Carpets On Walls
Carpets On Walls
Carpets On Walls
REF:
RISK ASSESSMENT FOR CARPET FLOOR AND WALL FINISHES REV:
DATE:
RISK RISK
RESIDUAL RISK
CONSEQUENCES/ EVALUATION LEVEL ACCEPT
S.N. ACTIVITY HAZARD CAUSES OF HAZARD IMPLEMENTED CONTROL MEASURES
IMPACT Y/N?
P S H/M/L P S H/M/L
1 Mobilization Mobilization/ Untrained/Improper handling of Injury to back, hands Safety induction and training for
and delivery Manual/ materials and equipments/ and feet while operatives working
of the Mechanical Obstructions /Unauthorized handling materials Specific training must be given to
materials Handling personnel and equipments/ those working with hot work,
Obstruction to free operators of certain equipments and
movement/ scaffolding
Injuries/fatalities Proper manual lifting methods to be
applied
Use of proper PPE
Stacking shall be made in a
designated location and the area
5 5 25 1 5 5 Y
shall be secured by using barriers
and signs
Access for vehicles and walkway
should not be obstructed
Proper stacking procedure must be
followed
TBT for operatives together with this
risk assessment
Provide training for the employee for
safe manual handling techniques
2 Surface Loose materials/ Death / Major Injury Do not keep loose material at the
preparation Fall of Materials edge.
Poor Housekeeping Do not over stack materials.
for
installation Clean all the waste materials from
the scaffold platform.
5 5 25 1 5 5 Y
Ensure toe boards are available.
Overhead protection should be
ensured to prevent fall of material
from top.
Barricade the area below the scaffolding.
3 Use of Unsafe use of No proper maintenance of Electrocution of Periodic check of electrical equipments/
portable electrical electrical equipments/ personnel machineries
tolls , machineries machineries 3 4 12 Electrical connection of power supply/ cable 1 4 4 Y
machines etc. Failure to deploy skilled management and arrangements
electricians
4 Application of Contact with skin, Chemical splashes, Lack of Illness, irritation, Workmen are trained on safe 1 5 5 Y
Chemical fire supervision injuries, property applications
(Glue/adhesiv damage Mixing procedures to be complied
e, Primer with manufacturer’s instruction
Page1 of 4
PROJECT NAME
REF:
RISK ASSESSMENT FOR CARPET FLOOR AND WALL FINISHES REV:
DATE:
5 Installation of Inhalation of dust Improper use of PPEs Lungs infection -Ensure trained and experienced employees
carpets during floor Unqualified workers Personal Injury, are assigned to the job.
cleaning Muscle strain
Poor house keeping
Lifting heavy -Respiratory protection, and standard PPEs
carpet manually to be worn at all the times.
slip, trip, fall -Lifting should be done according to lifting
plan in a proper sequence.
2 4 4 1 1 1 Y
Ensure thorough housekeeping and material
stacking throughout the workplace.
Persons in danger
Persons passing the site location/ truck routes, e.g. members of the public and persons in the Vehicles.
All personnel in the team are to be made aware of the safe systems of work.
Page2 of 4
PROJECT NAME
REF:
RISK ASSESSMENT FOR CARPET FLOOR AND WALL FINISHES REV:
DATE:
Emergency procedures
Site emergency procedures should make provision for the rescue of individuals from heights.
First-aid facilities should be available to cope with any significant injuries that may arise from the work.
Work should be monitored by Foreman and charge hand who are trained to ensure that any additional precautions or equipment required are
provided.
RISK MATRIX
Risk Rating (RR) – Severity x Likelihood
Page3 of 4
PROJECT NAME
REF:
RISK ASSESSMENT FOR CARPET FLOOR AND WALL FINISHES REV:
DATE:
LIKELIHOOD
(PROBABILITY)
Likely
(P) Rare Unlikely Possible Almost certain
Could happen often (on
Remote possibility (once Could happen but rare Could happen occasionally Could happen frequently
average once a month or
every 3 years or more) (typically once in a year) (on average quarterly) (once a week or more)
more)
SEVERITY 1 2 3 5
4
(IMPACT)
(S)
Low Low Low Low Medium
Insignificant 1
1 2 3 4 5
Quick, easy controls should be implemented immediately and further action planned for when resources permit. Monitoring required
1-4
ensuring controls are maintained. Manage through routine procedures. Go for economic improvements where possible. Incident
Low
report must be completed.
Aim to reduce risks but costs of prevention may be limited. Undertake a risk assessment of the situation / task and implement the
appropriate actions. Actions should have a timescale and should be monitored. Where the risk involves work in progress undertake
5-12 a risk assessment as soon as possible to ensure the safety of the situation or task. Work should not start until the risk is
Medium reduced to an acceptable level. Considerable resources may have to be allocated. Contact your Manager and Risk Manager by
telephone about the actions that should be taken to reduce the risk/s. incident report must be completed. Incident must be added
to service risk register.
Do not commence the activity until a risk assessment has been completed to ensure the safety of the situation or task. If it is
15-25 not possible to reduce or eliminate the risk even with unlimited resources, work must remain prohibited. Inform your relevant
High Director, your Manager and the Risk Manager immediately by telephone. Incident report must be completed. Incident must be
added to service risk register.
Page4 of 4