PMP 6 Presentation - Abdulfattah
PMP 6 Presentation - Abdulfattah
PMP 6 Presentation - Abdulfattah
(PMP)
Presented by :
Abdulfattah Ajlan
Certified PMP Trainer
Welcome
❑ Course : Project Management. Professional - PMP
The Owner:
Project Management Institute (PMI)
• Not-for-profit professional association. primary goal is
to advance the practice, science and profession of
project management.
• Recognized since 1969 by working PMs.
• Headquartered in Pennsylvania USA.
Fact File
PMP Exam Requirements
To be eligible for PMP Certification, you will need to demonstrate
that you meet certain minimum criteria as below:
❑ University Degree,
✓ 4,500 hours of project management experience,
✓ 35 hours of project management education.
Closing 7%
Total 100%
PMP examination content
Validity
❖ The credential is valid for 3 Years.
❖ Candidates must recertify every 3 years by earning 60
Professional Development Units (PDUs).
❖ How to earn 60 PDU?
• Course or Training.
• Work as a Practitioner.
• Create Content.
• Give a Presentation.
• Organization Meetings.
• Volunteer.
• Read.
• Share Knowledge.
CAPM Certificate
Certified Associate in Project Management (CAPM)®
Requirements:
• Secondary degree (high school diploma, associate’s degree or the global
equivalent).
• 23 hours of project management education completed by the time you sit for the
exam.
Presented by :
Abdulfattah Ajlan
Certified PMP Trainer
What is a Project
13
Fundamental elements of Project
14
Projects Vs. Operational Work
Project Operation
Temporary Ongoing
Create a unique product, service, or Produce repetitive products,
result services, or results
Moving the organization from one Work sustain the organization
state to another state overtime
15
Importance of Project management
Project management
Is the application of knowledge, skills, tools, and techniques to project activities
to meet the project requirements.
Project Management enables organizations to execute projects effectively and
efficiently
Project: Program:
Managed as a stand-alone project, within a program, Group of related projects, subsidiary
or within a portfolio, to get project objective. programs, and program activities
managed in a coordinated manner to
Portfolio: obtain benefits not available from
Is a projects, programs, subsidiary portfolios, and managing them individually.
operations managed as a group to achieve strategic
objectives.
16
Relation between Project, Program, Portfolio,& Operations
17
Relation between Project, Program, Portfolio,& Operations
Strategic
Objectives
Benefits
Objectives
18
12برنامج
96هدف استراتيجي رؤية المملكة العربية السعودية 2030
برنامج صندوق
برنامج تحقيق برنامج برنامج التحول برنامج خدمة
اإلستثمارات
التوازن المالي اإلسكان الوطني ضيوف الرحمن
العامة
مبادرة تخصيص
مبادرات مبادرة التشييد
األراضي
العمق العربي واإلسالمي -قوة استثمارية رائدة -ومحور ربط القارات الثالث 19
Relation between Project, Program, Portfolio,& Operations
20
Organizational Project Management (OPM).
Project Life cycle
Project life cycle
Is the series of phases that a project passes through from its start to its completion.
It provides the Basic Framework for managing the project.
Predictive life cycle (waterfall) scope, time, and cost are determined in the early phases.
Adaptive life cycles are agile or change-driven life cycles, it can be
iterative, or incremental. The detailed scope is defined and approved
before the start of an iteration.
Example 1 Example 2
23
Development Lifecycle
Development life cycles: one or more phases that are associated with the development.
Development
Phase 1 Phase 2 Phase 4 Phase 5
Phase 3
24
Development Lifecycle
Development life cycles: one or more phases that are associated with the development.
Predictive life cycle (waterfall) scope, time, and cost are determined in the early phases.
Iterative life cycle, the project scope is generally determined early, but time and cost
estimates are routinely modified.
Phase
Is a collection of logically related project activities described by attributes
(Name, number, Duration, Resource requirements, etc.)
Phase Gate
A phase gate, is held at the end of a phase.
The project’s performance and progress are compared to project and business
documents (business case, Project charter, Project management plan ,Benefits
management plan).
May be called (phase review, stage gate, kill point). A decision (e.g., go/no-go
decision) is made depending on the organization.
Development
Phase 1 Phase 2 Phase 4 Phase 5
Phase 3
27
Project Management Processes
29
Overlap of Process Groups
Executing
Effort
Planning
Initiating M&C Closing
30
Project Management Process Groups
Knowledge Areas
Initiating Planning Executing Monitoring and Controlling Closing
Project Integration 4.1 Develop 4.2 Develop Project Management Plan 4.3 Direct and Manage Project Work 4.5 Monitor and Control Project Work 4.7 Close
Management Project Charter 4.4 Manage Project Knowledge 4.6 Perform Integrated Change Control Project
5.1 Plan Scope Management
5.5 Validate Scope
Project Scope 5.2 Collect Requirements
5.6 Control Scope
Management 5.3 Define Scope
5.4 Create WBS
6.1 Plan Schedule
6.2 Define Activities
Project Schedule 6.6 Control Schedule
6.3 Sequence Activities
Management
6.4 Estimate Activity Durations
6.5 Develop Schedule Management
7.1 Plan Cost Management
Project Cost
7.2 Estimate Costs 7.4 Control Costs
Management
7.3 Determine Budge
Project Quality
8.1 Plan Quality Management 8.2 Manage Quality 8.3 Control Quality
Management
Project Resource 9.1 Plan Resource Management 9.3 Acquire Resources
9.6 Control Resources
Management 9.2 Estimate Activity Resources 9.4 Develop Team
9.5 Manage Team
Project 10.1 Plan Communications
Communications Management 10.2 Manage Communications 10.3 Monitor Communications
Management
11.1 Plan Risk Management
11.2 Identify Risks
Project Risk 11.6 Implement Risk Responses
11.3 Perform Qualitative Risk Analysis 11.7 Monitor Risks
Management
11.4 Perform Quantitative Risk Analysis
11.5 Plan Risk Responses
Project Procurement 12.2 Conduct Procurements 12.3 Control Procurements
12.1 Plan Procurement Management
Management
Project Stakeholder 13.1 Identify 13.4 Manage Stakeholder
13.2 Plan Stakeholder Engagement 13.4 Monitor Stakeholder Engagement
Management Stakeholders Engagement
Project Management Processes
Project Management Data and Information
Project data are regularly collected and analyzed throughout the project
life cycle
32
Project Management Processes
33
Project Management Business Documents
35
Project Management Business Documents
36
Project Management Business Documents
37
WORKSHOP
38
2. THE ENVIRONMENT
IN WHICH PROJECT OPERATE
Presented by :
Abdulfattah Ajlan
Certified PMP Trainer
39
Project Environment
40
Project Environment
Enterprise environmental factors
Refer to conditions, not under the control of the project team, that influence, constrain, or direct the
project positive or negative.
