2020 RNAReport Nov2020
2020 RNAReport Nov2020
A Report by the
New York Independent
System Operator
November 2020
Table of Contents
EXECUTIVE SUMMARY ................................................................................................................................................................ 1
1. INTRODUCTION .................................................................................................................................................................... 7
2. OVERVIEW OF RELIABILITY PLANNING PROCESS CHANGES ............................................................................................. 10
3. SUMMARY OF PRIOR COMPREHENSIVE RELIABILITY PLANS............................................................................................ 12
4. REGULATORY POLICY ACTIVITIES ...................................................................................................................................... 14
Peaker Rule: Ozone Season Oxides of Nitrogen (NOx) Emission Limits for Simple Cycle and
Regenerative Combustion Turbines..................................................................................... 15
Carbon Dioxide Performance Standards for Major Electric Generating Facilities ............... 19
Assumptions......................................................................................................................... 78
LIST OF APPENDICES
Appendix A - 2020 Reliability Needs Assessment Glossary
Appendix B - The Reliability Planning Process
Appendix C - Load and Energy Forecast 2021-2030
Appendix D - Resource Adequacy and Transmission System Security Assessments
Appendix E - Additional Exploratory Scenario Analysis
Appendix F - Historic Congestion
In 2019, the New York State Department of Environmental Conservation adopted a regulation to limit
nitrogen oxides (NOx) emissions from simple-cycle combustion turbines (referred to as the “Peaker
1Effective May 1, 2020, the scope of the RNA is limited to years 4-10 of the planning horizon while the NYISO Short-Term Reliability
Process is responsible for years 1-3 and also assesses years 4-5.
With the peakers unavailable, the bulk power transmission system could not securely and reliably
serve the forecasted load in New York City (Zone J) throughout the study period. Following the initial
phase of the Peaker Rule in 2023, instability of the grid may occur due to a lack of dynamic reactive power
capability and inertia available to parts of the New York City grid. These reliability issues include low
transient voltage response, loss of generator synchronism, and undamped voltage oscillations. With full
implementation of the Peaker Rule in 2025, several 345 kV circuits in the Con Edison service territory
would not meet transmission security requirements equating to a deficiency of 700 MW and increasing to
at least 1,075 MW by 2030. The duration of the deficiencies range from nine hours in 2025 (3,853 MWh) to
12 hours in 2030 (7,672 MWh). Similar transmission deficiencies would also occur within pockets of Con
Edison’s non-bulk system (138 kV), ranging in duration from 10 to 14 hours.
In addition to the transmission security issues, overall resource adequacy deficiencies in Zone J would
begin in 2027 and increase to at least 350 MW through 2030. Resource adequacy is the ability of the
electric systems to supply the aggregate electrical demand and energy requirements of the customers at all
times, taking into account scheduled and reasonably expected unscheduled outages of system elements.
The NYISO performs resource adequacy assessments on a probabilistic basis to capture the random nature
of system element outages. The New York system is deemed to have sufficient resources if the probability
of an unplanned disconnection of firm load (loss of load expectation, or “LOLE”) is equal to or less than the
standard of once in every 10 years or 0.1 events per year.
Figure 1 below quantifies each Reliability Need through the study period in terms of generic
compensatory resources, in megawatts (MW) or megavolt-amperes (MVA). Compensatory MW/MVA
amounts are determined by adding generic “perfect capacity” resources to NYISO zones or substations to
effectively satisfy the needs. “Perfect capacity” is a term used to describe resources that are always able to
2
https://www.dec.ny.gov/regulations/116131.html
In addition to the base case set of assumptions and findings, the RNA provides an assessment of risks
to the bulk electric grid under certain scenarios to inform stakeholders and policymakers of potential
alternate outcomes. Scenarios are variations on key base case assumptions such as higher load forecast,
capacity removal, or deviations from assumed system plans. If they occurred, the events analyzed in the
scenarios could change the timing, location, or degree of reliability issues identified in the base case. Each
of these variations of the base case for this 2020 RNA indicates potential increased risks of reliability
criteria violations in the future. The scenarios include higher peak load than forecasted, additional
generator retirements, and “status quo” in which major transmission and generation plans fail to come to
fruition.
70x30 Scenario
The Climate Leadership and Community Protection Act (CLCPA) mandates that New York consumers
be served by 70% renewable energy by 2030 (70x30). The CLCPA includes specific technology based
targets for distributed solar (6,000 MW by 2025), storage (3,000 MW by 2030), and offshore wind (9,000
MW by 2035), and ultimately establishes that the electric sector will be emissions free by 2040. Significant
shifts are expected in both the demand and supply sides of the electric grid, and these changes will affect
As policymakers advance the implementation plan of the CLCPA, the NYISO assessments are intended
to complement their efforts, and are not intended to define the specific steps that must be taken to achieve
the policy goals. Additional refinements in assumptions, models, and methods in the following years will be
necessary as more information becomes available from the perspective of policy implementation.
This 70x30 scenario utilizes the same load forecasts and renewable resource mixes from the 2019
CARIS 70x30 scenario. Approximately 110 sites of land-based wind, offshore wind, and utility-scale solar
were added to the system model along with additional behind-the-meter solar across the system. Initial
resource adequacy simulations did not identify a measurable loss-of-load expectation in either the higher
energy ‘Base Load’ case or lower energy ‘Scenario Load’ case. This result indicates a significant surplus of
generation resources in the model, equivalent to an installed capacity margin of 210% for the Base Load
case and 235% for the Scenario Load case.
In an electric grid with such excess capacity resources, it is reasonable to expect less efficient
generation would retire. For this scenario, the NYISO conducted an age-based retirement analysis by
removing fossil fuel generators, starting with the oldest, until the New York system is at the resource
adequacy reliability criteria. This age-based method is a simple analytical approach as a proxy to represent
unit retirements that may occur as surplus resources increase over time. In reality, many factors will affect
specific generator status decisions. For the Base Load case approximately 2,800 MW of fossil generation
could be removed before the resource adequacy criteria is exceeded, resulting in an installed capacity
margin of 191.8%. For the Scenario Load case the installed capacity margin is 173.4% following
approximately 12,300 MW of fossil generation removals. Additional analysis demonstrated that alleviating
renewable generation pocket transmission constraints, while beneficial from an energy perspective as
demonstrated in the 2019 CARIS, would not materially impact the reliability-based need for additional
generation resources. Figure 2 and Figure 3 show the resulting resource mix for each case.
Hydro Hydro
7% 10%
Fossil
Fossil Wind 26%
35% 25% Wind
29%
Pumped
Storage
3% Solar
Solar 25%
Pumped 25% Nuclear
Storage 8%
2% Nuclear
6%
The NYISO also conducted sensitivity analysis of these resource mixes for the retirement of the nuclear
fleet, and for the consideration of energy storage resources. Retirement of nuclear plants would result in
less surplus capacity and therefore more conventional generation (currently fossil-fueled) would need to
be retained in order to maintain a reliable system. Energy storage resources may provide a benefit to the
system from a reliability standpoint by assisting in meeting peak load (benefits depending on the size,
location, and duration of capacity shortfalls), thus allowing for additional fossil units to be retired. Energy
storage resources with a duration longer than four hours would provide additional benefit to the system.
The NYISO performed transmission security analysis for the 70x30 Base Load case considering various
load levels and coincident intermittent renewable resource generation for a sample hours throughout the
year. The results conclude that certain transmission constraints are observed during times of high
renewable output, while other constraints would occur under peak load conditions if the intermittent
renewable resources are not generating. Dispatchable resources would be needed to fill the gaps created
when intermittent renewable resources are not producing energy. Even with a large amount of installed
capacity of renewable resources, there would still be a need for significant dispatchable generation to meet
reliability requirements at various times throughout the year, including peak load. To maintain system
transmission security, approximately 750 MW of dispatchable resources would be needed in addition to
the 24,700 MW of dispatchable resources remaining in the model (i.e. after age-based removals and
peakers).
The NYISO will continue to monitor and track system changes. Subsequent studies, such as the
Comprehensive Reliability Plan, the next Reliability Planning Process and Economic Planning Process
cycles, and the Climate Change Impact and Resilience Study, will build upon the findings of this 70x30
scenario.
The Comprehensive Reliability Plan provides the plan to maintain system reliability and documents
the solutions determined to be viable and sufficient to meet any identified Reliability Needs. If applicable,
the Comprehensive Reliability Plan ranks any regulated transmission solutions submitted for the Board to
consider for selection of the more efficient or cost effective transmission project. If built, the selected
transmission project is eligible for cost allocation and recovery under the NYISO’s tariff. Other non-
transmission solutions, if built, will recover their cost under state law, such as through retail tariffs
established by the New York State Public Service Commission (PSC) and the rates established by the New
York Power Authority and the Long Island Power Authority.
Additionally, the needs identified in the Short Term Reliability Process in year 1 through year 3 will be
addressed in the applicable quarterly Short Term Assessment of Reliability (STAR), while the needs
identified in years 4 and 5 will only be addressed using the Short-Term Reliability Process if the identified
Reliability Need cannot timely be addressed through the Reliability Planning Process.
The RNA is developed by the NYISO in conjunction with stakeholders and all interested parties as the
first step in the Reliability Planning Process. The RNA assesses the reliability of the New York Bulk Power
Transmission Facilities (BPTFs) as the foundation study used in the development of the NYISO
Comprehensive Reliability Plan (CRP). Two major study types are performed: resource adequacy and
transmission security, over the RNA Study Period (i.e., year 4 through year 10, 2024-2030). If the RNA
identifies any violation of reliability criteria3 for BPTFs, the NYISO will report a Reliability Need quantified
by an amount of compensatory megawatts (MW) in a location that would resolve that need. After the
3 A condition identified by the NYISO in the RNA as a violation or potential violation of Reliability Criteria as defined by the OATT.
The CRP details the NYISO’s plan for continued reliability of the BPTFs during the Study Period and
identifies additional resources, or combinations of resources, that resolve any identified criteria violations
in the RNA. New or proposed resources included in the CRP may be provided by market‐based solutions
developed in response to market forces, and by the request for solutions. If the market does not adequately
respond, reliability will be maintained by either regulated backstop solutions developed by the Responsible
TOs, which are obligated to provide reliable service to their customers, or alternative regulated solutions
being developed by Other Developers. To maintain the long‐term reliability of the BPTFs, these additional
resources must be readily available or in development at the appropriate time to address the identified
need.
Proposed solutions that are submitted in response to an identified Reliability Need are evaluated in
the development of the CRP and must satisfy reliability criteria. However, the solutions submitted to the
NYISO for evaluation in the CRP do not have to be in the same amounts of MW or locations as the
compensatory MW reported in the RNA. There are various combinations of resources and transmission
upgrades that could meet the needs identified in the RNA. The reconfiguration of transmission facilities
and/or modifications to operating protocols identified in the solution phase could result in changes and/or
modifications of the needs identified in the RNA.
This report begins by highlighting the changes to the Reliability Planning Process recently
implemented in the NYISO’s tariffs and procedures. Next, this report summarizes the prior Reliability
Planning Process findings and reliability plans. The report continues with a summary of the load and
resource forecast for the RNA Study Period, the RNA Base Case assumptions and methodology, and the RNA
findings. Detailed analyses, data and results, and the underlying modeling assumptions are contained in the
appendices.
Along with addressing reliability, the Reliability Planning Process is also designed to provide
information that is both informative and of value to the New York wholesale electricity marketplace and
federal and state policymakers. For informational purposes, this RNA report reviews activities related to
environmental regulatory programs and other relevant developments. The RNA report also provides the
latest historical information for the past five years of congestion, and related data is posted on the NYISO’s
website.
In 2019, a major planning process was carved out of the Reliability Planning Process and defined as
the Short-Term Reliability Process (STRP). This process was approved by the FERC and its requirements
are contained in Attachments Y and FF of the NYISO’s OATT. With this process in place, the Reliability
Planning Process’s Study Period changes from a year 1 to year 10 analysis, into a year 4 to year 10 look
ahead. At the same time, the STRP evaluates year 1 through year 5 from the Short Term Assessment of
Reliability (STAR) Start Date, with a focus on Short-Term Reliability Needs arising in years 1 through 3 of
the Study Period. Each quarterly STRP concludes if the STAR or Generator Deactivation Assessment does
not identify a STRP Need, and states whether a STRP Need will be addressed in the Reliability Planning
Process or in the STRP.
Short-Term Reliability Process Needs that arise in the Near-Term (within three years) will be
addressed using the Short-Term Reliability Process (STRP). Short-Term Reliability Process Needs that are
not Near-Term needs on the BPTF will only be addressed using the STRP if an identified Reliability Need
cannot timely be addressed through the ISO’s Reliability Planning Process. If the Reliability Need is handled
through the STRP, the NYISO will solicit market-based solutions of all types, a regulated transmission
solution(s), and service offers from Generators, as appropriate. The NYISO will select a solution(s)
consistent with the STRP process which may include selecting Generators to remain in service under
temporary reliability must run (RMR) agreements until the transmission solution is complete.
One of the changes to the Reliability Planning Process, which was first implemented in the 2016 RNA, is
providing initial (“1st pass”) RNA results to stakeholders, usually in June of the first year of the biennial
planning process. The stakeholders can provide project updates focused on reducing or eliminating the
initial Reliability Needs, such as:
Updated LTPs
Changes in BPTFs
Changes in available resources such as generating unit status or authority to operate
in current equipment configuration past a date certain (e.g., due to a new or amended
environmental laws or regulations) 4
After the NYISO Board of Directors approves the RNA Report, and before NYISO issues a solicitation for
regulated backstop, market-based, and alternative regulated solutions, the NYISO will request updated
LTPs, NYPA transmission plans, and other5 status updates relevant to reducing, or eliminating, the
Reliability Needs, as timely received from Market Participants, Developers, TOs, and other parties. Changes
that would tend to increase the scope of Reliability Needs after the RNA lockdown date will be handled in
the STRP or a future RNA, as appropriate. The NYISO will then request solutions for the remaining
Reliability Needs, if any.
The 2018 version of the Reliability Planning Process Manual reflected a change in the “RNA Base Case
Development Process” section, mainly related to the Base Case inclusion rules applicable to proposed
projects, and also to the treatment of generation deactivations in the RNA Base Case. Specifically, additional
considerations were added in 2019 to reflect situations in which a Generator Owner lacks authority to
operate in its current equipment configuration past a date certain (e.g., due to a new or amended
environmental law or regulation).
Further details of the Reliability Planning Process and STRP are contained in Appendix B of this
report, and also in the Reliability Planning Process Manual located on the NYISO website.
The 2014 RNA identified both resource adequacy and transmission security related Reliability Needs,
which were subsequently eliminated by the system updates received during the 2014 CRP process.
The 2016 RNA identified two transmission security Reliability Needs beginning in 2017: the New York
State Electric & Gas Corp. (NYSEG) Oakdale 345/115 kV transformer, and the Long Island Power Authority
(LIPA) East Garden City to Valley Stream 138 kV line. Subsequent to the October 2016 approval of the RNA,
and prior to the start of the CRP, NYSEG and LIPA provided updates to their LTPs. With these updates the
two identified Reliability Needs were resolved, and there was no solicitation of solutions under the 2016
Reliability Planning Process cycle.
The 2018 RNA concluded that the New York State Bulk Power Transmission Facilities will meet all
applicable reliability criteria over the 2019 through 2028 study period.
The NYISO has not previously triggered any regulated backstop solutions to meet previously-identified
Reliability Needs due to changes in system conditions and the sufficiency of market solutions coming into
service.
Figure 5, below, presents the market solutions and TOs’ plans that were submitted in response to
previous requests for solutions.
Included in
Original I/S Proposal Target the 2020
Queue # Project Submitted Zone
Date Type I/S RNA Final
Base Case
339 RG&E Station 255 CRP 2012 B N/A TO Plan W 2020 Yes
National Grid Clay-Teall
N/A CRP 2012 C N/A TO Plan W2020 Yes
#10 115kV
NYSEG Terminal
upgrades, on Stolle Road-
N/A RNA 2016 A 2019 TO Plan I/S Yes
Gardenville 230 kV Line
#66
RG&E Terminal
upgrades, on Clay-
N/A RNA 2016 C 2019 TO Plan S2019 Yes
Pannell PC1 and PC2
345 kV lines.
NYSEG Oakdale
345/115 kV 3rd
N/A transformer and CRP 2016 C 2021 TO Plan W2021 Yes
substation
reconfiguration.
National Grid
N/A CRP 2014 C 2017 TO Plan W2020 Yes
Clay-Dewitt #3 115kV
Orange and Rockland
West Haverstraw
N/A RNA 2018 G S2021 TO Plan S2021 Yes
345/138 kV transformer
addition
Brookhaven to Edwards
Ave 138 kV line ratings
N/A increase, addressing the RNA 2018 K 2019 TO Plan S2019 Yes
overload in Eastern Long
Island from Y2028
Two initiatives in particular will lead to large changes in the type of resources available to serve the
demand in New York. First, the New York State Department of Environmental Conservation (NYSDEC)
“Peaker Rule” requires significant emission reductions from older high-emitting gas turbines, or “peakers,”
such that affected units may be unavailable as early as 2023. The RNA base case accounts for potential
impacts from the unavailable generation.
Second, the Climate Leadership and Community Protection Act (CLCPA) is a state law shaping
how energy will be supplied in New York State. The CLCPA calls for growing the portion of consumed
energy served by renewable resources to 70% by 2030. Looking beyond 2030, the CLCPA requires a
zero-emission grid by 2040. The RNA 70x30 Scenario in conjunction with other studies being performed by
the NYISO, such as the Climate Change Impact & Resilience Study, takes an initial review of the reliability
implications of the CLCPA targets.
Regional Greenhouse New York and other Reduce carbon dioxide emissions The NYS DEC proposed to expand
RGGI states cap by 30% from 2020 to 2030 and applicability in NYS to generators
Gas Initiative (RGGI)
expand applicability to currently of 15 MW or greater, whereas
exempt “peaking units” below current rules do not apply to
current 25 MW threshold generators less than 25 MW
Climate Leadership New York State Public Service 6,000 MW of distributed solar Transformation of the power
Commission, New York State installed by 2025, 185 trillion grid, necessitating examination of
and Community
Energy Research and BTU reduction in total energy market structures, planning
Protection Act Development Authority, consumption, including processes, flexible load, and
New York State Department of electrification to reduce fossil investment in bulk power system
Environmental Conservation, fuel use in buildings by 2025, infrastructure
Climate Action Council 3,000 MW of storage installed
by 2030, 70% of load supplied
by renewable resources by
2030, 9,000 MW of Offshore
Wind Installed by 2035, 100%
of load supplied by zero-
emissions resources by 2040
NYS Accelerated Office of Renewable Energy Siting Provides for an accelerated path for Intended to help accelerate siting
(ORES) within the NYS Department the permitting and construction of of eligible renewable resources in
Renewable Energy
of State, New York State Public renewable energy projects instead of support of state policy goals.
Growth and Community Service Commission, New York State through the Article 10 power plant Intended to establish new
Benefit Act Energy Research and Development siting law. Requires a comprehensive transmission investment priorities to
Authority (NYSERDA) study to identify cost-effective facilitate the achievement of state
distribution, local and bulk electric policies
system upgrades to support the state's
climate goals, and filing of
the study with the New York State
Public Service Commission
Peaker Rule: Ozone Season Oxides of Nitrogen (NOx) Emission Limits for Simple Cycle and Regenerative
Combustion Turbines
In December 2019, the DEC issued requirements to reduce emissions of smog-forming pollutants from
peaking generation units. Combustion turbines known as “peakers” typically operate to maintain bulk
power system reliability during the most stressful operating conditions, such as periods of peak electricity
demand. In addition, these units are often called upon at any time, seven days a week and 24 hours a day,
to be able to respond to contingencies or other near real time changes on the electric system. By being
The Peaker Rule6, which phases in compliance obligations between 2023 and 2025, will affect
approximately 3,300 MW of simple-cycle turbines located mainly in the lower Hudson Valley, New York
City and Long Island. The rule required peaking unit owners to submit compliance plans to the DEC in
March 2020. These generator compliance plans informed the NYISO’s 2020 Reliability Needs Assessment
(RNA) base case assumptions for years 2024-2030. The proposed plans are also being examined in the
NYISO Short-Term Reliability Process for the years 2021-2025. The rule provides a phased reduction in
emission limits, in 2023 and 2025, during the ozone season (May 1-September 30) and allows several
options for achieving compliance with the new lower limits applicable during the ozone season.
Compliance plans submitted to the NYSDEC were provided to the NYISO for assessment and inclusion
in the base case. The plans indicate approximately 1,800 MW of nameplate capacity (approximately 1,500
MW of net operating capability) are proposed to ultimately be unavailable during the summer to comply
with the emissions requirements. Remaining units stated either that they comply with the emission limits
as currently operated, or proposed equipment upgrades to achieve the emissions limits. A summary of the
individual generator plans is provided in the Figure 7, Figure 8 and Figure 9.
The regulations include a provision to allow an affected generator to continue to operate up to two
years, with a possible further two-year extension, after the compliance deadline if the generator is
designated by the NYISO or the local transmission owner as needed to resolve a reliability need until a
permanent solution is in place.
6 https://www.dec.ny.gov/regulations/116131.html
Units Nameplate CRIS (MW) Capability (MW) 2023 2023 2024 2024 2025 2025
MW Ozone non-Ozone Ozone non-Ozone Ozone non-Ozone
Season Season Season Season Season Season
Summer Winter Summer Winter May 2023 - October May 2024 - October May 2025 - October
September 2023 - April September 2024 - April September 2025 - April
2023 2024 2024 2025 2025 2026
Coxsackie GT 22 20 26 20 24 O/S O/S O/S O/S O/S O/S
Unavailable MW = 43 40 52 38 46
Impacted MW
O/S - Out-of-service
Gowanus 1&4 (1-1 320 279 364 274 365 O/S I/S O/S I/S O/S I/S
through 1-8, and 4-1
through 4-4)
Gowanus 2&3 (2-1 320 300 391 278 373 I/S I/S I/S I/S O/S I/S
through 2-8 and 3-1
through 3-8)
Narrows 1&2 (1-1 352 309 404 287 380 I/S I/S I/S I/S O/S I/S
through 1-8, and 2-1
through 2-8)
Ravenswood GTs (01, 10, 69 50 64 41 57 O/S O/S O/S O/S O/S O/S
11)
Arthur Kill GT1 20 17 22 12 15 I/S I/S I/S I/S O/S O/S
Astoria GTs (2-1 through 558 504 621 415 543 O/S O/S O/S O/S O/S O/S
2-4, 3-1 through 3-4, 4-1
through 4-4)
Con Ed 59th St 17 15 20 16 20 I/S I/S I/S I/S O/S O/S
Units Nameplate CRIS (MW) Capability (MW) 2023 2023 2024 2024 2025 2025
MW Ozone non-Ozone Ozone non-Ozone Ozone non-Ozone
Season Season Season Season Season Season
Summer Winter Summer Winter May 2023 - October May 2024 - October May 2025 - October
September 2023 - April September 2024 - April September 2025 - April
2023 2024 2024 2025 2025 2026
Glenwood GT1 16 14.6 19.1 11.4 14.5 O/S O/S O/S O/S O/S O/S
Northport GT 16 13.8 18.0 11.7 15.1 O/S O/S O/S O/S O/S O/S
Port Jefferson GT1 16 14.1 18.4 12.9 16.6 O/S O/S O/S O/S O/S O/S
I/S - In-service
Notes:
1. The service pattern in the last two columns repeats in subsequent years of the RNA Study Period
2. Other compliance plans were submitted in addition to what is shown on this table. The table lists the plants with compliance plans that resulted in
a change of status (i.e., as also listed in the 2020 Gold Book Table IV-6)
In addition, the New York State Reliability Council (NYSRC) has a minimum oil-burn requirement rule
that is intended to maintain electric system reliability in the event of gas supply interruptions.
The New York State DEC issued proposed RGGI regulations that would cap New York’s carbon dioxide
emissions at approximately 21 million tons by 2030.8 In 2019, New York generators emitted
approximately 24.6 million tons of carbon dioxide. The proposed rule seeks to expand applicability to
certain generators of 15 MW or greater, whereas currently RGGI rules do not apply to generators less than
25 MW nameplate. New Jersey re-joined the initiative in 2020, Virginia will be joining in 2021, and
Pennsylvania has pending legislation to join RGGI. The expansion of the RGGI region and anticipated
■ 70% of electricity delivered in New York State must be derived from renewable
resources by 2030;
■ 100% of the electricity consumed in New York State must be derived from
zero-emissions resources by 2040;
■ 9,000 MW of offshore wind installed by 2035;
■ 6,000 MW of distributed solar energy resources installed by 2025; and
■ 3,000 MW of energy storage installed by 2030.
The CLCPA created a 22-member Climate Action Council (CAC) to establish a roadmap for how the
state will work towards these goals. The CAC will develop many of the implementation details of the
CLCPA. The CLCPA establishes that the CAC should develop a draft scoping plan by the end of 2022 and
deliver a final plan to the Governor and the Legislature by the end of 2023.
The act also directs the New York State Department of Public Service, in consultation with NYSERDA,
the New York Power Authority (NYPA), the Long Island Power Authority, the investor-owned utilities, and
the NYISO, to conduct a comprehensive study to identify cost-effective distribution, local and bulk electric
system upgrades to support the state’s climate and clean energy policies. This State Power Grid Study is
targeted to be completed by end of 2020. The PSC has commenced a proceeding leading to a transmission
investment plan utilizing the NYISO’s Public Policy Process to select projects, while enabling the PSC to
designate NYPA, either on its own or with others, to carry out projects needed expeditiously to achieve the
CLCPA goals.9 NYPA and DPS Staff have petitioned the PSC proposing criteria for ranking transmission
9 http://documents.dps.ny.gov/public/MatterManagement/CaseMaster.aspx?MatterCaseNo=20-E-0197&submit=Search
This section highlights the key assumptions and modeling data updates for the RNA. These include the
load forecast model, the forecasted level of special case resources, the change in generation resource status,
LTPs, and bulk power transmission projects. As described above, the newly defined RNA Study Period is
from 2024 (year 4) through 2030 (year 10).
