Final Assignment 5

The document contains a Gantt chart planning project for the construction of a residential building over 165 days. It is divided into various tasks from document preparation to finishing work. The tasks are assigned durations and sequenced with predecessors. The project involves tasks such as tendering, design approval, site preparation, foundation work, structural framing, interior work, external works and finishing. The Gantt chart provides a timeline for completing each task to plan and schedule the overall construction project.

Uploaded by

Jack Bae
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
49 views

Final Assignment 5

The document contains a Gantt chart planning project for the construction of a residential building over 165 days. It is divided into various tasks from document preparation to finishing work. The tasks are assigned durations and sequenced with predecessors. The project involves tasks such as tendering, design approval, site preparation, foundation work, structural framing, interior work, external works and finishing. The Gantt chart provides a timeline for completing each task to plan and schedule the overall construction project.

Uploaded by

Jack Bae
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

BUILDING

CONSTRUCTION
PLANNING PROJECT
Introduction to Civil and
Environmental Engineering

Student Name
JEEONE BAE
Student ID

December 2025 24799809


TABLE OF CONTENTS

PAGE

Title Page 1
Table of Contents 2
Project Sheet 3
Reflection 4

2
ID Task Task Name Duration Start Finish Predecessors May '22 Jun '22 Jul '22 Aug '22 Sep '22 Oct '22 Nov '22 Dec '22
Mode 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 5 12 19 26
1 Residential Building Construction 165 days Mon 2/05/22 Fri 16/12/22
2 Document Preperation 95 days Mon 2/05/22 Fri 9/09/22
3 Tender 5 days Mon 2/05/22 Fri 6/05/22
4 Design and council approval 90 days Mon 9/05/22 Fri 9/09/22 3
5 Site Preperation and Foundation 43 days Mon 12/09/22 Wed 9/11/22

6 Site Mobilisation 5 days Mon 12/09/22 Fri 16/09/22 4


7 Site Fencing and basic 2 days Mon 12/09/22 Tue 13/09/22 6SS
requirement
8 House Peg-out Survey 1 day Mon 19/09/22 Mon 19/09/22 7,6
9 Benching 7 days Tue 20/09/22 Wed 28/09/22 8
10 Concrete Slab Constructiion 8 days Thu 29/09/22 Mon 10/10/22 9
11 Structural Framing and Brick 22 days Tue 11/10/22 Wed 9/11/22 10,16
Laying
12 Interior Work 6 days Tue 15/11/22 Tue 22/11/22
13 Construction of Stairs 3 days Tue 15/11/22 Thu 17/11/22 11,18
14 Painting 3 days Fri 18/11/22 Tue 22/11/22 13
15 External Works 51 days Thu 29/09/22 Thu 8/12/22
16 Termite Protection 1 day Thu 29/09/22 Thu 29/09/22 10SS
17 External Plumbing 2 days Tue 11/10/22 Wed 12/10/22 11SS,10
18 Roofing 3 days Thu 10/11/22 Mon 14/11/22 11
19 Driveaway Construction 3 days Tue 15/11/22 Thu 17/11/22 18
20 Fencing, Landscaping and 15 days Fri 18/11/22 Thu 8/12/22 19
Cleaning
21 Finishing Task 6 days Fri 9/12/22 Fri 16/12/22 15,12
22 Final Certifier Inspection 2 days Fri 9/12/22 Mon 12/12/22
23 Application for Occupational 1 day Tue 13/12/22 Tue 13/12/22 22
Certificate
24 Practical completion and 2 days Wed 14/12/22 Thu 15/12/22 23
Handover
25 Hand over the owner 1 day Fri 16/12/22 Fri 16/12/22 24

Task Project Summary Manual Task Start-only Deadline

Project: 48310 - Intro to Civil A Split Inactive Task Duration-only Finish-only Progress
Date: Fri 26/05/23 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 1
REFLECTION

As a part of Assessment Task 5, we were tasked with simulating the construction of


a residential building through a Gantt chart. Within it, students researched
possible time lengths of such a task and utilized the tool, Microsoft Project to
envision the building construction. Through personal research, I concluded that
this construction would range from 160-170 days and thus finalized a 170-day time
length. My personal research skills in design were developed, allowing for future use
in a construction-focused occupation to plan and budget for structures.

Its lessons in the future would prove useful as a further lengthened time frame
would only stretch the budget, which is a cost that businesses would rather avoid.
As such, knowledge of how to use MS Projects to produce a Gantt chart would
remain a highly sought skill by businesses in order for workers to remain on
schedule while also limiting increases in cost.