Room Integrity Requirements Checklist

This checklist is used to inspect gas enclosure rooms once every 12 years. It contains 23 inspection tasks to confirm the integrity of the ceiling, walls, floor, doors, ductwork, pressure relief systems, purge systems, electrical, and general room components. Upon completion, comments can be added to note any issues. The checklist is designed to identify any changes requiring retesting of the gas enclosure's integrity.

Uploaded by

Tri Thien Nguyen
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
518 views3 pages

Room Integrity Requirements Checklist

This checklist is used to inspect gas enclosure rooms once every 12 years. It contains 23 inspection tasks to confirm the integrity of the ceiling, walls, floor, doors, ductwork, pressure relief systems, purge systems, electrical, and general room components. Upon completion, comments can be added to note any issues. The checklist is designed to identify any changes requiring retesting of the gas enclosure's integrity.

Uploaded by

Tri Thien Nguyen
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 3

Room Inspection Checklist

Enclosure/ Room Name:

Date:

Enclosure/ Room ID:

Checked by (Name/ email):

Company Name:

Gaseous System ID:

This checklist may be used once every 12 months and completed to confirm that no
changes have occurred in the enclosure integrity that would require a retest of the
enclosure.

Ref Type Inspection/Task Yes/ Notes


No/[n/
a]
1 Ceiling All Penetrations are complete, with
any services and equipment installed.

2 Ceiling All Holes/Penetrations are fire stopped


and sealed.

3 Ceiling All False Ceilings are installed and


complete.

4 Walls All Penetrations are complete, with


any services and equipment installed.

5 Walls All Holes/Penetrations are fire stopped


and sealed.

6 Walls Where Walls meet the ceiling slabs are


sealed.

7 Walls Where Walls meet the floor, slabs are


sealed.

8 Walls All Penetrations are completely

1 G a se ou s Ro o m Ch e cklist
IN T E RNA L USE ON LY
Ref Type Inspection/Task Yes/ Notes
No/[n/
a]
sealed, with any services and
equipment installed.
9 Floor All Penetrations are completely
sealed, with any services and
equipment installed.
10 Floor False floors are complete and
installed.

11 Floor All Floor Grilles installed.

12 Doors All Permanent Doors and frames are


installed.

13 Doors Doors swing outwards and are self-


closing.

14 Doors If doors are able to be locked from the


outside, emergency exit button is
installed internally to allow exit.
15 Ductwork All Dampers [fire/motorized] installed
and able to provide the correct seal.

16 Pressure All Pressure Relief systems are


Relief installed with dampers.

17 Purge All Purge Systems are installed with


System dampers.

18 Electrical Cable trunking and trays are fire


stopped including fire expansion bags
installed, as required.
(e.g., expansion bags are intumescent and
ablative fireproof pillows certified under EN 1366-
3 for sealing up to  EI 240  of cable tray
penetrations).
19 General Room is clean and free of debris and
Room dust.

20 General Emergency exit routes around


Room equipment and aisles are clear.

21 General Emergency lighting and directional


Room signs are installed and operational

22 General Emergency/warning signs installed, in


Room line with local codes and regulations,

2 G a se ou s Ro o m Ch e cklist
IN T E RNA L USE ON LY
Ref Type Inspection/Task Yes/ Notes
No/[n/
a]
at all entrances to the space, external
and internally.
23 System Alarms, beacons and lights installed
and operate immediately upon
detection.
They operate until the system has
been reset.

Comments: