Anu Final. Com
Anu Final. Com
Anu Final. Com
2)PROJECTAPROJECTR
EPORTON
STRUCTURALDESIGNANDANALYSISOFBUILDING
Submitted
byANUPAMAT
19018436
SCMSCOLLEGE OFPOLYTECHNICS
Vaikkara,Perumbavoor–683549.Ernakulam.
STRUCTURALDESIGNANDANALYSISOFBUILDING
Submitted
byANUPAMAT
19018436
SCMSCOLLEGEOFPOLYTECHNICS
Vaikkara,Perumbavoor–683549.Ernakulam.
INTERNALEXAMINER EXTERNALEXAMINER
SCMSCOLLEGEOFPOLYTECHNICS
Vaikkara,Perumbavoor–683549.Ernakulam.
ACKNOWLEDGEMENT
Anyworkwouldnotbecompletedwithoutthementionedpeoplewhoseguidanceandencouragement
led to the development of the work. We consider ourselves privileged to expressgartitudeand
respect towardsall those whoguidedus throughoutour work.
WeexpressprofoundgratitudetoDr.InduNair,Director,SCMSCollegeofPolytechnics,Vaik
kara,Perumbavoorforofferringusachance.
WeexpressprofoundgratitudetoProf.BabyP.P,Principal,SCMSCollegeofPolytechnics,Vai
kkara,Perumbavoorforhis support and motivation.
WeareextremelygratefultoMr.ArunkumarkK.K,HeadofCivilEngineeringDepartmentfor
hisimmensehelpandencouragementgivenduringthecourseoftheprojectwork.
We are deeply indebted and gratefully acknowledge the constant support and
valuablepatronageofourproject
guideMrs.RoshniEldhose,LecturerofCivilEngineeringDepartment.
Weexpressoursincerethankstotheteachingandnon-teachingstaffsfortheircooperation, for
providing a very good infrastructure and all the kindness forwarded to us incarryingout this
projectwork in college.
We also thank our classmates for their help in bringing out this project work within
astipulated time.
The report would be incomplete if we do not thank our parents and well-wishers for
theirmoralsupport duringthecourseof project.
i
ABSTRACT
This project is intended to illustrate the structural design of a veterinary hospital in detail
withusing Auto CAD and manually calculating using limit state method of design and SI
unitsconform toIS .456– 2000.It incorporates the design of slabs, beams, columns ,stairs
andcolumnfootingsof different types.
In this project, it is particularly taken a veterinary hospital ofsize 20mX 21m including RRCSlab,
Beams, Column, Footing and staircase.Loads taken for design is as per IS 875-(1987).This
design will give a good exercise for beginners in the field of design in understanding
thedesignprinciplesandpracticesandthe usingofsoftwareAutoCAD.
i
LISTOFCONTENTS
ACKNOWLEDGEMENT i
ABSTRACT ii
LISTOFCONTENTS iii
LISTOFFIGURE vi
LISTOFTABLES vii
LISTOFABBREVIATION viii
1 CHAPTER1 :INTRODUCTION 1
2 CHAPTER2:LITERATURE REVIEW 2
3.1 OBJECTIVE 4
3.2 METHODOLOGY 4
4 CHAPTER4:PROJECTPLANNINGANDDRAWING 5
4.1 PROJECTPLANNING 5
4.1.4 VENTILATION 6
4.1.5 WINDOWS 6
4.1.9 FIREPROTECTION 7
i
4.1.10FRONTYARD 7
4.1.11REAR YARD 7
4.1.12SIDEYARD 7
4.1.13OPENSPACEFORBUILDING 7
4.1.14STAIRCASE 8
4.1.15ORIENTATION 8
4.1.16BASIC ZONE 8
4.1.17CLIMATIC FACTORS 9
4.1.18SOILINVESTIGATION 9
5 CHAPTER5 :STRUCTURALANALYSISANDDESIGN 10
5.1DEADLOAD 10
5.2LIVELOAD 10
5.3LIMITSTATEMETHOD 11
5.4THEORY OF DESIGNOFSTRUCTURALELEMENT 11
6 CHAPTER6 :DRAWINGS 12
7 CHAPTER7 : LAYOUTS 17
8.1DESIGNOFONEWAY6.2×3mSLAB ` 22
8.2DESIGNOFTWOWAY4.5×3mSLAB 25
8.3DESIGNOF2.2×3mSLAB 29
9.1BEAM1 34
9.2BEAM2 38
9.3BEAM3 42
i
10 CHAPTER10: DESIGN OFCOLUMN 47
10.1COLUMN1(450×200) 47
10.2COLUMN2(300×200) 49
11.1FOOTING1(450×200mm) 51
11.2FOOTING2(300×200mm) 54
12 CHAPTER12:INTRODUCTIONTO ESTIMATION 58
13 CHAPTER13:BAR BENDINGSCHEDULE 91
13.2 SCHEDULEOFSLAB 93
14 CHAPTER14: CONCLUSION 98
15 CHAPTER15: REFERENCES 99
v
LISTOFFIGURES
1 FIG6.1GROUNDFLOORPLAN 12
2 FIG6.2FIRSTFLOORPLAN 13
3 FIG6.3SECONDFLOORPLAN 14
4 FIG6.4SECTIONAA 15
5 FIG6.5ELEVATION 16
6 FIG7.1BEAMCOLUMNLAYOUT 17
7 FIG7.2BEAMCOLUMNLAYOUTOFGROUNDFLOORPLAN 18
8 FIG7.3BEAMCOLUMNLAYOUTOFFIRSTFLOORPLAN 19
9 FIG7.4BEAMCOLUMNLAYOUTOFSECONDFLOORPLAN 20
10 FIG8.1SLAB 33
11 FIG9.1BEAM 46
12 FIG11.1COLUMNANDFOOTING 57
vi
LISTOFTABLES
1 TABLE12.1ESTIMATION OF GROUNDFLOOR 59
3 TABLE12.3ESTIMATION OFSECONDFLOOR 81
4 TABLE12.4ESTIMATIONOFSEPTIC TANKANDSOAKPIT 89
6 TABLE13.2BBSOFSLAB 93
7 TABLE13.3BBSOF BEAM 96
vii
LISTOFABBREVIATIONS
A-Area
B-Breadthofbeamoreffectivewidthofslab
D-Overalldepthofbeamorslab
DL-Deadload
d-Effectivedepthofbeamorslab
d'-Depthofcompression reinforcementfromthehighlycompressedface
fck-Characteristiccubecompressivestrengthofconcrete
fy-Characteristicstrengthofsteel
k-Constantorcoefficientorfactor
Ld-Developmentlength
LL-Liveloadorimposedload
L-Effectivespanofbeamorslab
Ix-Lengthofshortersideofslab
ly-Lengthoflongersideofslab
M-Bendingmoment
t-Wallthickness
V-Shearforce
W-Totalload
w-Distributedload/unitarea
x-Depthofneutralaxis
viii
τv-Nominalshearstress
τbd-Designbondstrength
τc-Shearstressinconcrete
τcmax-Maximumshearstressinconcretewithshearreinforcement.
Mu -Factored bendingmoment
Pt-Percentage of steel
W-Totaldesign load
Wu -Factored load
-Diameterofbar
Pu-factored axialload
Mu,lim-Limitingmoment ofresistanceofasectionwithoutcompressionReinforcement
Ac-Areaof concrete
Asc-Areaoflongitudinalreinforcementforcolumn
ix
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
CHAPTER1
INTRODUCTION
We have great pleasure to present a report of project works under taken by final year
civilengineering students of SCMS COLLEGE OF POLYTECHNICS VAIKKARA . Project
work isa partof syllabus of finalyear Civil Engineer course. The project topic we selected for
theproject is STRUCTURAL DESIGN AND ANALYSIS OF BUILDING. The aim is to
conductprojectistogetthroughtheknowledgeandexperienceofanyprojectwithmethodofconstruction
and sophisticated architectural beautywith most economy.
The aim for conducting the project is to enable the students to understand various phases of
civilengineeringconstructionby
toapplyingtheirpracticalknowledgeintheconstructionfieldandexecutingtheprojectwithmodernmate
rials,modifiedconstructionmethodsandarchitecturalbeautywitheconomy.Thishelpsthestudentstom
anagecivilengineeringconstructionproperlyand systematically.
