07 Mikula

Download as pdf or txt
Download as pdf or txt
You are on page 1of 18

Ground Support 2013 — Y. Potvin and B.

Brady (eds)
© 2013 Australian Centre for Geomechanics, Perth, ISBN 978-0-9806154-7-0
doi:10.36487/ACG_rep/1304_07_Mikula

Shotcrete ribs and cemented rock fill ground control


methods for stoping in weak squeezing rock at Wattle
Dam Gold Mine

P. Marlow Ramelius Resources Pty Ltd, Australia


P.A. Mikula Mikula Geotechnics Pty Ltd, Australia

Abstract
Wattle Dam Gold Mine has successfully mined a significant gold orebody in very weak rock, where some of
the ore strength was less than 1 MPa. Almost 100% ore recovery was achieved despite the weak rock.
Conventional rockbolts did not achieve high anchorage capacities in this material. As mining extended to
depth, squeezing developed in the rock mass. The mine trialled several ground control options in response to
developing hazards and implemented two of them successfully. The first was shotcrete ribs for long-term
control. The ribs were installed after allowing some squeezing movement to occur. Novel methods were
developed to easily fabricate mesh for the ribs. The second option was cemented rock fill (CRF) for backfill of
stope panels in order to control convergence and overbreak. Novel crush firings were used to allow blasting
of stopes without conventional rises being required.

1 Introduction
Wattle Dam Gold Mine, operated by Ramelius Resources Ltd, has successfully mined a significant gold
orebody in very weak rock, achieving near 100% ore recovery within budget targets.
The Wattle Dam underground operations near Widgemooltha, Western Australia, commenced in 2009
followed the completion of an open pit stage. The nominal production rate was 15,000 t ore monthly until
the deposit was fully mined out in October 2012. In the final months, the production rate exceeded 30%
above target due to the excellent performance of the stopes and the ground support strategies. Operations
were carried out by HWE Mining (now Leighton Mining) under contract.
Geotechnically, the most significant feature of the deposit was the very weak strength of the ore, often less
than 1 MPa. Conventional friction bolts did not achieve high anchorage capacities in the weak rock
material. Then as mining extended to depth, up to 360 m below surface, squeezing developed in the rock
mass.
The mine trialled various ground control options in response to developing hazards, modified them to suit,
and implemented them successfully. Targets were met for effective production – there were very few
unplanned falls of ground, and rehabilitation strategies were successful.
This paper focuses on the characteristics of the squeezing ground, and the shotcrete ribs (Figure 1) and CRF
practices that were used to adequately manage that ground. The mine experienced a wide range of other
conditions common to many mines, but these are outside the scope of this paper.

2 Geomechanics: geology, lithology, stress


2.1 Geology and structure of the deposit
Local stratigraphy of the Wattle Dam deposit consisted of a sequence of steep west-dipping
metamorphosed ultramafic, sedimentary and basaltic units. The gold lode mineralisation zone was a major

Ground Support 2013, Perth, Australia 133


Shotcrete ribs and cemented rock fill ground control methods for stoping in P. Marlow and P.A. Mikula
weak squeezing rock at Wattle Dam Gold Mine

structural feature, being an altered shear zone within the ultramafic. The lode was generally 8 to 15 m wide
with an economic strike length of 30 to 60 m, and a depth extent of about 300 m.

Figure 1 A pair of shotcrete ribs installed for control of wide span backs at Wattle Dam

The hangingwall west side of the lode was a tremolite-chlorite ultramafic. Further to the west were a
schistose unit, and then a good quality basaltic sediment rock. The footwall side comprised a finer grained
actinolite-chlorite ultramafic unit. The mine access and infrastructure were located in the better quality
hangingwall rock mass.
The major faults were the west-dipping Charger fault which formed the top cutoff to the lode, and the
subvertical Regal fault which was well clear to the west of the lode. Another structure, the Graphite Shear,
was located in the sediment also well clear of the lode. It had significant water inflow.
On smaller scales, various joints and structures were present. These generally had relatively little
continuity. Defect surface profiles tended to be gently undulating, smooth, with chlorite, carbonate or clay
infill. Foliation was parallel to strike and was variably developed across the site.
Rock weathering depths were typically 50 to 60 m, but some areas of deeper oxidation near the Regal fault
were encountered down to 155 m depth.