Both the transmission security and resource adequacy studies in the RNA Base Case use a peak
demand and energy forecast originating from the baseline forecast reported in the 2020 Gold Book. The
baseline forecast from the 2020 Gold Book is derived from energy and peak models that are built based on
projections of end-use intensities and economic variables. End-use intensities modeled include those for
lighting, refrigeration, cooking, heating, cooling, and other plug loads. The baseline forecast includes the
projected impacts of energy efficiency programs, building codes and standards, distributed energy
resources, behind-the-meter energy storage, behind-the-meter solar photovoltaic power, electric vehicle
usage, and electrification of heating and other end uses. Economic variables considered include gross
domestic product (GDP), households, population, and commercial and industrial employment. The baseline
forecast also considers the near-term economic impacts of reduced energy consumption resulting from the
state’s response to COVID-19. For the resource adequacy study, the baseline load forecast was modified by
removing the behind-the-meter solar PV impacts in order to model the solar PV explicitly as a generation
resource to account for the intermittent nature of its availability.
The RNA Base Cases were developed in accordance with NYISO procedures using projections for the
installation and deactivation of generation resources and transmission facilities that were developed in
conjunction with Market Participants and TOs:
■ For the transmission security evaluations, the power flow RNA Base Case uses the NYISO 2020
FERC 715 filing as a starting point, adding and removing resources consistent with the base
case inclusion screening process provided in Section 3 of the Reliability Planning Process
Manual. Representations of neighboring systems are derived from interregional transmission
■ For the resource adequacy evaluations, the models are developed starting with prior resource
adequacy models, and are updated with information from the 2020 Gold Book and historical
data, with the application of the inclusion rules. Information on modeling of neighboring
systems is based on the input received from the NPCC CP-8 working group.
The demand-side management impacts included or accounted for in the 2020 Base Case forecast
derive from actual and projected spending levels and realization rates for state-sponsored programs such
as the Climate Leadership and Community Protection Act (CLCPA), Clean Energy Standard (CES), the Clean
Energy Fund (CEF), the NY-SUN initiative, the energy storage initiative, and earlier programs developed as
part of the Reforming the Energy Vision (REV) proceedings. The NYISO reviewed and discussed with
Market Participants, during meetings of the ESPWG and TPAS, projections for the potential impact of
energy efficiency, solar PV, electric vehicles, and other demand-side management impacts over the Study
Period. The factors considered in developing the 2020 RNA Base Case forecast are included in Appendix C
of this report.
The baseline energy forecast for the 2020 RNA is lower than the 2018 RNA baseline forecast, including
a 4.2% decline in 2020 and 1.7% decline in 2028. The baseline peak forecast for the 2020 RNA is also lower
than the 2018 RNA baseline forecast, including a 1.4% decline in 2020 and 1.1% decline in 2028. The
lower energy forecasts are attributed to both economic factors and the continued impact of energy
efficiency and behind-the-meter solar PV.
Figure 10 on the next page summarizes the three forecasts used in the 2020 RNA. Figure 12 shows a
comparison of the baseline forecasts and energy efficiency program impacts contained in the 2018 RNA
and the 2020 RNA. Figure 13 and Figure 14 present actual, weather-normalized forecasts of annual energy
and summer peak demand for the 2020 RNA. Figure 15 and Figure 16 present the NYISO’s projections of
annual energy and summer peak demand in the 2020 RNA for energy efficiency, distributed generation,
and behind-the-meter solar PV.
1For the resource adequacy study, the Gold Book baseline load forecast was modified by removing the behind-the-meter solar PV impacts in order to model the solar PV
explicitly as a generation resource to account for the intermittent nature of its availability.
2 The transmission security power flow RNA base cases use this Gold Book baseline forecast.
High Load Scenario and Adjusted High Load Scenario Energy Forecasts
Annual GWh 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030
2020 High Load End-Use Energy Forecast 157,619 160,258 164,181 164,969 166,559 167,968 169,339 170,492 171,550 172,327 172,962
-- Energy Efficiency and Codes & Standards 2,021 4,234 6,612 9,111 11,635 13,768 15,078 15,950 16,557 17,037 17,511
-- BtM Solar PV 2,560 3,079 3,645 4,233 4,794 5,301 5,716 6,052 6,298 6,479 6,612
-- BtM Non-Solar Distributed Generation 1,252 1,416 1,059 940 818 852 877 900 931 956 973
+ Storage Net Energy Consumption 19 43 67 99 130 160 189 221 254 281 309
+ Electric Vehicle Energy 199 345 538 781 1,085 1,456 1,889 2,407 3,031 3,765 4,506
+ Non-EV Electrification 389 996 1,890 2,815 3,897 5,122 6,462 7,873 9,362 10,907 12,588
2020 Gold Book High Load Scenario 152,393 152,913 155,360 154,380 154,424 154,785 156,208 158,091 160,411 162,808 165,269
+ BtM Solar PV 2,560 3,079 3,645 4,233 4,794 5,301 5,716 6,052 6,298 6,479 6,612
2020 RNA High Load Scenario 3 154,953 155,992 159,005 158,613 159,218 160,086 161,924 164,143 166,709 169,287 171,881
High Load Scenario and Adjusted High Load Scenario Summer Peak Forecasts
Annual MW 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030
2020 High Load Scenario End-Use Peak Demand 33,452 33,912 34,500 34,778 35,156 35,501 35,887 36,244 36,613 36,915 37,174
-- Energy Efficiency and Codes & Standards 313 629 1,000 1,396 1,791 2,142 2,372 2,534 2,641 2,720 2,800
-- BtM Solar PV 539 658 779 904 1,006 1,101 1,176 1,229 1,260 1,271 1,268
-- BtM Non-Solar Distributed Generation 218 251 189 169 148 154 158 164 170 174 177
-- BtM Storage Peak Reductions 5 14 26 44 63 91 125 159 206 250 292
+ Electric Vehicle Peak Demand 52 85 126 183 248 328 426 537 671 828 994
+ Non-EV Electrification 23 57 111 163 227 300 381 468 555 648 749
2020 Gold Book High Load Scenario 32,452 32,502 32,743 32,611 32,623 32,641 32,863 33,163 33,562 33,976 34,380
+ BtM Solar PV 539 658 779 904 1,006 1,101 1,176 1,229 1,260 1,271 1,268
2020 RNA High Load Scenario 3 32,991 33,160 33,522 33,515 33,629 33,742 34,039 34,392 34,822 35,247 35,648
3 The high load scenario forecast will be used for the high load resource adequacy scenario.
1For the resource adequacy study, the Gold Book baseline load forecast was modified by removing the behind-the-meter solar PV impacts in order to model the solar PV
explicitly as a generation resource to account for the intermittent nature of its availability.
2 2016 Gold Book values have been adjusted to include only those impacts from 2018 forward, so as to compare directly to the 2018 Gold Book values.
Annual Energy - Actual, Weather Normalized, and Forecasts with BtM Solar PV Added Back (GWh)
174000
172000
170000
168000
166000
164000
162000
160000
158000
156000
154000
152000
150000
148000
2010
2011
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030
Actual Weather Normalized RNA Base Case RNA High Load Scenario
Figure 14: 2020 Baseline and High Load Energy Scenario Summer Peak Demand Forecasts with Solar PV Added
Back
Summer Peak Demand - Actual, Weather Normalized, and Forecasts with BtM Solar PV Added Back (MW)
37000
36000
35000
34000
33000
32000
31000
30000
29000
28000
2010
2011
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030
Actual Weather Normalized RNA Base Case RNA High Load Scenario
Figure 17: Forecast of BtM Solar PV Coincident Summer Peak Demand Reductions (MW)
A total of approximately 543 MW of proposed generation (wind and solar) has been added to
the 2020 RNA Base Case as compared with the 2019 - 2028 CRP;
A total of approximately 2,582 MW of generation have been removed as compared with the
2019 – 2028 CRP Base Case either due to being in a deactivated state (e.g., retired, mothballed,
or in an ICAP-Ineligible Forced Outage (IIFO), or proposed to retire or mothball), or as
operationally impacted by the DEC Peaker Rule.
The comparison of generation status between the 2019 – 2028 CRP and 2020 RNA is detailed in Figure
18, Figure 19, and Figure 20. The MW values represent the Capacity Resources Interconnection Service
(CRIS) MW values from the 2020 Gold Book.
Figure 18: Proposed Projects Included in the 2020 RNA Base Case
11The term “Special Case Resource” is defined in Section 2.19 of Market Services Tariff and also in the Appendix A of this
report (Glossary)
2020 Gold Book Table Owner/ Operator Plant Name Zone CRIS 2020 RNA 2019-2028
Base Case CRP Base
Status* Case Status
International Paper Company Ticonderoga F 7.6 part of SCR part of SCR
program program
Helix Ravenswood, LLC Ravenswood 09 J 21.7 out out
Binghamton BOP, LLC Binghamton C 43.8 out out
Helix Ravenswood, LLC Ravenswood 2-1 J 40.4 out out
Table IV-3: Deactivated
Ravenswood 2-2 J 37.6
Units with Unexpired CRIS
Ravenswood 2-3 J 39.2
Rights Not Listed in Existing
Ravenswood 2-4 J 39.8
Capacity Table III-2
Ravenswood 3-1 J 40.5
Ravenswood 3-2 J 38.1
Ravenswood 3-4 J 35.8
Cayuga Operating Company, LLC Cayuga 2 C 154.7 out out
Lyonsdale Biomass, LLC Lyonsdale E 20.2 out in
Exelon Generation Company LLC Monroe Livingston B 2.4 out in
Innovative Energy Systems, Inc. Steuben County LF C 3.2 out in
Table IV-4: Deactivated
Consolidated Edison Co. of NY, Inc Hudson Ave 4 J 13.9 out in
Units Listed in Existing
New York State Elec. & Gas Corp. Auburn - State St C 5.8 out in
Capacity Table III-2
Cayuga Operating Company, LLC Cayuga 1 C 154.1 out in
Consolidated Edison Co. of NY, Inc Hudson Ave 3 J 16.0 out in
Albany Energy, LLC Albany LFGE F 4.5 out in
Table IV-5: Notices of Somerset Operating Company, LLC Somerset A 686.5 out in
Proposed Deactivations as National Grid West Babylon 4 K 49.0 out in
of March 15, 2020 Entergy Nuclear Power Marketing, LLC Indian Point 2 H 1,026.5 out out
Indian Point 3 1,040.4
Change in deactivation since 2019 - 2028 CRP** 956
Total 2020 RNA MW assumed as deactivated** 3,522
change in status
*Consistent with deactivation dates
** does not include peaker retirements
2020 Gold Book Table Owner/ Operator Plant Name** Zone CRIS 2020 RNA Base 2019-2028
Case Status CRP Base
(Deactivate Case Status
starting from)
Central Hudson Gas & Elec. Corp. Coxsackie GT G 19.9 2023 in
South Cairo 1 G 19.8
Consolidated Edison Co. of NY, Inc. 74 St. GT 1 & 2 J 39.1 2023 in
Hudson Ave 5 15.1
59 St. GT 1 15.4 2025
Helix Ravenswood, LLC Ravenswood 01 J 8.8 2023 in
Ravenswood 10 21.2
Ravenswood 11 20.2
National Grid Glenwood GT 1 K 14.6 2023 in
Table IV-6: Proposed Status Northport GT 13.8
Change to Comply with DEC Port Jefferson GT 01 14.1
Peaker Rule NRG Power Marketing, LLC Astoria GT 2-1, 2-2, 2-3, 2-4 J 165.8 2023 in
Astoria GT 3-1, 3-2, 3-3, 3-4 170.7
Astoria GT 4-1, 4-2, 4-3, 4-4 167.9
Arthur Kill GT1 16.5 2025
Astoria Generating Company, L.P. Gowanus 1-1 through 1-8 J 138.7 Winter -only 2023 in
Gowanus 4-1 through 4-8 140.1
Astoria GT 01 15.7 Winter-only 2025
Gowanus 2-1 through 2-8 152.8
Gowanus 3-1 through 3-8 146.8
Narrows 1-1 through 2-8 309.1
Additional total 2020 RNA MW assumed as out of service 1,626
change in status
Note: NYSDEC’s Part 227-3 applies to all simple cycle gas turbines with nameplates equal to or greater than 15 MW. Thus, all simple cycle generators are
subject to the rule and all owners of these machines were required to submit compliance plans to the NYSDEC. The compliance plans consist of
statements that the generator; (i) already complies with the new NOx limits, (ii) will retire, (iii) will limit operation during the ozone season, and/or (iv) will
retrofit emission control technology to meet the emission limits of the new rule. If the plant owners submitted compliance plans that state that the
generator will able to operate within the new NOx limits during the ozone season, these generators remain in service in the 2020 RNA base case.
The NextEra Empire State Line Project that was selected by the NYISO Board of Directors in
October 2017 to address the Western New York Public Policy Transmission Need. This project
includes a new 345 kV circuit and phase angle regulator (PAR) that will alleviate constraints in
the Niagara area. The planned in-service date for this project is June 2022.
The Segment A, AC Transmission joint project, by LS Power and New York Power Authority
(NYPA) that was selected by the NYISO Board of Directors in April 2019. The project includes a
new double-circuit 345 kV line between Edic and New Scotland substations, two new 345 kV
substations at Princetown and Rotterdam, two new 345 kV lines between Princetown to
Rotterdam substations, and retirement of the existing Porter to Rotterdam 230 kV lines. The
planned in-service date is December 2023.
The New York Transco Segment B, AC Transmission project, also was selected by the NYISO
Board of Directors in April 2019. The project includes a new double-circuit 345/115 kV line
from a new Knickerbocker 345 kV switching station to the existing Pleasant Valley substation,
50% series compensation on the Knickerbocker to Pleasant Valley 345 kV line, and retirement
of 115 kV lines between Greenbush and Pleasant Valley substations. The planned in-service
date is December 2023.
Zone G-J Capacity** 13,509 12,904 12,904 12,904 12,904 12,904 12,904
Cap+fullUDR+SCR/Load Ratio 91.7% 88.0% 87.7% 87.3% 86.9% 86.3% 85.8%
Zone G-J Capacity** 12,322 11,802 11,802 11,802 11,802 11,802 11,802
Cap+fullUDR+SCR/Load Ratio 82.4% 79.2% 78.9% 78.6% 78.2% 77.7% 77.2%
Notes:
*NYCA load values represent baseline coincident summer peak demand. Zones J and K load values represent non-coincident
summer peak demand. Aggregate Zones G-J values represent the G-J locality peak.
**NYCA Capacity values include resources electrically internal to NYCA, additions, re-ratings, and retirements (including proposed
retirements and mothballs). Capacity values reflect the lesser of CRIS and DMNC values. NYCA resources include the net purchases
and sales as per the Gold Book. Zonal totals include the full Unforced Capacity Deliverability Rights (UDRs) for those capacity zones.
• SCR: forecasted MW ICAP value from the 2020 Gold Book.
• Wind, solar, run-of river and landfill gas summer capacity is counted as 100% of nameplate rating.
*** For UCAP calculation, EFORd from GE-MARS output file are used for thermal units. For renewables, installed capacity
intermittent resources derating factors (received from IMO team) are used.
Notes:
1. Total Capacity = Capacity* + full UDR + SCR
2. *Capacity = lesser of (CRIS, DMNC). NYCA resources include the net purchases and sales as per the Gold Book.
3. ICAP = Installed Capacity
4. UCAP = Unforced Capacity (takes into consideration generation unavailability)
5. UCAP calculation:
For thermal units, average capacity derating factors from the MARS output are used
For renewables, installed capacity intermittent resources derating factors are used
As shown in the Figure 21, the total NYCA capacity margin, which is defined as capacity above the
baseline load forecast, varies between 24% and 27%. Figure 22 shows a comparison between the total
ICAP and total UCAP for 2030; the difference reflects generation unavailability for the resource mix
assumed in the RNA Base Case for year 2030.
Figure 23 shows the relative decrease in the capacity margin, by comparing the details of the capacity
margins for year 10 between the 2020 RNA (2030) and the 2019-2028 CRP (2028). The analysis reveals
two observations:
■ Negative net margin shows deterioration in the relative capability to serve load, when comparing
the two studies assumptions; and
■ Compared to the 2019 CRP, the system has less overall net resources.
Notes:
1. Includes the reductions due to projected energy efficiency programs, building codes and standards, distributed
energy resources and behind-the-meter solar photovoltaic resources; it also reflects expected impacts (increases)
from projected electric vehicle usage.
2. Includes the total SCRs, and net capacity purchases and sales from the applicable Gold Book.
Figure 24: 2020 RNA Zone J Load and Capacity Comparison with the 2019 - 2028 CRP
Notes:
1. Includes the reductions due to projected energy efficiency programs, building codes and standards, distribution
energy resources and behind-the-meter solar photovoltaic power; it also reflects expected impacts (increases)
from projected electric vehicle usage.
2. Does not include the total SCRs, and UDRs from the applicable Gold Book.
Overview
This section provides the methodology and results for the resource adequacy and transmission
security of the New York BPTF over the RNA Study Period. If any reliability criteria violations are identified,
the NYISO identifies Reliability Needs. Violations of the criteria are translated into MW or MVAr amounts to
provide a relative quantification of the Reliability Needs, and to support the development of solutions in the
CRP.
Transmission security is the ability of the power system to withstand disturbances, such as electric
short circuits or unanticipated loss of system elements, and continue to supply and deliver electricity.
Transmission security is assessed deterministically with potential disturbances being applied without
concern for the likelihood of the disturbance in the assessment. These disturbances (single-element and
multiple-element contingencies) are categorized as the design criteria contingencies, which are explicitly
defined in the reliability criteria. The impacts resulting from applying these design criteria contingencies
are assessed to determine whether thermal loading, voltage, or stability violations will occur. In addition,
the NYISO performs a short circuit analysis to determine if the system can clear faulted facilities reliably
under short circuit conditions. The NYISO’s “Guideline for Fault Current Assessment12” describes the
methodology for that analysis.
The analysis for the transmission security assessment is conducted in accordance with NERC
Reliability Standards, NPCC Transmission Design Criteria, and the NYSRC Reliability Rules. Contingency
analysis is performed on the BPTF to evaluate thermal and voltage performance under design contingency
conditions using the Siemens PTI PSS®E and PowerGEM TARA programs. Generation is dispatched to
match load plus system losses, while respecting transmission security. Scheduled inter-area transfers
modeled in the base case between the NYCA and neighboring systems are held constant.
The process of successive contingency testing (such as N-1-1) allows for corrective actions including
generator re-dispatch, PAR adjustments, and HVDC adjustments between the contingencies. For example,
for N-1-1 analysis allowable system adjustments occur between the first (N-1-0) and second (N-1-1)
contingencies. These corrective actions prepare the system for the next contingency by reducing the flow
to normal rating after the first contingency. An N-1-0 violation occurs when the flow cannot be reduced to
below the normal rating following the first contingency. An N-1-1 violation occurs when the facility is
reduced to below the normal rating following the first contingency, but the power flow following the
second contingency exceeds the applicable post-contingency rating.
Resource adequacy is the ability of the electric system to supply the aggregate electrical demand and
energy requirements of the customers at all times, taking into account scheduled and reasonably expected
unscheduled outages of system elements. Resource adequacy considers the transmission systems,
generation resources, and other capacity resources, such as demand response. The NYISO performs
resource adequacy assessments on a probabilistic basis to capture the random natures of system element
outages. If a system has sufficient transmission and generation, the probability of an unplanned
disconnection of firm load is equal to or less than the system’s standard, which is expressed as a loss of load
expectation (LOLE). The New York State bulk power system is planned to meet an LOLE that, at any given
point in time, is less than or equal to an involuntary firm load disconnection that is not more frequent than
once in every 10 years, or 0.1 events per year. This requirement forms the basis of New York’s Installed
If Reliability Needs are identified, various amounts and locations of compensatory MW required for
the NYCA to satisfy those needs are determined to translate the criteria violations to understandable
quantities. Compensatory MW amounts are determined by adding generic capacity resources to NYISO
zones to effectively satisfy the needs. The compensatory MW amounts and locations are based on a review
of binding transmission constraints and zonal LOLE determinations in an iterative process to determine
various combinations that will result in reliability criteria being met. These additions are used to estimate
the amount of resources generally needed to satisfy Reliability Needs. The compensatory MW additions are
not intended to represent specific proposed solutions. Resource needs could potentially be met by other
combinations of resources in other areas including generation, transmission and demand response
measures.
Due to the different types of supply and demand-side resources, and also due to transmission
constraints, the amounts and locations of resources necessary to match the level of compensatory MW
needs identified will vary. Reliability Needs could be met in part by transmission system reconfigurations
that increase transfer limits, or by changes in operating protocols. Operating protocols could include such
actions as using dynamic ratings for certain facilities, invoking operating exceptions, or establishing special
protection systems.
The procedure to quantify compensatory MW for BPTF transmission security violations is a separate
process from calculating compensatory MW for resource adequacy violations. This quantification is
performed by first calculating transfer distribution factors on the overloaded facilities. The power transfer
used for this calculation is created by injecting power at existing buses within the zone where the violation
occurs, and reducing power at an aggregate of existing generators outside of the area.
Steady-State Assessments
The RNA requires analysis of the security of the BPTF throughout the Study Period. The BPTF, as
defined in this assessment, include all of the facilities designated by the NYISO as a Bulk Power System
(BPS) element as defined by the NYSRC and NPCC, as well as other transmission facilities that are relevant
to planning the New York State transmission system. To assist in the assessment, the NYISO reviewed
For the 2020 RNA transmission security assessment, several transmission security violations (i.e.,
Reliability Needs) were identified for the Study Period. The transmission security Reliability Needs include
both thermal loading criteria violations on the BPTF. For the thermal loading violations, several 345 kV
circuits in the Con Edison service territory are overloaded under N-1-1 conditions beginning in year 2025
and increasing through 2030. Additionally, the Con Edison 345 kV system has 345 kV circuit overloads
under N-1-1-0 conditions beginning in 2025 and increasing through 2030. Figure 25 summarizes of the
worst overload for each BPTF element with a thermal criteria violation under N-1-1 conditions.
Appendix D provides the details of additional contingency combinations that also result in thermal criteria
violations for these BPTFs. Figure 26 provides a summary of the BPTF thermal criteria violations under N-
1-1-0 conditions. No BPTF steady state voltage violations are observed for this assessment.
Zone Owner Monitored Element Normal Contingency 1st Contingency 2nd Contingnecy 2025 2030
Rating Rating Summer Summer
(MVA) (MVA) Peak Flow Peak Flow
(%) (%)
I/J ConEd Sprainbrook-W49th St 844 1029 Sprainbrook- Tower F38 & F39 - 112
345 kV (51) Dunwoodie 345 kV
(W75)
I/J ConEd Sprainbrook-W49th St 844 1029 Sprainbrook- Tower F38 & F39 - 112
345 kV (52) Dunwoodie 345 kV
(W75)
I/J ConEd Dunwoodie-Mott Haven 785 925 Loss of Ravenswood 3 Dunwoodie-Mott 110 118
345 kV (71) Haven 345 kV (72)
I/J ConEd Dunwoodie-Mott Haven 785 925 Loss of Ravenswood 3 Dunwoodie-Mott 108 116
345 kV (72) Haven 345 kV (71)
J ConEd Mott Haven-Rainey 785 925 Mott Haven-Rainey Loss of Ravenswood - 108
West 345 kV (Q12) 345 kV (Q11) 3
J ConEd Mott Haven-Rainey 785 925 Mott Haven-Rainey Loss of Ravenswood - 108
East 345 kV (Q11) 345 kV (Q12) 3
J ConEd Goethals-Gowanus 345 518 738 Loss of Ravenswood 3 Stuck Breaker at 102 130
kV (26) Goethals 5
J ConEd Goethals-Gowanus 518 738 Loss of Ravenswood 3 Gowanus - Goethals 103 130
345kV (25) 345 kV (26)
I ConEd Sprainbrook/Dunwoodi 366 423 Loss of Ravenswood 3 Tower W89 & W90 106 109
e 345/138 kV (N7)
I ConEd Sprainbrook/Dunwoodi 309 438 Loss of Ravenswood 3 Tower W89 & W90 103 107
e 345/138 kV (S6)
I ConEd Dunwoodie 345/138 310 388 Loss of Ravenswood 3 Sprainbrook/Dunwo - 106
kV (W73) odie 345/138 kV
(N7)
Zone Owner Monitored Element Normal Contingency 1st Contingency 2nd Contingnecy 2025 2030
Rating Rating Summer Summer
(MVA) (MVA) Peak Flow Peak Flow
(%) (%)
I/J ConEd Dunwoodie-Mott Haven 785 925 Loss of Ravenswood 3 Dunwoodie-Mott 132 149
345 kV (71) Haven 345 kV (72)
I/J ConEd Sprainbrook-W49th St 844 1029 Loss of Ravenswood 3 Dunwoodie-Mott - 106
345 kV (51) Haven 345 kV (72)
I/J ConEd Sprainbrook-W49th St 844 1029 Loss of Ravenswood 3 Dunwoodie-Mott - 106
345 kV (52) Haven 345 kV (72)
Considering the utilization of all available PAR controls, the observed maximum deficiency (i.e.,
compensatory MW) for the New York City 345/138 kV Transmission Load Area (TLA) in 2025 is 700 MW.
Based on the load duration curve shown in Figure 27, the deficiency in 2025 may be observed for
approximately nine hours (3,853 MWh). This deficiency increases to 1,075 MW in 2030 and may be
observed for approximately 12 hours (7,672 MWh) as shown in Figure 28.
Figure 27: NYC 345/138 kV TLA – Approximate Projection for Year 2025
The BPTF transmission security violations begin at 700 MW in year 2025 and increase in magnitude
through year 2030. The maximum observed compensatory MW amount needed to address the BPTF
thermal issues described above is 1,075 MW in 2030.
Notes:
(1). Non-BPTF issues are reported for information only.
(2). Dynamic issues observed prior to 2024 will be evaluated in the Short-Term Reliability Process.
Dynamic Stability Criteria N-1-1 Violations (L/O Ravenswood 3 as First Level Event) (1), (2)
2024 2025 2030
Contingency Generator Transient Generator Transient Generator Transient
Contingency Description Synchronism Voltage Synchronism Voltage Synchronism Voltage
Name
Response Response Response
ConEd01 Fault at Astoria East 138 kV non-BPTF
with stuck breaker 3E
ConEd02 Fault at Astoria West 138 kV non-BPTF
and L/O Astoria CC1 and CC2
ConEd03 Fault at Astoria West 138 kV non-BPTF
with stuck breaker 2N
ConEd08 Fault at E. 13th St. 138 kV non-BPTF non-BPTF non-BPTF
with stuck breaker 4E
ConEd12 Fault at Freshkills 138 kV non-BPTF x non-BPTF
with L/O Arthur Kill 2
ConEd13 Fault at Freshkills 138 kV x non-BPTF
with stuck breaker BT1-2
ConEd14 Fault at Greenwood 138 kV non-BPTF x non-BPTF
with L/O Gowanus 345/138
(T2) 345 kV and PAR
ConEd15 Fault at Greenwood 138 kV non-BPTF x non-BPTF x non-BPTF
with stuck breaker 7S
ConEd16 Fault at Hellgate 138 kV with non-BPTF x BPTF & non-
stuck breaker 5 BPTF
ConEd20 Fault at Queensbridge 138 non-BPTF
kV with stuck breaker 7E
ConEd23_Q510 Fault at Farragut 345 kV with x BPTF & non-
L/O bus tie BPTF
ConEd25-Q461- Fault at E. 13th St. 138 kV non-BPTF non-BPTF non-BPTF
Q462 with stuck breaker
Notes:
(1). Non-BPTF issues are reported for information only.