Our proposed site is a veterinary hospital at Trissur. The building plan consist of a three
storiedbuildingwithpharmacy,storeroom, doctor’s room andoperation theatre.
The studentsare very co-operated toeachother for bring outthis project asasuccess. Theproject
works deals with the planning, structural designing, and estimate of all requirements of
aveterinaryhospital. Wedesigned it asareal one.
DEPARTMENTOFCIVILENGINEERING 1
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
CHAPTER2
LITERATUREREVIEW
InternationalJournalofScientific&EngineeringResearch,Volume 8,Issue 4,April-2017
Helps to analyze the plan of hospital building by using software techniques. InternationalJournal
ofAdvances in Science, Engineering and Technology (IJASEAT)is a scholarly online, open access,
peer-reviewed, interdisciplinary, quarterly, and fully refereed journal focusing on theories, methods
andapplications different field of Engineering Science and Technology. It is an international
scientificjournal that aims to contribute to the constant scientific research and training, so as to promote
researchinthedifferentfield. The journalcoversall areasofScience
InternationalJournalofScientificProgress andResearch(IJSPR)August 2021
Helpstofindoutthe differentstepsfor the designing of building.The applicationsof
highendequipmentinthehighlevelresearchisthedemandsoftechnologicalworldandResearchers,Engineerin
g Community is working hard to resolve all the above aspects. So there is a need of suchplatforms
where Researchers, Engineers and Scientists from all over the world share their innovativeideasto invent
great newthings andgive tothe world.
International Journal of Application or Innovation in Engineering & Management
(IJAIEM)April 2020
In this paper, ETABS software was used for analysis and design purpose mainly for the result of
shearforceandmaximumbendingmoment.RCCdetailingisofmostimportantconcernforclearunderstandinga
ndalso inexecutingthereinforcement workwithout anydifficulty.
IJISET - International Journal of Innovative Science, Engineering & Technology, Vol. 3 Issue
3,March2016
Inthispaper,STAADProV8ihasbeenusedfordesigningandanalysispurposesmainlyfortheresultof shear
force and maximum bending moment. An apartment building is analyzed and designed in thispaper. The
designing was done manually. Design of beam, column, slab, shear wall, stair case,
retainingwall,watertankandan isolatedfootingaredone.Andthedetailingis done usingAUTOCAD2016.
DEPARTMENTOFCIVILENGINEERING 2
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
DEPARTMENTOFCIVILENGINEERING 3
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
CHAPTER
3OBJECTIVESANDMETHODOLOGY
3.1 OBJECTIVE
Themainfocusoftheprojectare:
• Toidentifydifferentworkstobecarriedintheconstructionproject.
• Tocollectdatarelevanttotheprojectandcarryoutsitesurveys.
• Toselectthemostefficientmethodfromtheavailablechoicesandtodesigntherequiredelementsof
the project asper standardpractice.
• Topreparescheduleoftimeandsequencesofoperations
• Topreparetheworkingdrawingforprojectsandestimatethecostofproject.
3.2 METHODOLGY
DEPARTMENTOFCIVILENGINEERING 4
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
CHAPTER4
PROJECTPLANNINGANDDRAWING
4.1 PROJECTPLANNING
4.1.1 EconomyinConstruction
Economy in construction has three fold i.e., money, materials and time. The design must be
mosteconomical. It is clear that the cost of any project depends on many factors and design of
theprojectis oneof themajor factors.
4.1.2 PlanningofBuilding
4.1.3 OrientationofBuilding
Theplanningofthebuildingwithrespecttothegeographicaldirectionofbuilding.Orientationof the
building is the major consideration to achieve the maximum comfort and convenience
ofoccupants. The building should be placed in such a way that the utilized maximum benefit
fromair and nature and also it is protected from their harmful effects. In a topographical country
likeIndia direction of sun is a important parameters for building road face to east .So that on
summerseason comes the sun's southern desert in searching. Winter season sun rays enter
through thewindowdirectly.
DEPARTMENTOFCIVILENGINEERING 5
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
4.1.4 Ventilation
Ventilation consists on itself of fresh air exist of stay and maintain movement of air in the
roomsandbuildings.Forproperventilationwindowandventilatorsshouldbeprovidedtorequiredarea.T
heareaof ventilation forpublicmust beat least 20%offloorarea.
4.1.5 Windows
Theyadmitlightandairintotheroom.Theyshouldbeprovidedtorequiredarea.Theyshouldbe placed at
regular distance so to ensure uniformity of light. Windows should not be less than150ofthe floor
areaconveyor possiblethe principle lightningfrom thenorth.
4.1.6 ConsiderationEffectingCost
Costcontrolistheonetechniquewherewhichaimatfindingasolutiontolimitationofresources.Itisclear
thatcostof any projectdepends on many factorsand the design of theproject is one of the major
factors.If the span of theroom is increasedthan the depth of thebeam. It tends to rise and increase
the building height and the area of the walling to be build andmaintained. Further economy in
consideration can be achieved by improvement of traditionalmethod of construction at and also
by adopting new technique of design and construction usingnewmaterial.
4.1.7 AestheticViewOfTheBuilding
The building is designed in such a way has they have a good appearance. The masonry
basementis to be constructed in a good aesthetic view. The rubble works is pointed very nearly.
Now aday’s aesthetic view off the building is considered on the other sides. The natural
appearance oftherubble, bricks etc. areallowed to haveinothersides.
4.1.8 LocalMaterialsAvailable
The existing government approved quarry Vadakkanchery is very near to the site. Good earth
forfilling is available in the premises good quality of cement brick is used to the site, cement,
MSRod, paints, lime, all type of water supply fittings are available at town nearly to the site. In
allaspectconsideringavailabilityofconstructionofmaterials,thesitechosenisbest.While
DEPARTMENTOFCIVILENGINEERING 6
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
constructing a building at any locality the local materials available should be fully utilized
whichwill give full satisfaction to the local people and also employment to the local workers can
beprovided. There willbe considerable savings inthe transportation charges of the
materialsiflocalmaterialsareused.Thereshouldbeinvolvementoflocalpeoplein theconstruction
work.
4.1.9 FireProtection
We have provided possible fire protective measures. Pre-cast cement concrete block is used
forthe construction of super structure. Beams and slabs are constructed with RCC which has a
goodfire resistingcapacity.The wood shutters andframesfordoors,
windowshaveappropriatethicknesssuchthat does not catchfireeasily.The wallsareplasteredwith
cementmortar.
4.1.10 FrontYard
Every building shall have a clear front yard of 3m depth provided that Where the depth cannot
beobtained laterally through by reason of the exceptional circumstances It should suffer if the
meandepth is not less than 3m provided further that the minimum depth at any points shall not be
lessthan 1.8m.
4.1.11 RearYard
Every building has rear yard or depth not less than 3m.Laterally the rear yard shall not be
lessthan 206 of the area of the plot with minimum dimensions being not less than 1.8m at any
point.The rear yard for the purpose of this rule shall be considered as the space belonging
exclusivelytowhichisopentotheskybetweentheboundaryoftheplotonthatsideandline paralleltoitat
¼averagedepthoftheplot.
4.1.12 SideYard
A sideyard can also be considered as rearyard for the purpose of those rules if it is used
asutilityopen spaceand confirms therearyardrestriction containedabove.
4.1.13 OpenSpaceForBuilding
Everybuildinghaveaclearopenairnotlessthan1.5mwidthonitssidesotherthanthefrontandrearprovide
DEPARTMENTOFCIVILENGINEERING 7
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
dthattheauthoritymayhoweverpermitabuildingtoaboutonasideboundary
DEPARTMENTOFCIVILENGINEERING 8
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
of the plot. The open spaces stated above are for building up to 10m heights. Front, rear side
andinterior open spaces required for height of 10m. There shall be such increase in minimum
openspaces at the rate of .5 per every 3m height exceeding 10m or fraction there off. The set
back socalculatedshall beprovided fromgroundlevel.
4.1.14 StairCase
The minimum width of the stair shall not be less than .75m for building and 3m for
assemblingbuilding 1.2m for building of other occupancies. The width of thread without nosing
shall not belessthan 25cm foran internal staircaseofresidential building.
4.1.15 Orientation
The chief aim of orientation of building is to provide physically comfortable inside the
buildingbycreatingcondition,whichsuitableandsuccessfullywardofftheundesirableeffectbyjudiciou
suseof therecommendation and knowledgeof climatefactors.
4.1.16 BasicZones
For the purpose of orientation it would be convenient to divide the country in to the three
boardclimatezones
1. Hotandcold
2. Hotorwarmorhumid
3. Cold
It is to be remembered that here may be uniform climatic factors in a particular zone. They
mighteven vary during day nightinthe same zonalregion.Each zone, allthe same possess
certainbasicproblems.
DEPARTMENTOFCIVILENGINEERING 9
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
4.1.17 ClimaticFactors
From the point of view of lightning and ventilation the following climatic factors Influence
theoptimumorientation of thebuilding.
1. Solarradiationandtemperature
2. Clouds
3. Relativehumidity
4. Relativewinds
4.1.18 Soilinvestigation
For this investigation, we considered 4m deep soil. We observed there had only sandy clay.
Itsbearing capacity is 300kN/m. It was selected based on the soil bearing capacity ofthe
nearestbuilding.
DEPARTMENTOFCIVILENGINEERING 10
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
CHAPTER5
STRUCTURALANALYSISANDDESIGN
2. Liveload
5.1 DEADLOAD
The dead load in a building compress of the weight of all walls, partitions, floor and roof
shallinclude. The weight of all other permanent construction in the building, as unit weight of all
thematerials used in the proposed building are taken from IS 875-1984 1 As per this code the
unitweightofmaterials usedon the proposedbuilding are
1. Plaincementconcrete:24KN/m
2. Reinforcementcementconcrete:25KN/m
3. BrickWork:18.85KN/m
4. FloorFinish:19KN/m
5.2 LIVELOAD
Live loads, also called super imposed loads. Consists of variable loads due to people
occupants,theirfurniture,temporarystores,machineryetc.Liveloadcomingintheroofs,floors,stairetc.
of the proposed building is taken from IS 875 1984 part 1. As per this code the live loads
aretaken as floor of window and veranda: 5KN/m Stairs not liable to cover crowding: 3KN/m
Flatroofswith access provided:1 KN/m Flat roofswith access not provided:0.75KN/m.
DEPARTMENTOFCIVILENGINEERING 11
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
5.3 LIMITSTATEMETHOD
In this method of design based on limit state concept, the structure shall be designed withstand safely
allloadliabletoactonitthroughoutitslife.Itshallalsosatisfyserviceabilityrequirementssuchaslimitations on
deflection and cracking. The acceptable Limit for the safety and serviceability requirementsbeforefailure
occuriscalled limitstate.
5.4 THEORYOFDESIGNOFSTRUCTURALELEMENT
i. Beams
A beam is a structural member subjected to transverse loading system. The transverse load
whichare perpendicular to the axis of beam include shear force and bending moment in the beam.
Thisisin turn to produceshear stress andbendingstress in its cross section.
ii. Slabs
A slab is a thin flexural member used in floors and roofs of structures which is usually
supportedalong its edges. The slabs are divided as one way slab and two way slab according to
their loadtransferring. In the design of slabs one meter width is designed as wide rectangular
beam and thesame details are provided for the entire width of slab in one shorter span. But in two
way slab themainreinforcement is provided in both directions.
iii. Lintels
Lintelsarehorizontalstructuralelementsprovidedovertheopeningofwallstocarrythemasonry over
them. They are designed as small rectangular beams of width always equal to thethicknessof the
wall inwhich theyareprovided.
iv. Stairs
A staircase is a structural form provided in buildings to facilitate vertical movements for
personsfrom one floor to another. It generally consists of inclined waist slab with beams are
sometimesprovidedin staircasetosupport the waist slab.
DEPARTMENTOFCIVILENGINEERING 12
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
CHAPTER
6DRAWINGS
SCALE1:100
ALLDIMENSIONSAREINCM
DEPARTMENTOFCIVILENGINEERING 13
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
Fig6.2 FIRSTFLOORPLAN
SCALE1:100
ALLDIMENSIONSAREINCM
DEPARTMENTOFCIVILENGINEERING 14
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
Fig6.3 SECONDFLOORPLAN
SCALE1:100
ALLDIMENSIONSAREINCM
DEPARTMENTOFCIVILENGINEERING 15
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
Fig6.4SECTIONAA
SCALE1:100
ALLDIMENSIONSAREINCM
DEPARTMENTOFCIVILENGINEERING 16
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
Fig6.5 ELEVATION
SCALE1:100
ALLDIMENSIONSAREINCM
DEPARTMENTOFCIVILENGINEERING 17
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
CHAPTER
7LAYOUTS
Fig7.1 BEAMCOLUMNLAYOUT
DEPARTMENTOFCIVILENGINEERING 18
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
Fig7.2BEAMCOLUMNLAYOUTOFGROUNDFLOORPLAN
DEPARTMENTOFCIVILENGINEERING 19
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
Fig7.3BEAMCOLUMNLAYOUTOFFIRSTFLOORPLAN
DEPARTMENTOFCIVILENGINEERING 20
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
Fig7.4BEAMCOLUMNLAYOUTOFSECONDFLOORPLAN
DEPARTMENTOFCIVILENGINEERING 21
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
CHAPTER
8DESIGNOFSLAB
DEPARTMENTOFCIVILENGINEERING 22
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
8.1 DESIGNOFONEWAY6.2X3mSLAB
TYPE OFSLAB
Ly/lx=6.2/3=2.07>2(Longspan/
Shortspan>2)Hencetheslab is to bedesigned
asonewayslab.
EffectiveandOveralldepth(d&D)
Effectivedepth,d=span/(ModificationFactorXBasicValue)
=3000/(28)=108=110mm
Overalldepth,D=110+20+8/2=140mmEFFECTIVESPA
N(LE)
Minof:(IS456-2000cl.22.2)
a) Clearspan+Effectivedepth=lx+d=3000+110=3110mm
b) Thicknessofsupport/2+Clearspan+thicknessofSupport/2
=3000+200=3200 mm
Therefore,Le=3110mmU
LTIMATELOAD(WU)
W=sumof
=25x1x1x0.140=3.5kN/m
b) Floorfinish =1KN/m
c)Liveload =3kN/m
Wu=1.5x(3+1+3.5)
=11.25kN/mBENDINGMOMENT&SHEA
RFORCE
Bendingmoment,Mu=(wuxlx2)/8=11.25x(3.112)/8=13.6kNm
DEPARTMENTOFCIVILENGINEERING 23
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
Shearforce,Vu =(wux
required (dreq)Mu=0.133fckbd2
Effectivedepthrequired,dreq=71.503=75mm<dcalHenc
TENSIONREINFORCEMENT(AST)
Mu=0.87fyAstd(1-fyAst/fck bd)(IS456-2000cl.G.1.1)Ast
=305.42 mm2
Astmin=0.12%ofgrossarea=168mm2
Astmin<Ast.Hence,theTensileReinforcementprovidedissufficient.Prov
Spacing=(Astind/Astpro)x1000=144.57=150mm
DistributionreinforcementsameasAstmin=168mm2@spacingof150
mmc/c.
CHECKFORSHEAR
v<c(IS456-2000cl.40.1)
Nominalshear,v=Vu/bd=0.159N/
mm2Permissibleshear,c
c=0.372N/mm2
0.159<0.372,itssafeagainstshear
CHECKFORDEFLECTION
(l/d)cal<(l/d)pro(IS456-2000cl.23.2)
DEPARTMENTOFCIVILENGINEERING 24
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
Percentageofsteel,Pt=0.277
Fs=0.58xfy=0.58x500=290N/mm2
ModificationFactor(IS456-2000Fig4)=1.5
Then,(l/
d)pro=M.FX20=1.5X20=3030,henceits
safeagainstdeflection.
DEPARTMENTOFCIVILENGINEERING 25
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
8.2 DESIGNOFTWOWAY4.5X3MSLAB(TWOADJACENTEDGESDIS
CONTINUOUS)
TYPEOFSLAB
slab.EFFECTIVEDEPTHANDOVERALLDEPTH(d&
D)
Span/depth=l/dratio=35x0.8=28(IS456-
D=110+20+8/2=134=140mmEFFECTIVE
SPAN(Le)
Minof:(IS456-2000cl.22.2)
=3110mmb.Thicknessofsupport/2+Clearspan+thicknessofSup
port/2
=3000+200=3200mm
mmULTIMATELOAD(W
U)
W=sumof
DEPARTMENTOFCIVILENGINEERING 26
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
a.Selfweightofslab =SpecificWeightxlengthxbreadthxoveralldepth
=25x1x1x0.140=3.5kN/m
b.Floorfinish =1KN/m
DEPARTMENTOFCIVILENGINEERING 27
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
c.Liveload =3kN/m
Wu=1.5x(3+1+3.5)
=11.25kN/mBENDINGMOMENT&SHEA
RFORCE
αx+=0.056,αx-=0.075
αy+=0.047,αy-=0.035
(Condition4,Twoadjacentedgesdiscontinuous)b.