2.2 Groundwater
The water table was at 46 m below surface. Groundwater inflows to underground workings were initially
high but then reduced. There were inflows from the Graphite Shear at various depths, and often from
exploration boreholes intersected by underground development.
Water is a destabiliser in weak ground as it reduces the effective stress and thus the shear strength of rock.
This was a contributing factor to the squeezing ground. Weak ground preferably should be drained.

2.3 Rock strength


Some exploration holes encountered very weak or rubble zones within the ultramafic, i.e. gravel, sand and
silty fragments, with no or very few pieces of broken core. In one case (Figure 2) a large amount of
fragments was recovered from just a short core interval. This indicated that the material was washed out,
or caved into the borehole, leaving a large cavity behind.
Selected strength test data for the immediate hangingwall and footwall of the lode are shown in Table 1.
The lode ore itself was too weak to be suitably sampled for laboratory testing. For the ore, the typical

134 Ground Support 2013, Perth, Australia


Squeezing ground

material could be easily penetrated by thumb nail, and crushed in the hand, indicating an in situ strength
estimate of less than about 1 MPa, perhaps only 0.5 MPa.

Figure 2 Fragments recovered from borehole WDUD209

Table 1 Selected laboratory test data for material adjacent the ore

Rock Type Approx. Density UCS Elastic No. of


Depth (m) (t/m3) (MPa) Modulus (GPa) Tests
Hangingwall ultramafic, with moderate 230 2.84 25 8.8 1
chlorite alteration
Hangingwall ultramafic 241 2.81 23 11.4 1
Hangingwall ultramafic 289 2.68 8 1.6 1
Hangingwall ultramafic, remnant within 294 2.87 41 7.7 1
lode zone
Footwall ultramafic, weak/moderate 336 2.89 39 28.8 1
chlorite alteration

One result of the weak strength of the ore was that boreholes in ore were badly affected by washout
during drilling, causing diameter increase. The result for example was that the jumbo was able to drive a
47 mm jumbo Split set into a 35 mm diameter hole. It was not unexpected that friction bolts in ore had low
capacity (in situ proof load tests of installed bolts indicated 15 kN/m anchorage).

2.4 In situ stress regime


Based on the geological structural setting, the likely stress field was assumed to be as per Table 2. No stress
measurement was undertaken. Stresses were too low to be successfully measured using conventional
methods such as the Hollow Inclusion overcore.
The stress field was also estimated from observations of squeezing. For example significant squeezing in
ore first occurred on 40 Level, 300 m below surface. In that case the failure strain in the walls was
estimated at 0.12% (based on observation of the buckling geometry of thin slabs in the walls). For a
modulus of 10 GPa, this implied a stress of 12 MPa in the walls.

Ground Support 2013, Perth, Australia 135


Shotcrete ribs and cemented rock fill ground control methods for stoping in P. Marlow and P.A. Mikula
weak squeezing rock at Wattle Dam Gold Mine

2.5 Q system characterisation and ground support requirements


Table 3 presents the Barton Q-system summary of the rock domains and characterisation (Barton et al.,
1974). All rock types included localised and apparently random poor zones (structured, slickensided, slabby,
weaker strength) within a better quality rock.

Table 2 Assumed stress field in Wattle Dam at 200 m depths (pro-rata for other depths)

Component Assumed Orientation Assumed Magnitude


Sigma–1 In the plane of the foliation and along strike of the major 10 MPa
faults, i.e. subhorizontal trending NNW–SSE
Sigma–2 Normal to the major fault planes, i.e. shallow dip to the ENE 6.7 MPa
Sigma–3 Subvertical 5 MPa

In all rock types, unravelling tended to dominate over wedge formation, and wedge analysis was rarely
required. Therefore support demand estimation was based on the Q data supplemented by visual
observations of performance during excavation. The variability of the rock mass was reflected by choosing
the 25th percentile Q values in estimating the ground support demand.
These support demands indicated that typical rock and ore would require 50 to 90 mm shotcrete, and bolt
spacing of 1.4 to 1.7 m. The poor quality zones required additional shotcrete. Weak ore required 200 mm of
shotcrete, which was approximated by the installation of shotcrete ribs as described below.
The adopted Ground Support Schemes (GSS) for ore drives are shown in Table 4. Two schemes were in use,
being either with or without shotcrete ribs.
Spiling bolts (splitsets) generally controlled ore backs in development. Spiling bolts were effective to
support subvertical joint planes, to assist with control of weak or unravelling ground, or any situation
where backs failure is expected. Spiling bolts were placed as a fan of bolts less than 0.8 m apart, angled
about 10o above horizontal, prior to taking a cut.

Table 3 Indicative support requirements for conservative Q data. These requirements are
estimated for a depth of 200 m below surface

Rock Type Typical Q 25th Maximum Stable Suggested Suggested Support


Strength Percentile Unsupported Span Support Pressure in
(MPa) for Permanent Pressure in Intersections
Opening (m) Drives (kN/m2) (kN/m2)
Ultramafic typical 80 10 9 40 70
Ultramafic weak 25 5 7 50 90
Ore typical 10 1 2.5 130 220
Ore weak 1 0.7 2 170 290

3 Mining methods and sequence


3.1 Mining methods
Bulk open stoping mining methods with post extraction backfill were used. The target was 100% extraction
of the very high grade ore. The lode width generally exceeded that which could be recovered in a single
slice. Therefore a two-pass slice strategy (and locally, three slices) was used to achieve a high extraction
ratio. The first pass stopes were the footwall stopes, which were backfilled with cemented rock fill (CRF)

136 Ground Support 2013, Perth, Australia


Squeezing ground

prior to taking the next stope. Then the second pass hangingwall stopes were recovered from beside, and
in some cases beneath, CRF-filled primary stopes (Figure 3). CRF strategy is described in Section 6.

Ground Support 2013, Perth, Australia 137


Shotcrete ribs and cemented rock fill ground control methods for stoping in P. Marlow and P.A. Mikula
weak squeezing rock at Wattle Dam Gold Mine

Table 4 Minimum ground support schemes for 6 m wide × 5 m high arched ore drives

Scheme Backs/Shoulders Walls Standard Load


Capacity (kN/m2)
GSS 10 50 mm in-cycle fibrecrete 50 mm in-cycle fibrecrete Backs 280
Ore, no squeezing 3 m resin bolts @ 1.2 × 1.2 m 2.4 m Split sets @ 1.2 × 1.2 m Walls 230
Mesh over fibrecrete Mesh over fibrecrete to grade
Spiling bolts line

GSS 14 As above but with shotcrete As above but with shotcrete Backs 780
Ore, under CRF or rib rib Walls 730
with squeezing
Component data:
Resin bolts: Minova T20 paddle bolt, 19.5 mm diameter. Plates 150 × 150 × 4 mm.
Friction bolts: Split set Mining Systems Split set. Plates 150 × 150 × 4 mm.
Fibrecrete fibre: Synmix 65, 5 kg/m3.
Shotcrete ribs: Refer Section 5.

4 2

Footwall
Hangingwall Stopes
Stopes

3 1

Figure 3 Mine layout showing (left) longitudinal view of an upper block extracted and a lower
block in progress, (right) a typical cross-section of stope layout with bold numbers
indicating extraction sequence

138 Ground Support 2013, Perth, Australia


Squeezing ground

Ore drives were parallel to strike and to foliation. Fortunately foliation was poorly developed in the ore and
the immediate host rock else the degree of squeezing experienced would have been higher.

The design features of this method were:


 Stope access was by a footwall drive in the ore, then stoping and CRF backfilling of 6 m strike
length primary stopes on retreat (Figure 3). On completion of the footwall slice, a hangingwall
slice was taken in a similar manner.
 Large sill pillars separated a number of stoping blocks, for production rather than geotechnical
reasons. Sill pillars were one level interval high. Sill pillars were only removed once the overlying
and underlying stoping panels had been mined and backfilled.
 The sequence was to mine a footwall stope a long time (at least several weeks) ahead of its paired
hangingwall stope. Geotechnically, the advantage was that the CRF in the footwall stope was then
older and stronger.
 A standard stope strike length of 6 m was adopted, based on the stable/transitional demarcation
in the Mathews Stability Chart analysis (Trueman et al., 2000). This suited both geotechnical and
production requirements. It proved to be a good choice as very few cases of significant overbreak
were encountered.

Figure 4 The Panel three stope void on 185 Level seen from above. Drillhole collars seen in the
foreground are for the crush firing. The mound in the middle distance is the CRF of the
previous stope after being punched up by the previous crush firing

All hangingwall stopes performed better than their footwall stope pairs, i.e. less squeezing, less closure, less
brow instability. The favoured status of hangingwall stopes was because:
 they were dry – being drained by the footwall stopes,
 they were in destressed ground – the footwall void put the hangingwall areas into stress shadow,
so squeezing pressures in backs were minimal, as most closure had already occurred during
footwall development and stoping,
 they had stronger walls – a CRF east side wall and an ultramafic west side wall, whereas footwall
stopes had a weak ore wall.

3.2 Three firing types


The mine used three classes of firings as follows:

Ground Support 2013, Perth, Australia 139


Shotcrete ribs and cemented rock fill ground control methods for stoping in P. Marlow and P.A. Mikula
weak squeezing rock at Wattle Dam Gold Mine

Production firings: These were conventional firings of the stope.


Crush firings: The mining method required immediate CRF filling of each stope to maintain stability and
reduce wall convergence. Conventionally, this would require the drilling and blasting of a new slot rise for
every stope. In order to avoid that, the practice was adopted to ‘crush’ or compact the CRF by blasting
against it using pre-drilled blastholes immediately after CRF placement. A compression of about 20% in the
CRF was achieved, creating sufficient space for the next production firing. Crush firings are described in
Section 6.3.
Half-upper firings: These were designed to remove the intensive ground support in the ore access drives.
Half-uppers were fired prior to both the crush firings and the production firings.
 The half-uppers for the crush firing removed the shotcrete rib and some of the adjacent ground
support. Blastholes were also drilled in the shotcrete ribs themselves.
 The half-uppers for the production firing removed the remaining ground support for the stope.
These half uppers created a good brow, and also protected the next shotcrete rib (the future
stope brow) from the force of the main production rings.

4 Squeezing ground
Backs: Cracking and squeezing occurred in the backs of various ore drives (Figure 5). Essentially a skin of
ore, usually 1 m and up to 2 m thick, squeezed and fractured, bulked in volume, and pushed down onto the
fibrecrete skin, causing cracks. At the same time, horizontal stresses caused closure, sometimes causing
shearing damage in the fibrecrete.
The damage usually first appeared some hours after blasting rather than immediately, and gradually
worsened with time. Water in the drive above, if any, disappeared into the floor as the ground became
fractured. In some instances drilling of boreholes had water return loss, and brow cables took excess grout
– both indicating voids had opened in the backs.
Cracking and squeezing was more likely at depth, in a footwall drive, in wider spans, and under a sill pillar
(i.e. high local percentage extraction). A sill pillar width/height ratio of 1:1 showed squeezing (the 185–200
sill) whereas a thicker pillar (ratio 1.67:1) did not.
Walls: Vertical squeezing occurred in walls and pillar noses, fracturing the weak ore lode rock and causing
bulking (Figure 6). Fibrecrete initially cracked, then buckled into the drive, and winging (lifting of edges of
fibrecrete away from the wall) was common. Damage developed gradually over time. Squeezing was worse
where subvertical wall structure focussed stress between the excavation and the structure.

