Schedule

This document outlines the tasks, timelines, and resources required to complete a 132kV transmission line and substation project from Mirama to Kabale in Uganda over 3 years from 2022 to 2024. Key aspects of the project include contracting, design and engineering, civil works like site preparation and construction of foundations, installation of equipment, testing and commissioning of the transmission line and substations. The project is split into two lots - Lot 1 covers the transmission line and Lot 2 covers the substations.

Uploaded by

narinder kumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
49 views1 page

Schedule

This document outlines the tasks, timelines, and resources required to complete a 132kV transmission line and substation project from Mirama to Kabale in Uganda over 3 years from 2022 to 2024. Key aspects of the project include contracting, design and engineering, civil works like site preparation and construction of foundations, installation of equipment, testing and commissioning of the transmission line and substations. The project is split into two lots - Lot 1 covers the transmission line and Lot 2 covers the substations.

Uploaded by

narinder kumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Project: 132KV Mirama-Kabale OHTL and Susbtations

ID Task Name Duration Start Finish 2022 2023 2024 2025 2026
H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2
0 MK- LOT1 (OHTL) & LOT2 (SS) 766 days Sat 1/1/22 Wed 1/10/24
1 Contract Effectiveness (Lot 2 SS) 198 days Sat 1/1/22 Sun 7/10/22
2 Bid Submission, Opening & Evaluation 108 days Sat 1/1/22 Fri 4/15/22 PM

3 Contract Agreement & Site Handing Over 90 days Fri 4/15/22 Sun 7/10/22 PM

4 LOT2- SUBSTATIONS 766 days Sat 1/1/22 Wed 1/10/24


5 Design and Engineering 140 days Mon 7/11/22 Wed 11/23/22
6 Site survey and soil investigation 30 days Mon 7/11/22 Mon 8/8/22 COW,PM,RE Civil,Surveyor

7 Civil Design, S/Yard layouts 30 days Tue 8/9/22 Tue 9/6/22 COW,PM,RE Civil,RE Elect,SS Expert

8 Electrical designs, data sheets 110 days Tue 8/9/22 Wed 11/23/22 PM,Prot Expert,Scada Expert

9 Civil Activities 330 days Wed 9/7/22 Sat 7/22/23


10 Land development 120 days Wed 9/7/22 Sat 12/31/22 COW,PM,RE Civil,Surveyor,EHS Expert

11 Fencing 60 days Sat 12/31/22 Mon 2/27/23 COW,PM,RE Civil

12 CR Building, foundations ,cable trenches 120 days Sat 12/31/22 Wed 4/26/23 COW,PM,RE Civil,SS Expert,RE Elect

13 Internal roads, gravel, fire fighting, 60 days Wed 4/26/23 Fri 6/23/23 COW,PM,RE Civil

14 Access road and finsihing activities 30 days Fri 6/23/23 Sat 7/22/23 COW,PM,RE Civil

15 Elecrical Activities 398 days Wed 11/23/22 Tue 12/12/23


16 Manufacturing, FAT, delivery of equipments 120 days Wed 11/23/22 Sun 3/19/23 PM

17 Installation of equipments 75 days Wed 4/26/23 Sat 7/8/23 PM,SS Expert,EHS Expert,Prot Expert,Scada Expert,RE Elect

18 Installation of necessary equipments, 60 days Thu 5/11/23 Sat 7/8/23 PM,Prot Expert,Scada Expert
checking of interfacing arrangements at
NLDC

19 Manufacturing , FAT, delivery of power Trafo 235 days Wed 11/23/22 Sat 7/8/23 PM
& installation

20 Earthing, Cabling and precomm checks at SS 133 days Sat 7/8/23 Mon 11/13/23 PM,Prot Expert,Scada Expert,SS Expert,EHS Expert,RE Elect

21 Testing and comm. 30 days Mon 11/13/23 Tue 12/12/23 PM,Prot Expert,Scada Expert,SS Expert,RE Elect

22 Post closing activities 30 days Tue 12/12/23 Wed 1/10/24


23 Handing over and closing 30 days Tue 12/12/23 Wed 1/10/24 COW,PM,RE Civil,Prot Expert,Scada Expert

24 LOT1-(OHTL) 378 days Sat 1/1/22 Sat 12/31/22


25 Civil activities 190 days Sat 1/1/22 Sun 7/3/22
26 Foundation activities 190 days Sat 1/1/22 Sun 7/3/22 COW,PM,RE Civil,EHS Expert

27 Tower and string activities 348 days Sat 1/1/22 Fri 12/2/22
28 Tower manufacturing and delivery 135 days Sat 1/1/22 Wed 5/11/22 PM

29 Tower erection 120 days Wed 5/25/22 Sun 9/18/22 COW,PM,TL Expert

30 Stringing 110 days Sat 8/6/22 Sun 11/20/22 COW,PM,TL Expert

31 Testing and commissioning 13 days Sun 11/20/22 Fri 12/2/22 COW,PM,TL Expert

32 Post closing activities 30 days Sat 12/3/22 Sat 12/31/22


33 Handing over and closing 30 days Sat 12/3/22 Sat 12/31/22 COW,PM,RE Elect,SS Expert

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline Manual Progress
Project: MK- LOT1 (OHTL) & LOT2 Split External Tasks Inactive Summary Manual Summary Critical
Date: Thu 6/29/23
Milestone External Milestone Manual Task Start-only Critical Split
Summary Inactive Task Duration-only Finish-only Progress