$value
$value
$value
DEVELOPMENT MANAGEMENT
Municipal Building,
87 Pienaar Road,
Milnerton, 7441
Dear Sir/Madam
Herewith confirmation that the above application followed due process and is approved in
terms of the National Building Regulations and Standards Act (103 of 1977) and applicable
legislation as duly authorised in the City of Cape Town Council System of Delegations.
A copy of the approved plan and relevant documentation must be downloaded from the
City of Cape Town Development Management e-services portal
Additional Comments:
In addition to the specific points raised in the sections below, please be aware of the legal
compliance requirements and responsibilities of all the parties that have an interest in this
project.
You are advised to contact the assigned Building Inspector, Frans Beetge on 0214449851 or
by e-mail to [email protected] soonest, alternatively contact the District Office
on 27214440561 or by e-mail to [email protected]. Compulsory inspections
must be conducted by the building inspector to ensure that the building works complies with
the approved plan.
GENERAL INFORMATION
3. OCCUPANCY
3.1. The owner is advised that occupation and/or use of the building depicted on the
approved plan without a certificate of occupancy is unlawful.
3.2. An application for a certificate of occupancy must be accompanied by the following
certificates certifying (where applicable) that
3.2.1. The electrical wiring and electrical installation is in accordance with the
provisions of all applicable laws and,
3.2.2. the structural system ;
3.2.3. the mechanical ventilation system;
3.2.4. the fire protection system;
3.2.5. the fire installation system
3.2.6. and any rational designs done by duly appointed and accepted specialists
are in accordance with the application in respect of which approval was granted.
4. GENERAL
4.1. Proper notice, in terms of Regulation No. A22 shall be given to the relevant Building
Inspector before work is commenced, and before any excavation, or drainage is
covered up. Notice should also be given promptly to the relevant Building Inspector
on completion of the work.
4.2. All work shall be carried out in strict accordance with the National Building Regulations
and Building Standards Act No 103 of 1977, the SANS 10400 and all relevant
Ordinances, as amended from time to time, and all relevant resolutions of the Council,
and any other law administered by the Council, whether thus shown on the plan
application or not. A copy of the approved plan shall be available at all times on the
site.
4.3. All work shall be kept within the confines of the site and the footway/roadway may not
be utilised for storing any building materials, waste material of any kind or of any rubble
without the prior written consent of Council.
4.4. Approval of the plans does not absolve the owner nor the contractor from compliance
with any condition in the title deeds of the property, design guidelines, or any other
legal provisions applicable to the property to which these plans relate.
4.5. Approval of the plans in no way affects any question of ownership and does not relieve
the owner or contractor from responsibility in regard to any damage or expenditure
which may arise during or after the execution of the work.
4.6. All necessary steps, to the satisfaction of the responsible authorities concerned, shall
be taken to safeguard any underground or over ground Municipal or service authority
services traversing the property, and approval of the plans in no way absolves the
owner or contractor from taking such steps; and if such services are discovered only
after the work commences the Council reserves the right to require the plans to be
amended in such manner as it deems necessary to ensure that such services are
safeguarded.
4.7. The private boundary pegs of the property are to be pointed out to a representative
of Building Development Management prior to the commencement of the work, if
required: Regulation No. A11.
4.8. The work shall be executed to the building lines shown upon the plans. Floor and
drainage levels must conform to back of footway levels.
4.9. No projection, obstruction, or encroachment of any description shall be erected on
Council land.
7. ROADS ENGINEER
7.1. Permits are required for storage/hoarding on Council property/footways.
8. FUEL PUMPS
8.1. The approval of this plan (unless it is a plan for a petrol pump installation only) does not
include the right to erect any fuel pumps or install any tanks upon the premises or site to
which the plans refers.
11. MISCELLANEOUS:
11.1. No trees on Council property may be removed without written permission from
Council.
11.2. Attention is drawn to the By Law Relating to Streets, Public Places and the
Prevention of Noise Nuisances, PG 6469 promulgated on 28th September 2007.
11.3. All drainage to be constructed so as to prevent storm water from entering the
sewerage system.
11.4. The development of the property shall be such that there shall be no danger of
storm water (from whatever source) flooding any surrounding property. Council
will not be liable for any flooding, damage or additional costs if this condition is
not complied with.
11.5. 11.2.3 Actual position and depth of sewerage and underground storm water
connections to be ascertained on site before commencing private sewerage and
storm water drains.
11.6. 11.2.4 The overflow level of any trapped gully to be not less than 150mm above
the surrounding finished ground level.
11.7. No work may commence on site until the requirements of the Occupational
Health and Safety Act (Act 85 of 1993) and Section 141(1) of the Municipal
Ordinance have been complied with.
RESOURCES
12. WATER
Cape Town has experienced serious water shortages in the recent past due to insufficient
rainfall and fast declining dam levels. With the co-operation of many Capetonians we
were able to avoid Day Zero. This has been a cumulative effort of reassessing and
readjusting attitudes towards this precious resource and impacts individuals and business
at all levels.
There is a host of information available on the City of Cape Town’s website that is helping
to preserve and extend access to this resource. In light of your recent application approval
and to support all water saving efforts, please find information on alternative water sources
below.
Your recent application may have included the approval of a swimming pool. You are
reminded that this approval is valid for a period of 12 months and you may apply for an
extension of a further 12 months if you do not commence with building work during the first
approval period. Alternative water sources for construction are discussed later on.
Should you proceed with the construction of your swimming pool, you are reminded to
consult with Water By-Law that regulates permissions in affect at the time and how this will
impact on the filling of swimming pools during the various levels of restriction.
Currently, filling of, or topping up swimming pools with municipal water is not allowed, and
alternative water sources must be used. Sensible management of a swimming pool
includes minimizing evaporation, re-use of cleaned backwash and topping up from
alternative sources.
Treated Effluent:
The construction industry is currently the biggest user of treated effluent in the City.
Research has been conducted to verify the use of treated effluent from Potsdam Waste
Water Treatment Works that is currently also suitable for structural concrete. Water quality
testing in conjunction with concrete cube strength tests are recommended to ascertain
potential applications of treated effluent.
Whilst this effluent or municipal wastewater is treated to a safe standard, it is not potable,
and therefore not fit for human consumption. It is however recognized as a suitable
alternative for business and industry, but you must apply for access.
Please find information relating to the collection points for treated effluent or recycled
water here.
For more information on accessing treated effluent, please see this link.
13. ENERGY
13.1. Please refer to City of Cape Town website for additional information.