41
Project Environment
42
Project Environment
Governance Framework
Includes but is not limited to:
• Rules. • Relationships.
• Policies. • Systems.
• Procedures. • Processes.
• Norms.
44
Governance of Portfolios, Programs, and Projects
45
Organizational Structure type
Manages
Structure Type PM Authority PM Role Resource Av.
Budget
Part-time; may or may not be a designated job role
Organic or Simple L or none L or none Owner
like coordinator
Part-time; may or may not be a designated job role L or none
Functional L or none FM
like coordinator
Project-oriented H to almost total Full-time designated job role H to almost total PM
Matrix – strong Moderate to high Full-time designated job role M to H PM
Part-time; done as part of another job and not a
Matrix – weak L L FM
designated job role like coordinator
Part-time; embedded in the functions as a skill and Mixed
Matrix – balanced L to moderate L to moderate
may not be a designated job role like coordinator
Mixed
Virtual L to moderate Full-time or part-time L to moderate
Matrix – strong
Matrix – weak
47
Project-oriented Functional
48
Organizational Structure type
49
Project management office PMO
Supportive
• Provide a consultative role by supplying
templates, best practices, training, access
Directive
to information, and lessons learned from
other projects. • Directly managing the projects.
• Project managers are assigned by and
report to the PMO.
Controlling • The degree of control is high.
• Provide support and require compliance
• The degree of control is moderate.
50
Project management office PMO
51
Project Stakeholders:
1. Person
2. Group
3. Impact
4. Be impacted
5. Positively
6. Negatively
52
3. THE ROLE OF
PROJECT MANAGER
Presented by :
Abdulfattah Ajlan
Certified PMP Trainer
The Project Manager Competency
Project manager:
Is the person assigned by the performing
organization to lead the team responsible for
achieving the project objectives.
The Project Manager Competency
PMI studies applied the Project Manager Competency Development (PMCD) Framework to
the skills needed by project managers through the use of The PMI Talent Triangle.
Leadership
The knowledge, skills, and behaviors needed to guide,
motivate, and direct a team, to help an organization
achieve its business goals.
The Project Manager Competency
LEADERSHIP
Leadership skills involve the ability to guide, motivate, and direct a team.
include essential capabilities such as negotiation, resilience,
communication, problem solving, critical thinking, and interpersonal
skills.
57
Leadership styles
58
Manager vs Leader
Project managers need to employ both leadership and management in order to be successful.
Management Leadership
1. Direct using positional power 1. Guide, influence, and collaborate using relational power
2. Maintain 2. Develop
3. Administrate 3. Innovate
4. Focus on systems and structure 4. Focus on relationships with people
5. Rely on control 5. Inspire trust
6. Focus on near-term goals 6. Focus on long-range vision
7. Ask how and when 7. Ask what and why
8. Focus on bottom line 8. Focus on the horizon
9. Accept status quo 9. Challenge status quo
10.Do things right 10.Do the right things
11.Focus on operational issues and 11.Focus on vision, alignment, motivation, and inspiration
problem solving
59
Perform Integration
Presented by :
Abdulfattah Ajlan
Certified PMP Trainer
61
Project Integration Management
62
Key concepts for Project Integration Management
63
Project Management Process Groups
Knowledge Areas
Initiating Planning Executing Monitoring and Controlling Closing
Project Integration 4.1 Develop 4.2 Develop Project Management Plan 4.3 Direct and Manage Project Work 4.5 Monitor and Control Project Work 4.7 Close
Management Project Charter 4.4 Manage Project Knowledge 4.6 Perform Integrated Change Project
Control
Project Scope 5.1 Plan Scope Management 5.5 Validate Scope
Management 5.2 Collect Requirements 5.6 Control Scope
5.3 Define Scope
5.4 Create WBS
Project Schedule 6.1 Plan Schedule Management 6.6 Control Schedule
Management 6.2 Define Activities
6.3 Sequence Activities
6.4 Estimate Activity Durations
6.5 Develop Schedule Management
Project Cost 7.1 Plan Cost Management 7.4 Control Costs
Management 7.2 Estimate Costs
7.3 Determine Budge
Project Quality 8.1 Plan Quality Management 8.2 Manage Quality 8.3 Control Quality
Management
Project Resource 9.1 Plan Resource Management 9.3 Acquire Resources 9.6 Control Resources
Management 9.2 Estimate Activity Resources 9.4 Develop Team
9.5 Manage Team
Project 10.1 Plan Communications 10.2 Manage Communications 10.3 Monitor Communications
Communications Management
Management
Project Risk 11.1 Plan Risk Management 11.6 Implement Risk Responses 11.7 Monitor Risks
Management 11.2 Identify Risks
11.3 Perform Qualitative Risk Analysis
11.4 Perform Quantitative Risk Analysis
11.5 Plan Risk Responses
Project Procurement 12.1 Plan Procurement Management 12.2 Conduct Procurements 12.3 Control Procurements
Management
Project Stakeholder 13.1 Identify 13.2 Plan Stakeholder Engagement 13.3 Manage Stakeholder 13.4 Monitor Stakeholder
64
Management Stakeholders Engagement Engagement
Legend:
4.1 Develop Project Charter New Item
Already Explained Item
65
4.1 Develop Project Charter
66
حقائق PMP
67
4.1 Develop Project Charter Input
02
Agreements
• They are used to define initial intentions for a project.