(2). Dynamic issues observed prior to 2024 will be evaluated in the Short-Term Reliability Process
Figure 31: New York City (NYC) 345 kV Bus Voltage Recovery
During a fault, the observed voltage drop at a bus depends on the location of the fault on the system
13 https://www.nerc.com/docs/pc/tis/FIDVR_Tech_Ref%20V1-2_PC_Approved.pdf
As shown in Figure 29 and Figure 30, several contingencies result in loss of generator synchronism
with the transmission system. A primary driver to the loss of synchronism for these machines is the
sustained low voltages following the clearing of the fault. Examples of low voltages as observed from the
high-side of the generator step-up (GSU) transformer are shown in Figure 32 in response to a contingency.
As can be seen in Figure 32, the sustained low voltages are also observed at the high side of the GSU and
remain in the NERC PRC-024 “may trip” zone. In this example, due to the sustained low voltages an
equilibrium point for the generators is not reached, and the generators lose synchronism with the system.
As shown in Figure 33, Generator 1 loses synchronism and trips off line at about 3.5 seconds and Generator
2 goes out of synchronism and trips off line at about 10 seconds. The rotor angles plotted in Figure 33 are
relative to the system average rotor angle.
During the dynamic simulation timeframe, sufficient dynamic reactive resources to sustain transient
voltage support during the natural swings of the system are crucial. Generally, the system response to these
swings to maintain voltage comes from generator excitation system response, STATCOMs, static VAr
compensators (SVCs), wind and solar plant voltage controls, and other fast-acting resources.14 While pre-
contingency voltages can be maintained using static reactive resources, the dynamic system response
timeframe focuses primarily on dynamic reactive capability due to the transient nature of large power and
voltage swings and the short response time required.
The BPTF dynamic stability criteria violations compensatory values are measured by modeling
fictitious generators at the Farragut 345 kV, Astoria East 138 kV, and Greenwood North 138 kV buses with
a MW size determined by the compensatory MW for thermal violations. Focusing on the event combination
of the loss of Ravenswood 3 followed by event UC11 (as one of the more severe events), reactive capability
was added to the fictitious generators to the point where the BPTF transient voltage violations, sustained
oscillations, and generator synchronism criteria violations are no longer observed. Figure 34 provides a
description of dynamic compensation needed to address the event combination of the loss of Ravenswood
3 followed by event UC11. The impact of the added dynamic reactive capability is highly non-linear and
other event combinations and the location of the fictitious generators may cause significant variance to the
values stated in Figure 34.
14https://www.nerc.com/comm/PC_Reliability_Guidelines_DL/Reliability%20Guideline%20-
%20Reactive%20Power%20Planning.pdf
Notes:
(1). BPTF dynamic issues observed prior to 2024 will be evaluated in the Short-Term Reliability Process
In 2023, thermal overloads are observed on the Astoria East/Corona 138 kV TLA boundary feeders,
which are designed to a second contingency (N-1-1-0) based on the applicable Con Edison local design
criteria.
Considering the utilization of all available phase angle regulator (PAR) controls, the maximum
observed deficiency (i.e., compensatory MW) within this TLA ranges from 110 MW in 2023 to 180 MW in
2030 as shown in Figure 36. As shown in Figure 37 and Figure 38, the Astoria East/Corona 138 kV TLA
does not peak with the coincident system peak. Based on the load duration curves shown in Figure 37 and
Figure 38, the TLA may be deficient over 10 hours (659 MWh) on a peak day in 2023, increasing to 13
hours (1,461 MWh) on a peak day in 2030.
Figure 38: Astoria East/Corona 138 kV Load Duration Curve for 2030
In 2025, thermal overloads and voltage violations are observed on the Greenwood/Fox Hills 138 kV
TLA boundary feeders in the steady state (N-0) condition, which are exacerbated under N-1 and N-1-1
conditions.
Considering the utilization of all available PAR controls, the maximum observed deficiency (i.e.,
compensatory MW) within this TLA of 360 MW in 2025 to 370 MW in 2030 as shown in Figure 40. Based
on the load duration curve shown in Figure 41, the TLA may be deficient over 14 hours (3,571 MWh) over a
14 hour period on a peak day in 2025. The load duration curve for 2030 in Figure 42 shows that while the
amount of hours that the TLA is deficient does not increase compared to 2025, due to the increased
deficiency on peak, the total MWh of the deficiency increases to 3,696 MWh.
Figure 42: Greenwood/Fox Hills 138 kV TLA Load Duration Curve for 2030
Generation Model
The NYISO models the generation system in GE-MARS using several types of units. Thermal units
considerations include: random forced outages as determined by Generator Availability Data System
(GADS) — calculated EFORd and the Monte Carlo draw, scheduled and unplanned maintenance, and
thermal derates. Renewable resource units (i.e., solar PV, wind, run-of-river hydro and landfill gas) are
modeled using five years of historical production data. Co-generation units are also modeled using a
capacity and load profile for each unit.
Load Model
The load model in the NYISO GE-MARS model consists of historical load shapes and load forecast
uncertainty (LFU). The NYISO uses three historical load shapes in the GE-MARS model (2002, 2006 and
2007) in seven different load levels using a normal distribution. LFU is applied to every hour of these
historical shapes and each of the seven load levels are run through the GE-MARS model.
Summary of major GE-MARS topology changes16 (as compared with the 2019-2028 CRP):
71, 72, M51, M52 series reactors assumed bypassed after deactivation of Indian Point Unit Nos.
2 and 3
AC Transmission Public Policy Segment A and B Projects added starting January 2024
Removal of Cedars bubble/tie to Zone D model; adding the MW from the bubble to the HQ to D
tie limit.
The external areas model for PJM and ISO-NE were simplified by consolidating the five PJM
areas (bubbles) into one, and the eight ISO-NE areas into one.
The emergency transfer criteria limits used in the GE-MARS model were developed from an
assessment of analysis of the 2020 RNA power flow base cases, and analysis performed for other studies.
Figure 43, Figure 44 and Figure 45 provide the thermal and voltage emergency transfer limits for the major
NYCA interfaces. The 2018 RNA transfer limits are presented for comparison purposes.
Notes:
Grey italic font: Limit was not calculated
*change in limit between 2018 RNA and 2020 RNA is due to different modeling method used in GE-MARS. Additional topology
changes details are in Appendix D.
Notes:
Grey italic font: Limit was not calculated
T - Thermal, V - Voltage, C – Combined
The NYISO modeled a decrease in the thermal transfer limit for Dysinger East of 100 MW primarily
due to the retirement of the Somerset generation unit in Zone A.
Comparing the transfer limits reported for year 2021 through 2023 to the previous RNA, there is an
increase of 750 MW on the UPNY-Con Ed voltage limit for the 2020 RNA. The primary cause for this
increase is a change in the study assumption for the operation of the series reactors on the Dunwoodie –
Mott Haven 345 kV cables (71, 72) and the Sprain Brook – W. 49th Street cables (M51, M52). For the 2020
RNA, these series reactors were modeled as bypassed. This study assumption also resulted in a decrease of
50 MW in the I to J interface thermal limit.
The E to G interface thermal limit was modeled using a dynamic limit table in the 2020 RNA MARS
topology. The interface limit ranged from 1750 MW to a maximum of 2250 MW based on the availability of
the CPV Valley generation units. Starting in year 2024 the dynamic limit table was replaced with a single
interface limit of 2300 MW. The increase in the limit is the result of transmission facility upgrades included
in the AC Transmission Public Policy projects. Similarly, the UPNY-SENY MARS interface was modeled
using a dynamic limit table ranging from 5100 MW to a maximum of 5350 MW. With the large increase in
transfer capability when including the AC Transmission projects in 2024, the model was simplified by using
a single limit of 7150 MW, and does not constrain the flow of power in the GE-MARS simulation.
The topology used in the GE-MARS model for the 2020 RNA Base Case is represented in Figure 46.
100
CHAT EGUAY
1000
2665
1770
ON-NY
300 300 0
IESO D
1650
1300 1600
2000
1700 200
2650
CENTRAL EAST GROUP 0
ZONE A
GROUP
2200 1600 1500 5650 3925 800 800
A DYSINGER
B C VOLNEY-EAST
E CENTRAL-EAST
F ISONE
WEST-CENTRAL
EAST 1400 1400
330
550 600 300 800
3400 1600 414
2650
5650
MARCY SOUTH
CAPITAL-HUDV
UPNYSENY
7150
5400
G
1000
PJM-G
GROUP
Notes
150
1. PJM to NY emergency assistance (EA)
1045 assumption for calculating the PJM-NY Western
ties, PJM-G Group, and ABC Line Group flow
7375 distribution limit: 1500MW
330
PJM
PJM 8450 2. NYCA EA simultaneous import limit: 3,500 MW
WESTERN TIES
RECO H I CSC
425
MILLWOOD SOUTH 3. External areas representation based upon
515
information received from the NPCC CP-8 WG
DUNWOODIE Y49/
& Y49/Y50 Y50
GROUP
5643
CONED-
1000 4350 LIPA 1293 404
660 HTP 660
200 300
660 220 1613 Legend
550 105 Interface
PJMW PJM J2 J K
BC LINES
0 505 JAMAICA TIES Unidirectional Interface
320
315 Interface w/ Dynamic Ratings
J3
660 500 315 815 660
Interface Group
315 134
LI WEST
Interface Group w/ Dynamic Ratings
315 Monitoring Interface Group
315
VFT NYCA EA Interface Group Marker
Additionally, for information only, Figure 47 and Figure 48 represent the initial three years preceding the newly-defined RNA Study Period.
100
CHAT EGUAY
1000
2665
1690
ON-NY
150 150 0
IESO D
1650
1300 1600
1850
1700 200
2650
CENTRAL EAST GROUP 0
ZONE A
GROUP
1700 1600 1300 5650 3100 800 800
A DYSINGER
B C VOLNEY-EAST
E CENTRAL-EAST
F ISONE
WEST-CENTRAL
EAST 1400 1400
330
550 600 300 800
3400 1600 414
1850
5000
MARCY SOUTH
CAPITAL-HUDV
UPNYSENY DL
5250
3475
G
1000
PJM-G
GROUP
Notes
150
1. PJM to NY emergency assistance (EA)
1045 assumption for calculating the PJM-NY Western
ties, PJM-G Group, and ABC Line Group flow
7000 distribution limit: 1500MW
330
PJM
PJM 8450 2. NYCA EA simultaneous import limit: 3,500 MW
WESTERN TIES
RECO H I CSC
425
MILLWOOD SOUTH 3. External areas representation based upon
515
information received from the NPCC CP-8 WG
DUNWOODIE Y49/
& Y49/Y50 Y50
GROUP
5643
CONED-
1000 4350 LIPA 1293 404
660 HTP 660
200 300 660 220 1613 Legend
550 105 Interface
PJMW PJM J2 J K Unidirectional Interface
BC LINES JAMAICA TIES
0 505 320
Interface w/ Dynamic Ratings
315
J3
660 500 315 815 660 Interface Group
315 134 Interface Group w/ Dynamic Ratings
LI WEST
315 Monitoring Interface Group
315
VFT NYCA EA Interface Group Marker
100
CHAT EGUAY
1000
2665
1770
ON-NY
300 300 0
IESO D
1650
1300 1600
2000
1700 200
2650
CENTRAL EAST GROUP 0
ZONE A
GROUP
2200 1600 1500 5650 3100 800 800
A DYSINGER
B C VOLNEY-EAST
E CENTRAL-EAST
F ISONE
WEST-CENTRAL
EAST 1400 1400
330
550 600 300 800
3400 1600 414
2650
5000
MARCY SOUTH
CAPITAL-HUDV
UPNYSENY DL
5250
3475
G
1000
PJM-G
GROUP
Notes
150
1. PJM to NY emergency assistance (EA)
1045 assumption for calculating the PJM-NY Western
ties, PJM-G Group, and ABC Line Group flow
7000 distribution limit: 1500MW
330
PJM
PJM 8450 2. NYCA EA simultaneous import limit: 3,500 MW
WESTERN TIES
RECO H I CSC
425
MILLWOOD SOUTH 3. External areas representation based upon
515
information received from the NPCC CP-8 WG
DUNWOODIE Y49/
& Y49/Y50 Y50
GROUP
5643
CONED-
1000 4350 LIPA 1293 404
660 HTP 660
200 300 660 220 1613 Legend
550 105 Interface
PJMW PJM J2 J K Unidirectional Interface
BC LINES JAMAICA TIES
0 505 320
Interface w/ Dynamic Ratings
315 J3
660 500 315 815 660 Interface Group
315 134 Interface Group w/ Dynamic Ratings
LI WEST
315 Monitoring Interface Group
315
VFT NYCA EA Interface Group Marker
Note: NYCA load values represent baseline coincident summer peak demand.
Zones J and K load values represent non-coincident summer peak demand.
Aggregate Zones G-J values represent the G-J peak demand.
The LOLE is at or above the criterion of one day in 10 years, or 0.1 days per year, starting year 6
(2026) of the RNA Study Period, and increases through year 10 (2030). Therefore, the NYISO identifies
resource adequacy Reliability Needs starting in 2027 (with 2026 being at the 0.10 days/year criterion).
The deficiencies identified in this 2020 RNA are driven by the compound effect of increasing load
forecast (e.g., +495 MW in 2030) and loss of generation in Zone J (e.g., –1,372 MW in 2030) see Figure 50.
Compared to the 2019 - 2028 CRP, the system has less overall net resources. The Base Case models reflect
the application of the generator compliance plans for the DEC’s Peaker Rule to affected plants in New York
City (Zone J), Long Island (Zone K), and Hudson Valley (Zone G). In Figure 50, the negative net margin
shows deterioration in the relative capability to serve load, when comparing the assumptions in the two
studies.
Notes:
1. Includes the reductions due to projected energy efficiency programs, building codes and standards,
distribution energy resources and behind-the-meter solar photovoltaic power; it also reflects expected
impacts (increases) from projected electric vehicle usage.
2. Does not includes the total SCRs, and UDRs from the Gold Book.
“Perfect capacity” is capacity that is not derated (e.g., due to ambient temperature or unit
unavailability caused by factors such as equipment failures or lack of fuel), not subject to energy duration
limitations, and not tested for transmission security or interface impacts. Actual resources would need to
be larger in order to achieve the same impact as perfect-capacity resources.
The compensatory MW additions are not intended to represent specific solutions, as the impact of
specific solutions can depend on the type of the solution and its location on the grid. Rather, the
compensatory MW levels provide a generic order-of-magnitude measure to guide solutions. Resource
needs could potentially be met by combinations of solutions including generation, transmission, energy
efficiency, and demand response measures.
Following removal of the NYCA internal limits, the NYCA LOLE decreased to well below the criterion
throughout the Study Period. This result indicates that there is no statewide resource deficiency and that
transmission reinforcement to inject resources into Zone J is a potential option to resolve the identified
resource adequacy Reliability Need.
The results are in Figure 52 below, and indicate that transmission improvements can also eliminate
the LOLE violations.
17 No local transmission load area limits are modeled for the resource adequacy assessment – deficiencies at this local level are
identified in the transmission security assessments.
The NYISO performed additional topology limits variations to identify relieving which interfaces helps
the most. This information provides additional insights to support solutions development:
Increasing the transfer limits on the interface between Zones I and J only (I_to_J or Dunwoodie
South interface): An increase of 450 MW resolved the needs in 2030. This value is larger than
the identified Compensatory MW value of 350 MW because the I_to_J interface is not always
fully available due to partial outage states.
Modeling the I_to_J (Dunwoodie South) interface with no limit: The NYCA LOLE decreased to
0.05 days/year in 2030, which is close to the 0.04 days/year NYCA free flow result. This result
confirms that Zone J is the critical area in the GE-MARS analysis RNA Base Case, and that any
injection from any interface into Zone J would mitigate the resource adequacy zonal deficiency.
Beyond adding capacity or decreasing load in Zone J, increasing the interface limits into Zone J would
mitigate or fully address the resource adequacy deficiency. However, solutions would also need to address
the Zone J local18 transmission load area deficiencies identified in the transmission security evaluations.
18 No local transmission load area limits are modeled for the resource adequacy assessment – deficiencies at this local level are identified in the
transmission security assessments.
With full implementation of the Peaker Rule in 2025, several 345 kV circuits in the Con Edison
service territory would also be overloaded equating to a deficiency of 700 MW and increasing
to at least 1,075 MW by 2030. The duration of the deficiency ranges from nine hours in 2025
(3,853 MWh) to 12 hours in 2030 (7,672 MWh).
Similar transmission deficiencies would also occur within pockets of Con Edison’s non-bulk
system (138 kV), ranging in duration from 10 to 14 hours.
The system exceeds the LOLE criterion of one day in 10 years, or 0.1 days per year, starting in
2027, and increasing through 2030. Therefore, the NYISO identifies resource adequacy
Reliability Needs starting 2027.
The deficiencies identified in this 2020 RNA are driven by the compound effect of the
increasing load forecast (i.e., +495 MW in 2030) and loss of generation in Zone J (i.e., –1,372
MW in 2030).
19 No local transmission load area limits are modeled for the resource adequacy assessment – deficiencies at this local level are identified in the
transmission security assessments.
• The 2020 Gold Book High Load forecast were used for the resource adequacy analysis.
• Identification of the maximum level of zonal MW capacity that can be removed without
either causing NYCA LOLE violations, or exceeding the zonal capacity.
• Removal of proposed major transmission and generation projects assumed in the RNA
Base Case.
Additionally, the NYISO proposed to perform two exploratory scenarios, further detailed in Appendix E:
• Starting with the simplified external model described in footnote 20 and also in the
assumptions matrix in Appendix D, removing all load and generation from external
areas along with removing interfaces between external areas, followed by inserting
fixed amounts of capacity in each external area.
• The RNA Base Cases use historical load shapes from 2002, 2006, and 2007 for resource
20During the 2020 RNA, the External Areas Model for the RNA Base Case was simplified to consolidate five PJM (mid-Atlantic) areas into a single area
and eight ISO-NE areas into a single area.
The results of the scenarios 1-3 are summarized in the following sections; the exploratory scenarios 4
and 5 are in the Appendix E; the 70x30 scenarios are in Section 8 below.
Figure 53: 2020 Gold Book NYCA High Load vs. Baseline Summer Peak Forecast
Figure 55: 2020 RNA Resource Adequacy High Load Scenario NYCA LOLE Results
This scenario indicates that if expected energy efficiency and peak load reduction programs do not
materialize at expected levels, the criterion violations would be observed two years earlier, starting in
2025.
Scenario analyses were performed to determine the amount of capacity in each zone that could be
removed before the NYCA LOLE reaches 0.10 days/year, and offer another relative measure of how close
the system is from violating reliability criteria. This simulation is applicable to any RNA Study Years that
have LOLE levels that are below criterion, i.e., from 2024 through 2026. The NYISO reduced capacity one
zone at a time to determine when violations occur, in the same manner as the compensatory “perfect” MW
are added to mitigate resource adequacy violations, but with the opposite impact. The zonal resource
margin analysis is summarized in Figure 56.
Note: EZR - exceeds zonal resources (i.e., all generation can be removed without causing a violation)
The ZRAM assessment identifies a maximum level of capacity that can be removed from each zone
without causing NYCA LOLE criterion violations. However, the impacts of removing capacity on the
reliability of the transmission system and on transfer capability are highly location dependent. Thus, in
reality, lower amounts of capacity removal are likely to result in reliability issues at specific transmission
locations. The NYISO did not attempt to assess a comprehensive set of potential scenarios that might arise
from specific unit retirements. Therefore, actual proposed capacity removal from any of these zones would
need to be further studied in light of the specific capacity locations in the transmission network to
determine whether any additional violations of reliability criteria would result. Additional transmission
security analysis, such as N-1-1 analysis, would need to be performed for any contemplated plant
retirement in any zone.
Status-Quo Scenario
This scenario evaluates the reliability of the system under the assumption that no major transmission
or generation projects come to fruition within the RNA Study Period. This includes the removal of all
proposed transmission and generation projects that have met 2020 RNA Base Case inclusion rules and
removal of generators that require modifications to comply with the DEC’s Peaker Rule.
Figure 57: 2020 RNA Resource Adequacy Status-quo Scenario NYCA LOLE Results
From a resource adequacy perspective, this scenario indicates that if expected generation and
transmission projects are not built, the criterion violation advances by two years to 2025.
The steady state transmission security results show, as compared to the RNA base case, additional
overloads are observed under N-1-1 conditions in the Orange and Rockland and the Con Edison service
territories. No additional voltage issues were observed. The results of the steady state transmission
security N-1-1 evaluation of the BPTF for this scenario are shown in Figure 58.
Subsequent studies, such as this 2020 RNA scenario, as well as the Climate Change Impact and
Resilience Phase II Study, build upon the findings of the 2019 CARIS scenario, and provide further insight
focusing on system reliability aspects such as transmission security and resource adequacy.
As policymakers advance the implementation plan of the CLCPA, the NYISO assessments are intended
to complement their efforts, and are not intended to define the specific steps that must be taken to achieve
the policy goals. Additional refinements in assumptions, models, and methods in the following years will be
necessary as more information becomes available from policy implementation perspectives and simulation
methods and models perspectives.
Scope
This 70x30 Scenario consists of a series of cases to study the potential reliability impact of several
renewable energy mix and load levels assumptions. This study does not define the formula to calculate the
percentage of renewable energy relative to end-use energy, (i.e., how to account for 70% renewable energy
for the “70 by 30” target). As policymakers advance on the implementation plan of CLCPA, this NYISO
assessment is intended to complement their efforts, and is not intended to define the specific steps that
must be taken to achieve the policy goals. Instead, the findings are intended to provide insight into the
resource adequacy and transmission security reliability impacts of two load levels and their corresponding
renewable resources mix evaluated in the 2019 CARIS Phase I study. The goal of the analysis is to augment
the CARIS insights on congestion and curtailments with reliability perspectives.
1. Percentage of renewable energy relative to end-use energy: This study does not define the
formula to calculate the percentage of renewable energy relative to end-use energy, (i.e., how to
account for 70% renewable energy for the 70 by 30 or 70x30 target). Rather, two potential
renewable build-out levels were defined and modeled in the 2019 CARIS study, (and used in
this study), for corresponding load levels to approximate the potential future resource mix in
2030.
I. Siting and sizing: New renewable generators are modeled as interconnecting to 115 kV
or greater bus voltage levels, guided by the NYISO Interconnection Queue. There are
many alternative possible interconnection points, but this assessment assumes a single
approach for sizing and siting of renewable generation. Impacts of siting generators at
lower voltage buses are outside the scope of this study. Nevertheless, the NYISO
recognizes that constraints at the distribution level will affect the downstream
constraints, which may change the energy flows at the higher voltage level.
II. Operational constraints: Renewable resources are modeled as 8,760 hourly resource
shapes for the resource adequacy MARS simulations. These generation profiles are
synthetically generated resource shapes constructed using publicly available data and
tools. This deterministic modeling approach will not capture the uncertainty involved
with particular renewable resources.
Also, this analysis does not consider potential reliability impacts due to:
Unit commitment, ramp rate constraints, and other production cost modeling
techniques;
3. Transmission system modeling: These scenarios are not an interconnection level assessment
of the renewable buildouts, and do not review detailed engineering requirements, capacity
deliverability, or impact to the New York system reserve margin. Also, for the resource
4. External area representation: As the neighboring regions develop their own plans to achieve
higher renewable generation penetration, those regions’ demand, generation supply, and
transmission system may change. At the time of this report, the plans for NYISO’s neighboring
regions are taking shape. The external area representation remains consistent with the RNA
Base Case. An, exception is the HQ’s model, where import from Hydro Quebec (HQ) to Zone D is
modeled as a unit in MARS with hourly MW shape from the CARIS output into Zone D along
with the addition of a 1,310 MW proxy tie from Hydro Quebec (HQ) to Zone J. If the neighboring
areas increase their renewable generation, it is possible that the renewable curtailment
amounts assumed in the New York system from this analysis are underestimated.
5. COVID-19 impacts: Due to the rapidly evolving nature of the pandemic, the impacts to the load
forecast and other economic indicators are difficult to predict, and are not included in these
scenarios.
Assumptions
The RNA 70x30 Scenario assumptions are based on the 2019 CARIS 70x30 renewable resource mix
and associated load forecasts. The 2019 CARIS assumptions were based on the 2019 Gold Book, and used GE
MAPS for production cost simulations, and its findings are intended to provide insight of the extent to
which transmission constraints may prevent the delivery of renewable energy to New York consumers.
The RNA 70x30 Scenarios is intended to supplement the 2019 CARIS 70x30 analysis of congestion and
resource curtailment by providing insights on potential reliability impacts.
The 2019 CARIS 70x30 Scenario assessed two load levels labeled as ‘Base Load’ and ‘Scenario Load’
(described below). The production cost simulation utilized an hourly load profile for each of the load levels,
and the simulation output provided an hourly dispatch profile for the two renewable resource mixes. The
hourly dispatch profiles take into consideration transmission constraints that cause curtailments, as
identified and described in the 2019 CARIS report. That simulation output is utilized in this RNA scenario to
the resource adequacy and transmission security models, as applicable.
Load Assumptions
Two load models from the 2019 CARIS 70x30 Scenario are used for the RNA 70x30 Scenario:
1. ‘Base Load’, representing a higher energy shape (153 TWh) and a higher peak forecast
(31,303 MW); the 2002 load shape (8,760 hours) was scaled up to 2028 energy forecast
from the 2019 Gold Book. The same load shape was used for all MARS load levels; and
2. ‘Scenario Load’, representing lower energy shape (136 TWh) and a lower peak forecast
(25,312 MW); the CARIS-developed load shape was scaled to match CARIS 70x30 ‘Scenario
Load’ energy and peak demand forecast. The same load shape was used for all MARS load
levels.
Figure 59: Summer Energy and Peak Demand Forecast Zonal Distribution
Because the 2019 CARIS assumptions are based on the 2019 Gold Book, Figure 60 is a comparison of
the 2019 and 2020 Gold Book loads, for information.