Mu, Vu
Mx+=αx+x Wuxlex²=0.056x11.25x3.11²=6.093kNm
Mx-=αx¯xWuxlex²=0.075x11.25x3.11²=8.16kNm
My+=αy+xWux lex²=0.035x11.25x3.11² =3.808kNm
My-=αy¯xWux lex²=0.047x11.25x3.11²=4.026kNm
Vu=(Wux lex)/2=11.25x3.11/2=17.493Kn
EFFECTIVEDEPTHREQUIRED(DREQ)
Mumax=Mux¯=8.16x
10^6Nmm=0.133fckbd²8.16x10^6Nmm=0.133x 20x
1000x d²
Hence,theprovideddepthissufficientagainstmomentAR
EAOFSTEELREQUIRED (ASTREQ)
a.Astx
Mu=0.87xAstxdx(1-fyxAst/fckxbxd)(IS456-2000cl.G1.1)
𝑥= −𝑏±√𝑏2−4𝑎𝑐
2𝑎
DEPARTMENTOFCIVILENGINEERING 28
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
Mux+=0.87xAstx+xdx(1-fyxAstx+/ fckxbxd)
6.093x10^6=0.87x500 xAstx+x110x(1-500xAstx/20x1000x110),Astx+=131.25mm²
DEPARTMENTOFCIVILENGINEERING 29
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
Mux¯=0.87xAstx¯xdx(1-fyxAstx¯/ fckxbxd)
8.16x10^6=0.87xx500xAstx+x110x(1-500xAstx/20x1000x110),Astx¯=177mm²
b.Asty
Muy+=0.87xAsty+xdx(1-fyxAsty+/fckxbxd)
3.808x10^6=0.87x500xAsty+x110x(1-500xAsty+/20x1000x110),Asty+
=81.075mm²
=85.811mm²
c.Astymin
Astymin=0.12/100x1000x140=168mm²
TakeAstx+,Asty+,Asty¯=180mm²
SPACING
a.SpacingforXaxis
Atsupport=Astind/
Astx¯x1000Astind=(ᴨ/
4x8²)=50.265mm²
S=50.265/177x1000=286.016mm
Similarly,atmidspan,s=301.339mm
b.SpacingforYaxis
Atsupportandmidspan,S=301.339mmS=3
Henceprovide8mmbars@290mmc/calongtheXaxissupportand@300mmc/catXaxismidspan
and Y axis atsupport and at midspan asc/cspacing.
DEPARTMENTOFCIVILENGINEERING 30
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
CHECKFORSHEAR
(v<c)(IS456-2000cl.40.1)
d.Nominalshear,v=Vu/bd=17.493x
10^3/1000x110=0.159N/mm²e.Permissibleshear,c
fck=20N/mm²
FromTable19,cisinterpolatedasequalto0.313N/
mm²Here,v<c,hencesafe againstshear.
CHECKFORDEFLECTION
(lex/d)cal<(lex/d)pro(IS456-2000cl.23.2)f.(lex
/ d) cal = 3110/110=28.27
g.(lex/d)pro,
4)Fs=0.58x fy=0.58x500=290N/mm²
Pt=0.198%
Therefore,M.F=1.5(Fig4)
=20x1.5=30
So,(lex /d)cal<(lex/d)pro
Hencetheslabissafeagainstdeflection.
DEPARTMENTOFCIVILENGINEERING 31
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
8.3DESIGNOF2.2X3MSLAB(ONESHORTEDGEDISCONTINOUS)
TYPEOFSLAB
span<2)Hence,theslabistobedesignedastwo
wayslab.
EFFECTIVEDEPTHANDOVERALLDEPTH(D&D)
Span/depth=l/dratio=35x0.8=28(IS456-
D=80+20+8/2=104=110mm
EFFECTIVESPAN(LE)
Minof:(IS456-2000cl.22.2)
lx+d=2200+80=2280mmb.Thicknessofsupport/2+Clearspan+t
hicknessofSupport/2
=2200+200=2400mm
Therefore,le=2280mm
ULTIMATELOAD(WU)
W=sumof:
a.Selfweightofslab =sp.Weightxlengthxbreadthxoveralldepth
DEPARTMENTOFCIVILENGINEERING 32
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
=25x1x1x0.110=2.75kN/m
DEPARTMENTOFCIVILENGINEERING 33
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
b.Floorfinish=1KN/m
c.Liveload=3kN/m
Wu=1.5x(3+1+2.75)=10.125kN/m
BENDINGMOMENT&SHEARFORCE
αx+=0.053,αx-=0.040
αy+=0.037,αy-=0.028
(Condition2,Oneshortedgediscontinuous)
b.Mu,Vu
Mx+=αx+xWux lex²=0.053x10.125x2.28²=2.789kNm
Mx-=αx¯xWuxlex²=0.040x10.125x2.28²=2.105kNm
My+=αy+xWux lex²=0.037x11.25x2.28²=1.947kNm
My-=αy¯xWuxlex²=0.028x10.125x2.28²=1.473kNm
Vu=(Wuxlex)/2=10.125x2.28/2=11.542KN
EFFECTIVEDEPTHREQUIRED(DREQ)
Mumax=Mux¯=2.789x10^6Nmm=0.133fckbd²2.789x10
d=31.788mm<dprovided
Hence,theprovideddepthissufficientagainstmoment
a.Astx(IS456-2000cl.G.1.1)
Mu=0.87xAstxdx(1-fyxAst/ fckxbxd)
DEPARTMENTOFCIVILENGINEERING 34
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
𝑥= −𝑏±√𝑏2−4𝑎𝑐
2𝑎
Mux+=0.87xAstx+xdx(1-fyxAstx+/ fckxbxd)
2.789x10^6=0.87x500xAstx+x80x(1-500xAstx/
20x1000x80)Astx+=82.258 mm²
Mux¯ =0.87𝑥𝐴𝑠𝑡𝑥̅𝑥𝑑𝑥(1−𝑓𝑦𝑥𝐴𝑠𝑡𝑥̅/𝑓𝑐𝑘𝑥𝑏𝑥𝑑)
2.105x10^6=0.87x500xAstx+x80x(1-500xAstx/20x1000x80)
Astx¯=61.677mm²
b.Asty
mm²c.Astymin
Astymin=0.12/100x1000x110=132mm²TakeAst
x+,Astx¯Asty+,Asty¯=132mm²
SPACING(IS456-2000CL.26.3)
a.SpacingforXaxis
Atsupport=Astind/
=50.265mm²S =50.265/135
=389.42 mm
Similarly,atmidspan,s=389.42mmb.S
pacingforY axis
DEPARTMENTOFCIVILENGINEERING 35
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
Atsupportandmidspan,S=389.42mm
DEPARTMENTOFCIVILENGINEERING 36
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
Henceprovide8mmbars@240mmasc/cspacingalongtheXandYaxisatsupportandmidspan.
CHECKFORSHEAR
(v<c)(IS456-2000cl.40.1)
a. Nominalshear, v=Vu/bd=11.542x10^3/1000x80=0.144N/mm²
b. Permissibleshear,c
Percentageofsteel,Pt=100xAst/bxdPt=
fck=20N/mm²
FromTable19,cisinterpolatedasequalto0.34N/
mm²Here,v<c,hencesafe againstshear.
CHECKFORDEFLECTION
(lex/d)cal<(lex/d)pro(IS456-2000cl.23.2)a.
(lex /d)cal=2280/80=28.5
b.
(lex/d)pro,Modifica
tionFactor
Fs=0.58xfy=0.58x500=290N/mm²
Pt=0.225%
Therefore,M.F=1.45(Fig4)
Then,(lex/d)pro=BasicValuex M.F
=20x 1.45=29
So,(lex /d)cal<(lex/d)pro
Hencetheslabissafeagainstdeflection.
