PROJECT DOCUMENT CONTROL,
EP BRM CERNE PROCEDURE
DOCUMENT NUMBER REV DATE SHEET
DWE-PS-P.03, 2 veroa2016 | tafe
PROCEDURE AUTHORIZATION
This procedure have been generated and implemented | Department Authorization —_| Date:
to identify the control that shall be applied by members of
staff in the department when carrying out their duties, a oy Lofrol
This confirms that this procedure has been approved ‘Authorization Date:
official issue and that members of staff shall complelg SmpAny Director)
Befol.
a
Quality Authorization Date
(Quality Management Rep! s)
fart of the a lean “6 /i{rot .
controlled manner in accordance
procedures.
This procedure will be subject to audit &
company policy towards quali
PROCEDURE REVISION
Rev. Date Section Outline of Changed Authorization
o 15/01/2009 All First Issue
1 naoaned al To accommodate the result of
management review for improvements
2 | 18/04/2016 7.0 _| Revision of References
STATEMENT OF CONFIDENTIALITY
This procedure is for controlled circulation unless stamped "Uncontrolled Copy". The documents or
extracts from documents must nor be passed or copied to other companies, agents or persons without
the permission of the relevant Company Directors.TITLE
PROJECT DOCUMENT CONTROL
Gp DEPRIMANGGA ENGINEERING PROCEDURE
DOCUMENT NUMBER REV DATE ‘SHEET
DWE-PS.P-03 2 seioaa016 | 2016
TABLE OF CONTENTS
1.0 PURPOSE ..
2.0 SCOPE ...
3.0 ABBREVIATIONS
4.0 DEFINITIONS
5.0 RESPONSIBILITIES.
6.0 WORKFLOW / PROCESS.
7.0 REFERENCES
Oo eeeGP ,DEPRIANGGA ENGIEERNG PROCEDURE
TLE
PROJECT DOCUMENT CONTROL
DOCUMENT NUMBER REV DATE ‘SHEET
DWE-PS-P-03 2 isioai2016 | 3016
5.0.
6.0.
PURPOSE
The purpose of this procedure is to ensure effective preparation and control of all the
project documents in conformity with project requirements.
SCOPE
This procedure shall be applied for the preparation and control of:
(i) Documents and related with specific projects, such as project quality plan, project
execution plan and other required project procedures.
(i) External documents
ABBREVIATIONS
(i) PMT__: Project Management Team
(i) DWE. : PT. Depriwangga Engineering
DEFINITIONS
Tender — offer made by a supplier in response to an invitation to satisfy a contract award
to provide product.
Contract — Agreed requirements between a supplier and customer transmitted by the
project owner.
RESPONSIBILITIES
5.1 Project Manager shall ensure that preparation and control of project documents
adhere to this procedure.
5.2. Document Controller shall have responsible:
‘+ To handle project documents among the originator, the reviewer, the
approver and customers if required
* To register, distribute and file the above documents
WORKFLOW / PROCESS
6.1. _ Incoming Technical Documents
6.1.1. Check for the completeness of incoming documents, sign the transmittal
as received and send to sender as acknowledged receipt and marks with
‘comment if any missing or incomplete documents. Inform the sender of
any missing items.THLE
PROJECT DOCUMENT CONTROL
PT, DEPRIWANGGA ENGINEERING PROCEDURE
eberegsees
DOCUMENT NUMBER REV DATE ‘SHEET
DWE-PS-P-03 Bi waing2016 | 40f6
6.1.2.
6.1.5.
‘Stamp/mark the incoming documents with received date, if the incoming
documents are e-files, print-out the transmittal then stamp/mark the
incoming documents with received date.
Check the availability of the soft copy (PDF). If not available, scan the
package for electronic distribution.
‘Save the soft or scan copy on the server under project folder on sub folder
60 (document register).
Register the incoming technical documents.
Distribute the incoming technical document to the project team by
electronic distribution, in accordance with the approved distribution matrix.
Store hardcopies in Filing rack.
6.2. Outgoing Technical Documents
6.2.1
6.2.2.
6.2.3.
6.2.4.
6.2.5.
Check for the completeness of outgoing technical documents once
received from the originator before submission. Inform the originator of
incorrect or missing document and request to revise and complete the
documents.
Prepare the hard copy, soft copy (pdf) and transmittal prior to submission
to the client, except if requested by client to use project specific format as,
per PEP.
