ARUP Embodied Carbon Concrete 1
ARUP Embodied Carbon Concrete 1
ARUP Embodied Carbon Concrete 1
Embodied Carbon
Concrete
Reference: 07762000-RP-SUS-0003
01 | 5 June 2023
This document is a snapshot in time of industry research, opinion, and knowledge. The
information is subject to change as industry progresses and new information comes to light.
This document is to be periodically reviewed and any comments or suggestions are welcomed
via [email protected] and the BIPAS team. BIPAS is a multi-disciplinary group of
engineers within Arup, funded via Arup's internal investment programme. We carry out
research and create resources relating to sustainability, primarily for use within Arup but
shared externally when it is appropriate. Our objective is to address those areas that
engineers engage with on a daily basis, to enable them to address sustainability in an
informed and effective manner.
Job number 077620
Introduction 1
Lifecycle 2
Stage A 3
Stage B 11
Stage C 11
Stage D 11
References 14
Figure 1
Life cycle stages for Portland cement concrete into corresponding percentages of carbon emissions [5].
Figure 2 shows an example C30/37 concrete mix broken down into the principal constituents per m3, and
compares mass and embodied carbon (A1-A5) to show the materials with the most significant environmental
impacts. Note that the reinforcement contribution will be dependent on the recycled content of the steel.
100% 6
13 30
80% Rebar [150kg/m³]
Figure 2
C30/37 concrete example mix including only CEM I with no replacements, by mass and embodied carbon, not including mineral
additives [2].
Module A1 includes the carbon emissions associated with extracting and manufacturing each constituent
material of concrete, which includes four main components: cement or cementitious materials, fine
aggregates, coarse aggregates, and water. The A1 emissions for concrete includes the A1-A3 emissions of
extracting and producing each material. Figure 3 shows the breakdown of A1-A5 emissions. A1-A3 for
concrete typically accounts for 75% of the A1-A5 carbon emissions concrete production.
Figure 3
A1-A5 emissions process.
Water
Clean, uncontaminated water should be used for mixing and curing concrete. EN 1008:2002 specifies the
requirements for water that are suitable for making concrete. The emissions associated with water in the A1
stage are less than 1% and so are negligible.
Admixtures
Admixtures can be added to the concrete mix during the manufacturing process (A3). By adding certain
admixtures, this can increase the consistence (workability) of a concrete and reduce the amount of water
required in the mix, hence reducing the permeability of the concrete, and increasing the overall strength
without increasing the cement ratio which is carbon intensive [9]. However, by using a plasticising
admixture, not to increase consistence, but to use less water for the required consistence, the cement content
of the concrete can be reduced to maintain an equal water/cement ratio. The concrete will therefore have a
lower embodied carbon but with equal strength and durability. They can also be added to facilitate
environmentally optimised mixes and are generally only added in small amounts.
Environmental Product Declarations (EPDs) for admixtures are provided per kg of admixture, and this may
not reflect differences in the functional performance of each admixture; For example shrinkage-reducing
admixtures include both liquid and powder-based products. Table 1 shows average values of carbon
emissions per kg of various admixture types. Note that admixtures are typically a small contribution to
overall CO2 emissions, but there are other environmental impacts attributed to manufacture and safe storage.
Table 1
kgCO2e/kg of admixture types [8].
Carbon Air entrainer Hardening Plasticiser and Retarder Set Shrinkage Water
Emissions accelerator superplasticiser accelerator reducing resisting
kgCO2e/kg admixture admixtures
Supplementary Cementitious Material (SCM) and Portland Cement - Global annual supply and
demand
Portland Cement
Fly Ash
Slag
Natural Pozzolan
0 500 1000 1500 2000 2500 3000 3500 4000 4500 5000
Mt/year
Used Available Demand
Figure 5
Supply and demand of commonly used supplementary cementitious materials and Portland cement [10].
