carriageway to two
lane carriageway
1 with paved shoulder and 54.43 298.33
strengthening from Km.51.000
(50.675) to 105.000 of NH- 730A

Rehabilitation and Up- gradation of


Bahraich- Shrawasti section
(Km.248.40 to 310.00) of NH- 730 in
2 61.90 388.83
the State of
Uttar Pradesh to two
lanes with paved shoulder on EPC
mode

Rehabilitation and Up- gradation of


Harpalpur - Sugira
section
(Km.89.600 to 133.520) of NH- 76
3 41.47 208.50
(New NH No.339) in the State of
Uttar
Pradesh to two lane with
paved shoulder under EPC mode

Rehabilitation and Up- gradation of


from Km.285.000
to 326.000 of NH-
4 76 (Kalupur- Lalata road) to two lane 41.25 240.30
with paved shoulder on
EPC mode in
the State of Uttar Pradesh

Rehabilitation and Up- gradation of


Lakhimpur - Sisiya
section
(Km.140.00 to 188.80) of NH- 730  to
5 48.80 296.50
two lanes with paved shoulder on
EPC mode in the State of Uttar
Pradesh

Rehabilitation and Up- gradation of


Sultanpur - Pratapgarh section of
NH- 96 from existing km 60/000 to
6 km 90/000
[Design Ch. 60.000 to Ch. 30.87 208.88
90.865] to Two lane with paved
shoulders on EPC
mode in the state
of Uttar Pradesh

Rehabilitation and Up- gradation of


Tulsipur- Barhani Section (Km
351+000 to Km 385+000) of NH- 730
7 34.00 249.50
to two lane
with paved shoulder
under EPC mode in the State of
Uttar Pradesh

Rehabilitation and Up- gradation of


Sisiya- Nanpara section (Km.188.8 to
8 226.100) of NH- 730 in the State of 37.46 213.51
Uttar
Pradesh to two lanes with
paved shoulder under EPC mode

Rehabilitation and Up- gradation of


Pratapgarh to Allahabad Bypass
road junction section of NH- 96 from
existing
km 100+800 to km 135+230
9 34.70 599.34
[Design Ch.100+800 to Ch. 135+500]
to four lanes
with paved shoulders
on EPC mode in the state of Uttar
Pradesh

Rehabilitation and Up- gradation of


Puranpur - Khutar section (Km38.000
10 to 82.000) of NH- 730 in the State of 44.13 225.96
Uttar Pradesh to two lanes with
paved shoulder under EPC mode

  Sub- total
A 429.01 2929.65

11 Aligarh- Moradabad 146.37 503.34

12 Meerut
- Buldandshar 61.19 609.72

13 Varansi- Gorakhpur
(Pkg- II) 72.15 856.64

14 Varansi- Gorakhpur
(Pkg- III) 65.38 852.32
  TOTAL 839.72 6789.82

Table 9 :DPR Under


Preparation:

 Cost (TPC in
Sl No Name of the Projec t Length (km)
Crore)

NH(O)
Projec ts exec uted by State PWD

DPR of remaining
stretches of NH-
1 76, NH- 730, NH- 330A, NH- 19, NH- 700 7000
119

NHDP-IV
exec uted by NHAI

4- laning of Aligarh- Kanpur


section 282 km
2 of NH- 91 under NHDP Phase- IV on
BOT (Toll) mode

Lucknow Ring Road under


NHDP 100 km
3
Phase- VII

Varanasi Ring Road


(Phase- II) under 43 km
4  
Phase- VII

2- laning with paved


shoulders of 125 km
5 Varanasi- Hanumanha section of  
NH- 7 under NHDP Phase- IV on EPC
mode
6- laning of Hapur
bypass- 100 km
6 Moradabad section of NH- 24 under  
NHDP phase- V
2- laning with paved
shoulders of 50 km
7 Unnao- Lalganj section of NH- 232A  
under NHDP Phase- IV on BOT
(Annuity) mode
    700 7000

Total 1400
  14000

Table 10 : List
of CRF works:

Sl Name of the
proposal Length in Km. Modified
No c ost
by
Ministry
1. Widening and strengthening
OF Kairana- Khatauli 14.90 28.31
road from Km.33.000 to 47.900 (MDR)
2. Bhitaura- bahedi road
(ODR) from Km 1.000 to 41.80 77.93
42.800, comprising of widening and strengthening
work
from 3.75 m to 7 m (two laning).
3. Sishgarh- bahedi road(ODR)
from km 1 to 20, 20.00 36.68
comprising of widening and strengthening work
from 3.75 m to
7 m (two laning)
4 Widening and strengthening
of  Baha- Udi road from 9.000 18.83
Km.22 to 30
5 Widening and strengthening
of  Udi- Chakarnagar- 42.300 94.40
Bareh road
6 Widening and strengthening
of  Barkheda- 20.650 48.08
Daolatpur- Uganpur- Suhas road from Km 0.000 to
20.650
7 Strengthening of  Gawan
- Anupshahar  road from 9.390 12.24
Km 0.000 to 9.390
8 Widening and strengthening
of  Widening & 16.630 14.48
Strengthening of Babrala- Anupshahar road from
Km 0.00 to
Km 16.630
9 Widening &
Strengthening of Rajpura- Tikata- Bahjoi 24.800 36.32
road from Km 0.00 to 24.800
10 Widening &
Strengthening of link road connecting 17.000 26.75
Km 193 of NH- 93 (Chandausi) via
Ata- Mauassu-
Naglia ballu- Tharaisa Jai Singh up to Pawasa from
Km 0.00 to
17.00
11 Widening &
Strengthening of road connecting Km 11.850 20.14
from Km. 0.00 to 8.000
13 Widening &
Strengthening of Kanth - Mishripur - 33.700 67.80
Begampur - Karanpur - Rattupura -
Thakurdwara -
Jaspur Road (KMBK road from Km 0.000 to 13.600,
KRSJ road from
Km1.000 to 8.000, TR road from
Km 1.000 to 8.000 and TJ road from Km 0.000 to
5.000).
14 Widening &
Strengthening of Dalpatpur - Aliganj 42.000 64.27
from Km 0.000 to 42.000
15 Widening &
Strengthening of Bisalpur - Bilsanda 19.580 21.78
Gola road   from Km 1.580to 21.000.
16 Widening &
Strengthening of Nawabganj - 3.750 10.02
Dalelnagar- Vaharjagit- Barkheda road                   
(
Barkheda- Nawabganj road)      from Km 16.000 to
19.750
17 Widening of Bisauli- Aonla
road   from Km.0.000 to 14.000 12.39
14.000
18 Widening &
Strengthening from Gandinagar Jamo 6.575 8.64
road to Jodhnapur Madka via Barouliya
19 Strengthening of Jais -
Mohanganj road from Km 17.000 22.57
0.000 to 17.000
20 Strengthening of road from
Varisganj to Devkali 10.000 11.09
Chauraha via Raniganj from Km 0.000 to 10.000)  (
Varisganj- Shukulbazar- Subeha road)
21 Strengthening from road Km
2 of Sourikh- 10.000 20.93
Daulatabad road to Behatarampur –Kairda
Vishungad road (Km 0.00
to 10.00)
22 Widening &
Strengthening of Raebareli- 36.500 68.52
Gurubakshganj- Kheri- Semri road from Km 5.800 to
Km  to 42.300
23 Widening &
Strengthening of Lalganj- Semarpaha- 12.600 19.73
Ralpur road Km 7.00 to 19.600
24 Widening &
Strengthening of remaining portion of 2.953 3.12
Raebareli- Dalmau- Fatehpur road (Km 0.00
to Km
2.953)
25 Widening &
Strengthening of Dalmau- Jagatpur road 22.400 35.65
from Km 3.600 to Km 26.000
26 Widening &
Strengthening of Jahanabad Richa road 10.000 14.62
from Km. 0.00 to 10.000
27 Widening &
Strengthening of Puranpur Diyoriya 14.720 33.03
Kalan road  from Km. 30.00 to 44.720)
28 Widening &
Strengthening of Bareilly Bisalpur road 14.800 27.97
from Km 26.000 to Km 40.800
29 Strengthening of
Bilraya- Panwari road from Km 23.650 36.53
288.00 to Km 311.650
30 Strengthening of 
Muradganj- Ayana- Bijhalpur road 13.700 26.39
(Km 0.00 to 10.00)
31 Widening &
Strengthening of Biswan- Laharpur- 27.200 56.68
Hargaon road from Km 0.000 to Km 27.200
32 Widening &
Strengthening of Biswa – Mahmuda 24.830 56.39
road from Km 0.000 to 24.830
33 Widening &
Strengthening of Lalitpur - Mehrauni 22.140 41.48
road from Km 5.360 to 21.000 and from Km
35.500
to 42.000
34 Widening &
Strengthening of Jhansi- Unnao- Balaji 10.900 18.62
road from Km 0.000 to 10.900, which
starts from
Km 5 of NH- 75
35 Widening &
Strengthening of  Jalalpur- Rampur - 22.350 37.11
Bhagan- Tarun Aahirouli road from Km
0.000 to
22.350
36 Widening &
Strengthening of Bisalpur Banda 11.20 22.67
Puwayan Khutar road from Km 21.000 to 32.200
37 Widening &
Strengthening of Amroha ring road / 35.775 53.52
bypass from Km 0.00 to Km 35.775
38 Widening &
Strengthening of Chunahar Jamui 19.025 43.65
Aaharora road from Km 1.00 to 20.325
39 Widening and strengthening
of  Nawabganj - 16.000 27.82
Dalelnagar- Baherjageer road from Km 0.000 to
16.000
40 Widening and strengthening
of  Inayatpur - Ghopa 12.200 10.47
(Fulaona) link road
41 Widening and strengthening