Coincident peak demand is the projected zonal load during the date and hour of the NYCA system-wide
peak. The NYCA coincident peak typically occurs in late afternoon during July or August. Non-coincident
peak demand is the projected maximum load for each individual zone across a year or season.
70x30 'Base Load Case' (Nameplate MW) 70x30 'Scenario Load Case' (Nameplate MW)
Zone/Type OSW LBW UPV BTM-PV Zone/Type OSW LBW UPV BTM-PV
A - 2,286 4,432 995 A - 1,640 3,162 995
B - 314 505 298 B - 207 361 298
C - 2,411 2,765 836 C - 1,765 1,972 836
D - 1,762 - 76 D - 1,383 - 76
E - 2,000 1,747 901 E - 1,482 1,247 901
F - - 3,592 1,131 F - - 2,563 1,131
G - - 2,032 961 G - - 1,450 961
H - - - 89 H - - - 89
I - - - 130 I - - - 130
J 4,320 - - 950 J 4,320 - - 950
K 1,778 - 77 1,176 K 1,778 - 77 1,176
Total 6,098 8,772 15,150 7,542 Total 6,098 6,477 10,832 7,542
o Land-based wind (LBW): Hourly dispatch profiles (MWh shapes) are applied from CARIS
simulation output, including curtailments observed in the production simulation, for each of
the two load shapes. CARIS used the 2009 National Renewable Energy Laboratory (NREL)
hourly data as input.
o Off-shore wind (OSW): Hourly dispatch profiles (MWh shapes) are applied from CARIS
simulation output, including curtailments observed in the production simulation, for each of
the two load shapes. CARIS used the 2009 National Renewable Energy Laboratory (NREL)
hourly data as input.
o Utility-scale PV (UPV): Hourly dispatch profiles (MWh shapes) are applied from CARIS
simulation output, including curtailments observed in the production simulation, for each of
the two load shapes. CARIS used the 2017 production data for existing plants and the 2006
NREL hourly data for new plants as input.
o Behind-the-Meter PV (BtM PV): Hourly dispatch profile (MWh shapes) are applied from
CARIS simulation output, for each of the two load shapes. The CARIS behind-the-meter solar
profiles are based on hourly shapes created using NREL’s PV Watt tool.
Storage Assumptions
A four-hour battery storage is modeled in each NYISO zone, using the newly developed GE MARS
Energy Limited Resource Type 4 (EL4) model.21 The scenario assumes the same zonal MW distribution
modeled in the 2019 CARIS 70x30 scenario, as shown in the Figure 62 below. In these simulations, the EL4
units discharge their MW when the system is deficient, and recharge their energy when the system has an
excess of capacity. Units are modeled with a maximum energy discharge per day of four times their
maximum hourly discharge value. This paradigm allows the unit to discharge fully in four hours, or for
longer if not at full discharge. Also, at this time, only 100% roundtrip efficiency can be modeled in MARS,
which does not account for losses in charge/discharge cycle.
21 The MARS Energy Limited Resource type 4 (EL4) unit was introduced in the GE MARS version 3.29.1499 to better reflect battery behavior.
Zone MW
A 150
B 90
C 120
D 180
E 120
F 240
G 100
H 100
I 100
J 1,320
K 480
NYCA 3,000
External areas
PJM, Ontario and ISO-NE are modeled using same method as 2020 RNA Base Case. Imports from Hydro
Quebec (HQ) to Zone D are modeled as a generator in MARS with an hourly MW shape from the CARIS
output. Consistent with the CARIS assumptions, the model for this 70x30 Scenario includes a generic HVDC
tie from HQ directly to Zone J, capable of 1,310 MW. The generic HVDC tie is modeled as a generator in
MARS with an hourly MW shape from the CARIS output.
These initial resource adequacy simulations did not identify a measurable LOLE in either the ‘Base
Load’ or ‘Scenario Load’ 70x30 cases. This result occurs because large amounts of additional renewable
generation were modeled to meet the 70% energy goal, while retaining in the models the existing fossil fuel
Figure 63 and Figure 64 below show the resource mix for the two load levels with the renewables
added and no fossil removal.
Figure 63: Resource Mix in the 70x30 Figure 64: Resource Mix in the 70x30
‘Base Load’ Case before Capacity Removal ‘Scenario Load’ Case before Capacity Removal
Hydro
7%
Fossil Wind
38% 24%
Solar
24%
Pumped
Storage
2% Nuclear
5%
A Zonal Resource Adequacy Margin (ZRAM) analysis: ZRAM analysis identifies the amounts of
generic “perfect capacity” resources that can be removed from a zone while still meeting the
LOLE criterion. “Perfect capacity” is capacity that is not derated (e.g., due to ambient
temperature or unit unavailability caused by factors such as equipment failures or lack of fuel),
not subject to energy duration limitations, and not tested for transmission security or interface
impacts. Actual resources would need to be larger in order to achieve the same impact as
perfect-capacity resources.
An age-based retirement analysis where fossil units are removed from the model, starting with
the oldest, until the New York system is at LOLE criteria. This age-based approach is a simple
analytical approach as a proxy to represent unit retirements that may occur as surplus
resources increase. In reality many factors will affect specific generator status decisions.
Cases NYCA LOLE ZONE A ZONE B ZONE C ZONE D ZONE E ZONE F ZONE G ZONE H ZONE I ZONE J ZONE K
Base Case 0.19 ∞ ∞ ∞ ∞ ∞ ∞ ∞ ∞ ∞ 350 ∞
70x30 Base Load Case 0.00 -2,400 EZR -5,200 -1,750 EZR -7,200 -5,400 EZR EZR -1,500 -1,250
70x30 Scenario Load Case 0.00 -3,550 EZR -5,550 -1,750 EZR EZR EZR EZR EZR -4,200 -1,400
Notes:
• Negative numbers indicate the amount of MW that can be removed from a zone (one zone at a time in this case) without
causing a violation. For instance, NYCA LOLE reaches 0.1 days/year when 1,500 MW of “perfect capacity” is removed from
Zone J in the ‘Base Load’ Case.
• EZR - exceeds zonal resources: i.e., all generation from the respective zone can be removed without causing a NYCA LOLE
violation.
• The generation pockets in Zone J and Zone K are not modeled in detail in MARS, and the values identified here may be
larger as a result.
The ZRAM analysis results show that many of the zones in the NYCA can have all internal resources
removed without causing a violation of the LOLE criterion (i.e., those labeled ‘EZR’), a result pointing to the
large renewable additions upstate.
Figure 66: Fossil Removal Based on 70x30 ‘Base Load’ Scenario Cases
Notes:
• Case 67: most, but not all units 67 and older were retired in this case.
• Case 67*: a special evaluation of Case 67 where the marginal unit was derated, instead of fully removed, to obtain an
LOLE closer to 0.1 days/year.
The age-based analysis for the ‘Base Load’ scenario identifies that the removal of generators at least 67
years old would reduce the total capacity by 2,951 MW, which would exceed the LOLE criterion. An
additional analysis was performed to bring the LOLE closer to the 0.1 days/year criterion by derating the
capacity of the marginal unit (Case 67*), which identifies that the NYCA will exceed the LOLE criterion once
2,801 MW have been removed from the system, of which 1,804 MW is from Zone J. The age-based fossil
removal method has the effect to primarily remove the units from Zones J and K, accelerating the rate of
LOLE reaching its criterion violation. Because Zone J is driving the LOLE at criterion, and not upstate
generation, additional fossil generation can be removed from the upstate zones without affecting the LOLE
at criterion.
Figure 67: NYCA Resource Mix in 70x30 ‘Base Load’ Case at Criterion
Hydro
7%
Fossil Wind
35% 25%
Solar
Pumped 25%
Storage
2% Nuclear
6%
Figure 68: Zone J Resource Mix in 70x30 ‘Base Load’ Figure 69: Zone K Resource Mix in 70x30 ‘Base
Case at Criterion Load’ Case at Criterion
Wind
Wind
40% 34%
Fossil Fossil
60% 64%
Solar
1%
Figure 70 shows a comparison between the total installed capacity and unforced capacity for 70x30
Base Load case when the system is close to LOLE criterion. To bring the model to criterion, approximately
2,800 MW of fossil generation were removed resulting in an installed capacity margin of 191.8%,
equivalent to an unforced capacity margin of 114%. Out of 2,800 MW, approximately 1,800 MW were
removed from Zone J, resulting in installed capacity margin of 92% in Zone J, equivalent to unforced
capacity margin of 61%.
Total capacity in the 70x30 model before age-based removal2 62,837 38,322
Total thermal capacity in the 70x30 model before age-based removal 27,165 25,444
Total fossil units in the 70x30 model before age-based capacity removal 23,822 22,175
Total nuclear in the 70x30 model before age-based capacity removal 3,343 3,269
Age-based fossils removed to get to 0.1 LOLE ("model at criterion") 3 2,801 2,629
Total capacity ("model at criterion") 60,036 35,693
Capacity/ Load Ratio 191.8% 114.0%
NY_J Totals
Load (net of BtM Solar) 11,589 11,589
Total capacity in 70x30 Case 12,510 8,761
Total fossil units in 70x30 model before age-based fossil removal 8,190 7,602
Age-based fossils removed to get to 0.1 LOLE ("model at criterion")3 1,804 1,701
Total capacity ("model at criterion") 10,706 7,060
Capacity/Load Ratio 92.4% 60.9%
NY_K Totals
Load (net of BtM Solar) 4,730 4,730
Total capacity in 70x30 Case 5,782 4,400
Total fossil units in 70x30 model before fossil removal 3,962 3,745
Age-based fossils removed to get to 0.1 LOLE ("model at criterion") 3 602 579
Total capacity ("model at criterion") 5,180 3,821
Capacity/Load Ratio 109.5% 80.8%
Notes
1. UCAP calculation:
For thermal units, MARS EFORd data is used.
For renewables, UCAP is calculated based on the average output during peak hours.
2. Reflects additional peaker removal in Zone K.
3. Calculated based on 70x30 ‘Base Load’ Case 67.*
Figure 72, Figure 73 and Figure 74 below show the resource mix for NYCA, Zone J and Zone K
respectively, with the renewables added and fossil removal until an LOLE violation results for 70x30
Scenario Load case. The fossil generation percentages are calculated based on minimum between CRIS and
DMNC, while solar and wind generation are based on nameplate rating.
Figure 72: NYCA Resource Mix in 70x30 ‘Scenario Load’ Case at Criterion
Hydro
10%
Fossil
26%
Wind
29%
Pumped
Storage
3% Solar
25%
Nuclear
8%
Figure 73: Zone J Resource Mix in 70x30 ‘Scenario Figure 74: Zone K Resource Mix in 70x30 ‘Scenario
Load’ Case at Criterion Load’ Case at Criterion
Fossil Fossil
Wind
45% 42%
Wind 56%
55%
Solar
2%
Figure 75 shows a comparison between the total installed capacity and unforced capacity for 70x30
Scenario Load case when the system is close to LOLE criterion violation. To bring the model to criterion,
Figure 75: 70x30 ‘Scenario Load’ Load and Capacity Totals, ICAP vs UCAP
Notes
1. UCAP calculation:
• For thermal units, MARS EFORd data is used.
• For renewables, UCAP is calculated based on the average output during peak hours.
2. Reflects additional peaker removal in Zone K.
3. Calculated based on 70x30 ‘Scenario Load’ Case 38.
Figure 76: Nuclear Retirement Sensitivity based on 70x30 “Base Load” Case
Notes:
• Case 67: most, but not all units 67 and older were retired in this case.
• Case 67*: a special evaluation of Case 67 where the marginal unit was derated instead of fully removed
to obtain an LOLE closer to 0.1 days/year.
• **3,343: the amount of nuclear MW removed in the sensitivity.
Observations:
The removal of the nuclear units did not significantly affect the LOLE results on the case before the
age-based fossil removals, because the addition of upstate renewable resources outweigh the loss
of nuclear capacity.
The results previously identified in the age-based retirement analysis on the ‘Base Load’ case were
effectively unchanged by the removal of the nuclear units. Specifically, the 3,343 MW of retirement
of the upstate nuclear units does not significantly impact the NYCA LOLE results because the needs
are driven by downstate capacity deficiencies. It is important to note that other benefits of existing
generation, such as voltage and stability support, were not captured in this resource adequacy
simulation.
NYCA meets the LOLE criterion with 5,918 MW removed, of which 2,575 MW fossil (5,918 - 3,343 =
2,575).
NYCA exceeds the LOLE criterion when 6,144 MW are removed (at 67*), of which 3,343 MW are
nuclear units, and 2,801 MW are fossil-fueled units.
Observations:
NYCA meets the LOLE criterion in 2030 with 14,282 MW of existing generation removed.
• 14,282 – 3,343 nuclear = 11,170 MW fossil removed with nuclear units out of service,
versus 11,264 MW fossil removed when nuclear units are modeled in service.
As a result of the removal of nuclear units, the removal of 14,513 MW of thermal generation would
exceed the LOLE criterion. Of that amount, 11,170 MW is from fossil fuel generators.
For each of the two load cases, with the model at the LOLE criterion, the NYISO added storage based on
the zonal distribution utilized in the CARIS 70x30 Scenario, and recalculated the NYCA LOLE to determine
impact on resource adequacy.
Figure 78 identifies the amount of fossil fuel generation that is removed from the system to exceed the
LOLE criterion.
Note: the values in this table should not be used to approximate the Effective Load Carrying Capability (ELCC) of storage
resources because the analysis was not conditioned to perform this type of analysis.
On the ‘Base Load’ cases, the benefit of the energy storage resources is limited to around 250 MW (i.e.,
with additional storage, and with or without the existing nuclear units, around 260 MW of additional fossil
can be removed to reach NYCA LOLE violation).These effects occur mainly because of the location of the
capacity shortfalls (in Zones J and K), due to the storage resource allocation (1,320 MW in Zone J and 480
MW in Zone K), and due to the duration of the events, with many longer than four hours.
For the Scenario Load cases, the energy storage resources have additional benefits. Specifically, with
existing nuclear units in-service, and the additional storage resources in service, approximately 800 MW of
additional fossil can be removed to reach LOLE violation. With existing nuclear units out of service, and the
additional storage resources in service, approximately 380 MW of additional fossil can be removed to reach
LOLE violation.
An additional simulation was performed to gauge the impact of using an eight-hour EL4 model on the
‘Base Load’ scenario. When comparing with the four-hour model, a lot more (e.g. approximately 1,450 MW
for this specific simulation) fossil generation is removed until the LOLE criterion is exceeded. Results are
shown in the Figure 79 below.
To better quantify the locational benefit of energy storage resources, a simulation was performed on
the Base Load case that evaluated only modeling the Zone J resources. The results are consistent with those
in Figure 78, indicating that for the modeled system energy storage resources are most effective in Zone J.
This result is driven largely by the location of unit retirements in this scenario.
The use of non-curtailed renewables does not significantly affect the resource adequacy results. This
output demonstrates that alleviating the local constraints that caused the curtailments, while beneficial
from an annual energy production perspective as shown in CARIS, does not offset the need for dispatchable
generation to meet reliability requirements at peak load.
Case Load (Net Load including BtM solar Land-Based Wind Off-Shore Wind Solar
Case #
reductions, MW) (% of Pmax) (% of Pmax) (% of Pmax)
1 Day Peak Load (30,000) 10 20 45
2 Evening Peak Load (31,100) 0 0 0
3 Light Load (12,500 MW) 15 45 0
4 Light Load (12,500 MW) 0 0 0
5 Shoulder Load (21,500 MW) 0 0 40
6 Shoulder Load (21,500 MW) 15 45 40
The age-based fossil removals for the Base Load resource adequacy scenario, with no energy storage
resources (ESR), are also modeled in this assessment, including the removal of units that were in service
prior to January 1, 1963. This removal amounts to a total of 2,586 MW summer capability. The 2,586 MW
removal is utilized in the transmission security analysis, as it is the last point of generation removal prior to
observing resource adequacy LOLE violations.
The pairings of similar load levels (e.g., Cases 1 & 2, Cases 3 & 4, and Cases 5 & 6) with different levels
of renewable resource penetration shows that a balance in load and generation is achievable (i.e., the case
was able to match load plus losses with the available generation under N-0). While transmission security
analysis for this assessment does not consider an 8,760-hour type of load and generation variety, the six
cases considered cover, within reasonable bounds, load levels that can be seen for many hours. For all
cases (except Case 2), the renewable generation mix shown in Figure 80 was selected based on
observations from the CARIS 70x30 ‘Base Load’ results for similar load levels. Case 2 reflects the potential
for an evening peak load assuming no MW output from the wind and solar resources. The evening peak
load reflects approximately 93% of the peak load observed during the day peak with no output from the
behind-the-meter solar. For this assessment, after peaker generation removals and age-based removals,
both 10-minute and 30-minute operating reserve levels were maintained by utilizing the remaining
synchronous generation.
Case 1 and Case 2 result in N-1 thermal loading criteria violations. These violations are observed on
the Rainey 345/138 kV (8W) (both Case 1 and Case 2) and the Rainey 345/138 kV (8E) (Case 1 only)
transformers. These violations are primarily driven by local load pocket deficiencies created by the age-
based generation removals. No N-1 thermal loading criteria violations are observed in Cases 3, 4, 5, or 6.
Case 1 and Case 2 have N-1-1 thermal loading criteria violations. These violations are summarized in
Figure 81. In addition to the transmission security issues observed in the RNA Base Case, overloads are
The thermal loading issues indicate transmission constraints that may occur with high renewable
output, as well under peak load conditions without these resources. To secure the transmission system,
additional dispatchable resources would be needed. To maintain system transmission security,
approximately 750 MW of dispatchable resources would be needed in addition to the 24,700 MW of
dispatchable resources remaining in the model (i.e. after age-based removals and peakers). This
assessment did not consider the potential duration of the deficiencies or the sudden loss of all off-shore
wind. Rather, contingency events for renewable resources only considered loss of resources due to
electrical faults. For all cases, the NYISO locational reserves requirements were achieved by utilizing
dispatchable generation.
1. Adding renewables: The NYCA system represented in cases with the renewable resource mix
added is reliable with a significant surplus of resources when not taking into consideration
potential retirements.
2. Surplus generation: Depending on load, approximately 10% (70x30 Base Load) - 45% (70x30
Scenario Load) of fossil plants could be removed before exceeding LOLE criterion. The age-
based approach to remove fossil plants results in concentrating the removal in zones that had
the least amount of generation surplus. The total fossil removal also depends on other factors
such as unit unavailability, maintenance and location.
3. Nuclear sensitivity: Retirement of nuclear plants would result in less surplus capacity and
therefore more conventional generation (currently fossil-fueled) would need to be retained in
order to maintain a reliable system.
4. Energy storage resources: Energy storage resources may provide a benefit to the system
from a reliability standpoint by assisting in meeting peak load (subject to limitations identified
in this report), thus allowing for additional fossil units to be retired. Resources with a duration
longer than four hours would provide additional benefit to the system.
5. Curtailments due to local constraints: Alleviating the local transmission constraints that
cause renewable curtailments, while beneficial from an annual energy production perspective
as shown in CARIS, would not significantly offset the need for conventional generation to meet
system demands reliably.
6. Dispatchable generation: Even with a high output from intermittent renewable resources,
there is still a need for significant amounts of dispatchable generation to meet reliability
requirements at various times throughout the year, including peak load. Dispatchable
resources would be needed to fill the gaps created when intermittent renewable resources are
not producing energy. Even with a large amount of installed capacity of renewable resources,
there would still be a need for significant dispatchable generation to meet reliability
requirements at various times throughout the year, including peak load. To maintain system
7. Additional Resource Adequacy Considerations: The resource adequacy simulations did not
consider potential reliability impacts due to:
Unit commitment, ramp rate constraints, and other production cost modeling
techniques.
8. Transmission security thermal considerations: Thermal loading issues are observed in the
peak load case with a high penetration of land-based wind, off-shore wind, and solar, as well as
in a peak case without these resources. Dispatchable resources beyond those identified in
resource adequacy would be needed in the downstate area to address thermal reliability
criteria violations.
The NYISO will continue to monitor and track system changes. Subsequent studies, such as the
Comprehensive Reliability Plan, the Climate Change Impact and Resilience Study, and future economic and
public policy planning studies will build upon the findings of this 70x30 Scenario. To inform policymakers,
investors and other stakeholders as implementation unfolds, these forward-looking studies will provide
further assessment of the CLCPA.
The purpose of the NERC Reliability Standards is to “define the reliability requirements for planning
and operating the North American bulk power system and are developed using a results-based approach
that focuses on performance, risk management, and entity capabilities.” The objective of NPCC Directory #1
and the NYSRC Reliability Rules and Compliance Manual are to provide a “design-based approach” to
design and operate the bulk power system to a level of reliability that will not result in the loss or
unintentional separation of a major portion of the system from any of the planning and operations
contingencies with the intent of avoiding instability, voltage collapse and widespread cascading outages.
Figure 82 shows the various NERC Standards with requirements applicable to the NYISO as a NERC
registered Planning Coordinator and/or Transmission Planner. The NPCC planning compliance obligations
are primarily located in NPCC Regional Reliability Reference Directory #1 Design and Operation of the Bulk
Power System. The NYSRC planning compliance obligations are located in the Reliability Rules and
Compliance Manual.
Fundamental to any reliability study is the accuracy modeling data provided by the entities
responsible for providing the data. The data requirements for the development of the steady state,
dynamics, and short circuit models is provided in the NYISO Reliability Analysis Data Manual (RAD
Manual).23 This data primarily comes from compliance with NERC MOD standards. Much of this data is
collected through the annual database update process outlined in the RAD Manual and the annual FERC
Form 715 filing to which the transmitting utilities certify, to the best of their knowledge, the accuracy of the
22 https://www.nyiso.com/planning-reliability-compliance
23 https://www.nyiso.com/documents/20142/2924447/rel-anl-data-mnl.pdf
Following the completion of the annual database update, these databases are used for study work such
as the Reliability Planning Process, and for many other compliance obligations such as those listed in
Figure 82. Planning studies similar to the Reliability Planning Process include the NPCC/NYSRC Area
Transmission Reviews (ATRs) and the NERC TPL-001 assessments.
Figure 82: List of NERC Standards for Planning Coordinators and Transmission Planners
The first assessment evaluates the steady state and dynamics transmission security. For instances
where the transmission security assessments results indicate that the planned system does not meet the
specified criteria, a corrective action plan is incorporated to achieve conformance. As part of the ATRs, and
also for compliance with NERC FAC-013, thermal, voltage, and stability transfer limits are performed to
identify the limiting constraints for power transfers. The most resent ATR found no steady state or
dynamics transmission security criteria violations.
For the second assessment, steady state and dynamics analysis are conducted to evaluate the
performance of the system for low probability extreme contingencies. The purpose of the extreme
contingency analysis is to examine the post contingency steady state conditions, as well as stability,
overload, cascading outages, and voltage collapse, to obtain an indication of system robustness and to
determine the extent of any potential widespread system disturbance. In instances where the extreme
contingency assessment concludes there are serious consequences, the NYISO evaluates implementing a
change to design or operating practices to address the issues.
The extreme contingency analysis included in the most recent ATR concludes that the system
remained stable during most events and showed no thermal overloads over short-term emergency (STE)
ratings or significant voltage violations on the BPTF. For the events that did show voltage, thermal, or
dynamics issues, these events were local in nature (loss of local load or reduction of location generation)
24 https://www.nyiso.com/planning-reliability-compliance
25 https://www.nyiso.com/documents/20142/1397660/2019-NYISO-Interim-ATR-Final.pdf
The third assessment evaluates extreme system conditions that have a low probability of occurrence
such as high peak load conditions (e.g., 90th percentile load) resulting from extreme weather or the loss of
fuel supply from a given resource (e.g., loss of all gas units under winter peak load). The extreme system
conditions evaluate various design criteria contingencies to evaluate the post contingency steady state
conditions, as well as stability, overload, cascading outages and voltage collapse. The evaluation of extreme
contingencies indicate system robustness and determine the extent of any potential widespread system
disturbance. In instances where the extreme contingency assessment concludes that there are serious
consequences, the NYISO evaluates implementing a change to design or operating practices to address the
issues. For the extreme system conditions evaluated in the most recent ATR, the assessment found no
steady state or dynamics transmission security criteria violations.
The fourth assessment evaluates the breaker fault duty at BPTF buses. The most recent ATR found no
over-dutied breakers on BPTF buses.
The fifth assessment evaluates other requirements specific to the NYSRC Reliability Rules including an
evaluation of the impacts of planned system expansion or configuration facilities on the NYCA System
Restoration Plan and Local Area Operation Rules for New York City Operations, loss of gas supply – New
York City, and loss of gas supply – Long Island.
The sixth assessment is a review of Special Protection Systems (SPSs). This review evaluates the
designed operation and possible consequences of failure to operate or mis-operation of the SPS within the
NYCA.
The seventh assessment is a review of requested exclusions to the NPCC Directory #1 criteria.
The required system conditions to evaluate for this assessment include planned system
representations over a 10-year study period for a variety of system conditions. Figure 83 provides a
description of the steady state, dynamics, and short circuit cases required to be evaluated in the Planning
Assessment.
The steady state and dynamics transmission security analyses evaluate the New York State BES to
meet the applicable criteria. As part of this assessment, the unavailability of major transmission equipment
with a lead time of more than a year is also assessed. The fault duty at BES buses are evaluated in the
short-circuit representation. When the steady state, dynamics, or short circuit analysis indicates an
inability of the system to meet the performance requirements in the standard, a corrective action plan is
developed addressing how the performance requirements will be met. Corrective action plans are
reviewed in subsequent Planning Assessments for continued validity and implementation status.
For each steady state and dynamics case, the Planning Assessment evaluates the system response to
extreme contingencies. Similar to the ATR, when the Planning Assessment extreme contingency analysis
concludes there is cascading caused by an extreme contingency, the NYISO evaluates possible actions
designed to reduce the likelihood or mitigate the consequences and adverse impacts.
The most recent NERC Planning Assessment for compliance with TPL-001 was completed in June
2020. As this study contains Critical Energy Infrastructure Information (CEII), it is not posted on the NYISO
website. Generally, the results of this study are consistent with the ATR studies. Given that the study scope
of this assessment is different from the ATR is different (because the ATR evaluates the BPTF while the TPL
evaluates the BES), criteria violations were observed. The corrective action plans for criteria violations are
generally addressed in the affected Transmission Owner’s LTP and/or the proposed transmission facilities
listed in Section 7 of the Load and Capacity Data Report.
NYSRC Reliability Rules have recently added a requirement26 that the NYISO deliver a Long Term
Resource Adequacy Assessment report every RNA year, and an annual update in the non-RNA years. The
NYISO will first implement this requirement after finalizing the 2020 RNA.
The NYISO is also actively involved in other activities such as the NERC’s annual Long Term Reliability
Assessment (LTRA), along with its biennial Probabilistic Assessment (ProbA), performed by NERC with the
input from all the NERC Regions and Areas, as well as NPCC’s Long Range Adequacy Overview (LROA).
The NYISO is forecasting higher growth in energy usage, which can be attributed in part to the
increasing impact of electric vehicle usage and other electrification (i.e., conversion of home heating,
cooking, water heating, and other end-uses from fossil-fuel based systems to electric systems) especially in
the later years of the planning horizon. Significant load-reducing impacts are expected to occur due to
energy efficiency initiatives and the growth of distributed behind-the-meter energy resources, such as solar
PV. The relative behind-the-meter solar impact on peak declines over time as the summer peak is expected
to shift slightly further into the evening.
The NYISO has initiated a number of assessments of the impacts of various policies, including:
• 2019 Congestion Assessment and Resource Integration Study (“CARIS”), Phase I – The
NYISO’s congestion assessment under the Economic Planning Process. The recent study
contains a 70x30 scenario; one of the key findings is that renewable generation pockets are
likely to develop throughout the state as the existing transmission grid would be overwhelmed
by the significant renewable capacity additions. The results support the conclusion that
additional transmission expansion, at both bulk and local levels, will be necessary to efficiently
deliver renewable energy to New York consumers.
• Climate Change Study Phase I: Long Term Load Impacts – This study was performed by the
NYISO in collaboration with Itron. The core finding is that temperatures are rising across New
York and will have a significant impact on electric grid demand.
• Climate Change Study Phase II: Reliability and Resiliency - The NYISO retained the Analysis
Group (AG) to develop/analyze resource mixes to serve load under the CLCPA 2040 state goals
and then analyze various climate change-related scenarios that could impact the electric
system. One reasoned approach to gain an understanding of the challenges that may be faced
was to develop book-end type resource mixes where one of the key variables is increasing the
• Reliability and Market Considerations For A Grid In Transition: The NYISO initiated a white
paper followed by assessments focusing on potential market enhancements. The NYISO
supports reliability through three complementary markets: energy, ancillary services, and
capacity. Each market addresses distinct reliability needs through competitive market pricing
that benefits New York consumers while reducing costs. Together, energy, ancillary services,
and capacity market revenues provide economic signals for new investment, retirement
decisions, and participation by demand response providers. The Grid in Transition looked into
how the wholesale markets in New York can continue to provide the pricing and investment
signals necessary to reflect system needs and to incent resources capable of resolving those
needs.
In addition to these NYISO initiatives, the State of New York is engaging in its own analysis of the
future needs of the electric transmission system. The Accelerated Renewable Energy Growth and
Community Benefit Act (the “Act”)27 enacted in 2020 calls for the New York State Department of Public
Service (DPS) to “undertake a comprehensive study for the purpose of identifying distribution upgrades,
local transmission upgrades, and bulk transmission investments that are necessary or appropriate to
facilitate the timely achievement of the CLCPA targets.”28 The Act states that the DPS will conduct that
■ Maintaining ability to balance load and generation: Balancing high levels of intermittent
generation with system demand that may be difficult to forecast in
real-time operations.
■ Maintaining 10-minute operating reserves: High levels of intermittent resources may result
in challenges to maintaining sufficient 10-minute operating reserves and disturbance-control
performance requirements.
■ Maintaining total 30-minute operating reserves: High levels of intermittent resources may
lead to challenges in meeting operating reserve requirements in response to longer-term
variations in generation levels from intermittent generation.
■ Maintaining black start capability: The NYISO may be challenged to effectively restore the
system within expected timeframes following a blackout given a system with high levels of
intermittent generation.
■ Maintaining voltage support capability: The NYISO may be challenged to meet voltage
performance requirements with high levels of intermittent generation.
■ Maintaining frequency response capability: The NYISO may be challenged to meet frequency
performance requirements for a power system with high levels of intermittent generation.
29 Id.
■ Maintaining the ability to manage supply resource outage schedules: The NYISO may be
challenged to manage supply resource maintenance outage scheduling.
These concepts will continued to be explored in the 2021-2030 Comprehensive Reliability Plan and
numerous other reliability studies in the near future. None of the identified potential reliability gaps
relative to intermittent resources represent near-term concerns. However, the challenge for the NYISO is to
design and implement a portfolio of market products, reliability planning, and operational enhancements
that facilitate achievement of clean energy policies while maintaining system reliability through the
competitive wholesale electricity markets. There may also be a need for review of established reliability
criteria to address reliability gaps that may arise due to the changing system operating characteristics as
New York transitions to a zero emission resource mix.
This 2020 Reliability Needs Assessment finds that there are Reliability Needs on the Bulk Power
Transmission Facilities during the Study Period due to both resource adequacy and transmission security
reliability criteria violations. The deficiencies identified are mainly due to the compound effect of load
forecast increases and the assumed loss of generation in Zone J (New York City), affected by the
Department of Environmental Conservation’s (DEC’s) Peaker Rule.
In 2020, the New York State Department of Environmental Conservation adopted a regulation to limit
nitrogen oxides (NOx) emissions from simple-cycle combustion turbines (“Peaking Units”) (referred to as
the “Peaker Rule”). The Peaker Rule required all impacted plant owners to file compliance plans by March
2, 2020. NYISO considered the affected Generators’ compliance plans in the development of the 2020
Reliability Needs Assessment Base Case.
From the resource adequacy perspective, the Loss of Load Expectation (LOLE) is at or above New York
State Reliability Council’s (NYSRC’s) and Northeast Power Coordinating Council’s (NPCC’s) criterion of one
day in 10 years, or 0.1 days per year, starting in year 6 (2026) of the RNA Study Period, and increasing
through year 10 (2030). Therefore, the NYISO identifies resource adequacy Reliability Needs starting in
2027, with the year 2026 being at the resource adequacy criterion with an LOLE of 0.10 days/year.
The transmission security Reliability Needs include both thermal loading criteria violations on the
BPTF as well as dynamic stability criteria violations. For thermal loading, several 345 kV circuits in the Con
Edison service territory are overloaded under N-1-1 conditions beginning in year 2025 and increasing
through 2030. Additionally, the Con Edison 345 kV system has violations of an NYSRC local reliability rule
to design and operate 345 kV transmission system for the occurrence of a second contingency (N-1-1-0).
The 345 kV circuit overloads under N-1-1-0 conditions in Zone J begin in 2025 (with a deficiency of 700
MW) and increasing through 2030 (with a deficiency of 1,075 MW). The duration of the deficiency ranges
30 In 2019 the NYISO proposed to stakeholders creating a Short-Term Reliability Process (“STRP”) to evaluate and address reliability impacts
resulting from both Generator deactivations and other drivers of Reliability Needs that are identified in a quarterly Short-Term Assessment of
Reliability study. The NYISO made a tariff filing at FERC to create the STRP in February 2020, requesting a May 1, 2020 effective date. The FERC
accepted the NYISO filing on April 30, 2020, and the first quarterly STAR commenced on July 15, 2020. The 2020 RNA also incorporates the effects
of these tariff changes by assessing Reliability Needs in years 4-10 of the Study Period, while the STRP assesses five years from its start date, with a
focus on addressing needs in years 1-3 of the Study Period.
The dynamic stability criteria Reliability Needs are observed for the entire Study Period. The criteria
violations include violations of transient voltage response, loss of generator synchronism, and undamped
voltage oscillations. The transient voltage response violations arise on transmission facilities owned by Con
Edison in its Transmission District but extending into areas adjacent to their service territory. The loss of
generator synchronism is observed in generators within or near the Astoria and Greenwood load pockets
and is primarily driven by the transient voltage response violations in the local area.
In addition, the 2020 Reliability Need Assessment analyzes risks to the BPTF under certain scenarios to
inform NYISO stakeholders when developing projects, as well as informing policy makers when
formulating state policy.
The results of the 2020 Reliability Need Assessment scenarios indicate that a higher load level, or
proposed projects assumed in service in the Reliability Need Assessment Base Case not materializing, or
additional removal of capacity, could cause additional Reliability Needs, or Reliability Needs that occur
earlier.
In addition to the above-referenced scenarios, the NYISO also discusses the reliability risks associated
with the cumulative impact of environmental laws and regulations, which may affect the flexibility in plant
operation and may make fossil-fueled plants energy-limited resources.
A number of recent state policies and initiatives, along with various Department of Environmental
Conservation rulemakings are underway that have the potential to significantly change the resource mix in
the New York Control Area. These include the Climate Leadership and Community Protection Act (CLCPA),
the Accelerate Renewable Energy Growth and Community Benefit Act, the Clean Energy Standard, the
Offshore Wind Master Plan, the Large-Scale Renewable Program, the Zero Emission Credits Program for the
James A. FitzPatrick, R.E Ginna and Nine Mile Point nuclear power plants, and the implementation of the
DEC Peaker Rule. The NYISO will continue to monitor these and other developments to determine whether
changing system resources and conditions could impact the reliability of the Bulk Power Transmission
Facilities.
As part of its ongoing Reliability Planning Process, the NYISO monitors and tracks the progress of
market-based projects and regulated backstop solutions, together with other resource additions and
retirements, consistent with its obligation to protect confidential information under its Code of Conduct.
Among other things, the NYISO closely follows: 1. units interconnecting through the NYISO’s
interconnection processes; 2. the development and installation of local transmission facilities; 3. additions,
RNA Base Case Update: Following NYISO Board approval, additional steps are taken to further
minimize unnecessary solicitations. The process allows the NYISO to update the RNA Base Case by
considering status changes of proposed projects such as Local Transmission Owner Plans (LTPs), proposed
generation and transmission, and load forecast or demand response. As part of this step, the NYISO would
consider only those updates that may reduce or eliminate the Reliability Needs and that met the inclusion
rules. This would include any updates to the peak load forecast based on the NYISO’s current
understanding of residual impacts from COVID-19.
Solution Solicitation and Initial Review: If any Reliability Needs remain after these Base Case
updates, the NYISO will solicit market-based solutions, regulated backstop solutions, and alternative
regulated solutions to address the remaining Reliability Needs. The interested and qualified Developers
and Other Developers, as well as the Responsible Transmission Owner(s) can submit solutions within 60
calendar days from the solicitation. The Responsible Transmission Owner(s) must submit regulated
backstop solution(s) to address the Reliability Needs identified in their service territory, which can be
generation, transmission, demand side or combinations. Any Transmission Owner or Other Developer can
submit an alternative regulated solution and any Developer can submit a market-based solution. The
NYISO will review the solutions for completeness.
Viability and Sufficiency Assessments: The NYISO will evaluate whether each proposed solution is
viable and is sufficient to satisfy the identified Reliability Need by the need date. The proposed solutions
may include multiple components and resource types. When evaluating proposed solutions to Reliability
Needs from any Developer, all resource types – generation, transmission, demand response, or a
combination of these resource types – will be considered on a comparable basis as potential solutions to
the Reliability Needs identified. All solutions will be evaluated in the same general timeframe.
Establishment of Trigger Date of Proposed Regulated Solutions: Upon receipt of all proposed
regulated solutions pursuant to OATT Section 31.2.5.1, the NYISO will notify all Developers if any
Developer has proposed a lead time for the implementation of its regulated solution that could result in a
Viability and Sufficiency Report: The NYISO will present its Viability and Sufficiency Assessment to
stakeholders, interested parties, and the NYDPS for comment and will indicate at that time whether any of
the proposed regulated solutions found to be viable and sufficient will have a Trigger Date within 36
months of the date of the NYISO’s presentation of the Viability and Sufficiency Assessment to the ESPWG.
Evaluation and Selection of Proposed Regulated Transmission Solutions: If the NYISO determines
that the Trigger Date of any Developer’s proposed regulated solution that was found to be viable and
sufficient will occur within 36 months of the date of the NYISO’s presentation of the Viability and
Sufficiency Assessment to the ESPWG, the NYISO will request that all Developers of regulated transmission
solutions that the NYISO determined were viable and sufficient submit to the NYISO their project
information, as applicable, for: (i) a proposed regulated backstop transmission solution, or (ii) a proposed
alternative regulated transmission solution.
The Comprehensive Reliability Plan documents the NYISO’s findings regarding the viability and
sufficiency of solutions, the trigger dates of regulated solutions, and any recommendations that
implementation of regulated solutions is necessary to maintain system reliability. The draft CRP will reflect
any input from the NYDPS. If the CRP cannot be completed in the two-year planning cycle, the NYISO will
notify stakeholders and provide an estimated completion date and an explanation of the reasons the
additional time is required. The NYISO will include in the draft CRP the list of Developers that qualify and
will identify the proposed solutions that it has determined are viable and sufficient to satisfy the identified
Reliability Need(s) by the need date. The NYISO will identify in the CRP the regulated backstop solution
that the NYISO has determined will meet the Reliability Need by the need date and the Responsible
Transmission Owner. If the NYISO determines at the time of the issuance of the CRP that sufficient market-
based solutions will not be available in time to meet a Reliability Need, and finds that it is necessary to take
action to ensure reliability, it will state in the CRP that the development of regulated solutions (regulated
backstop or alternative regulated solution) is necessary.
Short-Term Reliability Process: Additionally, the needs identified in the Short-Term Reliability
Process in year 1 through year 3 will be addressed in the applicable quarterly Short-Term Assessment of
Reliability (STAR), while the needs identified in years 4 and 5 will only be addressed using the Short-Term
APPENDICES
November 2020
Table of Contents
APPENDIX A - 2020 RELIABILITY NEEDS ASSESSMENT GLOSSARY ............................................................................................. 1
APPENDIX B - THE RELIABILITY PLANNING PROCESS ................................................................................................................. 8
APPENDIX C - LOAD AND ENERGY FORECAST 2021-2030 ........................................................................................................ 13
Historical Overview ................................................................................................................ 13
Forecast Results.................................................................................................................... 16
Emergency Thermal Transfer Limit Analysis for Resource Adequacy Assessments ............. 54
Figure 3: Historical Energy and Seasonal Peak Demand - Actual and Weather-Normalized ..................................................... 13
Figure 4: Annual Energy and Average Growth – Actual and Forecast ....................................................................................... 14
Figure 5: Actual and Forecast Seasonal Peak Demand and Average Growth, and LFU Multipliers ........................................... 15
Figure 6: Gold Book Baseline Energy Forecast Growth Rates - 2020 to 2030 ........................................................................... 17
Figure 7: 2028 Energy Forecast Comparison between 2018 Gold Book and 2020 Gold Book .................................................. 17
Figure 8: Gold Book Baseline Summer Coincident Peak Demand Forecast Growth Rates – 2020 to 2030 ............................... 18
Figure 9: 2028 Summer Peak Forecast Comparison between 2018 Gold Book and 2020 Gold Book ....................................... 18
Figure 10: Annual Energy by Zone - Actual and 2020 Gold Book Baseline Forecast (GWh) ...................................................... 19
Figure 11: Summer Coincident Peak Demand by Zone - Actual and 2020 Gold Book Baseline Forecast (MW)........................ 20
Figure 12: Winter Coincident Peak Demand by Zone - Actual and 2020 Gold Book Baseline Forecast (MW) .......................... 21
Figure 13: 2020 Gold Book Behind-the-Meter Solar PV Baseline Annual Energy Reductions by Zone (GWh) .......................... 22
Figure 14: 2020 RNA Base Case Annual Energy Forecast with BTM Solar PV Added Back (GWh)............................................. 22
Figure 15: 2020 Gold Book Behind-the-Meter Solar PV Baseline Summer Coincident Peak Demand Reductions by Zone (MW)
................................................................................................................................................................................................... 23
Figure 16: 2020 RNA Base Case Summer Coincident Peak Demand Forecast with BTM Solar PV Added Back (MW) .............. 23
Figure 20: Additional Proposed Generation Projects from the 2020 Gold Book ....................................................................... 38
Figure 21: Additional Proposed Transmission Projects from the 2020 Gold Book .................................................................... 41
Figure 22: Firm Transmission Plans included in 2020 RNA Base Case ....................................................................................... 43
Figure 25: 2018 RNA and 2020 RNA UPNYSNY Dynamic Limit Table ......................................................................................... 56
Figure 27: UPNYSNY Topology Diagram in 2018 RNA and 2020 RNA ........................................................................................ 57
Figure 29: 2020 RNA Fault Current Analysis Summary Table for 2025 System Representation ............................................... 59
Figure 30: Transmission Security N-1-1 Violations of the 2020 RNA Base Case ........................................................................ 67
Figure 31: Transmission Security N-1-1-0 Violations of the 2020 RNA Base Case ..................................................................... 75
Figure 32: BPTF Bus List for Transient Voltage Response N-1 Violation .................................................................................... 76
Figure 33: BPTF Bus List for Transient Voltage Response N-1-1 Violation ................................................................................. 80
Annual Transmission Reliability Assessment (ATRA): An Review submitted to NPCC by the ISO pursuant to NPCC
assessment, conducted by the NYISO staff in cooperation requirements. (Source: Attachment Y of OATT definitions)
with Market Participants, to determine the System Upgrade
CARIS: The Congestion Assessment and Resource Integration
Facilities required for each generation project and Class Year
Study for economic planning developed by the ISO in
Transmission Project included in this Assessment to
consultation with the Market Participants and other
interconnect to the New York State Transmission System in
interested parties pursuant to Section 31.3 of this
compliance with Applicable Reliability Standards and the
Attachment Y. (Source: NYISO OATT)
NYISO Minimum Interconnection Standard. (Source:
Attachment S of OATT) Clean Energy Standard (CES): State initiative for 70% of
electricity consumed in New York State to be produced from
Area Transmission Review (ATR): The NYISO, in its role as
renewable sources by 2030.
Planning Coordinator, is responsible for providing an annual
report to the NPCC Compliance Committee in regard to its Climate Leadership and Community Protection Act (CLCPA):
Area Transmission Review in accordance with the NPCC State statute enacted in 2019 to address and mitigate the
Reliability Compliance and Enforcement Program and in effects of climate change. Among other requirements, the law
conformance with the NPCC Design and Operation of the Bulk mandates that; (i) 70% of energy consumed in New York
Power System. (Source: NPCC Directory #1) State be sourced from renewable resources by 2030, (ii)
greenhouse gas emissions must be reduced by 40% by
Baseline Forecast: The baseline forecasts from the NYISO’s
2030, (iii) the electric generation sector must be zero
Gold Book report the expected NYCA load, and include the
greenhouse gas emissions by 2040, and (iv) greenhouse gas
projected impacts of energy efficiency programs, building
emissions across all sectors of the economy must be reduced
codes and standards, distributed energy resources, behind-
by 85% by 2050. (Source: 2019 CARIS Phase I)
the-meter energy storage, behind-the-meter solar
photovoltaic power (solar PV), electric vehicle usage, and Contingencies: An actual or potential unexpected failure or
electrification of heating and other end uses. The baseline outage of a system component, such as a generator,
forecasts are used in the RNA Base Cases for determining transmission line, circuit breaker, switch, or other electrical
Bulk Power Transmission Facilities Reliability Needs for the element. A contingency also may include multiple
RNA Study Period. (Source: 2020 Gold Book) components, which are related by situations leading to
simultaneous component outages. (Source: NYSRC Reliability
Best Technology Available (BTA): NYS DEC policy establishing
Rules)
performance goals for new and existing electricity generating
plants for Cooling Water Intake Structures. The policy applies Dependable Maximum Net Capability (DMNC): The sustained
to plants with design intake capacity greater than 20 million maximum net output of a Generator, as demonstrated by the
gallons/day and prescribes reductions in fish mortality. The performance of a test or through actual operation, averaged
performance goals call for the use of wet, closed-cycle over a continuous time period as defined in the ISO
cooling systems at existing generating plants. (Source: Procedures. (Source: OATT Definitions)
Section 316(b), Clean Water Act, United States Electric System Planning Work Group (ESPWG): The Electric
Environmental Protection Agency) System Planning Work Group, or any successor work group or
New York State Bulk Power Transmission Facility (BPTF): The committee designated to fulfill the functions assigned to the
facilities identified as the New York State Bulk Power ESPWG in this tariff. (Source: Attachment S of OATT)
normal ratings. Pre-contingency voltages and transmission requirement established by the NYSRC in order to ensure
interface flows must be within applicable pre-contingency resource adequacy in the NYCA. (Source: NYSRC Reliability
b. Post-contingency line and equipment loadings within STE Installed Reserve Margin (IRM): The amount of installed
ratings. Post-contingency voltages and transmission interface electric generation capacity above 100% of the forecasted
flows within applicable post-contingency voltage and stability peak electric demand that is required to meet NYSRC
limits. (Source: NYSRC Reliability Rules) resource adequacy criteria. Most studies in recent years have
indicated a need for a 15-20% reserve margin for adequate
Fault: An electrical short circuit. (Source: NYSRC Reliability
reliability in New York.
Rules)
Local Transmission Plan (LTP): The Local Transmission Owner
Federal Energy Regulatory Commission (FERC): The Federal
Plan, developed by each Transmission Owner, which
Energy Regulatory Agency within the U.S. Department of
describes its respective plans that may be under
Energy that approves the NYISO’s tariffs and regulates its
consideration or finalized for its own Transmission District.
operation of the bulk electricity grid, wholesale power
(Source: Attachment Y of OATT)
markets, and planning and interconnection processes.
Local Transmission Planning Process (LTPP): The Local
FERC Form 715: An annual report that is required by
Planning Process conducted by each Transmission Owner for
transmitting utilities operating grid facilities that are rated at
its own Transmission District. (Source: Attachment Y of OATT)
or above 100 kV. The report consists of transmission systems
maps, a detailed description of transmission planning Loss of Load Expectation (LOLE): The probability (or risk) of
Reliability Criteria, detailed descriptions of transmission disconnecting any firm load due to resource deficiencies shall
planning assessment practices, and detailed evaluation of be, on average, not more than once in ten years. Compliance
anticipated system performance as measured against with this criterion shall be evaluated probabilistically, such
Reliability Criteria. that the loss of load expectation (LOLE) of disconnecting firm
load due to resource deficiencies shall be, on average, no
Forced Outage: An unscheduled inability of a Market
more than 0.1 day per year. This evaluation shall make due
Participant’s Generator to produce Energy that does not meet
allowance for demand uncertainty, scheduled outages and
the notification criteria to be classified as a scheduled outage
deratings, forced outages and deratings, assistance over
or de-rate as established in ISO Procedures. If the Forced
interconnections with neighboring control areas, NYS
Outage of a Generator starts on or after May 1, 2015, the
Transmission System emergency transfer capability, and
Forced Outage will expire at the end of the month which
b. Post-contingency line and equipment loadings within Order 1000: The Final Rule entitled Transmission Planning
applicable emergency (LTE or STE) ratings. Post-contingency and Cost Allocation by Transmission Owning and Operating
voltages and transmission interface flows within applicable Public Utilities, issued by the Commission on July 21, 2011,
post-contingency voltage and stability limits. in Docket RM10-23-001, as modified on rehearing, or upon
appeal. (See FERC Stats & Regs. ¶ 31,323 (2011) (Order No.
All contingencies listed in Table B2 “NYSRC Planning Design
1000), on reh’g and clarification, 139 FERC ¶ 61,132 (Order
Criteria: Contingency Event, “in the reliability rules apply
No. 1000-A), on reh’g and clarification, 141 FERC ¶ 61,044
under normal transfer criteria. (Source: NYSRC Reliability
(2012) (Order No. 1000- B). (Source: Attachment Y of OATT)
Rules)
Outage: The forced or scheduled removal of generating
Normal Transfer Limit: The maximum allowable transfer is
capacity or a transmission line from service.
calculated based on thermal, voltage, and stability testing,
considering contingencies, ratings, and limits specified for Peak Demand: The maximum instantaneous power demand,
normal conditions. The normal transfer limit is the lowest measured in megawatts (MW), and also known as peak load,
limit based on the most restrictive of these three maximum is usually measured and averaged over an hourly interval.
allowable transfers. (Source: NYSRC Reliability Rules)
Queue Position: Queue position shall mean the order of a
North American Electric Reliability Corporation (NERC): The valid Interconnection Request, Study Request, or
North American Electric Reliability Council or, as applicable, Transmission Interconnection Application relative to all other
the North American Electric Reliability Corporation. (Source: pending Requests, that is established based upon the date
OATT Definitions) and time of receipt of the valid Interconnection Request by
NYISO, unless specifically provided otherwise in an applicable
Northeast Power Coordinating Council (NPCC): The Northeast
transition rule set forth in Attachment P, Attachment X or
Power Coordinating Council, or any successor organization.
Attachment Z to the ISO OATT. (Source: Attachment X of
(Source: Attachment Y of OATT)
OATT)
Open Access Transmission Tariff (OATT): Document of Rates,
Rating: The operational limits of an electric system, facility, or
Terms and Conditions, regulated by the FERC, under which
element under a set of specified conditions.
the NYISO provides transmission service. The OATT is a
dynamic document to which revisions are made on a i. Normal Rating: The capacity rating of a transmission facility
collaborative basis by the NYISO, New York’s Electricity that may be carried through consecutive twenty- four (24)
Market Stakeholders, and the FERC. hour load cycles.