140 Ground Support 2013, Perth, Australia


Squeezing ground

Figure 5 Cracking of fibrecrete in the backs of the Panel nine stope, 185 Level

Figure 6 Squeezing in ore in walls at depth: (left) damage on 40 Level west wall, (right) damage
exacerbated by water inflow (20 Level)

4.1 The rate and amount of squeezing closure


On the 125 footwall ore drive, survey prisms (Figure 7) and borehole camera observations were used to
enable tracking of wall and back movements during development. The camera results indicated the rock
mass was significantly fractured for a distance variably 0.2 to 0.8 m into the wall as soon as it was
developed. Further localised damage was seen up to 1.5 m into the wall, and one camera hole was making
water from a joint about 5 m into the wall.
In the 40 Level study, the survey prism data indicated horizontal closure of 33 mm (total both walls) and
vertical of 13 mm, from the installation of the prisms to the completion of the development stage. The
horizontal closure by this time equated to 0.6% of the opening width in each wall. Unfortunately, damage
to the prisms prevented this monitoring continuing into the production stage. On 125 Level, wall closures
were about the same as on 40 Level during development, but backs closures were less. Maximum
measured 125 Level wall closure was 113 mm (total) or nearly 2% of the opening width.
Movement rates varied in line with mining (being less during a passive period while mining was conducted
elsewhere). The rate of passive period closure was the order of 0.4 mm/day in each wall. This compares to
a peak active period rate measured at 1.0 to 1.2 mm/day in each wall.

Ground Support 2013, Perth, Australia 141


Shotcrete ribs and cemented rock fill ground control methods for stoping in P. Marlow and P.A. Mikula
weak squeezing rock at Wattle Dam Gold Mine

In many locations, it was possible to visually estimate vertical strain from the geometry of bulking of slabs
in walls. Localised strains of up to 2.8% were estimated, which is quite high. Ground support schemes were
tasked to contain the broken rock and prevent it unravelling. Over time, squeezing movements were
sufficient to tear plates from bolts (but not from cable bolts which always remained intact).
Mercier-Langevin and Hadjigeorgiou (2011) presented a ‘Hard Rock Squeezing Index’ based on stress and
foliation data from several mines. The Wattle Dam performance for the walls is indicated (Figure 8) and
matches the Index expectations (1 to 5% strain). The ore performance is not shown because ore strength
was too low and outside of the Index limits.

4.2 Squeezing ground rationale


If placed under sufficient stress, weak unconfined rock failed towards the opening soon after development.
As the face moved on, stresses came to a new equilibrium, and movements slowed down.
Water exacerbated the failure and the movements. Groundwater is a destabilising influence in weak
ground (effective stress principle). Groundwater was associated with a fall of ore in the 225 NOD, and with
squeezing damage from 60 Level and deeper.

Figure 7 Survey prism data for closures in the 125 and 40 Level footwall ore development drives

142 Ground Support 2013, Perth, Australia


Squeezing ground

Figure 8 Wattle Dam hangingwall squeezing performance on the Hard Rock Squeezing Index
(Mercier-Langevin and Hadjigeorgiou, 2011). The arrow indicates the range of
performance at 300 m depth due to the range in strength

The strategy to control squeezing was:


 Apply initial in-cycle fibrecreting, followed by bolts and mesh, to lock up the walls, providing
confining stress which opposed bulking and reduced the eventual final movement.
 After enough time and when the face had advanced away, install fibrecrete ribs, and rehabilitate
as necessary with 100 mm fibrecrete and sometimes cables between the ribs.
Observations showed that most movement occurred as the face moved from 6 to 16 m away. Therefore
ribs were delayed until the face was at least 10 m away and often more. The delay recognised that some
squeezing and bulking was going to occur despite any practical level of ground support.
This approach has similarities with the New Austrian Tunnelling Method (NATM) described for example by
Pascoe et al. (1995), Sauer (2003), and Karakus and Fowell (2004). First pass support is installed at
development. Instrumentation is installed at development to track the movements and stress changes. As
development continues, when the movements are judged to be stabilising, a strong second pass support is
installed to lock up the rock mass and ensure long term stability.
Shotcrete ribs were not restricted to squeezing ground, but were also installed for other reasons, including
wider spans, and under CRF backs. As there were no squeezing pressures in these situations, the ribs were
installed close to the face.

4.3 Shotcrete island pillars


The mine also trialled the use of shotcrete island pillars (Figure 9) for support of squeezing ground in the
185 FWD backs under a particularly wide span (9 m). The pillars were successful, but were not as easy to
fabricate as a rib, so were not used going forwards.