Understanding the data for SCMs is an important step towards reducing the embodied carbon content of
concrete. Table 2 lists the A1-A3 embodied carbon emissions of cement and other cementitious materials
alongside relevant information on non-standard technologies, such as alkali-activated materials and carbon
sequestering technologies, for comparative purposes. However, it is noted that these technologies are not
currently commonly used in construction but may become increasingly popular in the next decade.
Table 2
A1-A3 embodied carbon emissions of cement and cementitious materials [2] [14].
Material / constituent Remarks Carbon factor Availability
[kgCO2e/tonne]
GGBS Widely used in concrete; up to 70- 42-70 [14] Short-term. Note that this is subject to change once
75% replacement. Up to 90% in economic allocation is incorporated throughout
certain applications This does not industry so could be up to 200 kgCO2e/tonne.
include
economic
allocation.*
Fly ash Widely used in concrete; up to 4 [2] Very limited in the UK. Note that this is subject to
35% replacement. Up to 55% in change once economic allocation is incorporated
certain applications This does not throughout industry so could be up to 200
include kgCO2e/tonne.
economic
allocation.*
Metakaolin Rarely used in concrete; mainly in 150-470 [14] Very limited to none in the UK
high strength concrete applications
where available. Up to 15-20%.
Natural Pozzolans Used in other countries; up to 35% Exact value Very limited in the UK. Exploration required
(e.g., volcanic ashes, replacement. Up to 55% unknown but
trass) replacement in special cases. normally low
(<50) [14]
Limestone fines Widely used as filler and has the 75 [2] Widely used. Not so much in the UK as SCMs but
potential to be regarded as SCM in industry is changing.
the UK; up to 25% replacement.
Alkali activated Portland cement free materials 50-400 [14] Somewhat in the UK; short-term. Inconsistent
materials / which utilise GGBS and fly ash material behaviour.
“Geopolymers” together with chemical activators
to produce concrete. Currently not
included in standards but covered
by PAS 8820.
Carbon sequestering Cementitious materials Highly variable – Under development in the UK (Concrete4Change,
technologies manufactured with sequestered from carbon Seratech) Note that carbon negativity is a
CO2 negative, to 700 controversial issue as it depends on the source of
CO2 used. It difficult to claim carbon negativity when
using commercial CO2 from methane reforming. If
CO2 from a cement plant is used, then there is a high
risk of double counting if both the cement plant and
the downstream user of the CO2 claim the benefit of
CO2 capture and sequestration.
GGBS and fly ash are by-products created from other industries; When assessing the embodied carbon of
structures, it is important that this carbon is calculated correctly. It is often tempting to take the highest
possible GGBS content (up to 70%) to lower embodied carbon in our design calculations – however, due to
the finite supplies of this material globally, increasing this content on one project may reduce the potential
for another building to do the same.
The carbon associated with internationally traded recovered resources currently stands behind a ‘double-
blind’ system of accounting: emissions do not register in the conventional territorial accounts of the
importing country and could be hidden from its consumption-based accounts too. The impacts of such trade
and related carbon accounting conventions are unclear, and we emphasise the need for further investigation.
A2 – Transport
Module A2 includes the carbon emissions attributed to the transport of concrete constituent materials from
their source or factories to the concrete batching plants. Globally, the raw materials used to make concrete
are typically abundant and locally supplied, making the transportation emissions of concrete minimal [15].
The type of transport mode used to move the different constituents of concrete will depend on the location of
the mines and quarries, processing facilities, and batching plants, but they are usually transported via road or
rail.
Portland cement
Portland cement is transported from the cement factories, often located near the quarries where the raw
materials are extracted, to various batching plants which are situated near towns or cities with the need for
concrete manufacture. It is worth noting that the UK currently imports around 20% of required cement.
Cement is also being traded globally and transported around the world. Vietnam and Türkiye are the biggest
cement exporters, with 13% and 10% respectively of shares in world exports of cement in 2021. The United
States and China are the biggest cement importing countries, accounting for 12% and 10% of global cement
import in 2021 respectively [16]. Table 3 shows the largest importing and exporting countries of cement and
cement clinkers.