Order 890: Adopted by FERC in February 2007, Order 890 is ii. Long Time Emergency (LTE) Rating: The capacity rating of a
a change to FERC’s 1996 transmission open access transmission facility that can be carried through infrequent,
regulations (established in Orders 888 and 889). Order 890 non- consecutive four (4) hour periods.
is intended to provide for more effective competition,
iii. Short Time Emergency (STE) Rating: The capacity rating of
transparency and planning in wholesale electricity markets
a transmission facility that may be carried during very
and transmission grid operations, as well as to strengthen
infrequent contingencies of fifteen (15) minutes or less
the Open Access Transmission Tariff (OATT) with regard to
duration. (Source: NYSRC Reliability Rules)
non-discriminatory transmission service. Order 890 requires
Reasonably Available Control Technology for Oxides of
magnetic fields of alternating-current equipment. Reactive Assessment as approved by the ISO Board under this
power is usually expressed as kilovolt-amperes reactive Attachment. (Source: Attachment Y of OATT definition)
(kVAr) or megavolt-ampere reactive (MVAr). Reliability Planning Process (RPP): The process set forth in
Regional Greenhouse Gas Initiative (RGGI): A cooperative this Attachment Y by which the ISO determines in the RNA
effort by a group of Northeast and Mid-Atlantic states to limit whether any Reliability Need(s) on the BPTFs will arise in the
power sector greenhouse gas emissions using a market- Study Period and addresses any identified Reliability Need(s)
based cap-and-trade approach. (Source: in the CRP, as the process is further described in Section
system that results in electricity being delivered to customers i. Alternative Regulated Solutions (ARS): Regulated solutions
within accepted standards and in the amount desired. submitted by a TO or other developer in response to a
Reliability may be measured by the frequency, duration, and solicitation for solutions to a Reliability Need identified in an
magnitude of adverse effects on the electric supply. Electric RNA.
system reliability can be addressed by considering two basic
ii. Gap Solution: A solution to a Reliability Need that is
and functional aspects of the electric system — adequacy and
designed to be temporary and to strive to be compatible with
security.
permanent market-based proposals. A permanent regulated
i. Adequacy: The ability of the electric systems to supply the solution, if appropriate, may proceed in parallel with a Gap
aggregate electrical demand and energy requirements of Solution. Note: The NYISO may call for a Gap Solution to an
their customers at all times, taking into account scheduled imminent threat to reliability of the Bulk Power Transmission
and reasonably expected unscheduled outages of system Facilities if no market-based solutions, regulated backstop
elements. Note: Adequacy encompasses both generation and solutions, or alternative regulated solutions can meet the
transmission. Reliability Needs in a timely manner.
ii. Security: The ability of the electric system to withstand iii. Market-Based Solutions: Investor-proposed projects that
disturbances such as electric short circuits or unanticipated are driven by market needs to meet future reliability
loss of system elements. The ability of the power system to requirements of the bulk electricity grid as outlined in the
withstand the loss of one or more elements without RNA. Those solutions can include generation, transmission
involuntarily disconnecting firm load. (Source: NYSRC and demand response Programs.
The NYISO RPP is an integral part of the NYISO’s overall Comprehensive System Planning Process
(CSPP). The CSPP is comprised of four components:
■ Reliability Planning Process (RPP), along with the newly defined quarterly Short Term
Reliability Process (STRP)
As part of the LTPP, local Transmission Owners perform transmission security studies for their BPTFs
in their transmission areas according to all applicable criteria. Links to the Transmission Owner’s LTPs can
be found on the NYISO’s website. The LTPP provides inputs for the RPP and STRP.
During the RPP, the NYISO conducts the Reliability Needs Assessment (RNA) and Comprehensive
Reliability Plan (CRP). The RNA evaluates the resource adequacy and transmission security of the bulk
power system over the RNA study period (i.e. year 4 through year 10). In identifying resource adequacy
needs, the NYISO identifies the amount of resources in megawatts (known as “compensatory megawatts”)
and the locations in which they are needed to meet those needs. After the RNA is complete, the NYISO
requests and evaluates market-based solutions, regulated backstop solutions, and alternative regulated
solutions that address the identified Reliability Needs. This step results in the development of the CRP for
the seven-year study period (i.e., year 4 through year 10).
The RPP is a long-range assessment of both resource adequacy and transmission reliability of the New
York bulk power system conducted over a seven-year planning horizon. There are two different aspects to
analyzing the bulk power system’s reliability in the RNA: adequacy and security. Adequacy is a planning
and probabilistic concept. A system is adequate if the probability of having sufficient transmission and
generation to meet expected demand is equal to or less than the system’s standard, which is expressed as a
loss of load expectation (LOLE). The New York State bulk power system is planned to meet an LOLE that, at
any given point in time, is less than or equal to an involuntary load disconnection that is not more frequent
Transmission Security is an operating and deterministic concept. N-1 events are evaluated to assess
their impact on the system, as viewed from the normal (or ‘N’) system condition. N-1-0 and N-1-1 analysis
evaluates the ability of the system to meet design criteria after a critical element has already been lost. An
N-1or N-1-1 violation occurs when the power flowing through a transmission element exceeds its
applicable rating (thermal violation) or the voltage at a bus exceeds its specified range (voltage violation).
Certain areas of the Con Edison system are designed and operated for the occurrence of a second
contingency. This type of combination can be described as N-1-1-0. For N-1-1-0 analysis, after the second
contingency occurs, systems adjustments are allowed to secure the system back to normal ratings. The Con
Edison planning criteria are contained in the NYSRC Reliability Rules, Rule G.1. Accordingly, a violation of
the N-1-1-0 criterion on the BPTFs in the Con Edison Transmission District will be identified as a Reliability
Need in the NYISO’s Reliability Needs Assessment.
The RPP is anchored in the market-based philosophy of the NYISO and its Market Participants, which
posits that market solutions should be the preferred choice to meet the identified Reliability Needs
reported in the RNA. In the CRP, the reliability of the bulk power system is assessed and solutions to
Reliability Needs evaluated in accordance with existing Reliability Criteria of the North American Electric
Reliability Corporation (NERC), the Northeast Power Coordinating Council, Inc. (NPCC), and the New York
State Reliability Council (NYSRC) as they may change from time to time. These criteria and a description of
the nature of long-term bulk power system planning are described in detail in the applicable planning
manual, and are briefly summarized below. In the event that market-based solutions do not materialize to
meet a Reliability Need in a timely manner, the NYISO designates the Responsible TO or Responsible TOs or
developer of an alternative regulated solution to proceed with a regulated solution in order to maintain
system reliability. The NYISO may provide regulated cost recovery for transmission solutions constructed
to meet a Reliability Need. Under the RPP, the NYISO also has an affirmative obligation to report historic
congestion across the transmission system. In addition, the draft RNA is provided to the Market Monitoring
Unit for review and consideration of whether market rules changes are necessary to address an identified
failure, if any, in one of the NYISO’s competitive markets. If market failure is identified as the reason for the
lack of market-based solutions, the NYISO will explore appropriate changes in its market rules with its
stakeholders and Independent Market Monitor. The RPP does not substitute for the planning that each TO
conducts to maintain the reliability of its own bulk and non-bulk power systems.
In 2019, a major planning process was carved out of the RPP and defined as the Short-Term Reliability
Process (STRP). This process was approved by the FERC and its requirements are contained in
Attachments Y and FF of the NYISO’s OATT. With this process in place, the RPP’s Study Period changes from
a year 1 to year 10 analysis, into a year 4 to year 10 look ahead. At the same time, the STRP evaluates year 1
through year 5 from the Short Term Assessment of Reliability (STAR) Start Date, with a focus on Short-
Term Reliability Needs arising in years 1 through 3 of the Study Period.
Consistent with Section 38.2 of the OATT, Short-Term Reliability Process Needs that arise within three
years of the later of (a) the conclusion of the 365 day prior notice period for that is described in Section
38.3.1.1 of the OATT for Generator Deactivation Reliability Needs, or (b) the posting of a completed Short-
Term Assessment of Reliability (STAR) for other Reliability Needs on the BPTF, will be addressed using the
Short-Term Reliability Process.
Short-Term Reliability Process Needs that arise in the Near Term (within three years) will be
addressed using the Short-Term Reliability Process (STRP). Short-Term Reliability Process Needs that are
not Near-Term needs on the BPTF (years 4 through 5) will only be addressed using the STRP if an
identified Reliability Need cannot timely be addressed through the ISO’s Reliability Planning Process. If
the Reliability Need is handled through the STRP, the NYISO will solicit market-based solutions of all types,
a regulated transmission solution(s), and service offers from Generators, as appropriate. The NYISO will
select a solution(s) consistent with the STRP process which may include selecting Generators to remain in
service under temporary Reliability Must Run (RMR) agreements until the transmission solution is
complete.
STRP Needs that arise more than three years after the later of (x) the conclusion of the 365 day prior
notice period for Generator Deactivation Reliability Needs, or (y) the posting of a completed STAR for other
Reliability Needs on the BPTF, will only be addressed using the STRP if the identified Reliability Need
cannot timely be addressed through the RPP set forth in this Attachment Y.
The CRP also provides inputs for the NYISO’s economic planning process known as CARIS. CARIS
Phase 1 examines congestion on the New York bulk power system and the costs and benefits of alternatives
to alleviate that congestion. During CARIS Phase 2, the NYISO evaluates specific transmission project
Another component of the CSPP is the Public Policy Transmission Planning Process. Under this
component, interested entities propose, and the NYPSC identify, transmission needs driven by Public Policy
Requirements. The NYISO then requests that interested entities submit proposed solutions to the Public
Policy Transmission Need(s) identified by the NYPSC. The NYISO evaluates the viability and sufficiency of
the proposed solutions to satisfy the identified Public Policy Transmission Need. Upon a confirmation by
the NYPSC that a need for a transmission solution still exists, the NYISO then evaluates and may select the
more efficient or cost-effective transmission solution to the identified need. The NYISO develops the Public
Policy Transmission Planning Report containing its findings regarding the proposed solutions. This report
is reviewed by NYISO stakeholders and approved by the Board of Directors.
In concert with each of the NYISO’s regional planning processes, interregional planning is conducted
with NYISO's neighboring control areas in the United States and Canada under the Northeastern ISO/RTO
Planning Coordination Protocol. The NYISO participates in interregional planning and may consider
Interregional Transmission Projects in its regional planning processes.
Figure 1 summarizes the CSPP and Figure 2 summarizes the RPP process.
Start RNA Base NYISO develops the RNA Base Case representations according to the inclusion rules for the Study Period
Case (i.e.: year 4 through year 10 following the year in which the RNA is conducted)
If local issues are identified in the Base Case, NYISO works with TOs to mitigate local problems and reports
the actions in RNA report
If reliability criteria violations are identified, develop compensatory MW to satisfy the Reliability Needs (RN)
RNA
Base Case NYISO determines if preliminary RN should be updated to include system updates that may reduce/eliminate
Updates RNs such as: capacity resources, BPTF, and TO LTP updates; inclusion rules are applied
NYISO completes Reliability Needs Assessment, finalizes report, and obtains Board approval
Post-RNA
Base Case NYISO determines if RN should be updated to include system updates that may reduce/eliminate RNs such as:
Updates capacity resources, BPTF, and TO LTP updates; inclusion rules are applied
Start CRP NYISO solicits solutions to satisfy the Reliability Needs, if any left from the above re-evaluation
CRP
Base Case NYISO performs its Viability and Sufficiency Assessment of the proposed solutions to determine if they
Updates adequately address the Reliability Needs by the need date
NYISO determines that the proposed solutions will not satisfy the
NYISO determines that the proposed solutions will satisfy the needs Reliability Needs and evaluates whether or not the STAR can
and Gap Solutions are not required
If STAR cannot address the Needs, initiate a Gap Process
NYISO determines that the earliest Trigger Date NYISO determines that the earliest Trigger Date
for the longest lead time regulated project is for the longest lead time regulated project is
NYISO solicits Gap Solutions
within 36 months of the viability and sufficiency beyond 36 months of the viability and sufficiency
determination determination
Notes:
* If an immediate threat to the reliability of the power system is identified, a Gap Solution outside of the normal RPP cycle may be requested by the NYISO Board.
Historical Overview
In order to perform the 2020 RNA, a forecast of summer and winter peak demands and annual energy
requirements was produced for the years 2020 - 2030. The New York Control Area (NYCA) is a summer
peaking system and is expected to remain a summer peaking system over the study period. In longer term,
the NYISO may become a winter peaking system in the mid-2030s due to increasing electrification
primarily via heat pumps and electric vehicles. Both summer and winter peaks show considerable year-to-
year variability due to the influence of peak-producing weather conditions for the seasonal peaks. Annual
energy is also influenced by weather conditions over the entire year. However, the resulting variation in
annual energy levels is relatively lower.
Figure 3 below reports the NYCA historic seasonal peaks and annual energy growth since 2010. The
table provides both actual results and weather-normalized results, together with annual average growth
rates for each table entry. The growth rates are averaged over the period 2010 to 2019.
Figure 3: Historical Energy and Seasonal Peak Demand - Actual and Weather-Normalized
1 Years listed reflect the NYISO capability year; For example, the year 2010 reflects the winter period spanning 2010-2011
In the first stage, baseline energy and peak models are built based on projections of end-use intensities
and economic variables. End-use intensities modeled include those for lighting, refrigeration, cooking,
heating, cooling, and other plug loads. Appliance end-use intensities are generally defined as the product of
saturation levels (average number of units per household or commercial square foot) and efficiency levels
(energy usage per unit or a similar measure). End-use intensities specific to New York are estimated from
appliance saturation and efficiency levels in both the residential and commercial sectors. These intensities
include the projected impacts of energy efficiency programs and improved codes and standards. Economic
variables considered include Gross Domestic Product (GDP), households, population, and commercial and
industrial employment. Projected long-term weather trends from the NYISO Climate Change Impact Study
Phase I are included in the end-use models.
In the second stage, the incremental impacts of additional policy-based energy efficiency, behind-the-
meter solar PV and distributed generation are deducted from the forecast; and the incremental impacts of
electric vehicle usage and other electrification are added to the forecast. The impacts of net electricity
consumption of energy storage units due to charging and discharging are added to the energy forecasts,
while the peak reducing impacts of behind-the-meter energy storage units are deducted from the peak
forecasts. In the final stage, the NYISO aggregates load forecasts by Zone. The 2020 summer peak forecast is
the 2020 ICAP forecast.
Forecast Results
Figure 6 through Figure 16 include information on the 2020 Baseline forecast specific to the 2020 RNA
look ahead period. Annual energy, summer, and winter peak forecasts and the corresponding average
annual growth rates are provided for reference along with comparisons to the 2018 RNA baseline forecast
used (Gold Book forecasts). Behind-the-meter impacts on summer peak reductions and total zonal peak
requirements (demand and solar PV) are also provided.
1,000
800 754
600
486
400 325
189
200
25
0
A B C D E F G H I J K NYCA
-7 -42
-200 -156
Figure 7: 2028 Energy Forecast Comparison between 2018 Gold Book and 2020 Gold Book
157 37
0
A B C D E F G H I J K NYCA
-78 -68 -67 -48 -411
-438
-1,000 -767
-978
-2,000
-2,482
-3,000
-4,000
-5,000
-5,143
-6,000
300
200
111
100
39
2
0
A B C D E F G H I J K NYCA
-100 -21 -32 -65
-90 -90 -73
-200
-300
-304
-400
-500
-526
-600
Figure 9: 2028 Summer Peak Forecast Comparison between 2018 Gold Book and 2020 Gold Book
2028 Summer Peak Demand Forecast Change - 2020 GB less 2018 GB (MW)
400
289
300
200
100
9 16
0
A B C D E F G H I J K NYCA
-13 -15 -25 -5
-100 -43
-52
-200 -179
-300
-400
-500
-600
-700
-695 -713
-800
Year A B C D E F G H I J K NYCA
2010 15,903 10,128 16,209 4,312 7,906 11,394 10,384 2,969 6,264 55,114 22,922 163,505
2011 16,017 10,040 16,167 5,903 7,752 11,435 10,066 2,978 6,208 54,059 22,704 163,329
2012 15,595 10,009 16,117 6,574 7,943 11,846 9,938 2,930 6,099 53,487 22,302 162,840
2013 15,790 9,981 16,368 6,448 8,312 12,030 9,965 2,986 6,204 53,316 22,114 163,514
2014 15,890 9,902 16,347 4,835 8,158 12,010 9,834 2,886 6,088 52,541 21,568 160,059
2015 15,761 9,906 16,299 4,441 8,141 12,422 10,065 2,847 6,299 53,485 21,906 161,572
2016 15,803 9,995 16,205 4,389 7,894 12,298 9,975 2,856 6,139 53,653 21,591 160,798
2017 15,261 9,775 15,819 4,322 7,761 11,823 9,669 2,883 5,976 52,266 20,815 156,370
2018 15,894 10,090 16,561 4,670 7,995 12,375 9,965 2,807 6,071 53,360 21,326 161,114
2019 14,872 9,715 15,809 4,825 7,868 11,829 9,574 2,816 5,976 52,003 20,545 155,832
2020 14,282 9,468 15,182 4,818 7,525 11,449 9,186 2,669 5,608 48,964 19,869 149,020
2021 14,441 9,602 15,400 5,154 7,584 11,542 9,259 2,774 5,590 49,242 20,039 150,627
2022 14,540 9,697 15,578 5,431 7,610 11,612 9,275 2,847 5,603 49,715 20,206 152,114
2023 14,446 9,665 15,557 5,622 7,531 11,531 9,163 2,876 5,500 48,835 19,818 150,544
2024 14,367 9,643 15,558 5,777 7,463 11,475 9,057 2,899 5,473 48,628 19,564 149,904
2025 14,280 9,616 15,538 5,875 7,396 11,420 8,951 2,919 5,452 48,433 19,287 149,167
2026 14,196 9,585 15,514 5,930 7,336 11,375 8,855 2,935 5,453 48,444 19,104 148,727
2027 14,111 9,547 15,478 5,950 7,282 11,337 8,776 2,949 5,466 48,562 19,090 148,548
2028 14,038 9,510 15,438 5,948 7,236 11,312 8,724 2,963 5,490 48,777 19,347 148,783
2029 13,976 9,479 15,399 5,935 7,201 11,296 8,701 2,977 5,528 49,115 19,576 149,183
2030 13,931 9,461 15,371 5,925 7,176 11,293 8,713 2,994 5,566 49,450 19,894 149,774
Year A B C D E F G H I J K NYCA
2010 2,663 1,985 2,846 552 1,437 2,339 2,399 700 1,487 11,213 5,832 33,453
2011 2,556 2,019 2,872 776 1,447 2,233 2,415 730 1,510 11,374 5,935 33,867
2012 2,743 2,107 2,888 774 1,420 2,388 2,242 653 1,393 10,722 5,109 32,439
2013 2,549 2,030 2,921 819 1,540 2,392 2,358 721 1,517 11,456 5,653 33,956
2014 2,227 1,617 2,574 527 1,267 2,033 2,036 584 1,333 10,567 5,017 29,782
2015 2,632 1,926 2,705 557 1,376 2,294 2,151 617 1,345 10,410 5,126 31,139
2016 2,672 2,008 2,812 561 1,384 2,328 2,123 636 1,392 10,990 5,169 32,075
2017 2,439 1,800 2,557 502 1,152 2,032 2,063 607 1,334 10,241 4,972 29,699
2018 2,391 1,947 2,747 600 1,300 2,378 2,190 631 1,393 10,890 5,394 31,861
2019 2,367 1,841 2,592 603 1,305 2,224 2,180 652 1,313 10,015 5,305 30,397
2020 2,662 1,948 2,728 583 1,348 2,352 2,167 647 1,430 11,316 5,115 32,296
2021 2,641 1,943 2,719 613 1,329 2,329 2,153 646 1,427 11,300 5,029 32,129
2022 2,626 1,941 2,715 640 1,313 2,313 2,144 646 1,435 11,397 4,958 32,128
2023 2,610 1,938 2,711 663 1,297 2,297 2,134 646 1,428 11,362 4,832 31,918
2024 2,597 1,936 2,708 682 1,283 2,285 2,127 647 1,429 11,395 4,749 31,838
2025 2,585 1,935 2,705 693 1,271 2,276 2,118 647 1,425 11,390 4,666 31,711
2026 2,575 1,933 2,702 699 1,263 2,271 2,111 648 1,431 11,446 4,591 31,670
2027 2,569 1,932 2,700 700 1,257 2,269 2,104 648 1,439 11,504 4,551 31,673
2028 2,567 1,930 2,698 699 1,255 2,271 2,100 649 1,446 11,583 4,558 31,756
2029 2,569 1,928 2,697 696 1,255 2,274 2,099 649 1,458 11,670 4,570 31,865
2030 2,572 1,927 2,696 694 1,258 2,279 2,102 649 1,469 11,757 4,589 31,992
Year A B C D E F G H I J K NYCA
2010-11 2,413 1,606 2,657 645 1,296 1,825 1,586 526 927 7,661 3,512 24,654
2011-12 2,220 1,535 2,532 904 1,243 1,765 1,618 490 893 7,323 3,378 23,901
2012-13 2,343 1,568 2,672 954 1,348 1,923 1,539 510 947 7,456 3,399 24,659
2013-14 2,358 1,645 2,781 848 1,415 1,989 1,700 625 974 7,810 3,594 25,739
2014-15 2,419 1,617 2,689 725 1,339 1,925 1,556 537 954 7,481 3,406 24,648
2015-16 2,253 1,486 2,469 667 1,307 1,861 1,496 453 889 7,274 3,164 23,319
2016-17 2,295 1,600 2,573 671 1,395 1,867 1,549 530 917 7,482 3,285 24,164
2017-18 2,313 1,533 2,766 735 1,398 2,012 1,638 506 933 7,822 3,425 25,081
2018-19 2,107 1,566 2,668 747 1,416 2,066 1,618 534 941 7,674 3,390 24,727
2019-20 2,100 1,460 2,482 741 1,305 1,854 1,468 479 842 7,398 3,124 23,253
2020-21 2,227 1,559 2,525 751 1,330 1,899 1,563 493 858 7,551 3,374 24,130
2021-22 2,229 1,556 2,531 782 1,331 1,899 1,558 494 866 7,630 3,327 24,203
2022-23 2,240 1,557 2,547 810 1,336 1,907 1,555 498 887 7,847 3,290 24,474
2023-24 2,251 1,559 2,561 836 1,342 1,914 1,551 501 900 7,984 3,251 24,650
2024-25 2,266 1,564 2,576 858 1,349 1,925 1,548 505 922 8,202 3,229 24,944
2025-26 2,281 1,569 2,588 873 1,356 1,936 1,545 509 947 8,432 3,215 25,251
2026-27 2,296 1,575 2,598 883 1,363 1,948 1,543 513 979 8,720 3,217 25,635
2027-28 2,310 1,581 2,605 890 1,368 1,959 1,543 517 1,008 8,971 3,236 25,988
2028-29 2,325 1,587 2,610 893 1,374 1,971 1,547 522 1,038 9,259 3,278 26,404
2029-30 2,342 1,594 2,616 897 1,381 1,984 1,555 527 1,076 9,591 3,325 26,888
2030-31 2,360 1,602 2,624 901 1,388 1,999 1,570 532 1,115 9,934 3,363 27,388
Year A B C D E F G H I J K NYCA
2020 199 95 261 18 202 431 363 49 64 335 614 2,631
2021 282 125 345 20 285 529 436 57 71 397 727 3,274
2022 384 158 437 24 381 631 505 63 78 460 778 3,899
2023 505 194 533 28 488 733 566 68 86 526 836 4,563
2024 635 230 622 34 592 831 614 72 93 588 882 5,193
2025 766 264 700 40 687 918 652 76 99 644 892 5,738
2026 885 294 762 48 766 992 681 77 105 694 901 6,205
2027 988 318 810 57 825 1,052 702 77 110 742 910 6,591
2028 1,069 337 846 66 868 1,096 716 79 115 782 919 6,893
2029 1,132 351 870 74 900 1,132 727 79 119 817 929 7,130
2030 1,178 360 889 83 922 1,158 736 80 120 825 938 7,289
Figure 14: 2020 RNA Base Case Annual Energy Forecast with BTM Solar PV Added Back (GWh)
Year A B C D E F G H I J K NYCA
2020 14,481 9,563 15,443 4,836 7,727 11,880 9,549 2,718 5,672 49,299 20,483 151,651
2021 14,723 9,727 15,745 5,174 7,869 12,071 9,695 2,831 5,661 49,639 20,766 153,901
2022 14,924 9,855 16,015 5,455 7,991 12,243 9,780 2,910 5,681 50,175 20,984 156,013
2023 14,951 9,859 16,090 5,650 8,019 12,264 9,729 2,944 5,586 49,361 20,654 155,107
2024 15,002 9,873 16,180 5,811 8,055 12,306 9,671 2,971 5,566 49,216 20,446 155,097
2025 15,046 9,880 16,238 5,915 8,083 12,338 9,603 2,995 5,551 49,077 20,179 154,905
2026 15,081 9,879 16,276 5,978 8,102 12,367 9,536 3,012 5,558 49,138 20,005 154,932
2027 15,099 9,865 16,288 6,007 8,107 12,389 9,478 3,026 5,576 49,304 20,000 155,139
2028 15,107 9,847 16,284 6,014 8,104 12,408 9,440 3,042 5,605 49,559 20,266 155,676
2029 15,108 9,830 16,269 6,009 8,101 12,428 9,428 3,056 5,647 49,932 20,505 156,313
2030 15,109 9,821 16,260 6,008 8,098 12,451 9,449 3,074 5,686 50,275 20,832 157,063
Year A B C D E F G H I J K NYCA
2020 34 18 49 4 35 89 78 11 12 74 151 555
2021 49 24 67 4 51 111 96 13 14 90 188 707
2022 67 30 85 5 70 132 111 15 16 106 204 841
2023 88 37 104 5 91 152 125 16 18 122 228 986
2024 112 43 123 6 112 171 135 17 19 136 228 1,102
2025 136 49 138 8 131 187 142 17 21 148 227 1,204
2026 158 55 150 9 147 199 146 17 22 158 226 1,287
2027 176 59 158 11 159 208 147 17 23 168 225 1,351
2028 190 62 162 12 165 214 147 17 24 175 224 1,392
2029 199 63 164 14 168 216 145 16 24 180 222 1,411
2030 203 63 163 15 169 215 143 16 24 180 220 1,411
Figure 16: 2020 RNA Base Case Summer Coincident Peak Demand Forecast with BTM Solar PV Added Back (MW)
Year A B C D E F G H I J K NYCA
2020 2,696 1,966 2,777 587 1,383 2,441 2,245 658 1,442 11,390 5,266 32,851
2021 2,690 1,967 2,786 617 1,380 2,440 2,249 659 1,441 11,390 5,217 32,836
2022 2,693 1,971 2,800 645 1,383 2,445 2,255 661 1,451 11,503 5,162 32,969
2023 2,698 1,975 2,815 668 1,388 2,449 2,259 662 1,446 11,484 5,060 32,904
2024 2,709 1,979 2,831 688 1,395 2,456 2,262 664 1,448 11,531 4,977 32,940
2025 2,721 1,984 2,843 701 1,402 2,463 2,260 664 1,446 11,538 4,893 32,915
2026 2,733 1,988 2,852 708 1,410 2,470 2,257 665 1,453 11,604 4,817 32,957
2027 2,745 1,991 2,858 711 1,416 2,477 2,251 665 1,462 11,672 4,776 33,024
2028 2,757 1,992 2,860 711 1,420 2,485 2,247 666 1,470 11,758 4,782 33,148
2029 2,768 1,991 2,861 710 1,423 2,490 2,244 665 1,482 11,850 4,792 33,276
2030 2,775 1,990 2,859 709 1,427 2,494 2,245 665 1,493 11,937 4,809 33,403
The NYISO used the MARS model to determine whether adequate resources would be available to
meet the NYSRC and NPCC reliability criteria of one day in ten years (0.1 days/year). The results identify
LOLE violations, and details are in the Section 6 of the RNA report.
