Contract Law
Contract Law
Contract Law
(AC 5.1)
Because the claimant has the burden of proving the amount of his loss, it is a great
convenience to him if the contract can simply state a sum which will be payable by the
defendant in the event of breach and the claimant can then sue for the state sum. On
the other hand, any such system is open to abuse if the sums might be set at a level far
higher than the loss actually suffered. The House of Lords attempted to reconcile these
arguments.
Part D
(AC 3.1)
In Connolly v Bellway Homes, the seller of development land was able to obtain
damages from the buyer on the basis that it relied upon a statement by the buyer about
the value per square foot of development land. The figure suggested by the buyer was
used as the base figure in a formula designed to provide the seller with a share of
increase in value of the side. The buyer’s representative adopted a figure of $210 per
square foot in the negotiations, giving the impression that this was comparable to other
developments.Negotiations continued in reliance on this representation and a base
figure of $212 was agreed.
(AC 3.2)
For the purpose of making a reckless statement, there is no need to prove dishonesty or
fraud: only that the statement was made without caring whether the statement was true
or not.
Section 2(1) of the Misrepresentation Act 1967 changed that. It introduced the
availability of damages as a remedy for negligent misrepresentation. Also, a court has a
discretion to refuse the remedy of rescission and award damages instead.
The pre-contractual statement was false, but the maker of the statement wasn’t
negligent in making the statement.
(AC 4.3)
The doctrine of frustration in contract law was initially defined by two points, namely: (1)
the doctrine was to be only permitted where it was raised as a defence to a primary
assumption on which the agreement was reached; and (2) the parties were entitled to
insert provisions as a contingency measure to provide for the occurrence of the same.
“From the nature of the contract it is apparent that the parties contracted on the basis of
the continued existence of the particular person or chattel”.
The application of the doctrine of frustration can arise in a variety of situations. The
body of case law on the subject, however, illustrates that there are typically situations in
which the doctrine arises. Most commonly, the doctrine arises in situations in which
there is an inability to perform the contract due to the subject-matters destruction or
unavailability:
The claimant’s action for breach of contract failed. The contract had been frustrated as
the fire meant the contract was impossible to perform.
There are a variety of issues which can prevent the doctrine of frustration from
occurring. Firstly, where one party is found to have been negligent, the doctrine shall not
apply. However, negligence per se does not strictly prevent frustration from occurring,
as it is for the person claiming frustration to provide proof of the same.
(1) There was no frustration of the charterparty as the absence of a licence was due to
the fact that the appellants' choice of vessels, which were to be granted licences.
(2) Therefore, the appellants remained liable for the hire of the vessel.