32.01 Excavations;
32.02 Backfilling
Cocrete curb Lm
51.01(a)i Gravel subbase layer, 97% MDD, AASHTO T-180 (Material from 6km) m3
Crushed Aggregate Base course compacted to 98% of modified AASHTO
52.01(b)I density (Material from 10km) m3
Bill No. 6 – Bituminous Surfacing
“6101 SCOPE
This Division covers the application of a bituminous prime coat to a prepared pavement layer. [ERA 2002]”
surface treament m2
64.02 50mm Asphaltic surfacing with (penetration grade 60/70 bitumen
8000 STRUCTURES
Irrespective of Depth m3
(b) (ii) High yield stress steel bars (Grade 420) ton
87.03 Bearings
91.01 Gabions
Sign face with area exceeding 2.0 sq.m but not exceeds 10 sq.m fixed on
94.01(a)ii post no.
94.03 (c) Class ‘A’ concrete for footing of road sign support m3
95.01(a) ii white broken (2.5m dash, 7.5m gap) 10cm line Km.
9900 SIDEWALK
99.01(a) Concrete tiles of 50mm thick including the necessary jointing works m2
Search for...
Recent Posts
vacancy(ሲቪል መሃንዲስ)
INVITATION FOR BID(ብሄራዊ ግልፅ ጨረታ ማስታወቂያ)
vacancy(Traffic Engineer)
vacancy(Project Coordinator)
vacancy(Material Engineer)
vacancy(Customer Support Engineer)
vacancy(Engineer Trainee)
Rate
21,887.82
1,000.00
Rate
23.11
155.64
87.15
170.55
2,194.74
2,450.47
2,922.94
3,845.81
276.74
1,640.77
2,352.68
2,800.37
24,369.77
289.81
237.82
650.00
986.85
construction of the embankments or capping layers, and the preparation of the sub-grade prior to the construction of the pavement layer
Rate
64.24
21.77
78.24
233.06
39.96
84
170.56
130.13
115.13
27.74
ment layers including the in-situ recycling of existing pavements. [ERA 2002]”
Rate
170.86
469.19
. [ERA 2002]”
41.56
107.58
289.09
r without reinforcement, and includes, inter alia, the specifications for materials, the placing and compacting of concrete, applying the sur
ng bridges, retaining walls, box and slab culverts etc. It provides in particular specifications for excavation, and back filling and for the cons
303.34
124.59
175.73
237.82
237.82
589.72
29,629.46
26,479.46
4,408.31
3,103.73
10,323.15
1,778.96
500
1,109.66
942.94
258.99
258.99
693.35
8320.2
636.61
23.11
170.55
2,477.73
5,459.44
3,546.81
5,459.44
123.89
struction of the pavement layers. [ERA 2002]”
ng of concrete, applying the surface texture, and constructing the joints. [ERA 2002]”
and back filling and for the construction of the foundation it self as well as the pile capping slabs or the caisson cover slabs. [ERA 200]”
on cover slabs. [ERA 200]”