Peak adjustments on a
seasonal basis.
3 Load Forecast Used updated summer LFU Updated via Load Forecast Same as 2020 RNA Base
Uncertainty (LFU) values for the 11 NYCA Task Force (LFTF) process Case
zones.
Reference: April 13 2020
LFTF presentation:
https://www.nyiso.com/doc
uments/20142/11883362
/LFU_Summary.pdf
Generation Parameters
2 Proposed New GB2018 with Inclusion Similar method Off-shore wind, land-based
Units Inclusion Rules Applied wind and utility scale PV
Determination added to align with CARIS
70x30 Case Renewable
Resources mix
3 Retirement, GB2018 with Inclusion Similar method Units that are retired in
Mothballed Units, Rules Applied 2020 RNA Base Case.
IIFO
Additionally, all unit
impacted by DEC’s Peaker
Rule were removed to align
with CARIS 70x30 Case
assumptions
4 Forced and Partial Five-year (2013-2017) Similar method Same as 2020 RNA Base
Outage Rates GADS data for each unit Case
represented. Those units
with less than five years –
use representative data.
Transition Rates
representing the Equivalent
Forced Outage Rates
(EFORd) during demand
periods over the most
recent five-year period
Probabilistic model is
incorporated based on five
years of input shapes, with
one shape per replication
randomly selected in the
Monte Carlo process.
9 Existing Wind Units Actual hourly plant output Similar method 8,760 hourly shapes
(>5 years of data) over the period 2013-2017. based on output profile
from CARIS 70x30 case.
Probabilistic model is
incorporated based on five Notes:
years of input shapes with 1. CARIS 70x30 case
one shape per replication output profile captures
being randomly selected in curtailments observed
Monte Carlo process
in the CARIS MAPS
simulations
2. CARIS 70x30 case
wind shape input
based on 2009 NREL
data.
10 Existing Wind Units For existing data, the actual Similar method 8,760 hourly shapes
(<5 years of data) hourly plant output over the based on output profile
period 2013-2017 is used. from CARIS 70x30 case.
11a Proposed Land Inclusion Rules Applied to Similar method 8,760 hourly shapes
based Wind Units determine the generator based on output profile
status. from CARIS 70x30 case.
Notes:
1. CARIS 70x30 case
output profile captures
curtailments observed
in the CARIS MAPS
simulations
2. CARIS 70x30 case
wind shape input
based on 2009 NREL
data.
12a Existing The 31.5 MW Upton Similar method 8,760 hourly shapes
Utility-scale Solar metered solar capacity: based on output profile
Resources probabilistic model chooses from CARIS 70x30 case.
from 5 years of production
data output shapes Notes:
covering the period 2013- 1. CARIS 70x30 case
2017 (one shape per output profile captures
replication is randomly curtailments.
selected in Monte Carlo 2. CARIS 70x30 case
process.)
existing utility scale PV
shape input based on
Y2017 historical data.
13 Projected The large projection of New Method: 8,760 hourly shape from
BtM Solar increasing retail (BtM) solar Will use 5-year of inverter CARIS 70x30 output.
Resources installations over the 10- production data.
year period require a Note: CARIS BtM solar
discrete model with detailed Probabilistic model is profile based on hourly
hourly performance. incorporated based on five shape created using
years of input shapes with NREL’s PV Watt tool.
New method: one shape per replication
A 8,760 hourly shape was being randomly selected in
created by using NREL’s PV Monte Carlo process
Watt 1 tool.
MARS will randomly select a Reference: April 6, 2020
daily shape from the current TPAS/ESPWG meeting
month for each day of each materials
month of each replication.
14 Existing BTM-NG New category: Similar method Same as 2020 RNA Base
Program These are former load Case
modifiers to sell capacity
into the ICAP market.
Modeled as cogen type 2
unit in MARS. Unit capacity
set to CRIS value, load
modeled with weekly
pattern that can change
monthly.
15 Existing Small New method: Similar method Same as 2020 RNA Base
Hydro Resources Actual hourly plant output Case
over the period 2013-2017.
Program randomly selects a
hydro shape of hourly
production over the 5-year
window for each model
replication. The randomly
1 NREL’s PVWatts Calculator, credit of the U.S. Department of Energy (DOE)/NREL/Alliance (Alliance for Sustainable Energy, LLC).
16 Existing Large Probabilistic Model based Similar method Same as 2020 RNA Base
Hydro on 5 years of GADS data. Case
Transition Rates
representing the Equivalent
Forced Outage Rates
(EFORd) during demand
periods over the most
recent five-year period
(2013-2017). Methodology
consistent with thermal unit
transition rates.
17 Proposed Energy N/A N/A Utilize MARS Energy
Storage Storage model, which
allows for charging and
discharging, and also
includes temporal
constraints (e.g.,
hours/days or
hours/month)
1 Capacity Grandfathered Rights and Similar method Same as 2020 RNA Base
Purchases other awarded long-term Case except for imports
rights from HQ, see HQ section
for additional information.
Modeled using MARS
explicit contracts feature.
Add 1310 MW HVDC
connection between HQ
and Zone J
2 Capacity Sales These are long-term Similar method Same as 2020 RNA Base
contracts filed with FERC. Case
References:
1. March 16, 2020
ESPWG/TPAS
2. April 6, 2020
TPAS/ESPWG
1 Interface Limits Developed by review of Similar method Same as 2020 RNA Base
previous studies and Case
2 New Transmission Based on TO- provided firm Similar method Same as 2020 RNA Base
plans (via Gold Book 2018 Case
process) and proposed
merchant transmission;
inclusion rules applied
3 AC Cable Forced All existing cable transition Similar method Same as 2020 RNA Base
Outage Rates rates updated with data Case
received from ConEd and
PSEG-LIPA to reflect most
recent five-year history
4 UDR unavailability Five-year history of forced Similar method Same as 2020 RNA Base
outages Case
1 Special Case SCRs sold for the program Similar method but with 15 Same as 2020 RNA Base
Resources discounted to historic calls/year Case
availability (“effective
capacity”). Summer values Note: also, combined the
calculated from the latest two SCR steps (generation
available July registrations, and load zonal MW)
held constant for all years
of study. 5 calls/month
2 EDRP Resources 2018 Gold Book with Not modeled: the values are Same as 2020 RNA Base
effective capacity modeled. less than 2 MW. Case
3 Other EOPs Based on TO information, Similar method Same as 2020 RNA Base
measured data, and NYISO Case
forecasts
External Control Areas
Miscellaneous
NYCA (MW)
Additions Reratings Deactivations Net capacity Summer
Year
Coincident
Baseline Load
Y2021 0 0 2,778 37,334 32,129
Y2022 568 0 2,778 37,902 32,128
Y2023 668 0 3,625 37,155 31,918
Y2024 668 0 3,625 37,155 31,838
Y2025 668 0 4,230 36,551 31,711
Y2026 668 0 4,230 36,551 31,670
Y2027 668 0 4,230 36,551 31,673
Y2028 668 0 4,230 36,551 31,756
Y2029 668 0 4,230 36,551 31,865
Y2030 668 0 4,230 36,551 31,992
Zone J (MW)
Year Additions Reratings Deactivations Net capacity Peak Load
Y2021 0 0 0 9,568 11,300
Y2022 0 0 0 9,568 11,397
Y2023 0 0 773 8,795 11,362
Y2024 0 0 773 8,795 11,395
Y2025 0 0 1,378 8,190 11,390
Y2026 0 0 1,378 8,190 11,446
Y2027 0 0 1,378 8,190 11,504
Y2028 0 0 1,378 8,190 11,583
Y2029 0 0 1,378 8,190 11,670
Y2030 0 0 1,378 8,190 11,757
The additional proposed projects from the Interconnection Queue are shown in Figure 20 and Figure
21.
Queue Owner/ Operator Proposed Generator Project Zone Proposed Date* Requested Summer
CRIS (MW)1 (MW)
Completed Class Year Facilities Study
387 Cassadaga Wind, LLC Cassadaga Wind A Dec-20 126.0 126.5
396 Baron Winds, LLC Baron Winds C Dec-20 300.0 238.4
422 NextEra Energy Resources, LLC Eight Point Wind Enery Center B Dec-20 101.2 101.8
363 Anbaric Development Parners, LLC Poseidon Offshore K Jan-21 500.0 500.0
349 Taylor Biomass Energy Montgomery, LLC Taylor Biomass G Apr-21 19.0 19.0
505 RES America Development Inc. Ball Hill Wind A Dec-22 100.0 100.0
393 NRG Berrians East Development, LLC Berrians East Replacement J Feb-23 508.0 431.0
Completed CRIS Requests
430 HQUS Cedar Rapids Transmission Upgrade D Oct-21 80.0 N/A
Class Year 2019
618 North Park Energy, LLC High River Solar F Nov-20 90.0 90.0
519 Canisteo Wind Energy LLC Canisteo Wind C Dec-20 290.7 290.7
531 Invenery Wind Development LLC Number 3 Wind Energy E Dec-20 105.8 105.8
546 Atlantic Wind, LLC Roaring Brook Wind E Dec-20 79.7 79.7
579 Bluestone Wind, LLC Bluestone Wind E Dec-20 124.2 124.2
617 North Park Energy, LLC Watkins Glen Solar C Dec-20 50.0 50.0
678 LI Solar Generation, LLC Calverton Solar Energy Center K Dec-20 22.9 22.9
683 KCE NY 2, LLC KCE NY 2 G Jun-21 200.0 200.0
535 sPower Development Company, LLC Riverhead Expansion K Oct-21 36.0 36.0
644 Hecate Energy Columbia County 1, LLC Columbia County 1 F Oct-21 60.0 60.0
495 Mohawk Solar LLC Mohawk Solar F Nov-21 90.5 90.5
571 Heritage Renewables, LLC Heritage Wind A Nov-21 200.1 200.1
591 Geronimo Energy, LLC High Top Solar C Nov-21 20.0 20.0
629 Silver Lake Solar, LLC Silver Lake Solar C Nov-21 24.9 24.9
637 Flint Mine Solar LLC Flint Mine Solar G Nov-21 100.0 100.0
706 High Brigde Wind, LLC High Brigde Wind E Nov-21 100.8 100.8
560 Atlantic Wind, LLC Deer River Wind E Dec-21 100.0 100.0
594 North Park Energy, LLC NW Energy C Dec-21 60.0 60.0
595 North Park Energy, LLC SW Energy A Dec-21 100.0 100.0
596 Invenergy Wind Development LLC Alle Catt II Wind A Dec-21 339.8 339.8
619 North Park Energy, LLC East Point Solar F Dec-21 50.0 50.0
697 Helix Ravenswood, LLC Ravenswood Energy Storage 1 J May-22 129.0 129.0
698 Helix Ravenswood, LLC Ravenswood Energy Storage 2 J May-22 129.0 129.0
746 Energy Storage Resouces, LLC Peconic River Energy Storage K Jun-22 150.0 150.0
620 North Park Energy, LLC North Side Solar D Nov-22 180.0 180.0
718 Cortland Energy Center,LLC Cortland Energy Center C Nov-22 50.0 50.0
720 North Light Energy Center, LLC North Light Energy Center C Nov-22 80.0 80.0
721 Excelsior Energy Center, LLC Excelsior Energy Center A Nov-22 280.0 280.0
612 Deepwater Wind South Fork, LLC South Fork Wind Farm K Dec-22 96.0 96.0
695 Deepwater Wind South Fork, LLC South Fork Wind Farm II K Dec-22 40.0 40.0
704 Bear Ridge Solar, LLC Bear Ridge Solar A Dec-22 100.0 100.0
791 Danskammer Energy LLC Danskammer Energy Center G Oct-23 88.9 595.5
276 EDF Renewables Development, Inc. Homer Solar Energy Center C Dec-23 90.0 90.0
668 North Bergen Liberty Generating, LLC Liberty Generating Alternative J Feb-24 1,172.0 1,171.0
737 Equinor Wind US LLC Empire Wind J Dec-24 816.0 816.0
738 Equinor Wind US LLC Empire Wind II K Dec-24 816.0 816.0
Gowanus Gas Turbine Facility
778 Astoria Generating Company LP J May-24 0.0 549.0
Repowering
* Generation projects that met 2020 RNA Inclusion Rule are assumed to be in-service one year later than 2020 GB Proposed Date
to reflect the potential impact of Covid-19 on construction and completion.
The NYISO utilized the RNA Base Case inclusion rules to screen the projects and plans for inclusion or
exclusion from the 2020 RNA Base Case. The NYISO revised the RNA Base Case inclusion rules as set forth
in Section 3 of the Reliability Planning Process Manual (Manual 26).
Specifically, the 2020 RNA Base Case does not include all projects currently listed on the NYISO’s
interconnection queue or those shown in the 2020 Gold Book. Rather, it includes only those which met the
screening requirements, as shown in the Figure 18 of the main report. The generation deactivation
assumptions are reflected in Figure19 and Figure 20 of the main report. The firm transmission plans
included in the RNA Base Case are listed in Figure 22 on the next page.
ConEd Jamaica Jamaica Reconfiguration In-Service 2019 138 138 N/A N/A Reconfiguration
ConEd East 13th East 13th xfmr In-Service 2019 345 345 N/A N/A Replacing xfmr 10 and xfmr 11
Street Street
ConEd Gowanus Gowanus xfmr In-Service 2019 345 345 N/A N/A Replacing xfmr T2
ConEd East 13th East 13th Reconfiguration In-Service 2019 345 345 N/A N/A Reconfiguration (xfmr 10 -xfmr 11)
Street Street
ConEd Rainey Corona xfmr/Phase In-Service 2019 345/138 345/138 1 268 MVA 320 MVA xfmr/Phase shifter
shifter
LIPA Far Rockaway Far Rockaway Reconfiguration In-Service 2019 34.5 34.5 N/A N/A Reconfigure 34.5 kV switchgear
LIPA Elwood Elwood Breaker In-Service 2019 138 138 N/A N/A Install double bus tie - Operate Normally
Open
LIPA Canal Southampton 5.20 In-Service 2019 69 69 1 1107 1169 2500 kcmil XLPE CU
LIPA Deer Park Deer Park - W 2019 69 69 1 N/A N/A Install 27 MVAR Cap Bank
LIPA MacArthur MacArthur - W 2019 69 69 1 N/A N/A Install 27 MVAR Cap Bank
LIPA West East Garden -2.92 In-Service 2019 69 69 1 1158 1245 477 ACSS
Hempstead City
LIPA West Hempstead 0.97 In-Service 2019 69 69 1 1158 1245 477 ACSS
Hempstead
LIPA Hempstead East Garden 1.95 In-Service 2019 69 69 1 1158 1245 477 ACSS
City
LIPA Pilgrim West Bus -11.86 In-Service 2019 138 138 1 2087 2565 2493 ACAR
LIPA West Bus Kings 8.25 In-Service 2019 138 138 1 2087 2565 2493 ACAR
LIPA Pilgrim Kings 4.81 In-Service 2019 138 138 1 2087 2565 2493 ACAR
NGRID Golah Golah Cap Bank In-Service 2019 115 115 1 18MVAR 18MVAR Capacitor Bank
NGRID Falls Park Schodack(NG) 17.33 In-Service 2019 115 115 1 186 MVA 227 MVA Loop for NYSEG Sub Will Reconfigure NG
Line #14 Into Two New Lines
NGRID Falls Park Churchtown 9.41 In-Service 2019 115 115 1 175 MVA 206 MVA Loop for NYSEG Sub Will Reconfigure NG
Line #14 Into Two New Lines
NGRID Battenkill Eastover Road -22.72 In-Service 2019 115 115 1 937 1141 New Schaghticoke Switching Station
NGRID Battenkill Schaghticoke 14.31 In-Service 2019 115 115 1 937 1141 New Schaghticoke Switching Station
(New Station)
NGRID Schaghticoke Eastover Road 8.41 In-Service 2019 115 115 1 937 1141 New Schaghticoke Switching Station
(New Station)
NGRID Mohican Luther Forest -34.47 In-Service 2019 115 115 1 937 1141 New Schaghticoke Switching Station
NGRID Mohican Schaghticoke 28.13 In-Service 2019 115 115 1 937 1141 New Schaghticoke Switching Station
(New Station)
NGRID Ohio St Ohio St In-Service 2019 115 115 N/A N/A New Distribution Station at Ohio Street
NGRID Albany Steam Greenbush 6.14 In-Service 2019 115 115 2 1190 1527 Reconductor Albany - Greenbush 115kV
lines 1 & 2
NGRID Schodack Churchtown -26.74 In-Service 2019 115 115 1 937 1141 Line removal tapped by Falls Park Project
NGRID Sodeman Rd Sodeman Rd In-Service 2019 115 115 N/A N/A New Distribution Station at Sodeman Road
NGRID Dewitt Dewitt In-Service 2019 115 115 N/A N/A New Distribution Station at Dewitt
NGRID Luther Forest Schaghticoke 6.34 In-Service 2019 115 115 1 1280 1563 New Schaghticoke Switching Station
(New Station)
NGRID Seneca Seneca - In-Service 2019 115/22 115/22 - 50MVA 50MVA Damage/Failure on TR2
NGRID Mortimer Mortimer Reconfiguration In-Service 2019 115 115 1 N/A N/A Reconfiguration of Station
NGRID Mohican Butler 3.50 S 2019 115 115 1 TBD TBD Replace 3.5 miles of conductor w/min
336.4 ACSR
NYSEG Wood Street Carmel 1.34 In-Service 2019 115 115 1 261 MVA 261 MVA 477 ACSR
NYSEG Flat Street Flat Street xfmr In-Service 2019 115/34.5 115/34.5 2 40MVA 45.2MVA Transformer #2
NYSEG Falls Park In-Service 2019 115/34.5 115/34.5 Tap to interconnect NG Line #14
115/34.5kV
NYSEG Falls Park Falls Park xfmr In-Service 2019 115/34.5 115/34.5 1 62 MVA 70 MVA Transformer #1
RGE Station 23 Station 23 xfmr In-Service 2019 115/11.5/1 115/11.5/ 2 75 MVA 84 MVA Transformer
1.5 11.5
RGE Station 23 Station 23 xfmr W 2019 115/34.5 115/34.5 2 75 MVA 84 MVA Transformer
CHGE North Chelsea North Chelsea xfmr S 2020 115/69 115/69 1 564 728 Replace Transformer 1
CHGE Fishkill Plains East Fishkill 2.05 S 2020 115 115 1 995 1218 1-1033.5 ACSR
CHGE North Catskill North Catskill xfmr W 2020 115/69 115/69 2 560 726 Replace Transformer 4 & 5
ConEd Buchanan Buchanan Reconfiguration S 2020 345 345 N/A N/A Reconfiguration (bus work related to
North North decommissioning of Indain Point 2)
LIPA Meadowbrook East Garden -3.11 S 2020 69 69 1 458 601 4/0 CU
City
LIPA East Garden Lindbergh 2.50 S 2020 69 69 1 575 601 750 kcmil CU
City
LIPA Lindbergh Meadowbrook 2.11 S 2020 69 69 1 458 601 4/0 CU
LIPA Elmont Floral Park -1.59 S 2020 34.5 34.5 1 644 816 477 AL
LIPA Elmont Belmont 1.82 S 2020 34.5 34.5 1 342 457 2/0 CU
LIPA Belmont Floral Park 2.04 S 2020 34.5 34.5 1 644 816 477 AL
NGRID Rosa Rd Rosa Rd - S 2020 115 115 N/A N/A Install 35.2MVAR Cap Bank at Rosa Rd
NGRID Rotterdam Curry Rd 7 S 2020 115 115 1 808 856 Replace 7.0 miles of mainly 4/0 Cu
conductor with 795kcmil ACSR 26/7
NGRID Elm St Elm St xfmr S 2020 230/23 230/23 1 118MVA 133MVA Add a fourth 230/23kV transformer
NGRID West Ashville West Ashville S 2020 115 115 N/A N/A New Distribution Station at West Ashville
NGRID Spier Rotterdam -32.74 S 2020 115 115 1 1168 1416 New Lasher Rd Switching Station
(#2)
NGRID Spier Lasher Rd 21.69 S 2020 115 115 1 1168 1416 New Lasher Rd Switching Station
(New Station)
NGRID Two Mile Two Mile S 2020 115 115 N/A N/A New Distribution Station at Two Mile Creek
Creek Creek
NGRID Maple Ave Maple Ave S 2020 115 115 N/A N/A New Distribution Station at Maple Ave
NGRID Randall Rd Randall Rd S 2020 115 115 N/A N/A New Distribution Station at Randall Road
NGRID GE Geres Lock 7.14 S 2020 115 115 1 785 955 Reconductoring 4/0CU & 336 ACSR to 477
ACCR (Line #8)
NGRID Gardenville Gardenville - S 2020 - - - - - Rebuild of Gardenville 115kV Station to full
115kV 115kV breaker and a half
NGRID Rotterdam Woodlawn 7 S 2020 115 115 1 Replace 7.0 miles of mainly 4/0 Cu
conductor with 795kcmil ACSR 26/7
NGRID Gardenville Gardenville xfmr S 2020 230/115 230/115 - 347 MVA 422 MVA Replacement of 230/115kV TB#4
230kV 115kV stepdown with larger unit
NGRID Oswego Oswego - W 2020 115 115 N/A N/A Rebuild of Oswego 115kV Station
NYPA Fraser Annex Fraser Annex SSR Detection S 2020 345 345 1 1793 MVA 1793 MVA MSSC SSR Detection Project
NYPA Niagara Rochester -70.20 W 2020 345 345 1 2177 2662 2-795 ACSR
NYPA Somerset Rochester -44.00 W 2020 345 345 1 2177 2662 2-795 ACSR
NYPA Niagara Station 255 66.40 W 2020 345 345 1 2177 2662 2-795 ACSR
(New Station)
NYPA Somerset Station 255 40.20 W 2020 345 345 1 2177 2662 2-795 ACSR
(New Station)
NYPA Station 255 Rochester 3.80 W 2020 345 345 2 2177 2662 2-795 ACSR
(New Station)
NYSEG Coddington E. Ithaca (to 8.07 W 2020 115 115 1 307 MVA 307 MVA 665 ACCR
Coddington)
O&R West Nyack West Nyack Cap Bank S 2020 138 138 1 - - Capacitor Bank
O&R Harings Corner Closter (RECO) 3.20 S 2020 69 69 1 1098 1312 UG Cable
(RECO)
O&R Ramapo Ramapo xfmr S 2020 345/138 345/138 1 731 731 -
RGE Station 122- Station 122- S 2020 345 345 1 1314 MVA- 1314 MVA- Relay Replacement
Pannell-PC1 Pannell-PC1 LTE LTE
RGE Station 262 Station 23 1.46 W 2020 115 115 1 2008 2008 Underground Cable
RGE Station 33 Station 262 2.97 W 2020 115 115 1 2008 2008 Underground Cable
RGE Station 262 Station 262 xfmr W 2020 115/34.5 115/34.5 1 58.8MVA 58.8MVA Transformer
RGE Station 255 Rochester 3.80 W 2020 345 345 1 2177 2662 2-795 ACSR
(New Station)
RGE Station 255 Station 255 xfmr W 2020 345/115 345/115 1 400 MVA 450 MVA Transformer
(New Station) (New Station)
RGE Station 255 Station 255 xfmr W 2020 345/115 345/115 2 400 MVA 450 MVA Transformer
(New Station) (New Station)
RGE Station 255 Station 418 9.60 W 2020 115 115 1 1506 1807 New 115kV Line
(New Station)
RGE Station 255 Station 23 11.10 W 2020 115 115 1 1506 1807 New 115kV Line
(New Station)
CHGE Hurley Avenue Leeds Static S 2021 345 345 1 2336 2866 21% Compensation
synchronous
LIPA Valley Stream East Garden 7.36 S 2021 138 138 1 1171 1171 2000 SQMM XLPE
City
LIPA Amagansett Navy Road 12.74 S 2021 23 23 1 577 657 750 kcmil CU
LIPA Navy Road Montauk 0.26 S 2021 23 23 1 577 657 750 kcmil CU
LIPA Riverhead Wildwood 10.63 S 2021 138 138 1 1399 1709 1192ACSR
LIPA Riverhead Canal 16.49 S 2021 138 138 1 1000 1110 2368 KCMIL (1200 mm²) Copper XLPE
LIPA Deer Park - Cap Bank S 2021 69 69 1 27MVAR 27 MVAR Capacitor bank
NGRID Clay Dewitt 10.24 S 2021 115 115 1 220MVA 268MVA Reconductor 4/0 CU to 795ACSR
NGRID Clay Teall 12.75 S 2021 115 115 1 220 MVA 268MVA Reconductor 4/0 CU to 795ACSR
NGRID Gardenville Gardenville xfmr S 2021 230/115 230/115 - 347 MVA 422 MVA Replacement of 230/115kV TB#3
230kV 115kV stepdown with larger unit
NGRID Huntley 115kV Huntley - S 2021 230 230 - N/A N/A Rebuild of Huntley 115kV Station
115kV
NGRID Mortimer Mortimer xfmr S 2021 115 115 50MVA 50MVA Replace Mortimer 115/69kV Transformer
NGRID Mortimer Mortimer - S 2021 115 115 N/A N/A Second 115kV Bus Tie Breaker at
Mortimer Station
NGRID New New - S 2021 115 115 N/A N/A New Bethlehem 115/13.2kV station
Bethlehem Bethlehem
NGRID New Cicero New Cicero S 2021 115 115 N/A N/A New Distribution Station at New Cicero
NGRID Mountain Lockport 0.08 S 2021 115 115 2 174MVA 199MVA Mountain-Lockport 103/104 Bypass
NGRID Royal Ave Royal Ave - S 2021 115/13.2 115/13.2 - - - Install new 115-13.2 kV distribution
substation in Niagara Falls (Royal Ave)
NGRID Niagara Packard 3.4 W 2021 115 115 1 344MVA 449MVA Replace 3.4 miles of 192 line
NYPA Moses 230 kV Adirondack Series S 2021 230 230 - ±13.2kV ±13.2kV Voltage Source Series Compensation
230 kV Compensation
NYPA St. Lawrence St. Lawrence xfmr S 2021 230/115 230/115 1 TBD TBD Replacement of St. Lawrence
230kV 115kV AutoTransformer #2
NYPA Plattsburg 230 Plattsburg xfmr W 2021 230/115 230/115 1 249 288 Refurbishment of Plattsburgh Auto
kV 115 kV Transformer #1
O&R Lovett 345 kV Lovett xfmr S 2021 345/138 345/138 1 562 MVA 562 MVA Transformer
Station (New
O&R Little Tor - Cap Bank S 2021 138 138 1 32 MVAR 32 MVAR Capacitor bank
O & R/ConEd Ladentown Buchanan -9.5 S 2021 345 345 1 3000 3211 2-2493 ACAR
O & R/ConEd Ladentown Lovett 345 kV 5.5 S 2021 345 345 1 3000 3211 2-2493 ACAR
Station (New
O & R/ConEd Lovett 345 kV Buchanan 4 S 2021 345 345 1 3000 3211 2-2493 ACAR
Station (New
CHGE St. Pool High Falls 5.61 W 2022 115 115 1 1010 1245 1-795 ACSR
CHGE High Falls Kerhonkson 10.03 W 2022 115 115 1 1010 1245 1-795 ACSR
CHGE Modena Galeville 4.62 W 2022 115 115 1 1010 1245 1-795 ACSR
CHGE Galeville Kerhonkson 8.96 W 2022 115 115 1 1010 1245 1-795 ACSR
CHGE Hurley Ave Saugerties 11.40 W 2022 69 115 1 1114 1359 1-795 ACSR
CHGE Kerhonkson Kerhonkson xfmr W 2022 115/69 115/69 1 564 728 Add Transformer 3
CHGE Kerhonkson Kerhonkson xfmr W 2022 115/69 115/69 1 564 728 Add Transformer 4
CHGE Rock Tavern Sugarloaf 12.10 W 2022 115 115 1 N/A N/A Retire SL Line
CHGE Sugarloaf NY/NJ State 10.30 W 2022 115 115 2 N/A N/A Retire SD/SJ Lines
Line
NGRID South Oswego Indeck (#6) - S 2022 115 115 1 - - Install High Speed Clearing on Line #6
NGRID Porter Porter - S 2022 230 230 N/A N/A Porter 230kV upgrades
NGRID Watertown Watertown S 2022 115 115 N/A N/A New Distribution Station at Watertown
NGRID Niagara Packard 3.7 S 2022 115 115 1 344MVA 449MVA Replace 3.7 miles of 191 line
NGRID Lockport Mortimer 56.5 S 2022 115 115 3 - - Replace Cables Lockport-Mortimer #111,
113, 114
NGRID Niagara Packard 3.7 W 2022 115 115 2 344MVA 449MVA Replace 3.7 miles of 193 and 194 lines
NGRID Gardenville Big Tree 6.3 W 2022 115 115 1 221MVA 221MVA Gardenville-Arcade #151 Loop-in-and-out of
NYSEG Big Tree
NGRID Big Tree Arcade 28.6 W 2022 115 115 1 129MVA 156MVA Gardenville-Arcade #151 Loop-in-and-out of
NYSEG Big Tree
NGRID Coffeen Coffeen - S 2022 115 115 - TBD TBD Terminal equipment replacements
NGRID Browns Falls Browns Falls - S 2022 115 115 - TBD TBD Terminal equipment replacements
NGRID Taylorville Taylorville - S 2022 115 115 - TBD TBD Terminal equipment replacements
NYPA Niagara 345 Niagara 230 xfmr W 2022 345/230 345/230 1 TBD TBD Replacement of Niagara AutoTransformer
kV kV #3
NYSEG South Perry South Perry xfmr W 2022 115/34.5 115/34.5 1 59 MVA 67 MVA Transformer #3
NYSEG South Perry South Perry xfmr W 2022 230/115 230/115 1 246 MVA 291 MVA Transformer
NYSEG Fraser Fraser xfmr W 2022 345/115 345/115 1 305 MVA 364 MVA Transformer #2 and Station
Reconfiguration
NYSEG Fraser 115 Fraser 115 Rebuild W 2022 115 115 N/A N/A Station Rebuild to 4 bay BAAH
NYSEG Delhi Delhi Removal W 2022 115 115 N/A N/A Remove 115 substation and terminate
existing lines to Fraser 115 (short distance)
NYSEG Erie Street Erie Street Rebuild W 2022 115 115 Station Rebuild
Rebuild Rebuild
NYSEG Big Tree Road Big Tree Road Rebuild W 2022 115 115 Station Rebuild
NYSEG Meyer Meyer xfmr W 2022 115/34.5 115/34.5 2 59.2MVA 66.9MVA Transformer #2
O&R Ramapo (NY) South 5.50 W 2022 138 138 2 1980 2120 1272 ACSS
Mahwah
RGE Station 168 Mortimer (NG 26.4 W 2022 115 115 1 145 MVA 176 MVA Station 168 Reinforcement Project
Trunk #2)
CHGE Saugerties North Catskill 12.46 W 2023 69 115 1 1114 1359 1-795 ACSR
NGRID Cortland Clarks 0.2 S 2023 115 115 1 147MVA 170MVA Replace 0.2 miles of 1(716) line and
Corners series equipment
NGRID Maplewood Menands 3 S 2023 115 115 1 220 MVA 239 MVA Reconductor approx 3 miles of 115kV
Maplewood – Menands #19
NGRID Maplewood Reynolds 3 S 2023 115 115 1 217 MVA 265 MVA Reconductor approx 3 miles of
115kV Maplewood – Reynolds Road #31
NGRID Elm St Elm St - S 2023 230/23 230/23 - 118MVA 133MVA Replace TR2 as failure
NGRID Packard Huntley 9.1 W 2023 115 115 1 262MVA 275MVA Walck-Huntley #133, Packard-Huntley
#130 Reconductor
NGRID Walck Huntley 9.1 W 2023 115 115 1 262MVA 275MVA Walck-Huntley #133, Packard-Huntley
#130 Reconductor
NGRID Kensington Kensington - W 2023 115/23 115/23 - 50MVA 50MVA Replace TR4 and TR5
Terminal Terminal
NGRID Malone Malone - S 2023 115 115 - TBD TBD Station Rebuild
NGRID Taylorville Boonville - S 2023 115 115 - TBD TBD Install series reactors on the 5 and 6 lines.