• Agreements May take the form of contracts,
memorandums of understanding (MOUs), service level
agreements (SLA), letters of acceptance, letters of intent,
verbal agreements, email, or other written agreements.
▪ A contract is used when a project is being performed for an
external customer.
03
Enterprise Environmental Factor
04
Organization Process Asset
68
4.1 Develop Project Charter Tools & Techniques
01 Expert judgment
▪ Defined as judgment provided based upon expertise in an
application area, Knowledge Area, discipline, industry, etc.,
as appropriate for the activity being performed.
▪ Such expertise may be provided by any group or person with
specialized education, knowledge, skill, experience, or
training.
02 Data Gathering
Brainstorming
• Is used to identify a list of ideas in a short period of time.
• It is conducted in a group environment and is led by a
facilitator.
• Brainstorming comprises two parts: idea generation and
analysis.
69
Project Integration Management
02
Data Gathering
Focus group
• Bring together stakeholders and subject matter experts to learn about the
perceived project risk, success criteria, and other topics in a more conversational
way than a one-on-one interview.
Interviews
• Are used to obtain information on high-level requirements, assumptions or
constraints, approval criteria, and other information from stakeholders by talking
directly to them.
70
Project Integration Management
01
Project Charter
• The project charter is the document issued by the project
initiator or sponsor that formally authorizes the existence of a
project and provides the project manager with the authority to
apply organizational resources to project activities
02 Assumption Log
• High-level strategic and operational assumptions and
constraints.
• Lower-level activity and task assumptions (technical
specifications, estimates, the schedule, risks)
• The assumption log is used to record all assumptions and
constraints throughout the project life cycle.
72
Project Integration Management
Project Charter
74
4.2 Develop Project Management Plan
75
Project Integration Management
01 Project charter
04
Organization Process Asset
76
Project Integration Management
01 Expert judgment
02 Data gathering
• Brainstorming
• Focus group
• Interviews
• Checklists: A checklist may guide the project manager to
develop the plan or may help to verify that all the
required information is included in the project
management plan.
03 Interpersonal and team skills
• Conflict management
• Facilitation
• Meeting management
04 Meetings
77
Checklists Example:
78
Project Integration Management
01 Project Management Plan is the document that describes how the project will be
executed, monitored and controlled, and closed. It integrates and consolidates all of
the subsidiary management plans and baselines, and other information necessary to
manage the project.
Progressive Elaboration
79
Project Integration Management
81
4.3 Direct and Manage Project Work
82
Project Integration Management
83
Project Integration Management
01 Expert judgment
03 Meetings
84
Project Integration Management
02
Work performance data: are the raw observations and measurements
identified during activities being performed to carry out the project work.
Such as (% of exact activity)
03 Issue log: is a project document where all the issues are recorded and
tracked.
85
Project Integration Management
04 Change Requests
87
Legend:
New Item
4.4 Manage Project Knowledge Already Explained Item
88
4.4 Manage Project Knowledge
89
Project Integration Management
2 Knowledge management using existing knowledge and connect people so they can work
together to create new knowledge.
3 Information management tools and techniques used to connect people to information.
4 Interpersonal and team skills
• Active listening. helps reduce misunderstandings and improves communication and
knowledge sharing.
• Facilitation.
• Leadership.
• Networking.
Allows informal connections and relations among project stakeholders to be
established and creates the conditions to share tacit and explicit knowledge.
• Political awareness.
Helps the project manager to plan communications based on the project environment
as well as the organization’s political environment. 91
Project Integration Management
92
Legend:
4.5 Monitor and Control Project Work New Item
Already Explained Item
Project documents (Assumption log) 14 Data analysis (Alternatives analysis) 13 Change requests 24
Project documents (Basis of estimates) 6 Data analysis (Cost-benefit analysis) 5 PM Plan updates (Any component) 5
Agreements 11
93
4.5 Monitor and Control Project Work
94
Project Integration Management
95
Project Integration Management
01 Expert judgment
02 Data analysis
• Alternatives analysis. is used to select the corrective actions or a combination of
corrective and preventive actions to implement when a deviation occurs.
• Root cause analysis (Cause & Effect) (Fish bone diagram) : focuses on
identifying the main reasons of a problem. It can be used to identify the reasons
for a deviation and the areas the project manager should focus on in order to
achieve the objectives of the project.
96
Project Integration Management
02 Data analysis
• Trend analysis.
✓ It is used to forecast future performance based on past results.
✓ It looks ahead in the project for expected slippages and warns the project manager
ahead of time that there may be problems later in the schedule if established trends
persist.
✓ This information is made available early enough in the project timeline to give the
project team time to analyze and correct any anomalies.