Ground Support 2013, Perth, Australia 143


Shotcrete ribs and cemented rock fill ground control methods for stoping in P. Marlow and P.A. Mikula
weak squeezing rock at Wattle Dam Gold Mine

Figure 9 Shotcrete island pillars on the 185 Level

5 The use and role of shotcrete ribs


Ribs were used where a very high level of static support capacity was required. Ribs contained a mesh
framework which was filled with sprayed fibrecrete. Ribs either comprised just the arch section
(terminating in the upper wall) or included legs, depending on the strength of the wall and the purpose of
the installation.
The estimated rib load capacity was based on the shear strength of fibrecrete. A rib of cross-section area
0.25 m2 had a nominal axial load capacity of 10,000 kN, and a shear strength capacity of 300 kN. Due to the
geometry of the rib (it had depth) it was resistant to buckling, and was able to achieve transfer of loads
from the backs into the legs of the rib and then into the walls. Overall support capacity provided by the
typical pattern of ribs, i.e. spacing of 6 m along a drive of span 6 m, was estimated as at least 500 kN/m2.
Some industry examples of the use of shotcrete ribs and arches are given by Chan and Shen (2008) and Li
(2005).

5.1 The construction of ribs – mesh bending machine


The site enjoyed the use of a mesh bending machine, designed and built in-house by a contractor
employee, for the preparation of mesh for the shotcrete ribs (Figure 10). Various profiles could be formed
by this machine. The one most used for shotcrete rib mesh was formed from a mesh sheet 4.5 m long by
1.0 m wide. A piece of 300 mm width was bent up along each long edge of the mesh sheet.
The arch or rib was shaped and constructed to withstand compression and reduce the risk of the snap-
through failure mechanism operating. The mesh cage was first bolted to the rock, then the cage was filled
with shotcrete (Figure 11). For best rib performance, significant steel content was positioned at the free
outer edge of the rib, furthest from the rock.

144 Ground Support 2013, Perth, Australia


Squeezing ground

Figure 10 Mesh bending machine

5.2 The performance of ribs


Generally during stoping, the ribs were stable. Ribs performed as least as well as fibrecrete skins in
containing poor ground. Fibrecrete skins tended to crack and bulk, despite more shotcrete going into the
skins compared to the ribs. As well as in squeezing ground and for support under CRF, ribs were used for
rehabilitation, and for brows (Figure 11). Shotcrete ribs at ore drive brows were useful, because in effect
they lowered the height of the backs, bringing the rill point lower, and increased safety for bogging.

Figure 11 Examples of mesh cage attached to rock, with portions being filled with fibrecrete

Ground Support 2013, Perth, Australia 145


Shotcrete ribs and cemented rock fill ground control methods for stoping in P. Marlow and P.A. Mikula
weak squeezing rock at Wattle Dam Gold Mine

Figure 12 Shotcrete ribs (left) for control in squeezing ground, with significant deformation prior
to the rib being installed, and (right) installed for support of a stope brow

Ribs were preferred over cables as they provided much more support. However they were stiff and strong,
and could not withstand very much deformation. Therefore rib timing was important in squeezing ground,
as previously described.
Several types of damage were observed to occur to ribs:
 Spalling, or cracking parallel to the surface of the rib (Figure 13). Thin plates of fibrecrete outside
the mesh cage separated off. Spalling damage was managed by periodic check-scaling of the ribs.
 Cracking across the thickness of the rib to form a hinge (Figure 13). This occurred due to lateral
loading (perpendicular to the rib axis).
 Shearing damage (Figure 14) due to high axial compressive loading in the rib due to closure of the
ground. Rarely, a rib had to be re-secured with bolting. Ribs nearly always survived for the life of
stoping on a level. In general the ribs brought equilibrium to the bulking in the backs.
 Blast damage (blastholes too close to the ribs) causing enough lateral loading to buckle the ribs.

Figure 13 (left) surface spalling, and (right) hinge failure developing in a rib

6 The use and role of CRF and crush firings


CRF suited Wattle Dam with its small stopes and placements where quality control was more easily
managed, and segregation could be avoided (Figure 15).

