RE Wall Methodology
RE Wall Methodology
RE Wall Methodology
List of Content:
References
Introduction
Specification of Material To Be Used
Sequence for Execution of Work
Organization Chart
Machinery Details
Checklist Details
References:
IRC:SP:102:2014
MoRT&H Specification 3100
IS:2720 (PART-8)
Introduction:
The work shall generally be carried out in conformity to the MORTH “Specification for Road and
Bridge Works": 5th revision (2013), Section 3100.
Description of materials to be used:
Woven Geotextile – Woven Textile shall be placed between base soil and granular
sub- base fill to function as a separator and to maintain sub surface drainage.
PP Biaxial Geogrid –Bi axial Geogrid used for enhancingthe bearing capacity of the
ground.
Granular Sub-Base (GSB): The fill used as Granular Sub base should be tested to
ensure that the angle of shearing resistance is equal to or greater than the design
value of angle of shearing resistance and the materials conform to the MoRT&H
Specifications and other criteria specified in the design and drawings. The
Recommended frequency of testing is minimum one set or tests per source.
Geo composite: Geo composite Layer shall be provided on the inner wall of
the RE Wall to let the moisture seep to the PVC pipe.
Geo strip: Geo strips of width P30 shall be 85mm and rest shall be 90mm
provided as per drawing.
U Hook: U hooks used shall be 250 mm in length.
Sequence of Execution:-
A Batter of 10 shall be provided with wooden battens in order to erect the RE panels.
The RE panels shall be fixed as per the drawing and the alignment & slope checking
shall be done simultaneously.
Subsequently RE panels are Erected and pond ash filling is done in the alignment, PVC
perforated drainage pipe in the longitudinal direction shall be provided at height of
350mm above the service road level and T sections to be provided at appropriate
distance for draining out the moisture.
Geo strips shall be installed as per drawing along with the reinforced pond ash filling
and shall be fixed with U hooks of 250mm.
Rolling shall be done with vibratory rollers & the terminal 1500 mm near the RE
panels shall be done with Baby roller.
EPDM pads shall be provided for packing of RE panels.
Geo composite shall be provided on the inner surface of the RE panels for the entire
stretch to maintain drainage (adhesive).
After the panels are erected , a coping beam shall be provided for levelling.
After levelling, friction slab shall be casted and a 20mm compressible fill shall be
provided between the RE panel and the friction slab and atop it, the crash barrier
shall be casted of M35 concrete.
The cross wall at the abutments shall be at a slope of 20 17’.
Precaution for Panel Installation Sequence:
Project Director
Ashok Kr. Choubey
Project Manager
Sanjeev Kr. Gupta
Manager - Highways
Ashwani Kr. Dwivedi
Dy. Manager
Vikram Chaurasiya
Client : MoRT&H
Consultant : Dohwa ICT Transtek
Contractor M/S S.P. Singla Construction Pvt. Ltd
Drainage Yes No
Is the Geo-composite laying as per approved drawing?
Is the drainage pipe laying as per the drawing?
Remarks: