d2 Load Bearing System
d2 Load Bearing System
Load-bearing tower d2
Introduction
2 999734002 - 02/2011
The Formwork Experts
User information Load-bearing tower d2 Introduction
Contents
4 Introduction
4 Elementary safety warnings
6 Doka services
8 System description
10 System overview
13 d2 in detail
14 Practical examples
16 Adapts to different ground plans, heights,
floor shapes and loads
18 Assembly instructions
19 Horizontal assembly
22 Assembling towers in the upright by hand
24 Assembling towers in the upright by forklift
truck
27 Repositioning
28 Repositioning using wheel units
30 Lifting by crane
32 Lifting by forklift truck
34 General remarks
34 Anchoring on the structure
36 Back-stays/shoring supports for the load-bea-
ring towers
40 Adapting to the building layout
42 Inclination adjustment
45 Steel primary beams
46 Transporting, stacking and storing
50 Structural design
53 Component overview
999734002 - 02/2011 3
The Formwork Experts
Introduction User information Load-bearing tower d2
4 999734002 - 02/2011
The Formwork Experts
User information Load-bearing tower d2 Introduction
Pouring
● Do not exceed the permitted fresh-concrete pres-
☞ Important note
Failure to observe this may lead to malfunc-
tion or damage.
sures. Excessively high pouring rates lead to form-
work overload, cause greater deflection and risk
causing breakage.
CAUTION / WARNING / DANGER
Failure to observe this may lead to material
Striking the formwork damage, and to injury to health which may
range up to the severe or even life-threaten-
● Do not strike the formwork until the concrete has
ing.
reached sufficient strength and the person in charge
has given the order for the formwork to be struck!
● When striking the formwork, never use the crane to
break concrete cohesion. Use suitable tools such as Instruction
timber wedges, special pry-bars or system features This symbol indicates that actions need to be
such as Framax stripping corners. taken by the user.
● When striking the formwork, do not endanger the
stability of any part of the structure, or of any scaf-
folding, platforms or formwork that is still in place! Sight-check
Indicates that you need to do a sight-check
Transporting, stacking and storing to make sure that necessary actions have
been carried out.
● Observe all regulations applying to the handling of
formwork and scaffolding. In addition, the Doka
slinging means must be used - this is a mandatory Tip
requirement.
Points out useful practical tips.
● Remove any loose parts or fix them in place so that
they cannot be dislodged or fall free!
● All components must be stored safely, following all
the special Doka instructions given in the relevant Reference
sections of this User Information booklet!
Refers to other documents and materials.
Miscellaneous
We reserve the right to make alterations in the interests
of technical progress.
999734002 - 02/2011 5
The Formwork Experts
Introduction User information Load-bearing tower d2
Doka services
Support in every phase of the
project
Doka offers a broad spectrum of services, all with a sin-
gle aim: to help you succeed on the site.
Every project is unique. Nevertheless, there is one
thing that all construction projects have in common –
and that is a basic structure with five phases. We at
Doka know our clients' varying requirements. With our
consulting, planning and other services, we help you
achieve effective implementation of your formwork
assignment using our formwork products – in every one
of these phases.
1 2 3
Project development phase Tendering phase Operations scheduling phase
Taking well-founded decisions Optimising the preliminary work Controlled, regular forming oper-
thanks to professional advice and with Doka as an experienced part- ations, for greater efficiency
consulting ner resulting from realistically calculated
formwork concepts
Find precisely the right formwork Draw up potentially winning bids, by Plan cost-effectively right from the
solutions, with the aid of ● basing them on realistically calcu- outset, thanks to
● help with the bid invitation lated guideline prices ● detailed offers
● in-depth analysis of the initial sit- ● making the right formwork ● determination of the commission-
uation choices ing quantities
● objective evaluation of the plan- ● having an optimum time-calcula- ● co-ordination of lead-times and
ning, execution, and time-risks tion basis handover deadlines
6 999734002 - 02/2011
The Formwork Experts
User information Load-bearing tower d2 Introduction
● Transparency
Optimum resource utilisation Seeing things through to a posi- Because our services and costs
with assistance from the Doka tive conclusion are completely transparent, there
Formwork Experts with professional support is no need for improvisation dur-
ing the project – and no unpleas-
ant surprises at the end of it.
999734002 - 02/2011 7
The Formwork Experts
System description User information Load-bearing tower d2
System description
System description
... provides optimum safety Site: Flyover at Rheinfelden customs zone on Swiss/German border
8 999734002 - 02/2011
The Formwork Experts
User information Load-bearing tower d2 System description
999734002 - 02/2011 9
The Formwork Experts
System description User information Load-bearing tower d2
System overview
Basic design concept The d2 system components
Head units (A)
4-way screw-jack
Screw jack U-head U-head D
A head
b
9734-203-01
a
a ... Inter-frame spacing = 100 / 125 / 152 / 175 / 200 / 225 / 250 cm
b ... Frame width = 152 cm
A Head unit
B Basic frame d2
C Brace d2
D Base unit
10 999734002 - 02/2011
The Formwork Experts
User information Load-bearing tower d2 System description
Horizontal con- Diagonal stiff- Diagonal stiff- Diagonal stiff- Bottom height-adjustment spindle for load-bearing towers.
nection brace ening brace ening brace ening brace The Split nut B can be swung
between the between the between the between the apart, meaning that it does not
basic frames. Basic frames Basic frames Basic frames need to be turned through the full
0.90m. 1.20m. 1.80m. length of the threaded
Is also used as spindle.
a horizontal
diagonal for all
types of basic
frame.
Slot-in bracing crosses made of tubular steel, for mounting between
the frames.
Identified by:
● Embossed marking (G) e.g. 18.250 (diagonal brace)
- 18 = frame height 1.80 m
- 250 = inter-frame spacing 250 cm
● Embossed marking (G) e.g. 250 (horizontal brace)
- 250 = inter-frame spacing 250 cm
As an alternative to the Braces d2, diagonal crosses
from the Doka load-bearing tower Staxo can also be
used here.
☞ Important note:
● The diagonal crosses cannot be used in
cases where the frames are spaced 100 cm
apart, as the crosses would foul the cross-
bars of the frames.
● Do not mix diagonal crosses and diagonal
braces on the same load-bearing tower.
● It is not possible to use diagonal crosses to
erect quadratic tower frames where the
frames of each section are placed at 90° to
those of the previous section (see "Quadratic
tower frames").
● In levels in which assembly battens are
mounted, horizontal bracing with "Diagonal
braces 12" or with diagonal crosses is no
longer needed. This only applies, of course,
if the assembly battens are left in place in this
"storey" until the very end of the assignment
(assembly, pouring etc.).
999734002 - 02/2011 11
The Formwork Experts
System description User information Load-bearing tower d2
12 999734002 - 02/2011
The Formwork Experts
User information Load-bearing tower d2 System description
d2 in detail
Basic frame d2 Safety catch
● tried-and-tested interconnection system (captive)
● secures the diagonal and horizontal braces
● two defined positions (closed – open)
Closed Open
9758-228-01
9718-234-01
C
a ... max. 16 cm (exception: where tubes are being connected for
constructional design purposes)
B
A Transition swivel coupler 48/60mm or Transition angle coupler
48/60mm
B Swivel coupler 48mm or Normal coupler 48mm
9718-218-01
999734002 - 02/2011 13
The Formwork Experts
System description User information Load-bearing tower d2
Practical examples
Tableforms and tower frames are both assembled from
the same system components. Tower frames
With a load-bearing capacity of up to 60 kN per leg, d2
Tableform units is an extremely strong loadbearing tower system.
● For repetitive use, the load-bearing tower can be It safely withstands horizontal forces such as wind
assembled into complete table-forms. loads.
The wide frames make for high stability right from the
word "go".
E
A B
9734-278-01
A Load-bearing tower
B Dokaflex
C Beam forming support 20
D Handrail post T 1.80m (optionally with Toeboard holder T
1.80m), Handrail clamp S or Handrail post 1.50m
E Lashing strap 5.00m
F Doka Express anchor 16x125mm and Doka coil 16mm
14 999734002 - 02/2011
The Formwork Experts
User information Load-bearing tower d2 System description
9734-227-01
9734-228-01
999734002 - 02/2011 15
The Formwork Experts
System description User information Load-bearing tower d2
e.g.: Heavy loads - frames spaced close together e.g.: Light loads - frames spaced further apart
9734-221-01
9734-217-01
9734-218-01 9734-222-01
9734-279-01
16 999734002 - 02/2011
The Formwork Experts
User information Load-bearing tower d2 System description
Note:
Where the bottom section is assembled from 0.90 m
frames, be sure to allow for LF min. when using Heavy
duty screw jacks 70!
999734002 - 02/2011 17
The Formwork Experts
Assembly instructions User information Load-bearing tower d2
Assembly
Assembly instructions
Horizontal assembly
Assembling in the upright
Standard set-up
9734-268-01
9734-251-01
9734-251-01
98003-101
18 999734002 - 02/2011
The Formwork Experts
User information Load-bearing tower d2 Assembly instructions
Horizontal assembly
Preliminary remark:
● The terms "vertical" and "horizontal" (e.g. referring to Erecting the first storey
the diagonal braces) are always used here with ref- ➤ Having regard to the instructions given above, place
erence to their installation situation in the finished, the tower frames on their sides on timber supports
upright tower. (min. 4cm high).
● The job of erecting the load-bearing tower begins
with the bottom (i.e. first) "storey". Bracing the frames in the vertical
☞ General remarks:
● Make sure that the frames are the right way
round! Otherwise, the safety catches (A) for
➤ Join the frames together with diagonal braces (F)
and horizontal braces (H) .
Right:
999734002 - 02/2011 19
The Formwork Experts
Assembly instructions User information Load-bearing tower d2
9734-268-01
9734-269-01
20 999734002 - 02/2011
The Formwork Experts
User information Load-bearing tower d2 Assembly instructions
H
G
b
9734-268-01
999734002 - 02/2011 21
The Formwork Experts
Assembly instructions User information Load-bearing tower d2
☞ General remarks:
● The gravity latches of the frame must always
point upwards. H
✔ ✗9758-226-01
9734-248-01
C
9734-249-01
B B
9734-247-01
22 999734002 - 02/2011
The Formwork Experts
User information Load-bearing tower d2 Assembly instructions
J
F
9734-250-01
9716-215-01
WARNING
➤ Where the primary beams cantilever out a
long way, protect them against being lifted
out or tipped over (e.g. with a tie-back, by
nailing board-plates over the beam joins, or
by fastening the beams to the screwjack
head-unit).
K ☞ Important note:
➤ When lifting and repositioning the entire
tower unit (or pre-assembled sub-units) by
crane: Follow the instructions in the section
headed "Lifting by crane"!
Dismantling
9734-251-01 To dismantle, perform the above steps in reverse order.
999734002 - 02/2011 23
The Formwork Experts
Assembly instructions User information Load-bearing tower d2
c
c
b
E
d
F
d
Tr745-200-05
B
WARNING
➤ While load-bearing towers are being erected
or dismantled, lifted or lowered: It is forbid-
den to walk or stand beneath suspended A Box-style fork extension
loads. B Open fork extension
24 999734002 - 02/2011
The Formwork Experts
User information Load-bearing tower d2 Assembly instructions
Tr745-200-05
Dismantling
To dismantle, perform the above steps in reverse order.
☞ Important note:
Always only dismantle the bottom "storey" of
the towerframe unit.
999734002 - 02/2011 25
The Formwork Experts
Assembly instructions User information Load-bearing tower d2
26 999734002 - 02/2011
The Formwork Experts
User information Load-bearing tower d2 Repositioning
Repositioning
Repositioning
999734002 - 02/2011 27
The Formwork Experts
Repositioning User information Load-bearing tower d2
B
h
9734-290-01 A
b
b
D
Wheel-unit variants: C
● Shifting carriage TG
● Modular system (with winches)
☞
9734-205-01
Important note:
When repositioning load-bearing towers that Equipment needed for one shifting unit
include standard superstructures, remember: Item Designation N° of items
Ratio w:h = max. 1:3, with 'w' being the narrow- A Winch 70 or 125 4
est side. B Frame for Staxo/d2 winch 4
C Solid-tyre wheel or Heavy-duty wheel 15kN 4
Custom constructions must be statically veri-
D Double wheeled transporter 4
fied!
28 999734002 - 02/2011
The Formwork Experts
User information Load-bearing tower d2 Repositioning
☞
9716-220-01
● The floor must be stable, firm and sufficiently
smooth (e.g. concrete).
● Max. gradient of floor: 5 %.
● Max. configuration that can be transported
using 2 Shifting carriages TG: Tables with 3
cross-frames per storey and a max. height of
5.0 m.
999734002 - 02/2011 29
The Formwork Experts
Repositioning User information Load-bearing tower d2
Lifting by crane
Where the tableforms are to be repositioned in the ver-
tical, i.e. crane-lifted, they must be fitted with a Lifting Connect the superstructure to the head units
rod 15.0 and Retaining plate 15.0 , which make it easy ➤ e.g. with Locking rod 15.0 (D) , Clamping plate (E)
to attach the transfer cables. and Wing nut 15.0 (F) .
Max. load: On Screw jack U-head On 4-way screw-jack head
1000 kg per Lifting rod 15.0 - where the load is applied
centrally
Assembly instructions
➤ Mount the Lifting rod 15.0 (A) and Retaining plate
15.0 (B) .
5.1 5.1
Only possible with Clamping
A plate a = 28 cm (2002 models
onward)
Preparations
WARNING
Secure the base units to prevent them drop-
Danger from loose and unsecured parts.
ping out: On Screw jack foot (H) and Heavy
➤ Observe the following points before lifting!
duty screw jack 70 or 130 using Split nut B
Connect superstructure components together ➤ Slot the fixing-handle (I) into the cross-bar of the
frame.
➤ e.g. connect the primary and secondary beams to
rafter plates, and nail on the form-ply.
30 999734002 - 02/2011
The Formwork Experts
User information Load-bearing tower d2 Repositioning
Secure the base units to prevent them drop- Shifting the table in skeleton construction
ping out: On Heavy duty screw jack 70 or 130 ➤ Take the load off the table by turning the threaded
using split nut, art.n°582640 (as manufactured spindles.
up until end of '96) ➤ Clamp on the wheel-units.
➤ First take the weight off the Heavy duty screw jack 70 ➤ Push in and secure the base units.
(e.g. with wheel units), then open the split nut.
➤ Push the Heavy duty screw jack 70 (J) into the frame
and secure it with a Spring-locked connecting pin 16
mm (K) .
9734-232-01
A M
9734-233-01
9734-234-01
b
a
d
d
Tr745-200-05
32 999734002 - 02/2011
The Formwork Experts
User information Load-bearing tower d2 Repositioning
999734002 - 02/2011 33
The Formwork Experts
General remarks User information Load-bearing tower d2
34 999734002 - 02/2011
The Formwork Experts
User information Load-bearing tower d2 General remarks
999734002 - 02/2011 35
The Formwork Experts
General remarks User information Load-bearing tower d2
☞ Important note:
Lashing straps are not suitable for transferring B
planned horizontal loads.
78.
C C
0
9734-275-01
C
0
36 999734002 - 02/2011
The Formwork Experts
User information Load-bearing tower d2 General remarks
Q
R Z
Q
9734-287-02
CAUTION
➤ The "Back-stay for load-bearing towers"
must not be dismounted until it is certain that
there is sufficient stability for the load-bear-
ing tower.
999734002 - 02/2011 37
The Formwork Experts
General remarks User information Load-bearing tower d2
G G F
9734-292-02
Note:
The "Bracing for load-bearing towers"is attached to the
multi-purpose waling directly by means of a "Spindle
unit", without a "Shoe (complete)".
9734-292-01
A
A
Note: Tr845-204-02
Tr845-204-01
Separate towers may also be braced in the frame plane
or bracing-strut plane only.
A Spindle unit
38 999734002 - 02/2011
The Formwork Experts
User information Load-bearing tower d2 General remarks
Shoring to the superstructure Loading capacity data for Eurex 60 550 (com-
For transferring planned horizontal loads e.g. wind
pressive force)*
loads, concrete loads or in custom applications (e.g. on
inclined load-bearing towers or for high load-bearing - when used as a shoring & plumbing accessory
capacities). 35
30
H
CAUTION
➤ The plumbing strut must not be dismounted
until it is certain that there is sufficient stabil-
ity for the load-bearing tower.
9734-286-01
999734002 - 02/2011 39
The Formwork Experts
General remarks User information Load-bearing tower d2
9745-211-01
60
50
Max. load [kN]
40
30
20
10
9745-100
0
3 4 5 6 7 8 9 10 11 12
9745-200-01
40 999734002 - 02/2011
The Formwork Experts
User information Load-bearing tower d2 General remarks
Holding primary beams Holding Eurex 60 550 floor props upright dur-
ing erection
U-head Eurex 60 for steel girders Four-way head Eurex 60 for sin-
(e.g. WS10), squared timbers or gle or double formwork beams H Removable folding tripod 1.20m
formwork beams H20 20
9745-201-01
9745-201-01
Assembly instructions
➤ Place the U-head or four-way head on the prop and
fix with spring-steel stirrup.
98003-315-01
9745-212-01
B
9745-203-01
A B
999734002 - 02/2011 41
The Formwork Experts
General remarks User information Load-bearing tower d2
Inclination adjustment
If the superstructure or the ground are inclined at an
angle of 1% or more, slope compensation must be using Staxo wedge support WS10
provided.
Used with timber wedges, this component provides
angle adjustment to floor-slab constructions with a
using Wedges for screw-jack ..... % max. inclination of 45°.
These prefabricated birch plywood wedges make it Bolted into the multipurpose waling or steel waling, this
possible to stand load-bearing towers in the perpendic- wedge support prevents the timber wedges slipping
ular on surfaces with various inclinations, even when and ensures that the loads are safely transferred.
utilising the full leg load.
CAUTION
☞ This type of connection is no substitute for extra
structural design measures such as back-
stays.
Excessively steep wedges may slip away!
➤ Maximum inclination: 20%! View without superstructure
Inclined superstructures
Securing the superstructure at angles of over 12%:
➤ Connect the head-plate to the longitudinal beam a ... min. 15 cm
(e.g. with Locking rod 15.0/33cm and Super-plate
15.0 or Angle anchor plate 12/18) A Staxo wedge support WS10
B Timber wedge, project-specific
C Multi-purpose waling or Steel waling WS10 Top50
D Nailed connection
B
☞
C
The grain of the timber wedges must always be
in the vertical!
A
Note:
If the legs of the load-bearing tower have to be located
outside the pattern of drilled holes in the multi-purpose
9703-255-01 waling or steel waling, then a suitable 20 mm diam.
hole must be drilled in the web of the waling.
A Wedge for screw-jack ..... %
B Locking rod 15.0/33cm
C Super-plate 15.0
using an M20 hexagonal bolt
In this case, the superstructure rests on e.g. an
Inclined ground surface M20x240 hexagonal bolt (A) . This bolt is inserted
through the recessed opening in the Screw jack U-head
and is secured with a self-locking M20 hexagon nut.
CAUTION
➤ Maximum inclination: 8%!
9703-254-01
A
9716-292-01
42 999734002 - 02/2011
The Formwork Experts
User information Load-bearing tower d2 General remarks
Note:
When assessing the oblique bending, always consult
the Statical Calculation Dept.!
A
● Maximum inclination of superstructure: 18% A Swivel bearing plate for Screw jack U-head
● Permitted overall inclination (in both the lon- B Screw jack U-head or Heavy duty screw jack 70 top
gitudinal and transverse directions): 18% C Staxo 100 frame
● From an overall inclination of 12%: Super- D Multi-purpose waling
structure must be secured! E Super-plate 15.0
● Allow for the oblique bending on the primary F Locking rod 15.0 330mm
beam! G Nuts, bolts etc.
● When calculating the extension lengths of
the head and base units, always allow for the
extra height of the Swivel bearing plate for
Screw jack U-head (92 mm).
999734002 - 02/2011 43
The Formwork Experts
General remarks User information Load-bearing tower d2
J
I
H
G
B
9734-289-01
L
9734-291-01
44 999734002 - 02/2011
The Formwork Experts
User information Load-bearing tower d2 General remarks
Tr777-200-01 Tr777-201-01
Tr770-201-03
Tr777-202-01 Tr777-203-01
999734002 - 02/2011 45
The Formwork Experts
General remarks User information Load-bearing tower d2
9234-203-01
46 999734002 - 02/2011
The Formwork Experts
User information Load-bearing tower d2 General remarks
Doka multi-trip transport box Using Doka multi-trip transport boxes as stor-
age units
1.20x0.80m galv.
Max. n° of boxes on top of one another
Outdoors (on the site) Indoors
Floor gradient up to 3% Floor gradient up to 1%
3 6
It is not allowed to stack empty
pallets on top of one another!
A
Tr755-200-02
Tr755-200-04 Tr755-200-05
999734002 - 02/2011 47
The Formwork Experts
General remarks User information Load-bearing tower d2
Doka stacking pallet 1.55x0.85m and Using Doka stacking pallets as transport
devices
1.20x0.80m
Storage and transport devices for long items: Lifting by crane
● durable
● stackable ☞ ● Multi-trip packaging items may only be lifted
one at a time.
● Use a suitable lifting chain. (Do not exceed
Suitable transport appliances:
the permitted load capacity). e.g: Doka 4-
● crane part chain 3.20m.
● pallet stacking truck ● Load the items centrically.
● forklift truck ● Fasten the load to the stacking pallet so that
The Bolt-on caster set B turns the stacking pallet into a it cannot slide or tip out.
fast and manoeuvrable transport trolley. ● When lifting stacking pallets to which Bolt-on
castor sets B have been attached, you must
Follow the directions in the "Bolt-on castor set
also follow the directions in these Operating
B" Operating Instructions!
Instructions!
● Spread-angle β max. 30°!
= =
a
92815-224-01
48 999734002 - 02/2011
The Formwork Experts
User information Load-bearing tower d2 General remarks
92816-206-01
999734002 - 02/2011 49
The Formwork Experts
Structural design User information Load-bearing tower d2
Structural design
Structural design
Table A
Variant A Variant B Variant C Basic items
Heavy duty screw jacks 70 + Split nuts B
9703-001
9703-001
U-heads D
Couplers
Operational Operational Operational
height h [m] height h [m] height h [m]
min. - max. min. - max. min. - max.
0.90 1.44 - 1.60 4 4 1.76 - 1.95 4 4 1.17 - 1.62 4 4 2 - - 2 1 - 4 4 - -
1.20 1.44 - 1.90 4 4 1.76 - 2.25 4 4 1.36 - 1.92 4 4 - 2 - - 3 - 4 4 - -
1.80 2.02 - 2.50 4 4 2.02 - 2.85 4 4 1.96 - 2.52 4 4 - - 2 - 1 2 4 4 - -
1.80 2.02 - 2.50 4 4 2.19 - 2.85 4 4 2.12 - 2.52 4 4 4 - - 4 1 - 6 4 4 8
2.10 2.32 - 2.80 4 4 2.32 - 3.15 4 4 2.26 - 2.82 4 4 2 2 - 2 3 - 6 4 4 8
2.40 2.62 - 3.10 4 4 2.62 - 3.45 4 4 2.56 - 3.12 4 4 - 4 - - 5 - 6 4 4 8
2.70 2.92 - 3.40 4 4 2.92 - 3.75 4 4 2.86 - 3.42 4 4 2 - 2 2 1 2 6 4 4 8
3.00 3.22 - 3.70 4 4 3.22 - 4.05 4 4 3.16 - 3.72 4 4 - 2 2 - 3 2 6 4 4 8
3.30 3.52 - 4.00 4 4 3.52 - 4.35 4 4 3.46 - 4.02 4 4 2 4 - 2 6 - 8 4 8 16
3.60 3.82 - 4.30 4 4 3.82 - 4.65 4 4 3.76 - 4.32 4 4 - - 4 - 1 4 6 4 4 8
3.90 4.12 - 4.60 4 4 4.12 - 4.95 4 4 4.06 - 4.62 4 4 2 2 2 2 4 2 8 4 8 16
4.20 4.42 - 4.90 4 4 4.42 - 5.25 4 4 4.36 - 4.92 4 4 - 4 2 - 6 2 8 4 8 16
4.50 4.72 - 5.20 4 4 4.72 - 5.55 4 4 4.66 - 5.22 4 4 2 - 4 2 2 4 8 4 8 16
4.80 5.02 - 5.50 4 4 5.02 - 5.85 4 4 4.96 - 5.52 4 4 - 2 4 - 4 4 8 4 8 16
5.10 5.32 - 5.80 4 4 5.32 -6.15 4 4 5.26 - 5.82 4 4 2 4 2 2 6 2 10 4 12 24
5.40 5.62 - 6.10 4 4 5.62 - 6.45 4 4 5.56 - 6.12 4 4 - - 6 - 2 6 8 4 8 16