of Birsingh – Halapur 17.050 18.90
link road
42 Widening and strengthening
of  road in Lambua via 15.500 23.60
Kothra Hagiganj, Rajumari to Tatomureni from  Km.
0.00
to 15.500
43 Widening and Strengthening
from  Aligarh Ramghat 15.300 29.44
road to Gaonkheda Godha CTK road from Km 0 00
45 Wideing and Strengthening
of  Chibramau- Kairda 9.800 21.26
road Km.0.000 to 9.800
46 Widening and Strengthening
of Lalitpur - Devgarh 32.300 53.77
road from Km 0.000 to 32.300
47 Widening and Strengthening
of Jakhora - Rajghat 19.000 35.31
road from Km 0.000 to 19.000
48 Widening and Strengthening
of Lalitpur - Rajghat 21.560 37.82
road from Km 0.000 to 21.560
49 Widening and Strengthening
of Karahi to Pathra via 9.00 4.13
Goura- Tigodwa from Km 0.000 to 9.000
50 Widening and Strengthening
of Baansi Ganguli 5.000 2.36
Chauraha to Gothwa Ghat via Piperhiya from Km
0.000 to
5.000
51 Strengthening of Chilaha-
Gopiganj road Km 0.00 to 10.400 14.31
10.40
52 Widening &
Strengthening of link road connecting 13.100 23.94
NH- 509 at Narora via  Jamuna singh
road-
Ishampur- Asadpur- Dabathra with State Road 18
(Junawa)  (Km 0.00 to
13.100)
53 Widening and Strengthening
of Gorakhpur- 19.485 36.78
Pipraich- Kaptanganj road from Km 0.000 to 19.485
54 Widening and Strengthening
of Sahajanwan - 23.200 60.02
Bakhira road from Km 0.000 to 23.200
55 Pipiganj - Jasval - Sisai
- Sahjanwan road from Km 20.200 28.36
0.000 to 20.200
56 Four laning of interna
lportion of old NH-2 from Km 18.200 127.32
161.800 to 180.000 (Kokhraj to Manauri)
57 Strengthening of city
protionof old NH- 93  handed 10.635 20.86
over to State PWD from Umed to Nagla Bhus from
Km
0.000 to 10.635
58 Widening and Strengthening
of Agra- Jalesar- 10.700 18.06
Sikandramau road from Km 62.000 to 74.4000
59 Widening and Strengthening
of Bhojubir- Sindhora 21.200 46.77
road from  Km 2.00 to 23.200
60 Widening and Strengthening
of link road connecting 20.925 41.44
NH- 11 to NH- 2 at (Achnera Deen Dayal Dham Farah
road)
Kirvali- Achnera- (Km 4.65
to 6.65)
Achnera- Zhundavai (Km 0.00
to Km 1.70)
Achnera- Farah (Km 0.00 to
Km 1.70 & Km 1.70 to
Km 9.025)
Farah- Achnera (Km 0.60 to
Km 8.20)
Farah- Shonkh (Km 0.00 to
0.60)
61 Widening &
Strengthening of Mau to 10.000 24.70
Mohmmadabad road via Yousufpur  (Km 0.00 to
Km
10.000)
62 Widening of BTIB to Mahowa
Dhobha Shahapur 18.000 27.25
road (Km 0.000 to Km 18.000
63 Widening &
Strengthening of Shoharatgarh to Palta 5.000 2.12
Devi lin road  via Ramwapur Chouraha
64 Widening &
Strengthening of Jaunpur- Malhani- 27.150 32.02
Khuthan road (Km 0.00 to Km 27.150)
65 Widening &
Strengthening of Kundaha- Sujanganj- 36.080 45.98
MachliShehar- Madiyahoo- Jalalpur- Kerakat-
Sultanpur
road (Km 0.00 to 27.080 & Km 87.500 to
96.200)
66 Widening &
Strengthening of Jivli - Devgaon - 15.060 15.23
Mehnajpur - Aodiyar road (Km 18.440 to Km
33.500)
67 Widening &
Strengthening of road from Babatpur- 39.350 93.28
Chaubepur- Bhagtua- Balua bridge (Km.
32.340 to
61.13)
68 Widening &
Strengthening of Baburi- Dharauli road 15.000 34.60
(Km 0.00 to 15.00)
69 Widening &
Strengthening of Chahaniya- Dhanapur- 42.000 76.59
Mahuji- Jamaniya road
70 Widening &
Strengthening of Lalapur Imliya Kanjasa 23.600 32.66
Bhita road (Km 0.00 to Km 23.600)
71 Widening &
Strengthening of Pailani- Galauli- Bara 15.000 27.52
road (Km 0.00 to 15.00)
72 Widening &
Strengthening of Kaptanganj- Siswan- 73.000 189.89
Nichlaul- Thuthiwari- Nautanwa
73 Widening &
Strengthening of Aligarh to Gonda road 16.200 27.01
(Km 0.00 to Km 18.200
74 Widening &
Strengthening of Gazi ka bagh 17.97
13.600
Mubarakpur link road (Km 0.00 to Km 13.600)
75 Widening &
Strengthening of SMK road to lutar 44.54
khaur bhaiyya Laxman ka Pura- Meja- Bhatauti
road 19.25
(Km 0 000 to Km 19 250)
  ISC Works    
1 Widening of existing
single lane carriageway to two 49.00 98.97
lanes with Strengthening from Km.0.00 to Km
49.00of  LalganjHaliyaAndawaManigaraha Road
(ODR)  upto Madhya Pradesh Border
2 Widening of existing
single lane carriageway to two 36.24 96.05
lanes Km. 2.50 to Km 36.24 and with two lane
paved shoulder from Km. 0.00 to Km 2.50 with
Strengthening from Km.0.00 to Km
36.24 of
Chopan to MP Border
Road (ODR)
3 Widening of existing carriageway
to two lanes with 15.43 59.42
paved shoulder with Strengthening from Km.0.00 to
Km 15.43
of BhabniPokharaAasandeeh
Road (ODR)
of Distt. Sonebhadrain
Sub-total 100.67 254.44
  Total 1706.653 3035