Size TBD
NYPA Moses Adirondack 78 S 2023 230 345 2 1088 1329 Replace 78 miles of both Moses-
Adirondack 1&2
NYPA Niagara 345 Niagara 230 xfmr W 2023 345/230 345/230 1 TBD TBD Replacement of Niagara AutoTransformer
kV kV #5
NYSEG Gardenville Gardenville xfmr W 2023 230/115 230/115 1 316 MVA 370 MVA NYSEG Transformer #3 and Station
Reconfiguration
NYSEG Wood Street Wood Street xfmr W 2023 345/115 345/115 1 327 MVA 378 MVA Transformer #3
O&R Burns West Nyack 5.00 S 2023 138 138 1 940 940 UG Cable
O&R Sugarloaf Shoemaker 12.00 W 2023 69 138 2 1062 1141 397 ACSS
ConEd Hudson Ave New Vinegar xfmrs/PARs/Fe S 2024 138/27 138/27 N/A N/A New Hudson Ave Distribution Switching
East Hill eders Station
NGRID Dunkirk Laona - S 2024 115 115 2 N/A N/A Remove series reactors from New Road
Switch Station and install new to Moons
Switch Station
NGRID Laona Moons - S 2024 115 115 2 N/A N/A Remove series reactors from New Road
Switch Station and install new to Moons
Switch Station
NGRID Golah Golah Reconfiguration S 2024 115 115 - - Add a Golah 115kV bus tie breaker
NGRID Dunkirk Dunkirk - S 2024 115 115 N/A N/A Rebuild of Dunkirk 115kV Station
NGRID Gardenville Dunkirk 20.5 S 2024 115 115 2 1105 1346 Replace 20.5 miles of 141 and 142 lines
NGRID Homer Hill Homer Hill - S 2024 115 115 - 116MVA 141MVA Homer Hill Replace five OCB
NGRID Inghams Saint 2.94 W 2024 115 115 1 1114 1359 Reconductor 2.94mi of 2/0 + 4/0 Cu (of
Johnsville 7.11mi total) to 795 ACSR
NGRID Inghams Inghams Breaker W 2024 115 115 - 2000 2000 Add series breaker to Inghams R15
115kV 115kV (Inghams - Meco #15 115kV)
NGRID Schenectady Rotterdam 0.93 W 2024 69 115 1 1114 1359 Reconductor 0.93mi of 4/0 Cu + 336.4
International ACSR (of 21.08mi total) to 795 ACSR
NGRID Rotterdam Schoharie 0.93 W 2024 69 115 1 1114 1359 Reconductor 0.93mi of 4/0 Cu (of 21.08mi
total) to 795 ACSR
NYSEG Westover 115 Westover Removal W 2024 115 115 N/A N/A Remove 115 substation and terminate
existing lines to Oakdale 115 (short
distance)
O&R Montvale - Cap Bank S 2024 69 69 1 32 MVAR 32 MVAR Capacitor bank
(RECO)
O&R Ramapo Sugarloaf 17.00 W 2024 138 138 1 1980 2120 1272 ACSS
O&R Burns Corporate 5.00 W 2024 138 138 1 1980 2120 1272 ACSS
Drive
RGE Station 418 Station 48 7.6 W 2024 115 115 1 175 MVA 225 MVA New 115kV Line
RGE Station 82 Station 251 W 2024 115 115 1 400MVA 400MVA Line Upgrade
(Upgrade Line
RGE Mortimer Station 251 1.00 W 2024 115 115 1 400MVA 400MVA Line Upgrade
(Upgrade Line
LIPA Southampton Deerfield 4.00 S 2025 69 138 1 1171 1171 2000 SQMM XLPE
NGRID Stoner Rotterdam 9.81 W 2025 115 115 1 1398 1708 Reconductor 9.81mi of 4/0 Cu + 336.4
ACSR (of 23.12mi total) to 1192.5 ACSR
LIPA Syosset Shore Rd Phase Shifter S 2026 138 138 1 TBD TBD Phase Shifter
NGRID Niagara Gardenville 26.3 S 2026 115 115 1 275MVA 350MVA Packard-Erie / Niagara-Garenville
Reconfiguration
NGRID Packard Gardenville 28.2 S 2026 115 115 2 168MVA 211 MVA Packard-Gardenville Reactors, Packard-
Erie / Niagara-Garenville Reconfiguration
NGRID Mortimer Pannell 15.7 S 2026 115 115 2 221MVA 270MVA
NGRID/NYSE Erie St Gardenville 5.5 S 2026 115 115 1 139MVA 179MVA Packard-Erie / Niagara-Garenville
G Reconfiguration, Gardenville add breakers
O&R West Nyack West Nyack - S 2026 138 138 1 Station Reconfiguration
O&R West Nyack Harings 7.00 W 2026 69 138 1 1604 1723 795 ACSS
(NY) Corner (RECO)
The NYISO developed the system representations for PJM, Ontario, New England, and Hydro Quebec
modeled in the 2020 RNA Base Case from the NPCC CP-8 2020 Summer Assessment. To avoid
overdependence on emergency assistance from the external areas, the emergency operating procedure
data was removed from the model for each external area. In addition, the capacity of the external areas was
further modified such that the LOLE value of each external area was a minimum value of 0.10 and capped at
a value of 0.15 throughout Study Period.
The topology used in the MARS model RNA Base Case is located in Figures 28 to 30 in the body of the
report. The internal transfer limits modeled are the summer emergency ratings derived from the RNA
power flow cases discussed above. The NYISO developed external transfer limits from the NPCC CP-8
Summer Assessment MARS database with changes based upon the RNA Base Case assumptions.
Interface 2025
Units Available
UPNYSNY
Year CPV Valley Cricket Athens
Limit (MW)
Valley
5250 2 3 3
5100 2 3 2
5350 1 3 3
5200 2 2 3
2021- 2023
5150 2 1 3
5250 1 1 3
5100 2 0 3
5350 All other conditions
The method for modeling the UPNY-SENY interface in the MARS topology was changed for the 2020
RNA. However, the changes apply to years 2021 through 2023, which are not included in the 2020 RNA
study period. Beginning in year 2024, the UPNY-SENY interface is modeled as a single limit because of the
large increases in transfer capability resulting from addition of the AC Transmission projects.
Figure 25: 2018 RNA and 2020 RNA UPNYSNY Dynamic Limit Table
The E to G (Marcy South) interface was also updated for the 2020 RNA. In the 2018 RNA, a joint
interface, CPV + Marcy Group, was utilized to capture the impact of the CPV Valley plant on the E to G
interface. A flow calculation on the joint interface effectively reduced the limit on E to G by 90% of the CPV
Valley plant output. For the 2020 RNA, this model was replaced with a DLT model applied to the E to G
interface as shown in Figure 26. The joint interface and flow calculation were removed and the CPV Valley
units were modeled directly in Zone G instead of as a separate MARS area.
E to G CPV Valley
1750 2
2000 1
2250 0
The modeling changes resulted in flows and LOLE results that were extremely close when the models
were tested and compared. The new simplified models are more straightforward to implement, maintain
and verify in the MARS database.
Figure 27: UPNYSNY Topology Diagram in 2018 RNA and 2020 RNA
2018 RNA (Study Year 2021) 2020 RNA Draft (Study Year 2021)
CENTRAL EAST GROUP
CENTRAL EAST GROUP
3100 3100
E F E CENTRAL-EAST
F
CENTRAL-EAST
3400 1600
3400 1600
5000 5000
MARCY SOUTH
GILBOA ATHENS
CAPITAL-HUDV
MARCY SOUTH
CAPITAL-HUDV
UPNYSENY DL
UPNYSENY
5600
3475
3475
5600 5250
G G
PJM-G
PJM-G
GROUP
GROUP
150 150
1045 1045
When removing the NYCA internal limits, the NYCA LOLE decreased to below the criterion level
throughout the Study Period, indicating that there is no statewide resource deficiency. It also showed that
transmission reinforcement, which would provide an injection into Zone J where the deficiency is located,
Additional topology limits variations were performed to identify which specific interface transfer
capability increases help the most, and to provide additional insights. The table below summarizes those
simulations.
Removing 0.14 Increasing limit J to J3 from 200 MW to 815 MW for most loss
dynamic limit of load events.
from J_to_J3 However, only 420 MW can flow on the interface because the
ABC interface limitations.
I_to_J +450 MW 0.097 Minimum of +450MW on Dunwoodie South to bring LOLE just
below 0.1 days/year
I_to_J unlimited 0.053 5,660 MW max flow on I to J observed in this MARS simulation
Figure 29: 2020 RNA Fault Current Analysis Summary Table for 2025 System Representation
Lowest
Nominal Maximum
Breaker IBA Breaker(s)
Substation Voltage Owner Bus Fault
Rating Required Overdutied
(kV) (kA)
(kA)
ACADEMY 345 63.0 Con Ed 35.0 N N
ADIRONDACK 230 32.4 N. Grid 10.5 N N
AES SOMERSET 345 40.0 NYSEG 16.7 N N
ALPS 345 39.0 N. Grid 17.4 N N
ALPS_EAST 345 N/A 2 N. Grid 7.9 N N
ALPS_PAR 1 345 N/A2 N. Grid 7.9 N N
ALPS_PAR 2 345 N/A2 N. Grid 7.9 N N
ASTE-ERG 138 63.0 Con Ed 49.7 N N
ASTE-WRG 138 63.0 Con Ed 49.7 N N
ASTORIA W-N 138 63.0 Con Ed 43.6 N N
ASTORIA W-S 138 63.0 Con Ed 43.6 N N
AstoriaAnnex 345 63.0 NYPA 44.8 N N
ATHENS 345 49.0 N. Grid 35.0 N N
BARRETT1 138 63.0 LIPA 48.8 N N
BARRETT2 138 63.0 LIPA 48.9 N N
BAYONNE 345 50.0 Con Ed 25.3 N N
BOONVILLE 115 23.0 N. Grid 10.8 N N
BOWLINE 2 345 40.0 O&R 26.8 N N
BOWLINE1 345 40.0 O&R 27.0 N N
BRKHAVEN 138 63.0 LIPA 26.8 N N
BUCH138 138 40.0 Con Ed 15.5 N N
BUCHANAN N 345 63.0 Con Ed 25.1 N N
BUCHANAN S 345 63.0 Con Ed 37.1 N N
C.ISLIP 138 38.9 LIPA 27.6 N N
CANANDAIGUA 230 40.0 NYSEG 8.5 N N
CARLE PL 138 63.0 LIPA 39.0 N N
CHASES LAKE 230 39.0 N. Grid 9.6 N N
CHURCHTOWN 115 21.4 NYSEG 8.3 N N
2
Future station with no LCB rating yet.
3
Future station with no LCB rating yet.
The NYISO observed dynamic stability criteria Reliability Needs for the entire study period. The
criteria violations include transient voltage response violations and loss of generator synchronism. The
transient voltage response violations are primarily in the Con Edison area but extend into areas adjacent to
their service territory. The loss of generator synchronism is observed in generators within or near the
Astoria and Greenwood load pockets, and is primarily driven by the delayed voltage recovery in the local
area. Figure 32 and Figure 33 shows the BPTF buses with transient voltage response violations and the
earliest year that each bus manifests the criteria violations for a given contingency.
Bus Bus Name Base Area Area Name Owner Earliest Year of Contingency Events which result in
Number kV Num Name observed transient transient voltage response violations
voltage response for this bus (See Note Below)
violations
126249 26T 345 10 NYC CONED 2030 (2), (3)
126262 BUCHANAN N 345 8 MILLWOOD CONED 2025 (2), (3)
126263 BUCHANAN S 345 8 MILLWOOD CONED 2025 (1), (2), (3)
126265 COGNTECH 345 10 NYC CONED 2030 (2), (3)
126266 DUNWOODIE 345 9 DUNWOODIE CONED 2025 (1), (2), (3)
126267 E VIEW 2N 345 9 DUNWOODIE CONED 2025 (2), (3)
126268 E VIEW 1N 345 9 DUNWOODIE CONED 2025 (1), (2), (3)
126269 E VIEW 2S 345 9 DUNWOODIE CONED 2025 (1), (2), (3)
126270 E VIEW 1S 345 9 DUNWOODIE CONED 2025 (1), (2), (3)
126272 E13ST 45 345 10 NYC CONED 2024 (1), (2), (3)
126273 E13ST 46 345 10 NYC CONED 2024 (1), (2), (3)
126274 E13ST 47 345 10 NYC CONED 2024 (1), (2), (3)
126275 E13ST 48 345 10 NYC CONED 2024 (1), (2), (3)
126277 FARRAGUT 345 10 NYC CONED 2024 (1), (2), (3)
126280 FARRAGUT TX9 345 10 NYC CONED 2024 (1), (2), (3)
126282 FRESH KILLS 345 10 NYC CONED 2030 (2), (3)
126283 GOTHLS 345 10 NYC CONED 2030 (2), (3)
126284 GOTHLS R 345 10 NYC CONED 2030 (2)
126285 GOW R4 345 10 NYC CONED 2030 (2), (3)
126286 GOW R16 345 10 NYC CONED 2030 (2), (3)
126287 GOWANUS 345 10 NYC CONED 2030 (2), (3)
126291 MILLWOOD 345 8 MILLWOOD CONED 2025 (1), (2), (3)
126292 PL VILLE 345 9 DUNWOODIE CONED 2025 (1), (2), (3)
126293 PL VILLW 345 9 DUNWOODIE CONED 2025 (1), (2), (3)
126295 RAINEY 345 10 NYC CONED 2024 (1), (2), (3)
126298 SPRAINBROOK 345 9 DUNWOODIE CONED 2025 (1), (2), (3)
Notes:
Event (1) UC11
Event (2) UC25A
Event (3) UC25B
Bus Bus Name Base Area Area Name Owner Earliest Year of observed Contingency Events which result in
Number kV Num Name transient voltage response transient voltage response violations
violations for this bus (See Note Below)
126249 26T 345 10 NYC CONED 2025 (4), (5), (6), (9), (10), (11), (12), (13),
(14), (15), (19)
126262 BUCHANAN N 345 8 MILLWOOD CONED 2025 (5), (8), (9), (10), (11), (12), (13), (14),
(15), (19)
126263 BUCHANAN S 345 8 MILLWOOD CONED 2025 (2), (4), (5), (6), (8), (9), (10), (11), (12),
(13), (14), (15), (16), (19)
126265 COGNTECH 345 10 NYC CONED 2025 (4), (5), (6), (9), (10), (11), (12), (13),
(14), (15), (19)
126266 DUNWOODIE 345 9 DUNWOODIE CONED 2024 (1), (2), (4), (5), (6), (7), (8), (9), (10),
(11), (12), (13), (14), (15), (16), (18),
(19)
126267 E VIEW 2N 345 9 DUNWOODIE CONED 2025 (2), (5), (7), (8), (9), (10), (11), (12),
(13), (14), (15), (16), (18), (19)
126268 E VIEW 1N 345 9 DUNWOODIE CONED 2024 (2), (5), (6), (7), (8), (9), (10), (11), (12),
(13), (14), (15), (16), (18), (19)
126269 E VIEW 2S 345 9 DUNWOODIE CONED 2024 (2), (4), (5), (6), (8), (9), (10), (11), (12),
(13), (14), (15), (16), (18), (19)
126270 E VIEW 1S 345 9 DUNWOODIE CONED 2024 (1), (2), (4), (5), (6), (8), (9), (10), (11),
(12), (13), (14), (15), (16), (18), (19)
126272 E13ST 45 345 10 NYC CONED 2024 (1), (2), (4), (5), (6), (7), (8), (9), (10),
(11), (12), (14), (15), (16), (18), (19)
126273 E13ST 46 345 10 NYC CONED 2024 (1), (2), (4), (5), (6), (7), (8), (9), (10),
(11), (12), (13), (15), (16), (18), (19)
126274 E13ST 47 345 10 NYC CONED 2024 (1), (2), (4), (5), (6), (7), (8), (9), (10),
(11), (12), (13), (14), (15), (16), (18),
(19)
126275 E13ST 48 345 10 NYC CONED 2024 (1), (2), (4), (5), (6), (7), (8), (9), (10),
(11), (12), (13), (14), (16), (18), (19)
126277 FARRAGUT 345 10 NYC CONED 2024 (1), (2), (4), (5), (6), (7), (8), (9), (10),
(11), (13), (14), (15), (16)
Notes:
Event (1) ConEd16 Event (6) UC11 Event (11) UC33_Q510 Event (16) UC39_Q510
Event (2) ConEd23_Q510 Event (7) UC19 Event (12) UC34_Q510 Event (17) UC048A_Q510
Event (3) TE02-UC02 Event (8) UC25A Event (13) UC35_Q510 Event (18) UC57_Q510
Event (4) TE03-UC03 Event (9) UC25B Event (14) UC36_Q510 Event (19) UC5_Q510
Event (5) TE20-UC20 Event (10) UC32_Q510 Event (15) UC38_Q510
• Starting with the simplified external model described in footnote 8 and also in the
assumptions matrix in Appendix D, the NYISO removed all load and generation from
external areas along with removing interfaces between external areas, followed by
inserting fixed amounts of capacity in each external area.
• The Resource Adequacy Base Cases use historical load shapes from 2002, 2006, and
2007. The Climate Change Phase 1 study developed forward-looking hourly load
shapes. This exploratory scenario identified that additional collaboration with the
Load Forecast Task Force and other stakeholders will be initiated, to identify if and
how future-looking load shapes would better represent an ever-changing system.
This further simplified scenario evaluates an alternative model for the external, non-NYCA, regions in
the MARS model. Starting in this RNA, the NYISO simplified the representation of each external region so
that they are represented by a single area, as shown in Figure 46. in the main report. This scenario expands
on this work by evaluating if additional simplifications to the external region model can be made while
maintaining consistent results.
To achieve this objective, the NYISO performed the following actions in each external region to
simplify the representation and to model a system in which the NYCA receives no emergency assistance:
- Disable the ability of UDRs to return from the host external region, while still allowing
emergency assistance over the interface if the resource is otherwise unavailable.
The next phase of this analysis evaluated the impact of modeling discrete capacity combinations in
each external region, as shown in Figure 34. For low levels of total assistance, the results aligned with the
single area adjustments previously discussed (i.e., the 1,200 MW cumulative result was similar to adding
1,200 MW to PJM or New England). Figure 34 also includes the observed NYCA LOLE for 2030, when
compared to the Base Case results (0.186), between 2,400 and 2,700 MW of always-available assistance
replace the external model. The amount of assistance needed through time increased. See Figure 35,
showing the 2024 Base Case result (0.016) using between 1,800 and 2,100 MW of assistance.
3000 MW
0.15 Base Case
0.10
0.05
0.00
2024 2025 2026 2027 2028 2029 2030
The next, and final, phase of this exploratory analysis was to apply derates to the amount of available
emergency assistance based upon the Area K load, as a proxy for NYCA Load. The derates were applied by
utilizing MARS functionality for ambient temperature derates to thermal units. This approach allows for
the simplified model to mimic the original model by having potentially less assistance available in the
higher load levels. Two derate profiles were tested, shown in Figure 36, on the 2,400, 2,700, and 3,000 MW
assistance cases Figure 37 to Figure 39, respectively.
EA Derate Profiles
1.05
Derate 1
1
Derate 2
Capacity Derate
0.95
0.9
0.85
0.8
0.75
0.85 0.9 0.95 1 1.05 1.1 1.15
NYCA Load (p.u. of Peak Load)
0.25
0.20
NYCA LOLE (dy/yr)
0.15
0.10
0.05
0.00
2024 2025 2026 2027 2028 2029 2030
0.25
0.20
NYCA LOLE (dy/yr)
0.15
0.10
0.05
0.00
2024 2025 2026 2027 2028 2029 2030
0.25
0.20
NYCA LOLE (dy/yr)
0.15
0.10
0.05
0.00
2024 2025 2026 2027 2028 2029 2030
The NYISO intends to continue refining this analysis with discussion at the Electric System Planning
Working Group and other stakeholder forums, as applicable in order to determine potential changes.
In 2019, the NYISO engaged in the Climate Change Phase 1 Study to develop a set of future-looking
hourly load shapes considering various energy efficiency and climate goals. The outputs from the Phase 1
study feeds into the Phase 2 study, which is analyzing reliability impact issues with a potential 2040 power
system. The NYISO will continue to explore building on the work from the Climate Change studies for
application in future resource adequacy analysis, and intends to collaborate with the Load Forecasting Task
Force and other stakeholders’ forums, as applicable in order to determine potential changes to be studied.
As part of its CSPP, the ISO will prepare summaries and detailed analysis of historic and projected
congestion across the NYS Transmission System. This will include analysis to identify the significant
causes of historic congestion in an effort to help Market Participants and other interested parties
distinguish persistent and addressable congestion from congestion that results from onetime events or
transient adjustments in operating procedures that may or may not recur. This information will assist
Market Participants and other stakeholders to make appropriately informed decisions.
Also, information on the NYISO’s Economic Planning Studies can be found here: