Method Statement Footing - PDF - Concrete - Deep Foundation

Download as pdf or txt
Download as pdf or txt
You are on page 1of 12

Bouquet Front porches LEARN MORE

Search Read free for 30 days


 0 ratings · 188 views · 4 pages
Method Statement Footing
Uploaded by Rizky V 'dHee' on Dec 22, 2019

Method Statement Footing Full description

     
Save 0% 0% Embed Share Print

Download now 1 of 4  Search document 


Front porch violations - This document is...
New front porch  Useful
Learn More  Not useful
We will build your new front porch, we are porch
and deck violation experts. cityporches.com
 

Method Statement for Footing


Concrete Pouring
By Noel MadesPosted on February 2, 2014In Method Statement (Civil)16 Comments 

Share17Save 
When we talk about foundations, there are various types that we can use
depending on the structural design. The types of foundations are: Isolated
footing, Combined Footing, Mat Foundations, Strap Foundations, Bored Pile,
Pile Drive etc.

In our project we do have usually Isolated footing foundations. When I was in


my previous company we had Mat Foundation which I’m going to write a
method statement later. So I’m going to share to you the Method Statement or
Procedure on how we’ll going to pour concrete on footing foundation.  

Here is the Method Statement for Footing Concrete Pouring 

1. Title 

Method Statement for Footing Concrete Pouring

2. Scope 

The purpose of this Method Statement is to describe the measures and ways
of completing concrete pour work for footings on this project. The works shall
be carried out in compliance with the drawings and project specification.

3. Work Procedure  

1.  Reinforcement
  It is intended to cut and bend rebar on site as per the bar bending

schedules.


This document is...
 
Front porch builders
near me
Front porch violations
We will build your new front porch, we are
porch and deck violation experts.
cityporches.com

Learn More


This document is...
 
 

 Some footings are composed of top and bottom reinforcement, the


 
bottom bars shall be supported with concrete block or spacer of
correct thickness.
  Inspection Request ( IR ) would be submitted for steel
reinforcement for checking and approval of the Engineer prior to
concrete casting.
2.  Casting
  Make sure that the area within the shutter to be poured with
concrete is cleaned. Remove all rubbish, dirt, and any other
deleterious material via air compressor.
  Inspection Request can be submitted to the Engineer or Consultant
for approval of fixed steel reinforcement and installed forms, if
casting shall not take place on the same day.

   Readymade concrete shall be provided from batching plant


approved by the Engineer. The rate of concrete supply shall be 30
to 50 Cubic Meter per hour.
   The required number of concrete pumps will be available on site;
extra pump will be on standby ready for any incident circumstances.
   Concrete vibrators shall be ready to use at time of receiving
concrete. Number of vibrators shall be depending on concreted
area to improve well compaction for concrete pump.
   Computerized delivery ticket shall be checked for conformity as per
the approved design mix.
   Slump and temperature shall be carried out from each concrete
truck mixer.
   Slump shall not more than 150mm and not less than 100mm as per
Engineers instruction and approval. Temperature of fresh concrete
shall not more than 30 deg. Celsius as per BS Standard.


This document is...
 

This document is...
 
 

   All data required for daily concrete schedule sheet will be recorded
in the daily concrete pour card.
   Concrete at truck mixer shall not exceed more than 90 minutes from
leaving batching plant.
   On acceptance, mix shall be directly unloaded in the concrete
pumps. Care shall be taken to make sure that concrete mix is not
dropping from more than a height of 2 meter.
   Concrete when introduced to the footing at first level of 400mm
shall then be vibrated, the same shall be done for the succeeding
layer of concrete until footing top level is reached.

   When concrete reach proposed level; hand trowelling should carry


out to get a smooth surface according to the top footing level.
   When the concrete is cured it shall then be applied with water
proofing system in accordance to the specification.
   For approval: Inspection request would be submitted to the
Engineer or Consultant for the concrete pouring approval.
4. Safety 

1.  All works shall comply with safety procedure or instruction set out in
project safety plan and Municipality rules and regulations.
2.  Basic PPE to worn by all staff and laborers.


This document is...
 

This document is...
 
 

3.  Trained operator and banks man will be engaged to control or operate
heavy equipment machine.
5. Equipment and Tools 

1.  Concrete pump


2.  Truck Mixer
3.  Boom loader
4.  Bobcat
5.  Concrete Vibrators
6.  Wheel borrow
7.  Surveying instrument
8.  Metal tape
9.  Slump cone
10.  Slump tray
11.  Trowel
12.  Cubes
13.  Shovel
6. Materials and Reference 

1.  C40/20 Concrete Grade with 70-80% GGBS


2.  Deformed Bars: 20mm dia., 16mm dia., 10mm dia.
The material mentioned above are as per our project specification, please
read your project specs before writing method statement.

If you have any further comment or suggestion on the above method


statement, you may write it down or leave a reply below.

Share this document


    

You might also like

Document 7 pages

Method Statement Concrete


Arthur Ruhinda
No ratings yet 
This document is...
 
Document 5 pages

r.c.work
Lynn Mail
No ratings yet

Document 8 pages

Method Statement
ardsilva
No ratings yet

Magazines Podcasts

Sheet music

Document 11 pages

MOS for Footing Concrete


Pouring.pdf
Ye Yint
No ratings yet

Document 6 pages

Method Statement for Footing


Concrete Pouring
Nino Celso Astillero

No ratings yet This document is...
 
Document 9 pages

Method Statement for Footing


Concrete Pouring
Kishore Kumar
No ratings yet

Document 9 pages

Method Statement for Footing


Concrete Pouring-converted
Kishore kumar Matcha
No ratings yet

Document 9 pages

statemtn
MuhammadIqbalMughal
No ratings yet

Document 4 pages

Method Statement
Arnold Roy Manalo
No ratings yet

Document 3 pages

Method Statment - Concrete


Pour SoG
Muhammad Zafar Iqbal 
This document is...
No ratings yet
 
Document 7 pages

concrete
ugrasen chaudhary
No ratings yet

Document 4 pages

Method Statement of casting


slab
Shakila Nishani
No ratings yet

Show more

About Support Legal Social

About Scribd Help / FAQ Terms Instagram

Press Accessibility Privacy Twitter

Our blog Purchase help Copyright Facebook

Join our team! AdChoices Cookie Preferences Pinterest

Contact us Publishers Do not sell or share my


personal information
Invite friends

Gifts

Scribd for enterprise

Get our free apps


This document is...

Audiobooks • Books • Documents • Magazines • Podcasts • 


Sheet music • Snapshots 
Language: English

Copyright © 2023 Scribd Inc.


This document is...
 

You might also like