Qap FPM1
Qap FPM1
FIRM DETAILS:
Signature Not
Verified Auto Industries
PlotbyNo -209 & 522, Ecotech-III, UK-II,
Digitally signed
NIKHAT Greater Noida Signature of Quality Head Page 1 of 16
Date: 2023.03.09
UP-201306
15:14:20 IST
Reason: IREPS-CRIS
Location: New Delhi
QUALITY ASSURANCE PLAN (QAP)
ITEM Fuel Pump Motor Date: 27-02-2023
SPECIFICATION: MISC 632 REV -02 Rev. Nil
Amendment History:
Table of Contents
1. Purpose: ................................................................................................................................................ 3
2. Scope of Application: ............................................................................................................................ 3
3. Item Details: ............................................................................................................................................
4. Reference Documents:.......................................................................................................................... 3
5. Organization Setup ............................................................................................................................... 4
5.1. Organization Chart ........................................................................................................................ 4
5.2. Qualification of Personals ............................................................................................................. 4
6. Manufacturing Process ......................................................................................................................... 5
6.1. Process Flow Chart ........................................................................................................................ 5
6.2. Machinery and Plant (M&P) ...........................................................................................................
6.3. Testing & Plant ................................................................................................................................
6.4. Details of Sub-assemblies/Components Manufactured ............................................................. 11
6.5. Details of Sub-vendors ................................................................................................................ 12
7. Quality Control .................................................................................................................................... 13
7.1. Quality Certification .................................................................................................................... 13
7.2. Calibration Plan for Testing & Measuring Equipment ................................................................ 13
7.3. Incoming Raw Material & In-process/Final Inspection ............................................................... 14
7.4. Handling of Rejected Material .................................................................................................... 15
7.5. System for Customer Complaints/Warranty Failures ................................................................. 15
7.6. Details of after Sales & Service ................................................................................................... 15
8. Additional Information........................................................................................................................ 16
Annexure: .................................................................................................................................................... 16
Auto Industries
Plot No -209 & 522, Ecotech-III, UK-II,
Greater Noida Signature of Quality Head Page 2 of 16
UP-201306
QUALITY ASSURANCE PLAN (QAP)
ITEM Fuel Pump Motor Date: 27-02-2023
SPECIFICATION: MISC 632 REV -02 Rev. Nil
1. Purpose:
The primary purpose of the Plan is to define how quality will be managed throughout the
life cycle of the FUEL PUMP MOTOR in the following areas:
• Quality Planning – provides the documentation standards and framework for quality
during the lifecycle of the FUEL PUMP MOTOR.
• Quality Assurance – provides the necessary attention to detail for continuous
improvement of activities and processes to achieve quality.
• Quality Control – monitor and inspection process that ensures every deliverable and
work product is measured, tested, and ensures results conform to quality standards.
• Quality Improvement–identifies quality improvement opportunities and implements
corrective action or process improvement.
2. Scope of Application:
Applicable for DC/AC converter based 15 AC motor driven Fuel Transfer Pump for ALCO &
HHP Locomotives.
3. Item Details:
4. Reference Documents:
ISO : 9001 : 2015
Auto Industries
Plot No -209 & 522, Ecotech-III, UK-II,
Greater Noida Signature of Quality Head Page 3 of 16
UP-201306
QUALITY ASSURANCE PLAN (QAP)
ITEM Fuel Pump Motor Date: 27-02-2023