Table 11: New


National Highways Dec lared

Length
in Date of
SN NH No Name of Highway
Km Dec laration

123
1 Dholpur to Bharatpur 15 13.8.2011

330 Allahabad- Pratapgarh- Sultanpur-


Faizabad- Ayodhya- Nawabganj- Gonda-
2 terminating
at NH- 730 near Balrampur 96 31- 07- 2013
(Portion from Ayodhya to Balramapur via
Gonda)
334A
3 Purkaji – Laksar – Haridwar road 15 26.02.2014

334B
4 New Meerut - Haryana Border 60 04.03.2014

219 New
5 Bihar Border- Chandauli (NH- 19) 5 04.03.2014

709A Haryana Border- Shamli- Budhana-


6 94 10.03.2015
Meerut
(NH- 34)
727A Gorakhpur (NH- 27)- Deoria- Salempur-
7 100 10.03.2015
Bihar Border
227A
Ayodhya (NH- 27)- Chhawni- Kalwadi-
8 218 10.03.2015
Barhalganj- Barhaj- Bihar Border
731A
Near Pratapgarh (NH- 31)- Jethwada-
9 Shrangverpur-
Manjhanpur- Rajapur- Near 160 10.03.2015
Chitrakoot (NH- 35)

330B Near Gonda (NH- 330)- Near Jaewal


(NH-
10 48 10.03.2015
927)