Virgin aggregates
In the UK, the average journey of raw materials to a concrete batching plant is around 54km [2]. This may
vary in locations around the world where there is a higher demand than local availability. In large cities or
hard to reach areas, materials are brought in via rail or ships and vehicles will be used to transport aggregates
and cement to site for the last few miles [2].
Table 5
Transportation CO2e values.
Location of Mill Carbon Emissions kgCO2e/kg Assumption
compared to the site
Global >1500km 0.183 Transported mostly (10,000 km) by sea and then 200km by road
The embodied carbon that is typically released through burning fossil fuels for transport varies from country
to country. The transport industry is aiming to decarbonise with the electrification of railways and
development of hydrogen powered heavy goods vehicles (HGVs).
A3 – Manufacturing
Module A3 includes the carbon emissions of the manufacture of concrete which is also described as the
“batching” of concrete. The individual components of concrete are stored at the batching plant in bins and
silos. They are weighed and then mixed in either a plant mixer or truck mixer, then transported to site. This
process is mainly fuelled by electricity or diesel depending on the batching facility and this is the main
contributor to CO2 emissions during this stage [4]. Admixtures are added at this stage. Table 6 shows carbon
emissions produced in the A3 stages to batch concrete per kg in-situ and precast.
Table 6
A3 manufacturing process – batching plants [ICE database].
Item Carbon Emissions kgCO2e at A3
A4 – Transport
The batching of concrete is done in many locations positioned around cities and towns to ensure minimal
transport times. The A4 emissions associated with transporting the concrete from the batching plant to the
final site contribute relatively small amounts of CO2 to the total A1-A5 emissions [4].
In-situ concrete is most commonly transported to site in a concrete mixer. This allows for concrete to be
batched and pre-mixed ready for use on site immediately. Due to the restricted setting times of concrete, this
limits how far away the batching plants can be from the site; Hence, they are usually relatively close to the
site. For example, in-situ concrete in the UK travels on average 16km from batching plant to site. Batched
concrete is transported to site in wagons fuelled by diesel.
Alternative methods of transport can vary due to project requirements. A volumetric mixer is a mobile
batching plant which transports the ingredients of concrete to site, mixing it on the way, or once the vehicle
has arrived on site. This is a useful transportation method on projects where different types of concrete are
needed in small volumes.
A5 – Site construction
Module A5 includes carbon emissions of construction related activities associated with placing concrete on
site. This includes the emissions from the equipment used for installation, and the emissions associated with
the waste material. A5 typically accounts for approximately 14% of the A1-A5 carbon emissions of in-situ
concrete, however this value can vary [6].
Formwork
Timber formwork (generally 18mm plywood) is a flexible solution which is commonly used to shutter
concrete on site. The embodied carbon is significantly affected by the reuse rate and End of Life (EoL)
scenario, aspects which can be difficult to determine in the earlier stages of a project. Due to the short service
life of timber formwork, it would be inappropriate to include the benefit of sequestration within embodied
carbon calculations as the carbon is only stored in the short term.
RICS guidance assumes that, in the absence of project specific information, plywood formwork is re-used
three times before being incinerated [19]. Information from contractors suggests that this may not reflect the
reality, with a lot of plywood formwork being used just once. Plain and special finish concrete can result in a
single use ply, as remnants remaining on the sheet make it unsuitable for further pours. Ordinary finish
concrete makes allowances for small defects, hence timber plywood can often be reused multiple times.
Plywood formwork may get reused on site in a different role, such as for fencing, but this can vary project to
project and will still result in new formwork being required for further pours. How the ply is recycled/reused
is down to the supply chain.
It is important that engineers engage early with architects and contractors to discuss the benefits of
specifying a lower grade finish, changing formwork reuse rates, and alternative formwork types.
