0A RCM Workshop Program Content
0A RCM Workshop Program Content
TRAINING / WORKSHOP ON
RCM
(Application of RCM – Reliability Centered Maintenance)
20 – 21 Mar 2014
AMC Jamshedpur
02 Days RCM Workshop Schedule
Date Session Content
Day 1 First A) Equipment Reliability, Fundamentals, Definitions:
Half Introduction on Modern Trends in Engineering on Equipment Reliability &
its affects on Business Strategy & Performance
Failures, Failure Rate (ROCOF – Rate of occurrence of Failures), Failure
Modes, Failure Patterns & Characteristic (Wear-in, Random, Wear out)
ROCOF Curve and Six Classic patterns of Failures
Equipment Dynamics, Criticality, Availability, MTTR, MTBF & Reliability,
Probability of Failure, RBD - Reliability Block Diagram
Failure Distribution Plots (Normal, Weibull etc)
Reliability Growth Plot, Cost of Reliability and Unreliability
Sample Exercize on Reliability Parameters like Criticality, MTTR, MTBF,
Reliability, RBD
Second B) RCM (Reliability Centered Maintenance), Maintenance
Half Strategy & Predictive Maintenance Techniques)
RCM Introduction & its difference from conventional Maintenance System
Maintenance Goals & Objective, Maintenance Strategy Selection –
Reactive, Preventive, Predictive & Proactive – Advantages / Disadvantage
Application of Weibull Failure Distribution for Maintenance Strategy
selection (B Factor, L10, L50, L90)
Operation & Maintenance Strategy Selection Overview
RCM Strategy Selection for Maintenance Plan Formulation Exercize.
Predictive Maintenance Techniques – Role & Application,
Selecting Key Parameters, Alarm, Warning & Baseline. Key CBM
Techniques - Vibration, WDA, Thermography, NDT and Case study
discussion. CBM Plan formulation Exercize
02 Days RCM Workshop Schedule
Day 2 First C) Risk Management – Application of RCM & Root Cause
Half Failure Analysis Tools
Risk Management, Risk Criteria based on Criticality
Parameters
Exercize on Sample Critical Equipment and Selection based
on Risk assessment (Rotating & Stationary Equipment)
Introduction to Root Cause Failure Analysis (RCFA) Tools -
Cause & Effect, Why Why Analysis, Fish bone, FMEA,
FME©A / FTA & Factor Analysis and Process of Failure
Analysis for Zero Downtime Activity.
Sample Exercize on RCFA Tools on Plant Problem Cases.
Second D) Life Cycle Cost (LCC), Fitness for Service (FSS) &
Half Steps for RCM Setup
Concept of LCC, Constituents of LCC, NPV, Acquisition &
Sustaining cost. LCC in decision Making, Exercize on LCC
Concept of FSS, application and Degradation Basics &
Failures attributes Like Fracture, Corrosion/Erosion, Cracks
etc.
Steps & Approach to Setup RCM implementation Program at
Plant Critical Equipment and Reliability Health Index
Feed back / Reviews & Action Plan formulation as per day 1,
2, learning
Key Course Objective