DEPARTMENTOFCIVILENGINEERING 37
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
Fig8.1Slab
DEPARTMENTOFCIVILENGINEERING 38
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
CHAPTER9DE
SIGNOFBEAM
9.1 BEAM-1
Span =4.5m
Wallthickness =0.2m
Effectivespan =4.5+0.2
=4.7mDimensionofrectangularbeam=200×400
D=400mm,b=200mm,d’=40,d
=400-40
=360mm
Fck=20,fy=500
LOADCALCULATION
Factoredload(Wu) =20KN/m
CALCULATIONOFBENDINGMOMENTANDSHEARFORCE
2
BendingmomentMu=𝖶𝑢𝑙
8
20×(4.7)2
= 8
=55.25×106𝑁mm
ShearforceVu =𝖶𝑢𝑙
2
20×4.7
= 2
=47×103N
Mu =0.133×𝑓𝑐𝑘𝑏𝑑2
𝑀𝑢
d =√
0.133×𝑓𝑐𝑘×𝑏
DEPARTMENTOFCIVILENGINEERING 39
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
55.22×10 6
=√ 0.133×20×200
=322.175mm
dprovid>dreq,∴thesectionissafe
Mulim =0.133×𝑓𝑐𝑘×𝑏×𝑑2
=68.94×106N/mm
∴underreinforcementbeam,singlyreinforcementbeamAR
EA OFSTEEL
Xumax =0.46×𝑑
=0.46×360
=165.6
Mulim =0.87×𝑓𝑦×𝐴𝑠𝑡×(𝑑−𝑥𝑢𝑚𝑎𝑥)
68.94×106
Ast = 0.87×500×(360−0.42×165.6)
=545.64𝑚𝑚2
Provide20mmdiabars
Numberofbars =𝐴𝑠𝑡
𝜋
×𝑑2
4
545.64
= 𝜋×202
4
=1.736=2nos
Henceprovide4nosof20mmdiabarsamainreinforcement.CHE
CKFOR SHEAR
ReferIS456200PgNo.72τv
=𝑉𝑢
𝑏𝑑
DEPARTMENTOFCIVILENGINEERING 40
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
47×103
=200×360
=0.65N/mm^2
𝜋
Ast =2×
4 ×𝑑2
𝜋
=2×
4 ×202
=628.31mm^2
Pt =𝐴𝑠𝑡×100
𝑏𝑑
628.31×100
= 200×360
=0.87%
𝑟𝑐 =0.588
ReferIS456200Table19PgNo.72
𝑟𝑣>𝑟𝑐
Thegivenbeamisunsafeagainstshear.shearreinforcementhastobedesigned.Inthis
Shearresistanceofconcrete
ReferIS456200PgNo.48
Asv =𝜋×82×2
4
=100.53
0.87×500×100.53×360
1)Sv = 4.62×103
=3414.96mm
𝐴𝑠𝑣×0.87×𝑓𝑦 100.53×0.87×500
2)Sv = 0.4×𝑏 =
0mm
=
546.63mm3)0.75×𝑑=0.75×200=27
DEPARTMENTOFCIVILENGINEERING 41
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
0.4×200
DEPARTMENTOFCIVILENGINEERING 42
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
4)300mm
Provide2barsof8mmstirrupsataspacingof270
mmc/casreinforcement.CHECKFORDEFLECTION
(l/d)calculated <
(l/d)provided(l/d)cal
=4700/360=13.055
=0.58 ×𝑓𝑦×
𝑎𝑟𝑒𝑎𝑜𝑓𝑐𝑟𝑜𝑠𝑠𝑠𝑒𝑐𝑡𝑖𝑜𝑛𝑜𝑓𝑠𝑡𝑒𝑒𝑙 𝑟𝑒𝑞𝑢𝑖𝑟𝑒𝑑
Fs 𝑎𝑟𝑒𝑎𝑜𝑓𝑐𝑟𝑜𝑠𝑠𝑠𝑒𝑐𝑡𝑖𝑜𝑛𝑜𝑓𝑠𝑡𝑒𝑒𝑙𝑝𝑟𝑜𝑣𝑖𝑑𝑒𝑑
𝜋
2× ×202
=0.58×500× 4
545.64
=333.94N/𝑚𝑚2
MF =0.8
(l/d)prov =20×0.8=16
(l/d)cal<(l/d)provided
Hencethegivenbeamissafeagainstdeflection.
DEPARTMENTOFCIVILENGINEERING 43
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
9.2 BEAM2
Span =1.5m
Wallthickness =0.2m
Effectivespan =1.5+0.2
D=400mm,b=200mm,d’=40,d
=400-40
=360mm
Fck=20,fy=500
LOADCALCULATION
Factoredload(Wu) =20KN/m
CALCULATIONOFBENDINGMOMENTANDSHEARFORCE
2
BendingmomentMu=𝖶𝑢𝑙
8
20×(1.7)2
= 8
=7.225×106𝑁mm
ShearforceVu =𝖶𝑢𝑙
2
20×4.7
= 2
=17×103N
Mu =0.133×𝑓𝑐𝑘𝑏𝑑2
𝑀𝑢
d =√
0.133×𝑓𝑐𝑘×𝑏
DEPARTMENTOFCIVILENGINEERING 44
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
7.225×10 6
=√ 0.133×20×200
=116.536mm
dprovid>dreq,∴thesectionissafe
Mulim =0.133×𝑓𝑐𝑘×𝑏×𝑑2
=0.133×20 ×200×(360)2
=68.94×106Nmm
∴underreinforcementbeam,singlyreinforcementbeamAR
EA OFSTEEL
Xumax =0.46×𝑑
=0.46×360
=165.6
Mulim =0.87×𝑓𝑦×𝐴𝑠𝑡×(𝑑−𝑥𝑢𝑚𝑎𝑥)
68.94×106
Ast = 0.87×500×(360−0.42×165.6)
=545.64𝑚𝑚2
Provide20mmdiabars
Numberofbars =𝐴𝑠𝑡
𝜋×𝑑
4
545.64
= 𝜋×202
4
=1.736=2nos
Henceprovide4nosof20mmdiabarsamainreinforcement.CHE
CKFOR SHEAR
ReferIS456200PgNo.72
τv =𝑉𝑢
𝑏𝑑
DEPARTMENTOFCIVILENGINEERING 45
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
17×103
=200×360
=0.236N/mm^2
𝜋
Ast =2×
4 ×𝑑2
𝜋
=2×
4 ×202
=628.31mm2
Pt =𝐴𝑠𝑡×100
𝑏𝑑
628.31×100
= 200×360
=0.87%
𝑟𝑐 =0.588
ReferIS456200Table19PgNo.72
𝑟𝑣>𝑟𝑐
Thegivenbeamisunsafeagainstshear.
STIRRUP
ReferIS456200PgNo.48
Asv =𝜋×82×2
4
=100.53
0.87×500×100.53×360
1)Sv = 25.39×103
=620.047mm
𝐴𝑠𝑣×0.87×𝑓𝑦 100.53×0.87×500
2)Sv = 0.4×𝑏 =
4)300mm
=
546.63mm3)0.75×𝑑=0.75×200=2
70mm
DEPARTMENTOFCIVILENGINEERING 46
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
0.4×200
DEPARTMENTOFCIVILENGINEERING 47
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
Provide2barsof8mmstirrupsataspacingof270mmc/
casreinforcement.CHECKFOR DEFLECTION
(l/d)calculated<(l/
d)provided(l/d)cal
=1700/360=4.72
𝑎𝑟𝑒𝑎𝑜𝑓𝑐𝑟𝑜𝑠𝑠𝑠𝑒𝑐𝑡𝑖𝑜𝑛𝑜𝑓𝑠𝑡𝑒𝑒𝑙𝑟𝑒𝑞𝑢𝑖𝑟𝑒𝑑
Fs =0.5× 𝑎𝑟𝑒𝑎𝑜𝑓𝑐𝑟𝑜𝑠𝑠𝑠𝑒𝑐𝑡𝑖𝑜𝑛𝑜𝑓𝑠𝑡𝑒𝑒𝑙𝑝𝑟𝑜𝑣𝑖𝑑𝑒𝑑
𝜋
2× ×202
4
=0.58×500×
545.64
=333.94N/𝑚𝑚2
MF =0.6
(l/d)prov =20×0.6=12
(l/d)cal<(l/d)provided
Hencethegivenbeamissafeagainstdeflection.