✓ The results of trend analysis can be used to recommend preventive actions if
necessary.
97
Root cause analysis Trend analysis
98
Project Integration Management
03 Decision making
Voting.
➢ Voting can take the form of unanimity, majority, or plurality
04 Meetings
99
Project Integration Management
01
Work performance reports:
are the physical or electronic representation of work performance
information intended to generate decisions, actions, or awareness.
02 Change requests
03 Project management plan updates
Project documents updates
• Cost forecasts
• Issue log
• Lessons learned register
• Risk register
• Schedule forecasts
100
Project Management Processes
101
Legend:
4.6 Perform Integrated Change Control New Item
Already Explained Item
Change requests 1
102
4.6 Perform Integrated Change Control
103
Project Integration Management
104
Project Integration Management
01
EXPERT JUDGMENT
In addition to the project management team’s expert judgment, stakeholders may be asked to
provide their expertise and maybe asked to sit on the change control board (CCB).
105
Project Integration Management
03
DATA ANALYSIS
• Alternatives analysis.
• Cost-benefit analysis.
04 DECISION MAKING
• Voting.
➢ Voting can take the form of unanimity, majority, or plurality to decide on whether
to accept, defer, or reject change requests.
• Autocratic decision making.
➢ One individual takes the responsibility for making the decision for the entire group.
• Multi-criteria decision analysis.
➢ This technique uses a decision matrix to provide a systematic analytical approach
to evaluate the requested changes according to a set of predefined criteria.
05
MEETINGS
106
Project Integration Management
01
APPROVED CHANGE REQUESTS
• Approved change requests will be implemented through the
Direct and Manage Project Work process.
• All change requests are recorded in the change log as a
project document update.
107
Project Integration Management
the project manager reviews the project management plan to ensure that all project
work is completed and that the project has met its objectives.
Actions and activities necessary to satisfy completion or exit criteria for the
phase or project
• Making certain that all documents and deliverables are up-to-date and that all
issues are resolved.
• Confirming the delivery and formal acceptance of deliverables by the customer.
• Ensuring that all costs are charged to the project.
• Closing project accounts.
• Reassigning personnel.
• Dealing with excess project material.
• Reallocating project facilities, equipment, and other resources.
• Elaborating the final project reports as required by organizational policies.
108
Legend:
4.7 Close Project or Phase New Item
Already Explained Item
Project documents (Basis of estimates) 6 Data analysis (Trend analysis) 7 OPA updates 10
Accepted deliverables 1
Agreements 11
Procurement documentation 4
110
Project Integration Management
01 PROJECT CHARTER
02 PROJECT MANAGEMENT PLAN
03 PROJECT DOCUMENTS
04 ACCEPTED DELIVERABLES.
05 BUSINESS DOCUMENTS.
06 AGREEMENTS.
07 PROCUREMENT DOCUMENTATION.
08 OPA.
111
Project Integration Management
01 EXPERT JUDGMENT
02
DATA ANALYSIS
• Document analysis.
Review the available documentation will help in identifying lessons learned and
knowledge sharing for future projects and organizational assets improvement.
• Regression analysis.
Analyzes the interrelationships between different project variables that contributed to
the project outcomes to improve performance on future projects.
• Trend analysis.
• Variance analysis.
03 MEETINGS
112
Project Integration Management
4.7 Close Project or Phase Output
03 FINAL REPORT
The final report provides a summary of the project performance.
04 OPA UPDATES
113
5. PROJECT
SCOPE MANAGEMENT
Presented by :
Abdulfattah Ajlan
Certified PMP Trainer
Project Scope Management
115
Key concepts for Project Scope Management
116
Scope Creep
(Requirement creep, Function creep) Refers to changes, continuous or
uncontrolled growth in a project’s scope. It occurs when the scope of a project is
not properly defined, documented, or controlled.
117
Project Management Process Groups
Knowledge Areas
Initiating Planning Executing Monitoring and Controlling Closing
Project Integration 4.1 Develop 4.2 Develop Project Management Plan 4.3 Direct and Manage Project Work 4.5 Monitor and Control Project Work 4.7 Close
Management Project Charter 4.4 Manage Project Knowledge 4.6 Perform Integrated Change Project
Control
Project Scope 5.1 Plan Scope Management 5.5 Validate Scope
Management 5.2 Collect Requirements 5.6 Control Scope
5.3 Define Scope
5.4 Create WBS
Project Schedule 6.1 Plan Schedule 6.6 Control Schedule
Management 6.2 Define Activities
6.3 Sequence Activities
6.4 Estimate Activity Durations
6.5 Develop Schedule Management
Project Cost 7.1 Plan Cost Management 7.4 Control Costs
Management 7.2 Estimate Costs
7.3 Determine Budge
Project Quality 8.1 Plan Quality Management 8.2 Manage Quality 8.3 Control Quality
Management
Project Resource 9.1 Plan Resource Management 9.3 Acquire Resources 9.6 Control Resources
Management 9.2 Estimate Activity Resources 9.4 Develop Team
9.5 Manage Team
Project 10.1 Plan Communications 10.2 Manage Communications 10.3 Monitor Communications
Communications Management
Management
Project Risk 11.1 Plan Risk Management 11.6 Implement Risk Responses 11.7 Monitor Risks
Management 11.2 Identify Risks
11.3 Perform Qualitative Risk Analysis
11.4 Perform Quantitative Risk Analysis
11.5 Plan Risk Responses
Project Procurement 12.1 Plan Procurement Management 12.2 Conduct Procurements 12.3 Control Procurements
Management
Project Stakeholder 13.1 Identify 13.2 Plan Stakeholder Engagement 13.3 Manage Stakeholder 13.4 Monitor Stakeholder
Management Stakeholders Engagement Engagement 118
Project Scope Management
Legend:
New Item
5.1 Plan Scope Management Already Explained Item
Project management plan (Quality 7 Data analysis (Alternatives analysis) 13 Requirements management plan 1
management plan)
Project management plan (Project life 1 Meetings 28
cycle description)
Project management plan (Development 2
approach)
Enterprise environmental factors 40
119
5.1 Plan Scope Management
120
Project Scope Management
01 PROJECT CHARTER
01 Expert judgment
02 Data Analysis
• Alternatives analysis
03 Meetings
122
Project Scope Management
01
SCOPE MANAGEMENT PLAN
Component of the project management plan that describes how the
scope will be defined, developed, monitored, controlled, and validated;
123
Project Scope Management
Legend:
New Item
5.2 Collect Requirements Already Explained Item
Project management plan (Scope 8 Data gathering (Brainstorming) 6 Requirements traceability matrix 1
management plan)
Project management plan (Requirements 7 Data gathering (Interviews) 8
management plan)
Project management plan (Stakeholder 8 Data gathering (Focus groups) 3
engagement plan)
Project documents (Assumption log) 14 Data gathering (Questionnaires and surveys) 3
Context diagram 1
Prototypes 1 124
5.2 Collect Requirements
125
Project Scope Management
01
PROJECT CHARTER
02
PROJECT MANAGEMENT PLAN
• Scope management plan.