146 Ground Support 2013, Perth, Australia


Squeezing ground

Figure 14 Shearing failure in a rib

6.1 CRF mix and placement


CRF preparation commenced with the mixing of a specified quantity of grout slurry at a surface plant. The
batch of grout was then reticulated underground via a borehole system to the required level location. The
grout poured out into a mixing cuddy and directly onto five or seven buckets of waste rock which had been
prepared in the cuddy. The mix was trammed into the stope, and the process repeated until the stope was
full. A stope could be filled in 13 hours in the absence of interruptions.
Laboratory tests of large samples for the design of backfill gave 2.2 MPa and 2.5 MPa strength at 5%
cement. The adopted design strength was 3.5 MPa at 28 days. Walls of CRF at this strength stand extremely
well. CRF usage parameters were:
 Cement content in footwall stopes was normally 5%, thus 1 m3 cement required for 25 m3 fill, or
3 t slurry to 60 t of waste rock (called a five-bucket mix). However, cement content was reduced
to 3.5% (a seven-bucket mix) in hangingwall stopes which were final stopes where CRF was not
exposed by any future mining.
 Cement slurry design was 1,180 kg/m3 cement. GP cement was used.
 Minimum seven days curing time before being exposed by adjacent mining (except for the crush
firing).
 The waste rock for CRF comprised both sediment and ultramafic. Some of the ultramafic was low
strength, which was a factor in the success of the crush firings which are described later.

Figure 15 CRF examples: (left) CRF forming a stope wall, (right) development of a HW drive
(centre) alongside a CRF-filled FW drive (right)

Ground Support 2013, Perth, Australia 147


Shotcrete ribs and cemented rock fill ground control methods for stoping in P. Marlow and P.A. Mikula
weak squeezing rock at Wattle Dam Gold Mine

6.2 CRF function


CRF performed as expected, except once when a fall occurred due to a cold joint above the backs. Cold
joints were formed at time-interruptions to CRF batching placement, and adversely affected stability if
undermined. Also, CRF forming the floor of a drive was covered with dust/mud and became a future cold
joint. A vertical but irregular cold joint in the CRF existed between the FW and HW panels. Vertical joints
were less of a problem (being clamped by stresses, irregular profile) but were release surfaces for other
potential failures.
Strategies for mining under CRF were:
 Designs considered where adverse cold joints may locate, and modified ground support to make
the cold joints tolerable. The standard practice for mining under CRF became to place shotcrete
ribs at 6 m spacings along the drives, i.e. one rib per stope. The rib supported the section of CRF
that was at risk of a cold joint. A spin-off benefit was that the rib formed a good brow for the
bogging of each stope.
 In some cases, additional ribs were placed where the CRF was judged to be more adverse –
irregularities in cement content, or not fully tight filled.
 The CRF base varied with traffic furrows, potholes, and fugitive roadfill. Where development
under CRF was required, early practice was to blast about 0.4 m below the expected CRF and
allow/promote falloff to the CRF. Washing down before fibrecreting ensured loose material was
removed. Later practice was to mine out the lowest 1 m of CRF, to ensure the new drive backs
were positioned above any potential poor quality patches. No mesh or other reinforcing was
placed in the CRF.