5.70 5.92 - 6.40 4 4 5.92 - 6.75 4 4 5.86 - 6.42 4 4 2 2 4 2 4 4 10 4 12 24
6.00 6.22 - 6.70 4 4 6.22 - 7.05 4 4 6.16 - 6.72 4 4 - 4 4 - 6 4 10 4 12 24
6.30 6.52 - 7.00 4 4 6.52 - 7.35 4 4 6.46 - 7.02 4 4 2 - 6 2 2 6 10 4 12 24
6.60 6.82 - 7.30 4 4 6.82 - 7.65 4 4 6.76 - 7.32 4 4 - 2 6 - 4 6 10 4 12 24
6.90 7.12 - 7.60 4 4 7.12 - 7.95 4 4 7.06 - 7.62 4 4 2 4 4 2 7 4 12 4 16 32
7.20 7.42 - 7.90 4 4 7.42 - 8.25 4 4 7.36 - 7.92 4 4 - - 8 - 2 8 10 4 12 24
7.50 7.72 - 8.20 4 4 7.72 - 8.55 4 4 7.66 - 8.22 4 4 2 2 6 2 5 6 12 4 16 32
7.80 8.02 - 8.50 4 4 8.02 - 8.85 4 4 7.96 - 8.52 4 4 - 4 6 - 7 6 12 4 16 32
8.10 8.32 - 8.80 4 4 8.32 - 9.15 4 4 8.26 - 8.82 4 4 2 - 8 2 3 8 12 4 16 32
8.40 8.62 - 9.10 4 4 8.62 - 9.45 4 4 8.56 - 9.12 4 4 - 2 8 - 5 8 12 4 16 32
8.70 8.92 - 9.40 4 4 8.92 - 9.75 4 4 8.86 - 9.42 4 4 2 4 6 2 7 6 14 4 20 40
9.00 9.22 - 9.70 4 4 9.22 - 10.05 4 4 9.16 - 9.72 4 4 - - 10 - 3 10 12 4 16 32
9.30 9.52 - 10.00 4 4 9.52 - 10.35 4 4 9.46 - 10.02 4 4 2 2 8 2 5 8 14 4 20 40
1)The values in this column only apply to quadratic tower frames with the frames of each section placed at 90° to those of the previous section. In
this case, the column "Horizontal brace xxx" is no longer relevant and should be ignored.
50 999734002 - 02/2011
The Formwork Experts
User information Load-bearing tower d2 Structural design
K
L
1.80/1.20/0.90 m frames, or single-storey with
1.20 m frames
9734-262-01
● Bottom height adjustment:
- Heavy duty screw jack 70 or Screw jack foot
● Top height adjustment:
a b
- Screw jack U-head, 4-way screw-jack head or U-
F
L
head placed directly on frame Also allows for wind-loads acting on the load-bearing tower
a ... 1.0 - 2.5 m
F F F F b ... 1.5 m
V V V V
K
L
70
60
40
L
B
30
a b
Also allows for wind-loads acting on the load-bearing tower
a ... 1.0 - 2.5 m 20
b ... 1.5 m
70 10
9734-101
60 0
Permitted leg load Fv (effective resistance) [kN]
0 10 20 30 35
A
Screw-jack U-head extension length LK [cm]
50
A LF 35 cm
B B LF 70 cm
40
10
9734-100
0
0 10 20 30 35
A LF 35 cm
B LF 70 cm
999734002 - 02/2011 51
The Formwork Experts
Structural design User information Load-bearing tower d2
52 999734002 - 02/2011
The Formwork Experts
User information Load-bearing tower d2 Component overview
Basic frame d2 0.90m 21.0 582703000 Diagonal cross 9.150 5.2 582773000
Basic frame d2 1.20m 24.1 582701000 Diagonal cross 9.165 5.7 582627000
Basic frame d2 1.80m 32.8 582702000 Diagonal cross 9.175 6.1 582334000
Grundrahmen d2 Diagonal cross 9.200 6.6 582774000
Galvanised Diagonal cross 9.250 7.7 582775000
Diagonal cross 12.150 5.7 582612000
Diagonal cross 12.165 6.1 582628000
Diagonal cross 12.175 6.3 582335000
Diagonal cross 12.200 6.9 582614000
Diagonal cross 12.250 8.3 582616000
Diagonal cross 18.150 6.9 582622000
Diagonal cross 18.165 7.3 582629000
Diagonal cross 18.175 7.8 582336000
Diagonal cross 18.200 7.8 582624000
Diagonal cross 18.250 9.1 582626000
Diagonalkreuz
Galvanised
Delivery condition: folded closed
999734002 - 02/2011 53
The Formwork Experts
Component overview User information Load-bearing tower d2
Wing nut 15.0 0.31 581961000 Heavy duty screw jack 130 13.0 582711000
Flügelmutter 15,0 Lastspindel 130
Galvanised Galvanised
Length: 10 cm Height: 173 cm
Height: 5 cm
Width-across: 27 mm
54 999734002 - 02/2011
The Formwork Experts
User information Load-bearing tower d2 Component overview
Assembly batten 40/100cm 4.2 582630000 Pin coupling 60mm 1.0 582546000
Assembly batten 40/200cm 7.5 582632000 Zapfenkupplung 60mm
Assembly batten 40/250cm 9.7 582633000 Galvanised
Montagebelag Width-across: 22 mm
Aluminium
999734002 - 02/2011 55
The Formwork Experts
Component overview User information Load-bearing tower d2
Lifting rod 15.0 1.9 586074000 Staxo/d2 adapter frame 14.1 582781000
Umsetzstab 15,0 Staxo/d2-Adapter
Painted blue Painted blue
Height: 57 cm Length: 37 cm
Follow the directions in the "Operat- Width: 36 cm
ing Instructions"! Height: 36 cm
56 999734002 - 02/2011
The Formwork Experts
User information Load-bearing tower d2 Component overview
Spring cotter 5mm 0.05 580204000 4-way head Eurex 60 4.5 582655000
Federvorstecker 5mm Vierwegkopf Eurex 60
Galvanised Galvanised
Length: 13 cm Length: 25 cm
Width: 21 cm
Height: 21 cm
999734002 - 02/2011 57
The Formwork Experts
Component overview User information Load-bearing tower d2
Plumbing strut 340 for precast members 18.2 588296000 Stair tower d2-225
Justierstütze 340 für Fertigteile
Galvanised
Stair bracket 225 right 24.6 582681000
Length: 190 - 341 cm Stair bracket 225 left 24.6 582682000
Treppenlauf 225
Galvanised
Length: 263 cm
Height: 111 cm
Plumbing strut 540 for precast members 33.3 588297000 Pin 7x60mm 0.02 582683000
Justierstütze 540 für Fertigteile Steckbolzen 7x60mm
Galvanised Galvanised
Length: 309 - 550 cm
58 999734002 - 02/2011
The Formwork Experts
User information Load-bearing tower d2 Component overview
Anchoring shoe for stair tower 3.4 582680000 Doka stacking pallet 1.20x0.80m 39.5 583016000
Ankerschuh für Treppenturm Doka-Stapelpalette 1,20x0,80m
Galvanised Galvanised
Length: 22 cm Height: 77 cm
Width: 12 cm Follow the directions in the "Operat-
Height: 22 cm ing Instructions"!
999734002 - 02/2011 59
The Formwork Experts
Doka load-bearing tower d2 - the safe and sure way of
carrying your floor-slab loads.
Flexible, economical and strong, this Doka load-bearing tower gives stability to every structure -
when it comes to the costing calculations, too.
You can either rent, lease or purchase the Doka load-bearing tower d2.
At any of the Doka branches in your region.
Why not give us a call?
Doka international
Certified to Doka GmbH
ISO 9001 Josef Umdasch Platz 1, A 3300 Amstetten, Austria
Tel.: +43 (0)7472 605-0, Fax: +43 (0)7472 64430
E-Mail: [email protected]
Internet: www.doka.com