  TOTAL 811
 

Table 12 :
National Highways dec lared  ‘In Princ iple’:

Length in
Sl.
Name of
Highway / road U.P. (in
No.
Kms)
1 Allahabad- Jaunpur- Gorakhpur 170.00
2 Panipat- Haryan / UP border -
Shamli-Muzaffarnagar-Bijnor-Nagina 131.00
3 Delhi- Saharanpur 170.00
4 Ghaziabad- Noida- Faridabad- Sohna (Total length= 75
km; Haryana= 57 km;
18.00
UP= 18 km)
5 Nuh- Mandkola- Palwal- Jewar- Bulandshahar (Total
length= 60 km; Haryana=
8.00
52 km; UP= 8 km)
6 Palwal- Aligarh (Total length= 83 km; Haryana= 17 km;
UP= 66 km) 66.00
7 Faridabad (Kheri
Bridge)- Jasana- Cheersi- Manjhawali- Atta Gujaran- Dankor-
8.00
Yamuna Expressway
(Total length= 25 km; Haryana= 17 km; UP= 8 km)
8 Guna- Ashok Nagar – Thuban- Piprod- Chanderi – MP/UP
Border near
Rajgahtdam - Lalitpur – intersecting N- S
corridor- Panari- Rajwara-
55 00
10 Stretch from Bareilly (junction at NH- 30 near Civil
Lines)- Bhutah –Bisalpur 36.00

11 Stretch from Bewar (on NH- 34) Fatehgarh- Miranpur


Katra (on NH- 30)
191.00
Bisalpur (on NH- 370)- Pillibhit on NH- 730
12 Stretch from Nawalpur–Ubhaon crossing- Sikandrapur- Maniar- Bansdih-
108.00
Reoti- junction
with NH- 31
13 Stretc h from Allahabad
–Koraon-Drumanodganj-Haliya-Awadhadam-
Pipra-Manigarha- UP /MP border- Karondiya- Bagdara- Chatrangi- Singrauli
104.00
extended up to junction on
NH- 39 in Madhya Pradesh near Waidhan
(Total=176 km,U.P=104 km, M.P= 72km)
14 Stretch from Karmaini (junction on NH- 24 near
Compierganj)- Menhdalwal   
105.00
Kahliabad- Dhanghata- Ramnagar- Nyori (junction on
NH- 28- Azamgarh
15 Stretch form Agra (junction on NH- 509 near Islam
Nagar- Jalesar- Etah
79.00
(junction on NH- 34 near Police line)
16 Stretch from Balia (junction on NH- 31 nearTeekha )-
Mau- Azamgarh on
100.00
NH- 28
17 Stretch from Jaunpur to Khuthan extended upto NH- 31
near Saidpur 60.00

18 Stretch from Palia Shajahanpur via Hardoi –Lucknow 270.00


19 Stretch from Mathura (NH- 44) Hathras- Badaun- Bareilly
(NH- 30) 215.00
Stretc h from Moradabad- UP / Uttrakhand border- Jaspur- Kashipur
20 53.00
(Total=58km,U.P=53km, Uttarakhand=5km,)
21 Saidpur- Sadat- Jakhania- Jalalabad mor- Mardah 50.00
22 Tarighat- Bara- Buxar(Uttarpradesh= 38.20 km;
Bihar=10.80 Km) 38.20
23 Akbarpur- Baskhari 23.00
24 Muzzafarnagar- Jansath- Miranpur
on NH 34 40.00
25 Khurja on NH 34- Jewar 34.00
26 Meerut- Garhmukteshwar (junction
at NH 9) 47.00
27 Sikandarpur- Ballia 35.00
28 Jalesar- junction with NH 34 near
Sinkandara Rao 25.00
29 Gorakhpur (junction at NH
27)- Paratawal 32.00
30 Maharajganj- Nichlaul- Thuthibari
road (upto Nepal border) 39.00
31 Basti- Mehdawal- Kaptanganj 92.00
32 Faizalnagar- Tamkuhi- extended
upto Salempur on NH 727A 52.00
33 Salemgarh- Sewarhi- Padrauna 49.00
34 Zamania- Gehmar 21.00
35 Tamkuhira (NH 28)- Betia (NH 28B) 36.00
  Total 2591.20
 
 
For Distric t wise details of NH works in Uttar Pradesh, Clic k here for the link

*****