Appendix-11-B-rev Anchor Handling
Appendix-11-B-rev Anchor Handling
Appendix-11-B-rev Anchor Handling
Revision History
Note: It is recommended that chain connectors (kenter, etc.) are being used for connecting
for all mooring line segments. The use of shackles in mooring line should be avoided.
Note: Depending on mooring line dimension Shackles should be avoided in the mooring line.
Buoy off
System
Net buoy uplift to be 30% higher than
Surface buoy carried weight in system
Shackle
Shackle
Studless tail
Kenterlink
Kenterlink
Studless tail
Kenterlink
Wire Swivel
Kenterlink
1. Use an appropriate rated swivel in the working wire to prevent wire spinning.
5. Use correct wire length for the water depth, i.e. 1 ½ times water depth.
Recommended design is below
4 PIGGYBACK SYSTEM
Recommended design of piggyback system - with associated equipment.
Note: The minimum breaking load of equipment between piggyback anchor and primary
anchor shall be a minimum of 70% of the main anchor line minimum breaking load.
Piggyback anchor shall be appropriate to sea bottom conditions based on the site
survey.
Piggyback should be landed with use of a bridle system to ensure right anchor
orientation.
5 CHASING PENDANT
Sling I Important:
1) Clear communication between winch, crane and AHV
2) Rig winch operator to monitor chain lenght paid out
Sling II
Tugger wire
Sling II
Sling II
Surface Buoy
Rigging and Safe Deployment
Preparation
1. Socket placed in shark jaw
2. Wire sling in end of work wire around
crucifix (lower part)
Deployment
1.
2. 3.
Surface Buoy
Deep Water Safe Deployment
400-1000mtr water depth
Preparation
Deployment
Surface Bouy
Work wire
Pennant wire
Vessel to head back to anchor and take position fix of installed anchor (or marker buoy if
anchor is not visible). Check that final anchor position is within the acceptance criteria
given in Work Specification. An ROV can also be used to observe anchor penetration.
General
Fibre ropes are extremely robust when handled in accordance with procedures, but can
be very easily damaged if there is abrasion caused by 3rd party interaction such as wire
ropes, anchor flukes, trawl lines from fishing vessels, welding spots on deck, etc.
Ropes shall under no circumstances be exposed to high temperatures such as welding,
welding sparks, flare or grinding.
Ropes must not be exposed to chemicals. If this happens, rinse with fresh water and
seek immediate advice from manufacturer prior to use.
A special sand and clay barrier is installed on all fibre ropes used for mooring operations
(see figure):
Sand Barrier
Mobilisation
The ropes should be spooled on to the vessel’s drum, under tension, using a spooling
device which shall be either secured on the vessel’s deck or secured on the quayside
leading to the stern of the vessel.
The Mooring Equipment Representative shall ensure that the following points are in
place prior to commencing the loading of the fibre ropes:
• Clear deck policy is adhered to during the operation
• Ensure clear communication lines between spooling machine operator and
vessel winch operator are in place.
• Ensure that there are no obstructions in the path of the fibre rope.
• Ensure that the vessel’s winch is free from any sharp edges.
• Check socket compartment for other wire rope / shackles that may damage rope.
Also check that the dimensions of compartment are sufficient to fit the fibre rope
eye + fittings.
• The Inner end of fibre rope needs to be fitted with a spool piece, shackle and 10-
link chain adapter. This is to be connected to the wire forerunner on the vessel’s
winch.
• The spool piece in the eye of the rope shall be secured by lashing 10-12mm
ropes through dedicated holes in the steel spool.
• During spooling the fibre should never be in contact with the end-spool
termination.
• If spools are to remain in the fibres, protective matting must be utilized on the
vessel’s drum to avoid damages.
Several methods are being used for recovery and connecting fibre ropes in mooring
lines.
The following description is of the most common of these methods where PCP is hang
off from the rig and chaser stopper is between rig chain and fibre rope.
The following principles are recommended to be used for the different methods.
• AHV to connect the 60m PCP to rig chain and deliver PCP to the rig.
• AHV to heave in work wire, recover and disconnect the chain segment and
recover fibre and any Sub Surface Buoys
• AHV to connect swivel and 400m pennant wire to anchor chain and buoy off,
using safe release method.
Note: When paying out fibre rope, pay special attention to fibre position on the stern.
High tension should not be observed during pay out; the fibre should be on the stern
roller and have a straight line towards the anchor or rig, in order to avoid high friction
which may cause heat damage.
With the fibre rope and rig chain secured in shark jaw and the vessel positioned 90
degrees on the mooring line; allow the vessel to find its own equilibrium with decreasing
power to avoid unnecessary use of power and strain to the equipment.
For deep water operations it is recommended to cool down the fibre with water spray
when the fibre is passing the stern roller in order to avoid overheating.