Method Statement - Line Impedance Measurement - Single Line Circuit and Double Line Circuit
Method Statement - Line Impedance Measurement - Single Line Circuit and Double Line Circuit
Method Statement - Line Impedance Measurement - Single Line Circuit and Double Line Circuit
Author
Anas Abdulkhader [email protected]
Mob: +97333626420
Notes
General purpose method statement describing procedure and safety related to Line Impedance Testing with
CPC 100 + CP CU1 + CP GB1
© OMICRON Page 1 of 14
Content
2 Safety Instructions
Testing and measuring with the CP CU1 must comply with the relevant national and international safety
standards listed below:
• EN 50191 (VDE 0104) "Erection and Operation of Electrical Equipment"
• EN 50110-1 (VDE 0105 Part 100) "Operation of Electrical Installations"
• IEEE 510 "IEEE Recommended Practices for Safety in High-Voltage and High-Power Testing"
• LAPG 1710.6 NASA "Electrical Safety"
In order to estimate the interference and find an adequate current range on the CP CU1, the following
steps are recommended for preparation of the measurement four criteria have to be checked:
4.3
Fig 4: Estimating the open line voltage
This is the most important criteria to select the range. To perform the check, please follow below steps.
1. Switch off, short-circuit and ground the power line on both sides, using an installed grounding switch
or, if no grounding switch is available on site, using grounding cables
2. Make sure that the connection to ground at the far end of the power line is not removed during the
complete test procedure.
3. In addition to the grounding switch, ground the line at the near end, using a grounding set consisting
of three cables rated for the maximum short-circuit current possible on the line.
4. Open the near grounding switch in order to measure the entire circular current via the grounding set.
5. Then measure the current in each of the three phases of the grounding set with a common current
clamp and note the values. Depending on the geometry of the line the values for the currents could slightly
differ.
6. Close the grounding switch again.
The estimated voltage can now be calculated according to below equation by using the highest of the three
measured currents.
Note: If line length is measured in kilometres
► Select the CP CU1’s current range according to this Table 2 Do not select a higher current range than
selected according to line length! Only select a lower range if necessary.
Note: If the calculated voltage exceeds 500 V, the measurement cannot be performed, since the
CP CU1 is designed for a maximum working voltage of 500 V! If this is the case, please consider the
► Set up the CP CU1 and the CP GB1 according to Figure below. The Kelvin clamps on the
grounding box must be connected to the phase where the highest circular current has been
measured and ground.
Note: If the measured voltage exceeds 500 V, the measurement cannot be performed, since the
CP CU1 is designed for a maximum working voltage of 500 V! If this is the case, please consider the
options given in the previous section Please use the same table 2 for selection of current range.
• Connect the CP CU1 to the power line under test and after checking at least 3 criteria
• Use the Sequencer card or line impedance card depending on the license available. Detailed
procedure for using the sequencer card is available on the next section.
• Change the connection accordingly for all other test loops as shown in above figure
• Before changing the connection, please ensure that CPC 100 stopped injection, press emergency
button and ground the transmission line.
• In all the cases remote end remained connected to earth.
• Open the nearby end earth for injection only and should close immediately after the injection.
Settings of
Measurement
In the CPC 100 settings, Device setup, please ensure the external booster is CU1 and the clamp and input
transformer setting is same as below picture
1. use the dedicated template on the CPC 100 by following this path in the file operations view
CPC >> Templates >> Cables and Transmission Lines >> Old line impedance >> Line Imp
CU1 10A 50Hz
2. Choose the template matching the current range selected on the CP CU1.
3. The Schema test cards are comment test cards, which show how to connect the clamps to the CP
GB1.The measurement is then performed in the sequencer test card which is following the Schema
(L1-L2, L1-L3, L2-L3, L1-E, L2-E, L3-E, L1L2L3-E)
4. Press the I/O Button on the CPC 100’s front panel to start a measurement after you have
connected the clamps to the CP GB1 according to the respective Schema test card as well as
Figure 6.
5. The measurement is stopped automatically after the sequence has terminated.
Note: The near end of the line must not be grounded during the injection of the test current! Ground the
line immediately after the measurement!
It is recommended to save the test file on the CPC 100 after each individual test loop to prevent loss of
data in the event of an unexpected outage.
6. After all tests have been performed, open the CPC 100 file (xml-file) with the corresponding Excel
template (Line Imp.xlt) from the CPC 100 Start Page in the section Test Templates. Check the test results
carefully. The cell comments in the test report sheet help you to assess the test results.
The results are extracted from CPC 100 and Copy in to your computer. When you are using external USB
disk, don’t connect more than 1 GB. Otherwise it will hang the system.
Use CPC Start page and on templates use the dedicated template excel file loader.
Example for 10A setting, Templates >> Cables and Transmission Lines >> Old line impedance >> Line
Imp CU1 10A 50Hz >> Open Line impedance.xlt
Load the xml file that is copied from CPC 100 generate the report.
8.1 Using the CPC 100’s Sequencer test card to perform the line impedance
measurement on a double-circuit line
1. Use the dedicated template on the CPC 100 by following this path in the file operations view
CPC >> Templates >> Cables and Transmission Lines >> Old mutual coupling >> Mutual
coup. CU1 10A 50Hz
2. Choose the template matching the current range selected on the CP CU1.
3. The Schema test cards are comment test cards, which show how to connect the clamps to the CP
GB1. The measurement is then performed in the sequencer test card which is following the Schema
test card.
4. Press the I/O Button on the CPC 100’s front panel to start a measurement after you have
connected the clamps to the CP GB1 according to the respective Schema test card as well as
Mutual coupling measurement loop Figure 10. The measurement is stopped automatically after the
sequence has terminated.
Note: The near end of the line must not be grounded during the injection of the test current! Ground the
line immediately after the measurement!
It is recommended to save the test file on the CPC 100 after each individual test loop to prevent loss of
data in the event of an unexpected outage.
4. After all tests have been performed, open the CPC 100 file (xml-file) with the corresponding Excel
template (Mutual Coupling.xlt) from the CPC 100 Start Page in the section Test Templates. Check
the test results carefully. The cell comments in the test report sheet help you to assess the test results.
The results are extracted from CPC 100 and Copy into your computer. When you are using external USB
disk, don’t connect more than 1 GB. Otherwise it will hang the system.
Use CPC Start page and on templates use the dedicated template excel file loader.
1. Example for 10A setting, Templates >> Cables and Transmission Lines >> Old mutual coupling
>> Mutual coup. CU1 10A 50Hz >> Open Mutual Coupling.xlt