Exam 2 '
Exam 2 '
Exam 2 '
Institute of Technology
2. Under each Part of the examination, you are instructed to choose & attempt
certain exam. Questions.
3. The type of examination is open book. You are allowed, however, only to
consult your course material, the relevant standard conditions of contract,
the Civil Code & other directly relevant reference materials.
4. Please, also consider & comply other instructions under each part of the
examination.
1
I. General Course Knowledge Exam. Questions (30%)
The purpose of this part of the examination is to check your knowledge about the
general concepts that have been discussed or covered during the semester.
Please, choose & attempt only three questions from the following four exam.
Questions.
Please, discuss the difference between Interim Payment Certificate & Final Payment
Certificate. (5%)
Please, also discuss the legal & contractual effects of the Final Payment & Account.
(5%). It is expected to mention & discuss, at least, three major legal and/or
contractual effects of the Final Payment.
Objective
The objective of the exam. Question is to check the understanding of the student
about the difference between interim & final payment certificates, and the legal
effects of the final payment certificate.
Instruction
You may discuss the exam. Question within the context of the MDB FIDIC Version-
2006.
Your reply may not exceed more than two pages for both exam. Questions.
Imagine the absence of an Engineer in the Construction Contract, where the Project
Delivery System is design-bid-build (DBB).
What possible adverse contractual effects might result due to the absence of the
Engineer in the construction contract administration & supervision?
2
Objective
The objective of this part of the exam. Question is to check the student’s
understanding about the importance of the role of the Engineer or the Architect in
the construction phase of a construction project.
Instructions
You are expected to distinguish & discuss, at least, five negative effects on the
project.
You may discuss your exam. Question by giving project context like road or water
or building project under the MDB FIDIC Version-2006.
Please, discuss the exam. Question in not less than two pages.
What do you understand by Program & Method Statement? Please, define &
discuss in detail. (4%)
Objective
The objective of this exam. Question is to check the student’s understanding about
the concept of Program & Method Statement within the context of the construction
project & contract and whether or not the said Program and/or Method Statement
do form part of the construction contract.
Instructions
You may discuss your exam. Question by giving project context like road or water
or building project under the MDB FIDIC Version-2006.
Please, discuss the exam. Question in not more less two pages.
4. Sub-contracting (10%)
3
Sub-contracts are signed between the Main Contractor & the Sub-contractor, more
often, after the Main Contract has been signed between the Main Contractor & the
Employer.
As you certainly know, except the information relative to prices of the Main
Contract, all other & relevant information of the Main Contract should, expressly,
be incorporated in to the subsequent Sub-contract.
Assuming that you are acting as the Project Manager for the Sub-contracting
Company. Now, you are negotiating with the representatives of the Main
Contractor on behalf of the Sub-contracting Company.
Exam. Questions
a) What would, in your opinion, be the contractual & legal effects, if the
relevant part of the Main Contract has not expressly been incorporated in
your Sub-contract? (4%)
b) What are the other possible critical issues to be raised & negotiated with the
representatives of the Main Contractor for your Sub-contract? It is expected
to raise, at least, four critical issues & the reasons behind each critical issue.
(6%)
Objective
The objective of this part of the exam. Question is to check the understanding of the
student with respect to the difference & relationship between the Main Contract &
the intended Sub-contract & other critical issues in respect thereof.
Instructions
You may give project context (road or water or building project…) to your
discussion.
Please, provide your answer for each exam. Question in not less than two pages.
4
Please, read the following facts of the Project.
5
The type of construction contract is exactly similar to MDB FIDIC
Version 2006.
The Project has a sectional completion dates, i.e. for the hydropower,
for water supply & for irrigation scheme, separately.
2. Instruction
You are expected to discuss in detail every question & to give reasons
for your analysis or arguments or decision or award, as the case may
be, either from the applicable contract clause and/or the articles of the
applicable law;
6
Notified the Insurance Company to call the
Professional Indemnity Insurance;
Withheld the remaining Fees to be paid to the
Consulting firms i.e. USD 1 Million;
Initiated a court proceeding to secure a court order for
the attachment of the properties of the Consulting
firms imported for the purpose of the execution of the
Project amounting to USD 1 Million;
7
liability should not exceed beyond our Fees under the
Consultancy Agreement i.e. USD 10 Million;
Exam. Questions
b) Assuming that you are a sole Arbitrator for the case, based
on all the parties (multi-party arbitration) agreement i.e. the
Employer, the Contractor & the Consultants, what do you
do, in the first place, before you consider the issue of liability
of the JV Contractors and/or the JV Consulting firms i.e.
whether or not the collapse of the Dam was attributable to
faulty design or defective construction? (6%)