‘Submit the document to the Client in the format agreed by Client.
Update the outgoing technical documents register.
Store hardcopies in Filing rack.
6.3. Master Document Register (MDR)
6.3.1
6.4, Filing, Storage, Backup and Archi
6.4.1
6.4.2
To control the preparation, distribution and submission of project
documentation, Document Controller will prepare an MDR.
9
All original design and project documents shall be stored and maintained
by Document Controller Team.
Filing, storage, backup and archiving
6.5. Project Documents
6.5.1
6.5.2.
6.5.3.
A\list of project documents shall be prepared by the various disciplines and
departments as required in accordance to the progress of each discipline
of the project to meet customer's contractual requirements.
The list of project documents shall be documented, and the type of
documents i.e. Engineering, General, Drawings, Procedures, etc.
Asa minimum, the document list shall include the project name, document
tite, document number, revision no. and date. This shall be maintained
and updated by the project manager and copy shall be given to other
parties for reference.pL DEPRIWANGGA ENGINEERING PROCEDURE
TITLE
PROJECT DOCUMENT CONTROL,
a DOCUMENT NUMBER REY DATE SHEET
DWE-PS-P-03 2 reio4i2016 | Sofé
6.6.
67.
6.8.
6.9.
6.10.
6.5.4. Project Document shall have a cover page which contains information
such as Customer's name, Project name, Document title, Document
number, Revision number, Prepared by, Checked by, Approved by and
Date.
Document Numbering System
The document numbering system used shall be based on the Customer
Document Numbering System. And if required by the Contract, DWE shall
provide the specific numbering system.
Originator of Documents
6.7.1. Project Manager shall_ensure that the personnel responsible for
preparation for project documents are issued with the relevant
specifications and information to accurately produce the documents.
6.7.2. Personnel responsible for preparation of project deliverables shall ensure
that all affected parties have been consulted and the document checked
prior to review and approval by the designated authority.
Review and Approval
6.8.1. The project document drafted shall be reviewed and approved by the
Project Manager.
6.8.2. Project documents shall be issued to Customer for approval as required by
the contractual requirements,
Document Transmittal
6.9.1. Project documents issued to Customer for approval shall be accompanied
by a Document Transmittal, where the Customer is required to
acknowledge receipt:
6.9.2. The Document Transmittal should contain Customer's name, contact
person, address, telephone no., the list of documents to be transmitted,
date and sender's name and initial.
6.9.3. The Document Transmittals shall be kept by the Document Controller.
Revi
ns/Changes
6.10.1. Issued for Review
Project documents during draft stage shall be identified with Rev. “A”. Any
changes to the documents during the draft stage shall be identified by the
date. This is to track the revision history during the preliminary stage.
6.10.2, Issued for Approval
Project documents during draft stage shall be identified with Rev. A. Any
changes to documents during the draft stage shall be identified by
6.10.3. Approved for Construction
Project documents have been approved for use, the revision status shall
be changed to numeric sequence. E.e. Rev. 0, 1, 2, 3, etc,TT
PROJECT DOCUMENT CONTROL
PT, DEPRIWANGGA ENGINEERING PROCEDURE
feet DOCUMENT NUMBER REV DATE ‘SHEET
DWE-PS-P.03 2__| ianaaoie | oot6
7.0.
6.13. Uncontrolled Docume:
6.11. Documents Handling and Distribution Control
6.11.1. The Project Documents Controller of each project shall handle project
documents among the originator of the document, the reviewer, the
approver and customer if required
6.11.2.When each revision is reviewed and approved by the designated
authority, Project Document Controller shall distribute the copies of
documents in accordance to the distribution list determined by the Project
Manager.
6.12. Original and Obsolete Documents,
6.12.1, The Project Manager shall maintain the original of the approved project
documents.
6.12.2, When the documents are revised, jMe origin of the previous documents
reference, they shall be
original of the previous ergot f
a us version, including their copies,
are considered as “uncoMfrolled documents”.
6.13.2. The Project Manager and the discipline heads shall ensure that the
project: documents of the previous version are clearly distinguished form
the latest ones by making and providing the documents status list for the
project participants.
REFERENCES
List of Associated Procedure
DWE-HSQ-M01 HSEQ Manual
List of Form
No form
List of Attachment
No Attachment