Sensitivity Analysis
Sensitivity Analysis
D.17
YEAR INITIAL INV VARIABLE COST
0 -14000
1 -4000
2 -4000
SENSITIVITY MARGIN:
=NPV/PV OF VARIABLE *100
1 SALES SENSITIVITY :
=2049/23182*100 8.84%
5 COST OF CAPITAL
FIND IRR
YEAR CF DF 8%
0 -14000 1
1 9000 0.925925925925926
2 9000 0.857338820301783
SENSITIVITY = IRR-COC/COC
=18.5-8/8
131%
D.18
YEARS DF AT 10% INITIAL INV
0 1 -1000
1 0.909090909090909
2 0.826446280991735
3 0.751314800901578
4 0.683013455365071
1000
NPV = 267.95
8 COC SENSITIVITY
=IRR-COC/COC*100
IRR:
YEAR CASH FLOW DF AT 10%
0 -10000 1
1 400 0.909090909090909
2 400 0.826446280991735
3 400 0.751314800901578
4 400 0.683013455365071
-47.11%
CASH INFLOW NET CASH FLOW
PV DF 20% PV IRR
-14000 100% -14000 18.52%
8333.3333333333 0.833333333333333 7500
7716.0493827161 0.694444444444444 6250
2049 -250
IRR =8+(2049/(2049+250)*(20-8))
1870%
LOWEST SENSITIVITY
8.45% IF THE MATERIAL COST INCREASES BY8.45%, THEN THE NPV WILL BE 0
21.13% IF THE LABOUR COST INCREASES BY 21.13%, THEN THE NPV WILL BE 0
84.53% IF THE FIXED COST INCREASES BY 84.53%, THEN THE NPV WILL BE 0
21.13% IF THE SALES VOLUME DECREASES BY 21.13%, THEN THE NPV WILL BE 0
26.80% IF THE INITIAL INV INCREASES BY 26.80%, THEN THE NPV WILL BE 0
PV DF AT3% PV DF 1% PV
-10000 1 -10000 1 -10000
363.63636363636 0.970873786407767 388.349514563107 0.990099009901 396.039603960396
330.5785123967 0.942595909133754 377.038363653502 0.9802960494069 392.118419762768
300.52592036063 0.91514165935316 366.056663741264 0.9705901479276 388.236059171058
273.20538214603 0.888487047915689 355.394819166275 0.9609803444828 384.392137793126
-8732.05 -8513.16063887585 -8439.21377931265
NPV 2049
PV OF LABOUR COST VARIABLE OH PV OF VARIABLE OH FIXED COST PV OF FC
A.NPV AT 10%
YEAR CF DF 10% PV
0 -20000 1 -20000
1 14000 0.909091 12727.27 THE PROJECT WILL BE ACCEPTED AS IT IS POSITIVE
2 10000 0.826446 8264.463 BUT DOESN’T CONSIDER RISK
3 10000 0.751315 7513.148
NPV 8504.88
D.20
YEAR 0 1 2 3 4
INITIAL INVESTMENT -20000
REVENUE 40000 38000 36000 34000 32000
MATERIAL COST 15000 15900 16500 17250 17700
LABOUR COST 5000 5300 5500 5750 5900
NET CASH FLOW -20000 16800 14000 11000 8400
RFR 5% 1 0.952381 0.907029 0.863838 0.822702
PV -20000 16000 12698.41 9502.214 6910.701
NPV 25111.33
E ACCEPTED AS IT IS POSITIVE
PROBABILITY ANALYSIS:
INCORPORATES RISK INTO THE INVESTMENT APPRAISAL
EXAMPLE:
ASSUME THE FRST YR CF IS NOT AFFECTING SCND YR CF
DISCOUNT RATE IS 10%
FIND NPV
YEAR CF PROBABILITY EV
0 -1000 -1000
500 50%
1 600 30% 570
700 20%
500 40%
2 450 30% 500
550 30%
IF THE FRST YEAR CF IS AFFECTING THE SCND YEAR CF, THEN WE SHOULD USE JOINT PROBABILIT
D.21
NPV PROB EXPECTED NPV
100 0.5 50
PROJECT A 200 0.4 80
1400 0.1 140 270
0 0.5 0
PROJECT B 500 0.4 200
600 0.1 60 260
180 0.5 90
PROJECT C 190 0.4 76
200 0.1 20 186
OF POSSIBLE OUTCOMES
NNOT BE AASSIGNED
DF 10% PV
1 -1000
0.909091 518.1818181818