DEPARTMENTOFCIVILENGINEERING 48
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
9.3 BEAM3
Span =3m
Wallthickness =0.2m
Effectivespan =3+0.2
=3.2mDimensionofrectangular
beam=200×400
D=400mm,b=200mm,d’=40,d
=400-40
=360mm
Fck=20,fy=500
LOADCALCULATION
Factoredload(Wu) =20KN/m
CALCULATIONOFBENDINGMOMENTANDSHEARFORCE
2
BendingmomentMu=𝖶𝑢𝑙
8
20×(3.2)2
= 8
=25.6×106𝑁mm
ShearforceVu =𝖶𝑢𝑙
2
20×3.2
= 2
=32×103N
Mu =0.133×𝑓𝑐𝑘𝑏𝑑2
𝑀𝑢
d =√
0.133×𝑓𝑐𝑘×𝑏
25.6×106
=√
0.133×20×200
DEPARTMENTOFCIVILENGINEERING 49
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
=219.36mm
dprovid>dreq,∴ thesectionissafe
Mulim =0.133×𝑓𝑐𝑘×𝑏×𝑑2
=0.133×20 ×200×(360)2
=68.94×106Nmm
∴underreinforcementbeam,singlyreinforcementbeamAR
EAOFSTEEL
Xumax =0.46×𝑑
=0.46×360
=165.6
Mulim =0.87×𝑓𝑦×𝐴𝑠𝑡×(𝑑−𝑥𝑢𝑚𝑎𝑥)
68.94×106
Ast = 0.87×500×(360−0.42×165.6)
=545.64𝑚𝑚2
Provide20mmdiabars
Numberofbars =𝐴𝑠𝑡
𝜋
×𝑑2
4
545.64
= 𝜋×202
4
=1.736=2nos
Henceprovide4nosof20mmdiabarsamainreinforcement.CHE
CKFORSHEAR
ReferIS456200PgNo.72
τv =𝑉𝑢
𝑏𝑑
47×103
=200×360
=0.65N/mm^2
DEPARTMENTOFCIVILENGINEERING 50
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
𝜋
Ast =2×
4 ×𝑑
2
𝜋
=2×
4 ×202
=628.31mm2
Pt =𝐴𝑠𝑡×100
𝑏𝑑
628.31×100
= 200×360
=0.87%
𝑟𝑐 =0.588
ReferIS456200Table19PgNo.72
𝑟𝑣>𝑟𝑐
Thegivenbeamisunsafeagainstshear.ST
IRRUP
ReferIS456200PgNo.48
Asv =𝜋×82×2
4
=100.53
0.87×500×100.53×360
1)Sv = 10.39×103
=1515206.73mm
𝐴𝑠𝑣×0.87×𝑓𝑦 100.53×0.87×500
2)Sv = 0.4×𝑏 = 0.4×200
546.63mm3)0.75×𝑑=0.75×200=2
70mm
4)300mm
Provide2barsof8mmstirrupsataspacingof270mmc/
casreinforcement.CHECKFOR DEFLECTION
DEPARTMENTOFCIVILENGINEERING 51
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
(l/d)calculated<(l/d)provided
DEPARTMENTOFCIVILENGINEERING 52
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
(l/d)cal =3200/360=10
=333.94N/𝑚𝑚2
MF =0.6
(l/d)prov =20×0.6=12
(l/d)cal<(l/d)provided
Hencethegivenbeamissafeagainstdeflection.
DEPARTMENTOFCIVILENGINEERING 53
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
Fig9.1Beam
DEPARTMENTOFCIVILENGINEERING 54
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
CHAPTER
10DESIGNOFCOLUM
10.1COLUMN-1(450×200)
N
AxialLoad,P=400kN=400×103NULTI
MATE LOAD
Pu=1.5×400×103=600× 103
PERCENTAGEOFSTEEL(PT)0.
8 <1 >6
Asc=1%ofAg=0.01Ag
AREAOFCONCRETE(AC)
Ac=Ag-Asc=Ag-0.01AgAc=0.99
Ag
GROSSAREA(AG)
ReferIS4562000PgNo.71Cl39.3
Pu=0.4fck Ac=0.67 fy
Asc600×103=0.4×20×0.99Ag+0.67×500×0.0
1Ag
600×103
Ag = =53238.68mm2
11.27
DIMENSIONSOFCOLUMN
Ag=a253238.68
=a2
A=230.735mm
DEPARTMENTOFCIVILENGINEERING 55
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
A=450mmb=200mm
GrossArea=90000>53238mm2
DEPARTMENTOFCIVILENGINEERING 56
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
AREAOFCONCRETE&STEEL
NUMBEROFBARS(N)
As 900
n= c
πd2
= 𝜋×16 2 =4.476 ⁓ 5
4 b 4
LATERALREINFORCEMENT
a) Diameteroftie
DiameterofLongbar
= 16
4
=4mm
4
b) 6mm
Provide6mmtiesSP
ACING
a) Leastlateraldimension=200mm
b) 16xdiaoflongbar=16x16=256mm
c) 300mm
Provide200mmSpacing
DEPARTMENTOFCIVILENGINEERING 57
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
10.2COLUMN-2[300x200]
AxialLoad,P=400kN=400×103NULTI
MATE LOAD
Pu=1.5×400×103=600 ×103
PERCENTAGEOFSTEEL(PT)0.8
<1 >6
Asc=1%ofAg=0.01Ag
AREAOFCONCRETE(AC)
Ac=Ag-Asc=Ag-0.01AgAc=0.99
Ag
GROSSAREA(AG)
ReferIS4562000PgNo.71Cl39.3
Pu=0.4fck Ac=0.67 fyAsc
600×103=0.4×20×0.99Ag+0.67×500×0.01Ag
600×105
Ag= =53238.68mm2
11.27
DEPARTMENTOFCIVILENGINEERING 58
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
DIMENSIONSOFCOLUMN
Ag =a2
53238.68=a2
A=230.735mm
A=300mmb=200mm
GrossArea=60000>53238mm2ARE
AOFCONCRETE&STEEL
Asc=0.01x60000=600mm2NUM
BEROFBARS(N)
As 600
n= c = 𝜋×16 =2.984 ⁓ 4
πd2 2
4 b 4
LATERALREINFORCEMENT
c) Diameteroftie
DiameterofLongbar
= 16
4
=4mm
4
d) 6mm
Provide6mmtiesSP
ACING
d) Leastlateraldimension=200mm
e) 16xdiaoflongbar=16x16=256mm
f) 300mm
Provide200mmSpacing
DEPARTMENTOFCIVILENGINEERING 59
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
CHAPTER
11DESIGNOFFOOTIN
G
11.1 FOOTING1[450x200mm]
kNSafeBearingcapacity =300kN/m2
Fck =20N/mm2
Fy =500N/mm2
1 LOAD
CALCULATIONSServiceload
=1200kN
SelfWeightofFooting=1200of10%=1200x0.10=120kNTotal
Load =1320 kN
2 SIZEOFFOOTING
TotalLoad=…1320…
SBC 300
=4.4m2
Oneside=2.1 m
3 BENDINGMOMENT
DEPARTMENTOFCIVILENGINEERING 60
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
DEPARTMENTOFCIVILENGINEERING 61
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
2
= wly = (408.16x 2.1x 0.952)/2
= 386.78kN-m
4 AREAOFSTEEL (AST):
ReferIS4562000PgNo.96
Mu=0.87Astd[1- FyAst]
fckbd
500Ast
386.786×106=0.87×500×Ast×530×[1- ]
20×2100×530
1677666=Ast -
500𝐴𝑠𝑡
22.26×𝑥106
500 Ast2-22.26x106At+3.73448x106=0
Ast=1746.151mm²
Provide12mmbars,themspacing
DEPARTMENTOFCIVILENGINEERING 62
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
𝜋
×122
S=𝐴𝑠𝑡× = 4 x2100
𝐴𝑠𝑡 1746.151
=136.0159
Provide12mmbarsataspacingof130mmc/c
5 ONEWAYSHEAR
1ShearResistance,τ=0.28 x2100 D -2
Equating1&2=>0.40816×2100×(950−𝐷)=0.28× 2100×𝐷