Waste
The volume of site waste and the associated carbon emissions, varies depending on the processes used by the
contractor. Global waste values are typically 1-6%, but can sometimes reach as much as 13% due to
overordering of concrete as a precaution. Additional elements to enable the concrete pour should also be
taken into consideration such as concrete blinding, temporary works including timber formwork and
falsework [20]. Table 7 shows the associated waste ratios and waste factors for several concrete products
[20].
Table 7
Waste ratios and factors for in-situ/precast concrete and formwork.
Material/product Waste ratio (WR) Waste factor (WF)
Stage C
Stage C includes the emissions associated with demolishing and removing concrete components from a
building.
Global figures on the waste and disposal of concrete are not readily available and are expected to be highly
variable from country to country as well as from region to region. Many different factors contribute to these
variations such as local laws and regulations for landfilling of demolition waste and the access to virgin
aggregates. Often there are incentives or penalties and therefore there may be increased interest in recycling
concrete as aggregate, rather than letting the material go to landfill. High recycling rates are reported in the
Netherlands, UK and Japan [22]. Concrete waste can also be used as an Alternative Raw Material (ARM) or
Mineral Component (MIC) in the manufacture of new cement, but this is still under development.
Stage D
Circular economy
For concrete this could be re-using concrete by crushing for aggregate, cutting it up into smaller blocks, or
more effectively, re-using structural elements, allowing for maximum use before being recycled or replaced
[23]. Carbon could be saved by extending a concrete frame’s life; however, this is project-specific and needs
to be calculated on a case-by-case basis. Designing for deconstruction with concrete is difficult, so the future
use of buildings needs to be considered at the outset of a project. [23].
Recycled aggregate
Recovered concrete can be recycled as aggregate in new concrete, but the quantities may be limited by local
regulations and physical properties, especially for structural concrete applications. Regardless, in some
situations crushed and reused concrete can often be better than virgin aggregates [24]. It is important to only
specify recycled aggregates when there is a local source available, otherwise transportation emissions may
outweigh the intended carbon benefits [18]. Additionally, depending on the type of recycled or secondary
aggregates, there may be increased water demand and a need to increase the cement content of the concrete
to achieve the specified characteristic strength, with a consequential increase in eCO2.
The potential for CO2 uptake during the demolition, crushing and waste handling stages is relatively larger
than the B1 stage due to the increased surface area of concrete, however it is still only a small percentage of
the overall carbon impact [19] [21]. It has been claimed that if a concrete element is crushed and left on site
for 26 weeks before being moved, it can reabsorb up to 5% of the original A1-A3 emissions carbon produced
[13].
De-carbonisisation of electricity
36
Carbon capture and utilisation/storage (CCUS)
11
Efficiency in concrete production
22
Efficiency in design & construction
Figure 6
Projected pathway to net-zero for the cement and concrete industry and the different contributors to achieve net-zero before 2050
[25].
Efficiency in design
According to the GCCA 2050 Cement and Concrete Industry Roadmap for Net-Zero Concrete, ‘Efficiency in
design and construction’ is the second largest area that will impact achieving net-zero carbon emissions by
2050. As designers, we can lower our carbon impact by:
Using less: Design with the minimal amount of concrete required by revising assumptions which are often
conservative; Aiming to have maximum utilisation can also be beneficial [26]. Using less can have the
biggest cost and carbon savings on a project!
Specifying concrete more effectively: Reduce the use of CEM I/Portland cement where possible, specify
appropriate concrete grade, allow the use of alternative aggregates and admixtures within concrete [27]. This
includes precast elements.
Benchmarking concrete: Establishing carbon benchmarks for concrete is important to classify concrete by
embodied carbon. There is ongoing work around this; However, this will require cross-industry support to
standardise the measuring, reporting and benchmarking of emissions produced by different concrete mixes
[10].
Design for the future: If future changes are anticipated, trying to delay the need for any replacement/major
refurbishment can have significant long term carbon reduction [26]. Also, circular economy principles
should be incorporated into the design and detail for easy disassembly and re-use at end of life. We should
also be designing to make maintenance and repair easier.
[2] The Concrete Center, “Whole-Life Carbon and Buildings,” MPA The Concrete Centre 2016, 2016.
[3] E. Sentucq and M. Clayton, “Beyond Portland cement: Low-carbon alternatives,” The Institution of
Structural Engineers.
[5] Fragkoulis Kanavaris (Arup), Karen Scrivener (EPFL), “The confused world of low-carbon concrete,”
Concrete Magazine, vol. 57, no. 3, pp. 36-39, 2023.
[6] P. Astle, “How can we reduce the embodied carbon of structural concrete?,” The Institute of Structural
Engineers, 2021.
[8] Low Carbon Materials, “OSTO - Carbon negative lightweight aggregate for carbon zero blockwork,”
2022. [Online]. Available: https://www.lowcarbonmaterials.com/products. [Accessed June 2023].
[11] K. Scrivener, F. Martirena, S. Bishnoi and S. Maity, “Calcined clay limestone cements,” in Cement and
Concrete Research, 2018.
[12] World Business Council for Sustainable Development, “Net-zero buildings: Halving construction
emissions today,” 2023.
[13] The Institution of Structural Engineers, “How to Calculate Embodied Carbon,” 2020.
[14] Arup, “Low Carbon Concrete: Practical guidance for Arup engineers,” 2019.
[15] Global Cement and Concrete Association, “Availability: Abundant, Local and Cost-effective,”
[Online]. Available: https://gccassociation.org/sustainability-benefits-of-concrete/availability/.
[16] International Trade Centre, “Trade Map,” International Trade Centre, [Online]. Available:
https://www.trademap.org/Index.aspx. [Accessed Jan 2023].
[17] Concrete Society Working Party, “Cementitious materials,” The Concrete Society, 2011.
[18] The Concrete Centre, “Specifying Sustainable Concrete - Understanding the role of constituent
materials,” www.concretecentre.com/publications, 2021.
[19] The Institute of Chartered Surveyors, “Whole life carbon assessment for the built environment,” 2017.
[20] The Institute of Structural Engineers , “How to Calculate Embodied Carbon,” 2020.
[23] The Concrete Centre, “Concrete futures: How concrete is evolving for a net-zero built environment”.
[25] Global Cement and Concrete Assosiation, “Concrete future: The GCCA 2050 Cement and Concrete
Industry Roadmap for Net Zero Concrete,” October 2021. [Online].
[26] M. Moynihan, “Steel, concrete and climate change,” The Institution of Structural Engineers, 2019.
[27] J. Burridge, “How to specify lower carbon concrete,” The Institution of Structural Engineers, 2020.
[28] Esri, “Ecosystem Science for Global Restoration,” in 2018 Esri User Conference Plenary, 2018.
[29] Price & Myers, “Avoiding false accounting - why correct carbon factors matter,” 2021.
[30] Z. P. V. I. B. Millward-Hopkins, “Resource recovery and low carbon transitions: The hidden impacts
of substituting cement with imported ‘waste’ materials from coal and steel production,”
Elsevier/Global Environmental Change, 2018.
Contributors
Content created by: Jo Spencer, Leonora Pilakoutas (Skanska), Fragkoulis Kanavaris, Magdalena Janota,
Orlando Gibbons, Liu Chang, Beth Lockhart, Conor Hayes, George Dalkin, Cameron Creamer, Rogier van
Reen.
Content kindly reviewed by: Grace Di Benedetto, Chris Carroll, Ed Hoare (Arup), Ryan Roberts (Holcim),
Melanie Jans-Singh (BEIS), Mike de Silva (Clancy Group), Apostolos Tsoumelekas (SCS Railways), Paul
Astle (Ramboll), Bahman Ghiassi (Birmingham University), Gareth Wake (MPA Ready-Mixed Concrete),
Michal Drewniok (Leeds University)