6.3 CRF crush firings


In order to avoid the need to blast a conventional slot rise for every stope, the practice was adopted to
crush the CRF by blasting against it soon after placement.
Crush firings had a comparatively higher powder factor, and this energy could damage the adjacent brow.
Sometimes this meant propagation of overbreak into the brow. In comparison, production firings had less
energy and tended not to cause brow damage. The positions of ends of blastholes were checked (weights
on strings were observed) and excessively deviated holes were redrilled.
Firing of the CRF crush rings was a little less effective for longer blasthole lengths, compared to shorter
geometry stopes. It was thought that ore displaced in the crush firing did not clear the slot as quickly for
the longer hole lengths, and some of it became compressed into the CRF or into stope corners rather than
falling to the bottom.
CRF was deformable by slot blasting up to 20 hours after placement. After that time it gained too much
strength to allow successful crush firing. Therefore designs either facilitated rapid CRF placement, or did
not depend on CRF deformation by blasting. A crush firing blasthole array is shown in Figure 16.
The shorter the time between placement and crush firing, the greater the compression or ‘punch-back’ of
the CRF that was achieved. Compressions of about 20% were regularly obtained by the blast. This increased
the CRF bulk density, but at the cost of breaking some of the cement bonds. The strength of the CRF was
due in part to the tightness of packing of the CRF particles after the blast.
For a five-bucket CRF mix, the crush firing achieved a punch-back of about 1.5 m. This means that the CRF
was compressed by 1.5 m, placing the CRF endwall of the new stope 1.5 m further back. The new stope
void, once completed, was 7.5 m in strike length rather than the nominal 6 m. For the weaker seven-bucket
mix, the punch-back was 2 to 3 m (based on visual observations).

148 Ground Support 2013, Perth, Australia


Squeezing ground

Figure 16 Crush firing blasthole pattern indicated by collars. Weights on cords are suspended in
the holes for visual check of hole toes on the level below

7 Conclusions
The Wattle Dam ground support strategy was successful because of due attention given to observing
performance, combined with willingness to introduce, modify and develop best practice in some less
common ground management techniques. By the end of mine life, the shotcrete arches routinely installed
by the Contractor were works of art as much as effective ground support.
A key outcome was that adequate support in squeezing ground depended on timing as well as capacity –
the flexible initial support, followed after due time by a stronger second pass for long term stability. The
shotcrete ribs provided this support and almost always survived to the completion of stoping.
The crush firings and CRF performance were likewise effective elements in the success of the mining
strategy. The ability to undermine the CRF and support it with shotcrete ribs was an integral part of the
strategy to achieve full extraction of the orebody.

Acknowledgement
The authors admire the skill of HWE Mining (now Leighton) in shotcrete arch construction to suit the mine.
The authors gratefully acknowledge the Wattle Dam management, engineers and operators for their
support, and Ramelius Resources for permission to publish this paper.

References
Barton, N.R., Lien, R. and Lunde, J. (1974) Engineering classification of rock masses for the design of tunnel support, Rock
Mechanics and Rock Engineering, Springer, Vol. 6 (4), pp. 189–236.
Chan, I. and Shen, B. (2008) Use of shotcrete arch as tunnel support – a case study, in Proceedings 13th Australian Tunnelling
Conference, Melbourne, May, pp. 71–76.
Karakus, M. and Fowell, R.J. (2004) An insight into the New Austrian Tunelling Method (NATM), in Proceedings ROCKMEC 2004 –
VIIth Regional Rock Mechanics Symposium, Sivas, Turkey, 14 p.
Li, C. (2005) Ground control of a mine stope in weak rocks subjected to high in-situ stresses – a case study, in Proceedings 24th
International Conference on Ground Control in Mining, Morgantown, pp. 203–207.
Mercier-Langevin, F. and Hadjigeorgiou, J. (2011) Towards a better understanding of squeezing potential in hard rock mines, Mining
Technology, Vol. 120, No. 1, pp. 36–44.
Pascoe, M.J., McGuckin, P.H. and Logan, A.S. (1995) Operational rock mechanics at the Cannington exploration decline, in
Proceedings AusIMM Underground Operators' Conference. Kalgoorlie, November, pp. 57–62.
Sauer, G. (2003) Ground support and its toolbox, in Proceedings Earth Retention Systems 2003: A Joint Conference of the ASCE
Metropolitan Section Geotechnical Group, the Deep Foundations Institute, and ADSC The International Association of
Foundation Drilling. New York, May, pp. 204–224.
Trueman, R., Mikula, P., Mawdesley, C. and Harries, N. (2000) Experience in Australia with the application of the Mathews method
for open stope design, CIM Bulletin, Vol. 1036, pp. 162–167.

Ground Support 2013, Perth, Australia 149


Shotcrete ribs and cemented rock fill ground control methods for stoping in P. Marlow and P.A. Mikula
weak squeezing rock at Wattle Dam Gold Mine

150 Ground Support 2013, Perth, Australia

You might also like