854.136x(950-D)=588 D
1.4571x(950-D)=0
1384.82–1.4577xD=D
1384.82=D x(1+1.4577 )
=563.465
6 CHECKTWOWAYSHEAR
ShearOccurred=QxAreaofShaded
O.40816 x(21002-(450+600)x(200+600))
= 1.4571312x106=1457N/mm2
= 2481N/mm2 Therefore,HenceSafe
DEPARTMENTOFCIVILENGINEERING 63
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
11.2 FOOTING2[300x200mm]
kNSafeBearingcapacity =300kN/m2
Fck =20N/mm2
Fy =500N/mm2
LOADCALCULATIONS
Serviceload =600kN
SelfWeightofFooting=600of10%=1200x0.10 =60kNTotal
Load =660 kN
SIZEOFFOOTING
Load 660
SBC = 300
=2.2m2
Oneside=1.4m⁓1.5m
BENDINGMOMENT
Mulim = 0.138fckBD2=0.138x20x1.5xD2=195D2
=√47101.449
D = 285mm⁓300mm
AREAOFSTEEL(AST):
ReferIS4562000PgNo.96
Mu=0.87F y Astd[1-FyAst]
fckbd
195×106=0.87×500×A×300×[1- 500Ast
]
st
20×1500×300
1677666=Ast -
500𝐴𝑠𝑡
22.26×𝑥106
500 Ast2-22.26x106At+3.73448x106=0
Ast=1746.151mm²
Provide12mmbars,themspacing
𝜋
×122
S=𝐴𝑠𝑡× = 4 x2100
𝐴𝑠𝑡 1746.151
DEPARTMENTOFCIVILENGINEERING 65
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
=136.0159
Peovide12mmbarsataspacingof130mmc/c
ONEWAYSHEAR
Shearoccurred=QxAreaofShear= 0.4×1500×(650−𝐷)-
1ShearResistance,τ=0.28 x1500 D -2
Equating1&2=>0.400×1500×(650−𝐷)=0.28×1500 ×𝐷
854.136x(950-D)=588 D
1.4571x(950-D)=0
1384.82–1.4577xD=D
1384.82=D x(1+1.4577 )
=563.465
CHECKTWOWAYSHEAR
ShearOccurred=QxAreaofShaded
O.400 x(.51002-(450+600)x(200+600))
= 1.4571312x106=1457N/mm2
= 2481
N/mm2Therefore,HenceSafe
DEPARTMENTOFCIVILENGINEERING 66
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
Fig11.1ColumnAndFooting
DEPARTMENTOFCIVILENGINEERING 67
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
CHAPTER
12INTRODUCTIONTOESTIMATION
Approximate estimate may be prepared by various methods but accurate estimate is prepared
bydetailedEstimatemethod.Thepreparationofdetailedestimateconsistsofworking outthequantities
of different items of work and then working out the cost by details measurement form.In Abstract
Estimate the cost of each item of work is calculated in a tabular form from
thequantitiesalreadycomputed and total cost is workedout.
The schedule of bars (BBS) is a list of reinforcement bars in a tabular form giving the
particularsof bars, shape of bars, shape of bending with sketches, length of each, total length and
totalweightofsteel.
DEPARTMENTOFCIVILENGINEERING 68
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
12.1 ESTIMATIONOFGROUNDFLOOR
ESTIMATIONOFGROUNDFLOOR
ITEM NAME
NO. LENGTH BREADTH HEIGHT QUANTITY
NO. OFWOR
(m) (m) (m) (m3)
K
Earthwork
1
Excavation
Column
5 0.9 0.9 1.5 6.075
Excavation(
C20)
Column
6 0.9 0.9 1.5 7.29
Excavation(
C30)
Column
8 0.9 0.9 1.5 9.72
Excavation(
C40)
Column
6 0.9 0.9 1.5 7.29
Excavation(
C45)
Total 30.375
TOTAL
EARTHWORK 30.375
EXCAVATION
2 PCC
ColumnPCC
DEPARTMENTOFCIVILENGINEERING 69
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
Total 10.384
BeamPCC
Total 4.024
Deduction
DEPARTMENTOFCIVILENGINEERING 70
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
Total 0.154
TOTALPCC 3.87
3 Earthfilling
StairRoomand
1 6 3 0.4 7.2
Canteen
Total 45.296
TOTAL
45.296
EARTHFIL
LING
4 Brickwall
DEPARTMENTOFCIVILENGINEERING 71
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
TOTAL 63.872
Deduction
Lintel(inm3) 2.168
DEPARTMENTOFCIVILENGINEERING 72
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
Total 20.758
TOTAL
43.114
BRICKWO
RK
5 RCCWORK
Column
a.columnfooting
B.Columnstem
Total 47.868
DEPARTMENTOFCIVILENGINEERING 73
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
Plinthbeam
Total 8.048
Beam
Total 8.048
Lintel
DEPARTMENTOFCIVILENGINEERING 74
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
Total 2.168
Sunshade
Total 0.81
InsidePlastering
Pharmacy
DEPARTMENTOFCIVILENGINEERING 75
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
DC
CE
toilet
OT
stairroomandcan
teen
ExtraPlaster
1 37.7 3.6 135.72
ing(passages)
Sunshade
DEPARTMENTOFCIVILENGINEERING 76
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
Total 1792.64
Deductions
Shutter 1 2 1.5 3
TOTAL 123.15
Total
1669.49
PlasteringWitho
utCeiling
Ceilingplastering
Pharmacy 1 3 3 9
DEPARTMENTOFCIVILENGINEERING 77
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
Total 96.32
TOTALPL
1765.81
ASTERING
7 WhiteWashing
TOTAL
WHITEWASHIN
1765.81
GINCLUDING
CEILING
8 Flooring
TOTALF
96.32
LOORING
9 Woodworks
Frames
D(150X210)
D1(100X210)
DEPARTMENTOFCIVILENGINEERING 78
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
D2(80X210)
W(150X150)
V(60X60)
Totalwoodforf
0.726
rames
10 Paintingofwood
Door
Total 81.06
Window
W2(100X150) 6 1 1.5 9
DEPARTMENTOFCIVILENGINEERING 79
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
W4(200X150) 4 2 1.5 12
Total 72.75
Ventilator
4.62
TOTAL 158.42
Table12.1EstimationofGroundfloor
DEPARTMENTOFCIVILENGINEERING 80
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
12.2 ESTIMATIONOFFIRSTFLOOR
ESTIMATIONOFFIRSTFLOOR
ITEM
NAMEOFWORK NO. LENGTH BREADTH HEIGHT QUANTITY
NO.