SPECIFICATION: MISC 632 REV -02 Rev. Nil
5. Organization Setup
5.1. Organization Chart
b) Quality Control
Auto Industries
Plot No -209 & 522, Ecotech-III, UK-II,
Greater Noida Signature of Quality Head Page 4 of 16
UP-201306
QUALITY ASSURANCE PLAN (QAP)
ITEM Fuel Pump Motor Date: 27-02-2023
SPECIFICATION: MISC 632 REV -02 Rev. Nil
d) R&D/Design
6. Manufacturing Process
6.1. Process Flow Chart
Auto Industries
Plot No -209 & 522, Ecotech-III, UK-II,
Greater Noida Signature of Quality Head Page 5 of 16
UP-201306
QUALITY ASSURANCE PLAN (QAP)
ITEM Fuel Pump Motor Date: 27-02-2023
SPECIFICATION: MISC 632 REV -02 Rev. Nil
Auto Industries
Plot No -209 & 522, Ecotech-III, UK-II,
Greater Noida Signature of Quality Head Page 6 of 16
UP-201306
QUALITY ASSURANCE PLAN (QAP)
ITEM Fuel Pump Motor Date: 27-02-2023
SPECIFICATION: MISC 632 REV -02 Rev. Nil
13 Lathe 6 Relience
Auto Industries
Plot No -209 & 522, Ecotech-III, UK-II,
Greater Noida Signature of Quality Head Page 7 of 16
UP-201306
QUALITY ASSURANCE PLAN (QAP)
ITEM Fuel Pump Motor Date: 27-02-2023
SPECIFICATION: MISC 632 REV -02 Rev. Nil
42 Shearing Machine Up to 6 mm -
Bhagwan Sons, Ludhiana
43 Centerless Grinding Dia 100 mm
Capable to test all locomotive fuel pump Paragon, USA
44 Test Bench for Fuel pump
Paragon, USA
45 Facility for Fuel pump Assemble -
Auto Industries
Plot No -209 & 522, Ecotech-III, UK-II,
Greater Noida Signature of Quality Head Page 8 of 16
UP-201306
QUALITY ASSURANCE PLAN (QAP)
ITEM Fuel Pump Motor Date: 27-02-2023
SPECIFICATION: MISC 632 REV -02 Rev. Nil
Auto Industries
Plot No -209 & 522, Ecotech-III, UK-II,
Greater Noida Signature of Quality Head Page 9 of 16
UP-201306
QUALITY ASSURANCE PLAN (QAP)
ITEM Fuel Pump Motor Date: 27-02-2023
SPECIFICATION: MISC 632 REV -02 Rev. Nil
Auto Industries
Plot No -209 & 522, Ecotech-III, UK-II,
Greater Noida Signature of Quality Head Page 10 of 16
UP-201306
QUALITY ASSURANCE PLAN (QAP)
ITEM Fuel Pump Motor Date: 27-02-2023
SPECIFICATION: MISC 632 REV -02 Rev. Nil
c) Part III: Details of items outsourced from other than DLW/RDSO approved items
Auto Industries
Plot No -209 & 522, Ecotech-III, UK-II,
Greater Noida Signature of Quality Head Page 11 of 16
UP-201306
QUALITY ASSURANCE PLAN (QAP)
ITEM Fuel Pump Motor Date: 27-02-2023
SPECIFICATION: MISC 632 REV -02 Rev. Nil
Auto Industries
Plot No -209 & 522, Ecotech-III, UK-II,
Greater Noida Signature of Quality Head Page 12 of 16
UP-201306
QUALITY ASSURANCE PLAN (QAP)
ITEM Fuel Pump Motor Date: 27-02-2023
SPECIFICATION: MISC 632 REV -02 Rev. Nil
• M&P and T&P required for each stage should be clearly mentioned.
• Pre manufacturing stage and after manufacturing stage inspection & testing should
be clearly mentioned along with checklist.
• Checklist should be attached with the QAP.
• Please attach ISO certificates of sub-vendors.
7 Quality Control
7.1 Quality Certification
a) ISO
b) Any other Document/certification
c) Part III: Calibration plan for the items identified for specified calibration in
STR/Specification
Auto Industries
Plot No -209 & 522, Ecotech-III, UK-II,
Greater Noida Signature of Quality Head Page 13 of 16
UP-201306
QUALITY ASSURANCE PLAN (QAP)
ITEM Fuel Pump Motor Date: 27-02-2023
SPECIFICATION: MISC 632 REV -02 Rev. Nil
SN Incoming Sample Size & Parameters Mode of Acceptance Rejection & Trace-ability Register No.
Product/Assy. its Frequency for Inspection/ Limits/Criteria Disposal/
of Inspection Inspection Equipment /Specified Reprocessed/S
Used Value craped
1 All Casting Parts 100% Per Lot As per AS per AS per Internal Reject & Incoming Inspection
Internal drg Internal Control Plan Return to F-1/8.4C
Control Plan Supplier
2 All BOP items 100% Per Lot As per PO AS per AS per Internal Reject & Incoming Inspection
Internal Control Plan Return to F-1/8.4C
Control Plan Supplier
3 Fasteners/Hardw 100% Per Lot As per AS per AS per Internal Reject & Incoming Inspection
ares Internal drg. Internal Control Plan Return to F-1/8.4C
Control Plan Supplier
4 Bearings 100% Per Lot As per AS per AS per Internal Reject & Incoming Inspection
Internal drg. Internal Control Plan Return to F-1/8.4C
Control Plan Supplier
5 Rotar, stator, 100% Per Lot As per AS per AS per Internal Reject & Incoming Inspection
motor Internal drg. Internal Control Plan Return to F-1/8.4C
Control Plan Supplier
6 All Types of seals 100% Per Lot As per AS per AS per Internal Reject & Incoming Inspection
Internal drg. Internal Control Plan Return to F-1/8.4C
Control Plan Supplier
7 O Rings 100% Per Lot As per AS per AS per Internal Reject & Incoming Inspection
Internal drg. Internal Control Plan Return to F-1/8.4C
Control Plan Supplier
8 Bar Stock 100% Per Lot As per AS per AS per Internal Reject & Incoming Inspection
Internal drg. Internal Control Plan Return to F-1/8.4C
Control Plan Supplier
SN Incoming Sample Size Mode of Acceptance Rejection & Trace-ability Register No.