1 Brickwork
TOTAL 45.12
Deduction
DEPARTMENTOFCIVILENGINEERING 81
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
Lintel(inm3) 1 0.798
TOTAL 1 12.21
TOTALBRICKWORK 32.91
2 RCCWork
Column
Total 5.568
Beam
DEPARTMENTOFCIVILENGINEERING 82
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
Total 5.704
Lintel
Total 0.798
Sunshade
DEPARTMENTOFCIVILENGINEERING 83
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
Total 1.098
TOTALRCCWORK 32.278
3 Plastering
Insideplastering
LSO
Dining
DEPARTMENTOFCIVILENGINEERING 84
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
Laboratory
Toilet
DC
DC(sub)
stairroom
Sunshade
DEPARTMENTOFCIVILENGINEERING 85
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
Total 899.56
Deductions
Door(D1) 10 1 2.1 21
Window(W1) 4 1 1.5 6
Total 71.91
Totalplasteringwithoutceiling 827.65
CeilingPlastering
LSO 1 3 3 9
Dining 1 4 3 12
DC 1 3.5 3 10.5
DEPARTMENTOFCIVILENGINEERING 86
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
Total 82.49
TOTALPLASTERING 910.14
4 Whitewashing
TOTALWHITEWASHINGIN
910.14
CLUDINGCEILING
5 Flooring
TOTALFLOORING 82.49
6 WOODWORKS
Frames
D1(100X210)
D2(80X210)
W(150X150)
DEPARTMENTOFCIVILENGINEERING 87
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
W1(100X150)
W2(50X150)
V(60X60)
Totalwoodforframes 0.828
Shutterarea(forallfloors)
DEPARTMENTOFCIVILENGINEERING 88
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
Ventilator
Totalwoodforshutterarea 85.44
Totalwood 86.268
7 Paintingofwood
Door
Total 24.36
Window
W2(100X150) 8 1 1.5 12
W4(200X150) 2 2 1.5 6
Total 31.5
Ventilator
DEPARTMENTOFCIVILENGINEERING 89
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
TOTAL 57.54
Table12.2EstimationofFirstFloor
DEPARTMENTOFCIVILENGINEERING 90
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
12.3 ESTIMATIONOFSECONDFLOOR
ESTIMATIONOFSECONDFLOOR
ITEM
NAMEOFWORK NO LENGTH BREADTH HEIGHT QUANTITY
NO
1 Brickwork
Total 43.136
Deductions
DEPARTMENTOFCIVILENGINEERING 91
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
Lintel(inm3) 0.594
Total 9.946
TOTALBRICKWORK 33.19
2 RCCWork
Column
Total 5.568
Beam
DEPARTMENTOFCIVILENGINEERING 92
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
Total 5.472
Lintel
Total 0.594
Sunshade
DEPARTMENTOFCIVILENGINEERING 93
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
Total 0.924
TOTALRCCWORK 31.668
3 Plastering
InsidePlastering
NightStay
Toilet
ConferenceHall
DEPARTMENTOFCIVILENGINEERING 94
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
StairRoom
Sunshade
Total 529.56
Deduction
Window(W1) 6 1 1.5 9
Total 52.56
Totalplasteringwithoutceiling 477
DEPARTMENTOFCIVILENGINEERING 95
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
Ceilingplastering
storeroom 1 3 3 9
stairroom 1 6 3 18
Total 121.36
TOTALPLASTERING 598.36
4 Whitewashing
TOTALWHITEWASHINGI
598.36
NCLUDINGCEILING
5 Flooring
TOTALFLOORING 121.36
6 WOODWORKS
Frames
D1(100X210)
DEPARTMENTOFCIVILENGINEERING 96
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
D2(80X210)
W(150X150)
W1(100X150)
V(60X60)
TOTAL 0.6066
7 Paintingofwood
Door
DEPARTMENTOFCIVILENGINEERING 97
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
Total 41.16
Window
W2(100X150) 8 1 1.5 12
W4(200X150) 2 2 1.5 6
Total 31.5
Ventilator
TOTAL 73.5
Table12.3EstimationofSecondFloor
DEPARTMENTOFCIVILENGINEERING 98
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
12.4 ESTIMATIONOFSEPTICTANKANDSOAKPIT
SEPTICTANKANDSOAKP
1
IT
a Earthworkexcavation
Total 54.28
b Cementconcrete1:3:6
Total 3.578
Firstclassbrickworkinsepticta
c
nk
Longwalls
Shortwalls
DEPARTMENTOFCIVILENGINEERING 99
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
Total 7.34
Secondclassbrickworkinsoakpit
d
Total 1.846
Secondclassdrybrickworkinso
e 1 8.796 0.3 1.5 3.958
akpit
f RCCwork
Total 2.196
g 12mmplasteringinseptictank
20mmplastering 1 6 1.5 9
Total 36
h Brickaggregate
DEPARTMENTOFCIVILENGINEERING 10
0
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
Total 3.277
Coarsesandoutersideofsoakpit
i 1 11.152 0.15 1.5 2.5
j Ironfootsteps 4 4nos
Table12.4SeptictankandSoakpit
DEPARTMENTOFCIVILENGINEERING 10
1
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
CHAPTER13
BARBENDINGSCHEDULE
13.1 COLUMNANDFOOTING
STIRUPS
0.4x0.2 1.368 62 0.2 16.963
135.7kg
0.45x0.2 1.468 62 0.2 18.203
DEPARTMENTOFCIVILENGINEERING 10
2
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
109.218kg
0.3x0.2 1.168 62 0.2 14.483
86.898kg
Table13.1ColumnandFooting
DEPARTMENTOFCIVILENGINEERING 10
3
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
13.2 SCHEDULEOFSLAB
Dia
lab Length Quantity
Sl. ofb Nos Weight Total
size Description Shape (m) (kg)
No ars /m(kg) (kg)
(m)
ar
5. 3x2.2 Mainbar 8 14 2.843 0.39 15.522
DEPARTMENTOFCIVILENGINEERING 10
5
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
DEPARTMENTOFCIVILENGINEERING 10
6
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
bar
Top 6 4 8.163 0.22 7.183 82.04
extrab
ar
3no.s 246.1
2
Total 2119.
128
kgor
21.19
1
Quint
al
Table13.2BBSofSlab
DEPARTMENTOFCIVILENGINEERING 10
7
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
13.3 SCHEDULEOFBEAMS
SL TOTAL
DESCRIPTION LENGT WT/M QUANTI
.NO SHAPE NO QUANT
H TY
ITY
1. GroundFloor
Stirrups
2. FirstFloor
Stirrups
3. SecondFloor
Stirrups
DEPARTMENTOFCIVILENGINEERING 10
8
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
4. ThirdFloor
Total 2403.84kg
Table13.3BBS ofbeam
DEPARTMENTOFCIVILENGINEERING 10
9
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
CHAPTER
14CONCLUSI
ON
As a part of study, we selected this place to build a veterinary hospital which is in
degradingcondition and also there is no other such a hospital with good requirements and
facilities in thislocality. In this situation our project is make a count on this problem. This is
main objective ofour project.We have successfully completed our
missionwithagoodguidanceandhardworking.Wehaveplanned it as real one.
TOTALESTIMATEDCOSTASPERPWDRATE =5455124RS
DEPARTMENTOFCIVILENGINEERING 11
0
SCMSCOLLEGEOFPOLYTECHICS,VAIKKARA,PERUMBAVOOR STRUCTURALDESIGNANDANALYSISOFBUILDING
CHAPTER15
REFERENCES
[1] Dr.AshokkumarN,”Planning,Analysis&DesignofHospitalBuildingUsingStaadProv8i”InternationalJ
ournal ofScientific&EngineeringResearch(2017)
[2] AshishThapak,”SeismicPerformanceEvaluationofHospitalBuilding(G+5)AnalysisandComparison
by Changing the Size of Rectangular Column and Beam Using STAAD Pro.” InternationalJournalOf
ScientificProgressAnd Research.(2021)
[3] Srikanth,”Planning, Analysis and Designing of MultiSpeciality Hospital Building
“InternationalJournalofApplicationorInnovation inEngineering&Management(2020)
[4]Y.Sombabu,”Design & Analysis Of Hospital Building (G+3) By Using STAAD Pro”Journal
OfResourceManagementAndTechnology(2017).
[5] Purushothaman, P. “Reinforced Concrete Structural Element”, Tata McGraw-Hill, New
Delhi,1984,Chapter-8, Page424.
[6] Prof.DeepakRastogi,”IMPACTOFCORROSIONOFREINFORCEMENTINCONCRETECONSTRUC
TION”(2019).
[7] MuhammedAfzal,”Reinforcedconcretestructuraldesignoptimization”,(2020).
[8]J. N. Bandyopadhyay ,”Design of concrete structures” , Prentice Hall of India, New Delhi, (2018).
[9]Ashok K.Jain,”Reinforced concrete design,Limit statedesign”,(2012).
[10]Shah,V.LandKarve,S.R,“Limit StateTheoryandDesignReinforcedConcrete”,(2014).
[11].MehadSayed Emara," Toward asuggestedproposedmodelfortheuse
ofbuildinginformationmodeling(BIM)in theimplementationphaseforlandscaping" Ain Shams
EngineeringJournal(2022)
[12].PiaSchönbeck,AndersAnsell,"Potentialofautomatedconfigurationcontroltoreducehospitalbuildingdeficiencies"
Procedia Computer Science(2022)
[13]. Shaikh Ibrahim," Design and Analysis of Residential Building" International Research Journal of
EngineeringandTechnology(2019)
[14]. Kiran Kumar.j," Planning, Analysis and Design of (G+5) Hospital building" International Journal of Pure
andAppliedMathematics(2018)
[15].ShivamAsawa," StructuralDesignofconcretestructureusingE-
Tabs"JournalofMechanicalandCivilEngineering(2017)
[16]. Mahesh N. Patil," Seismic Analysis of Multi-storied Building" International Journal of Engineering
andInnovative Technology(2015).
DEPARTMENTOFCIVILENGINEERING 111