Product/Assy. & its Inspection/Equipm Limits/Criteria/Specified Disposal/
Frequency ent Used Value Reprocessed/S
of craped
Inspection
1 All Machining 100% As per Internal As per Internal Control Plan Reject/Rework In process Inspection
items Drawing F-1/8.4F
2 Motor end plate 100% As per Internal Diameter = 151.2 mm Reject/Rework In process Inspection
assembly Drawing Thickness = 24.1 mm F-1/8.4F
Mounting Hole PCD = 129 mm
3 Motor outer 100% As per Internal Overall Diameter = 143 mm Reject/Rework In process Inspection
body and stator Drawing Inner Diameter = 139 mm F-1/8.4F
assembly Overall Height = 114 mm
4 Rotor and shaft 100% As per Internal Overall length = 128.6 mm Reject/Rework In process Inspection
assembly Drawing Overall Shaft Dia = 31.7 mm F-1/8.4F
Hole Dia = 6.3 mm
Auto Industries
Plot No -209 & 522, Ecotech-III, UK-II,
Greater Noida Signature of Quality Head Page 14 of 16
UP-201306
QUALITY ASSURANCE PLAN (QAP)
ITEM Fuel Pump Motor Date: 27-02-2023
SPECIFICATION: MISC 632 REV -02 Rev. Nil
5 Pump Gear & 100% As per Internal Overall length = 124.15 mm Reject/Rework In process Inspection
Shaft Assembly Drawing Overall Width = 121.96 mm F-1/8.4F
Overall Thickness = 36.85 mm
Inlet & Outlet Holes distance =
71.3 mm
6 Complete motor 100% As per Internal Height = 134.62 mm Reject/Rework In process Inspection
& Pump Drawing Width = 215.90 mm F-1/8.4F
assembly Thickness of Mounting Plate=
12.70 mm
7 Inverter 100% As per Internal As per Internal Control Plan Reject/Rework In process Inspection
assembly Drawing F-1/8.4F
SN Name of the Sample Size & Parameter for Mode of Acceptance Rejection & Trace-ability
Test/ Its Frequency Inspection Inspection/ Limits/Criteria/ Disposal/ Register No.
Process of Inspection Equipment Used Specified Value Reprocessed/
Scraped
1 Dimensional 100% As Per Internal As per Internal As per tolerances Reject/Rework Final Inspection
check Drawing Control Plan F-2/8.6
2 Final 100% As Per Internal As per Internal As per tolerances Reject/Rework Final Inspection
Performance Drawing Control Plan F-2/8.6
test
Date of compliance
person deputed for
in case of warranty
cause of failure
Brief details of
collecting field
end rejection
Whether any
Date of joint
inspection /
failure/ Call
Consignee
complaints
inspection
complaint
complaint
failure/ In
/ General
Warranty
Letter no
for joint
sample
service
Sl.No.
from
Format Noted
* The firm shall maintain a complaint register in the above format and the summary
required to be given during renewal
Auto Industries
Plot No -209 & 522, Ecotech-III, UK-II,
Greater Noida Signature of Quality Head Page 15 of 16
UP-201306
QUALITY ASSURANCE PLAN (QAP)
ITEM Fuel Pump Motor Date: 27-02-2023
SPECIFICATION: MISC 632 REV -02 Rev. Nil
8 Additional Information
• The firm can furnish any other information which they wish to submit on items other than
furnished above.
Annexure:
1. Work Instruction for each stage:
2. Inspection check sheet for:
a. Incoming material:
b. In-process/stage inspection:
c. Final material:
3. ISO Certificate:
4. Any other quality/design certification
Auto Industries
Plot No -209 & 522, Ecotech-III, UK-II,
Greater Noida Signature of Quality Head Page 16 of 16
UP-201306