• Requirements management plan.
• Stakeholder engagement plan.
03 PROJECT DOCUMENTS
• Assumption Log.
• Lessons learned register.
• Stakeholder Register.
04 BUSINESS DOCUMENTS
05 AGREEMENTS
06 EEF
07 OPA
126
Project Scope Management
Benchmarking Comparing
Questionnaires & surveys. actual or planned products, to
Sets of questions designed to those of comparable
organizations to identify best
quickly accumulate information
practices, generate ideas for
improvement.
127
Project Scope Management
03 DATA ANALYSIS
Document analysis: reviewing and assessing any relevant documented information to
elicit requirements by analyzing existing documentation and identifying information relevant
to the requirements.
04 DECISION MAKING
Voting.
• Unanimity - everyone agrees on a single course of action.
• Majority – More than 50% of the members agree.
• Plurality. – Largest block in a group decides.
Autocratic decision making one individual takes responsibility for making the decision.
Multi-criteria decision analysis uses a decision matrix to provide a systematic analytical
approach for establishing criteria to evaluate and rank many ideas.
128
Project Scope Management
130
Mind Map consolidates ideas into a single map to reflect commonality and differences
131
Project Scope Management
08
CONTEXT DIAGRAM
Visually depict the product scope by
showing a business system, and how
people and other systems (actors)
interact with it.
132
Project Scope Management
01
REQUIREMENTS DOCUMENTATION
➢ Business requirements. describe the higher-level needs of the organization as a whole.
➢ Stakeholder requirements. describe needs of a stakeholder or stakeholder group.
➢ Solution requirements. describe features, functions, and characteristics of the product,
service, or result that will meet the business and stakeholder requirements.
Functional Ex: actions, processes, data, and interactions that the product should execute
Nonfunctional Ex: reliability, security, performance, safety, level of service,
supportability, retention.
➢ Transition and readiness requirements. Capabilities needed to transition from the current
state to the desired future state, such as training requirements.
➢ Project requirements. actions, processes, or other conditions the project needs to meet.
➢ Quality requirements. Ex: include tests, certifications, validations, etc.
133
Project Scope Management
134
Project Scope Management
Legend:
New Item
5.3 Define Scope Already Explained Item
135
5.3 Define Scope
136
Project Scope Management
01 PROJECT CHARTER
03
PROJECT DOCUMENTS
• Assumption log: identifies assumptions and constraints about
the product, project, environment, stakeholders, and other
factors that can influence the project
• Requirements documentation.
• Risk register.
04
ENTERPRISE ENVIRONMENTAL FACTORS
05 ORGANIZATIONAL PROCESS ASSETS
137
Project Scope Management
01
EXPERT JUDGMENT
02 DATA ANALYSIS
Alternatives analysis: can be used to evaluate ways to meet
the requirements and the objectives identified in the charter.
03 DECISION MAKING
05 PRODUCT ANALYSIS
used to define products and services. It includes asking
questions about a product or service and forming
answers to describe the use, characteristics, and other
relevant aspects of what is going to be delivered.
138
Project Scope Management
Product Analysis
139
Project Scope Management
140
Project Scope Management
Project scope
statement
141
Statement of Work VS Scope Statement
142
Project Scope Management
Legend:
New Item
5.4 Create WBS Already Explained Item
143
5.4 Create WBS
144
Project Scope Management
145
Project Scope Management
146
Project Scope Management
01 EXPERT JUDGMENT
02
DECOMPOSITION is a technique used for dividing and subdividing the
project scope and project deliverables into smaller, more manageable parts.
147
Project Scope Management
148
Project Scope Management
149
Project Scope Management
150
Project Scope Management
Fahad decided to renovate his house. He decided to repaint walls for 3 rooms,
buy new kitchen and replacing light bulb
Since they didn’t have enough budget; they decides to save some money from
their monthly salary for 2 months.
151
Option 1 “PMP Decoration Works
Project”
1.2.2 Room 2
1.2.3 Room 3
152
Option 2 “PMP Decoration Works Project”
1.2.1
Paint Walls
1.1.2 1.1.4
1.1.1 1.1.3
Collect Many Searching for Sign Contract Design
Contractor 1.2.2
Buying Kitchen
1.1.1.1 Month1
1.2.2
Replacing Light Bulbs
1.1.1.2 Month2
153
Project Scope Management
Legend:
New Item
5.5 Validate Scope Already Explained Item
154
5.5 Validate Scope
155
Project Scope Management
01
Project management plan
• Scope management plan
• Requirements management plan
• Scope baseline
02
Project documents
• Lessons learned register
• Quality reports
• Requirements documentation
• Requirements traceability matrix
04
Work performance data
156
Project Scope Management
01 INSPECTION
• Includes activities such as measuring, examining, and validating
to determine whether work and deliverables meet requirements
and product acceptance criteria.
• Inspections are sometimes called reviews, product reviews, and
walkthroughs.
02 DECISION MAKING
Voting is used to reach a conclusion when the validation is
performed by the project team and other stakeholders.
157
Project Scope Management
03 CHANGE REQUESTS
04
PROJECT DOCUMENTS UPDATES
• Lessons learned register.
• Requirements documentation.
• Requirements traceability matrix.
158
Project Scope Management
Legend:
New Item
5.6 Control Scope Already Explained Item
159
5.6 Control Scope
160
Project Scope Management
02 PROJECT DOCUMENTS
• Lessons learned register
• Requirements documentation.
• Requirements traceability matrix.
03
WORK PERFORMANCE DATA
04
ORGANIZATIONAL PROCESS ASSETS
161
Project Scope Management
01
DATA ANALYSIS
➢ Variance analysis.
Is used to compare the baseline to the actual results and
determine if the variance is within the threshold amount or
if corrective or preventive action is appropriate.
➢ Trend analysis.
Examines project performance over time to determine if
performance is improving or deteriorating.
162
Project Scope Management
02 CHANGE REQUESTS
03
PROJECT MANAGEMENT PLAN UPDATES
• Scope management plan.
• Scope baseline.
• Schedule baseline.
• Cost baseline.
• Performance measurement baseline.
163
6. PROJECT
SCHEDULE MANAGEMENT
Presented by :
Abdulfattah Ajlan
Certified PMP Trainer
164
Project
Schedule
Management
167
6.1 Plan Schedule Management
168
6.1 Plan Schedule Management Input
01
PROJECT CHARTER
02
PROJECT MANAGEMENT PLAN
• Scope management plan.
• Development approach: define the scheduling
approach, estimating techniques, scheduling tools, and
techniques for controlling the schedule.
03
ENTERPRISE ENVIRONMENTAL FACTORS
169
6.1 Plan Schedule Management Tools & Techniques
01
Expert judgment
03 Meetings
170
6.1 Plan Schedule Management Output
01
SCHEDULE MANAGEMENT PLAN
• Establishes the criteria and the activities for developing, monitoring,
and controlling the schedule.
171
Legend:
New Item
6.2 Define Activities Already Explained Item
172
6.2 Define Activities
173
6.2 Define Activities Input
03
ORGANIZATIONAL PROCESS ASSETS
174
6.2 Define Activities Tools & Techniques
01
Expert judgment
02 Decomposition
04 Meetings
175
6.2 Define Activities Output
01 Activity list
Includes the activities required on the project, it’s includes an
activity identifier and a scope of work description for each
activity in sufficient detail to ensure that project team members
understand what work is required to be completed. In rolling
wave planning or agile techniques, the activity list will be
updated periodically as the project progresses.
02 Activity attributes
Extend the description of the activity by identifying multiple
components associated with each activity.
Examples:
- Constrains - Durations - Resources
- Relations - Name - ID - WBS related
176
6.2 Define Activities Output
Remember:
No standard templates
With PMP.
177
6.2 Define Activities Output
03
Milestone list
• A milestone is a significant point or event in a project.
• A milestone list identifies all project milestones and indicates whether the milestone is
mandatory, such as those required by contract, or optional, such as those based on
historical information.
• Milestones have zero duration because they represent a significant point or event.
04 Change requests
179
6.3 Sequence Activities
180
6.3 Sequence Activities Input
02 PROJECT DOCUMENTS
• Activity attributes
• Activity list
• Assumption log
• Milestone list
181
6.3 Sequence Activities Tools & Techniques
01
Precedence diagramming method (PDM)
▪ PDM is a technique for constructing a schedule model in which activities are
represented by nodes and are graphically linked by one or more logical relationships to
show the sequence in which the activities are to be performed.
Predecessor Successor
Note:
PDM Is Activity On Node (AON); It Mean Activity Present By Node.
or Activity On Arrow (AOA); Activity Present By Arrow.
182
6.3 Sequence Activities Tools & Techniques
01
Precedence diagramming method
▪ PDM includes four types of dependencies or
logical relationships.
• Finish-to-start (FS).
• Finish-to-finish (FF).
• Start-to-start (SS).
• Start-to-finish (SF).
183
6.3 Sequence Activities Tools & Techniques
Finish-to-start (FS)
Activity A Activity B
Activity A Activity A
Start-to-start (SS) Finish-to-finish (FF)
Activity B Activity B
Activity A Activity B
Start-to-finish (SF)
184
6.3 Sequence Activities Tools & Techniques
02
Dependency determination and integration
185
6.3 Sequence Activities Tools & Techniques
03
Leads and lags
186
6.3 Sequence Activities Output
01
PROJECT SCHEDULE NETWORK DIAGRAMS
Graphical representation of the logical relationships, also referred to as
dependencies, among the project schedule activities.
187
6.3 Sequence Activities Output
02
PROJECT DOCUMENTS UPDATES
• Activity attributes.
• Activity list.
• Assumption log
• Milestone list.
188
Exercise
Activity Description Predecessors Duration-Days
A Contracting - 10
E Tile C,D 5
F Kitchen E 7
C
Start A B E F End
D
190
Legend:
New Item
6.4 Estimate Activity Durations Already Explained Item
191
6.4 Estimate Activity Durations
192
6.4 Estimate Activity Durations Input
02 Project documents
▪ Activity attributes ▪ Project team assignments
▪ Activity list ▪ Resource breakdown
▪ Assumption log structure
▪ Lessons learned register ▪ Resource calendars
▪ Milestone list ▪ Resource requirements
▪ Risk register
01 Expert judgment
02 Analogous estimating
• A technique for estimating the duration or cost of an activity or a project using
historical data from a similar activity or project.
• Less costly
• Less time
• Less accurate
03 Parametric estimating
• An estimating technique in which the duration is calculated based on historical
data and project parameters.
• It uses a statistical relationship between historical data and other variables to
calculate an estimate for activity parameters.
• Provide higher level of accuracy compared with analogous estimating
technique
194
6.4 Estimate Activity Durations Tools & Techniques
04
Three-point estimating
The accuracy of single-point activity duration estimates may be improved by considering
estimation uncertainty and risk.
❖ Triangular distributions. used when there is insufficient historical data or when using
judgmental data
E = (O + M + P)/ 3
195
6.4 Estimate Activity Durations Tools & Techniques
05
Bottom-up estimating
estimating project duration by aggregating the estimates of the lower-level components
of the WBS
06 Data analysis (Alternatives analysis)
07 Data analysis (Reserve analysis)
Determine the amount of contingency and management reserve needed for the project.
✓ Contingency reserves
• Associated with the known-unknowns that can affect a project.
• Contingency should be clearly identified in the schedule documentation.
✓ Management reserves
• Associated with the unknown-unknowns that can affect a project.
• Management reserve is not included in the schedule baseline, but it is part of the
overall project duration requirements.
08
Decision Making (Voting)
09
Meetings
196
6.4 Estimate Activity Durations Output
01 Duration Estimates
• Number of time periods that are required to complete an activity, a phase, or a project.
• Duration estimates do not include any Lead or lags.
• May include some indication of the range of possible results.
02 Basis of Estimates
• Documentation of the basis of the estimate.
- How it was developed - Assumptions made - Known constraints
- Range of possible estimates (e.g., ±10%)
- Indication of the confidence level of the final estimate
- Project risks influencing this estimate.
03 Project documents updates
• Activity attributes
• Assumption log
• Lessons learned register
197
Legend:
New Item
6.5 Develop Schedule Already Explained Item
Project documents (Project schedule network 1 Project documents updates (Duration estimates) 1
diagrams)
Project documents updates (Lessons learned
Project documents (Project team assignments) 7 29
register)
Project documents updates (Resource
Project documents (Resource calendars) 7 3
requirements)
Project documents (Resource requirements) 8 Project documents updates (Risk register) 23
Agreements 11
199
6.5 Develop Schedule Input
200
6.5 Develop Schedule Tools & Techniques
201
Duration
Activity Name
Late Start Late Finish
Total Float
202
Schedule Network Analysis
203
Schedule Network Analysis
5 Days
?? ??
B
?? ??
Duration 5 Days 15 Days
TF =
?? ?? ?? ??
Start A D Finish
?? ?? ?? ??
10 Days
Total Float = TF =
?? ??
C
?? ??
TF =
204
Schedule Network Analysis
5 Days
6 10
B
11 15
Duration 5 Days 15 Days
TF = 5
1 5 16 30
Start A D Finish
1 5 16 30
10 Days
Total Float = 0 TF = 0
6 15
C
6 15
TF = 0
TF = LS – ES Critical Path
LF – EF
Non Critical Path
205
6.5 Develop Schedule Tools & Techniques
206
6.5 Develop Schedule Tools & Techniques
03 RESOURCE OPTIMIZATION
used to adjust the start and finish dates of activities to adjust
planned resource use to be equal to or less than resource
availability.
Resource leveling
• A technique in which start and finish dates are adjusted
based on resource constraints.
• A way to fix resource over allocation.
• Critical path may change.
Resource Smoothing
• A technique that adjusts the activities of a schedule
model to solve utilization.
• Critical path is not changed and the completion date may
not be delayed.
• Activities may be delayed within their free and total float.
207
6.5 Develop Schedule Tools & Techniques
208
6.5 Develop Schedule Tools & Techniques
04
DATA ANALYSIS
209
6.5 Develop Schedule Tools & Techniques
06
SCHEDULE COMPRESSION
Shorten the schedule duration without reducing the project scope, in order to meet
schedule constraints, imposed dates, or other schedule objectives
❖ Crashing:
A technique used to shorten the schedule duration by adding resources (increase cost)
❖ Fast tracking:
Activities or phases normally done in sequence are performed in parallel (increase Risk).
210
6.5 Develop Schedule Tools & Techniques
211
6.5 Develop Schedule Tools & Techniques
212
6.5 Develop Schedule Output
01 Schedule Baseline
The approved version of a schedule model that can be changed only through
formal change control procedures and used as a basis for comparison to
actual results. Accepted & approved by the appropriate stakeholders.
02
Project Schedule
presents linked activities, detailed or summary with planned dates, durations,
milestones, and resources.
It can be presented in tabular form using below formats:
• Bar charts (Gantt charts)
• Milestone charts
• Project schedule network diagrams (logical diagram) presented in the
activity-on-node diagram format showing activities and relationships without
a time scale,
213
6.5 Develop Schedule Output
214
6.5 Develop Schedule Output
03
Schedule Data
The collection of information for describing and controlling the schedule.
Includes (milestones, schedule activities, activity attributes, and
documentation of all identified assumptions & constraints)
04 Project calendar
Identifies working days and shifts that are available for scheduled
activities. In addition to the project team members vacations. The
project calendars may be updated as required.
05 Change requests
06 Project management plan updates
07 Project documents updates
215
Legend:
New Item
6.6 Control Schedule Already Explained Item
Project documents (Schedule data) 1 Resource optimization 2 Project documents updates (Basis of estimates) 2
216
6.6 Control Schedule
217
6.6 Control Schedule Input
01
Project management plan
• Schedule management plan
• Schedule baseline
• Scope baseline
• Performance measurement baseline
02 Project documents
• Lessons learned register
• Project calendars
• Project schedule
• Resource calendars
• Schedule data
218
6.6 Control Schedule Tools & Techniques
01
DATA ANALYSIS
02
Critical Path Method
03 Project Management Information System
04 Resource Optimization
05 Leads And Lags
06 Schedule Compression
219
6.6 Control Schedule Output
02 Schedule forecasts
are estimates or predictions of conditions and events in the project’s future based
on information and knowledge available at the time of the forecast.
03 Change requests
04
Project management plan updates
• Schedule management plan
• Performance measurement baseline
220
7. PROJECT
COST MANAGEMENT
Presented by :
Abdulfattah Ajlan
Certified PMP Trainer
Project Cost Management
222
Project Management Process Groups
Knowledge Areas
Initiating Planning Executing Monitoring and Controlling Closing
Project Integration 4.1 Develop 4.2 Develop Project Management Plan 4.3 Direct and Manage Project Work 4.5 Monitor and Control Project Work 4.7 Close
Management Project Charter 4.4 Manage Project Knowledge 4.6 Perform Integrated Change Project
Control
Project Scope 5.1 Plan Scope Management 5.5 Validate Scope
Management 5.2 Collect Requirements 5.6 Control Scope
5.3 Define Scope
5.4 Create WBS
Project Schedule 6.1 Plan Schedule 6.6 Control Schedule
Management 6.2 Define Activities
6.3 Sequence Activities
6.4 Estimate Activity Durations
6.5 Develop Schedule Management
Project Cost 7.1 Plan Cost Management 7.4 Control Costs
Management 7.2 Estimate Costs
7.3 Determine Budge
Project Quality 8.1 Plan Quality Management 8.2 Manage Quality 8.3 Control Quality
Management
Project Resource 9.1 Plan Resource Management 9.3 Acquire Resources 9.6 Control Resources
Management 9.2 Estimate Activity Resources 9.4 Develop Team
9.5 Manage Team
Project 10.1 Plan Communications 10.2 Manage Communications 10.3 Monitor Communications
Communications Management
Management
Project Risk 11.1 Plan Risk Management 11.6 Implement Risk Responses 11.7 Monitor Risks
Management 11.2 Identify Risks
11.3 Perform Qualitative Risk Analysis
11.4 Perform Quantitative Risk Analysis
11.5 Plan Risk Responses
Project Procurement 12.1 Plan Procurement Management 12.2 Conduct Procurements 12.3 Control Procurements
Management
Project Stakeholder 13.1 Identify 13.2 Plan Stakeholder Engagement 13.3 Manage Stakeholder 13.4 Monitor Stakeholder
Management Stakeholders Engagement Engagement 223
Legend:
New Item
7.1 Plan Cost Management Already Explained Item
224
7.1 Plan Cost Management
225
7.1 Plan Cost Management Input
01 PROJECT CHARTER
02
PROJECT MANAGEMENT PLAN
226
7.1 Plan Cost Management Tools & Techniques
01 Expert judgment
03 Meetings
227
7.1 Plan Cost Management Output
01 Cost management plan
Describes how the project costs will be planned, structured, and
controlled.
• Units of measure.
• Level of precision. rounded up or down.
• Level of accuracy. The acceptable range (e.g., ±10%).
• Organizational procedures links. Each control account is assigned
a unique code or account number(s) that links directly to the
performing organization’s accounting system.
• Control thresholds. the percentage deviations from the baseline
plan.
• Rules of performance measurement. EVM rules
• Reporting formats. The formats and frequency for cost reports.
228
Legend:
New Item
7.2 Estimate Costs Already Explained Item
229
7.2 Estimate Costs
230
7.2 Estimate Costs Input
02 PROJECT DOCUMENTS
04
ORGANIZATIONAL PROCESS ASSETS
231
7.2 Estimate Costs Tools & Techniques
01 Expert Judgment
02 Analogous Estimating
03 Parametric Estimating
04 Bottom-up Estimating
05 Three-point Estimating
06 PMIS
07 Decision Making
08 Data Analysis
- Alternatives Analysis
- Reserve Analysis
- Cost Of Quality. (Prevention costs - Appraisal costs - Failure costs)
232
7.2 Estimate Costs Output
01 COST ESTIMATES
Include quantitative assessments of the costs required to complete project work, as
well as contingency amounts to account for identified risks, and management reserve
to cover unplanned work.
• Direct cost : labor, materials, equipment, information technology, Etc.
• Indirect costs: can be included at the activity level or at higher levels.
02 BASIS OF ESTIMATES
should provide a clear and complete understanding of how the cost estimate was
derived.
233
7.3 Determine Budget
234
Legend:
New Item
7.3 Determine Budget Already Explained Item
Agreements 11
235
7.3 Determine Budget
236
7.3 Determine Budget Input
237
7.3 Determine Budget Tools & Techniques
01 EXPERT JUDGMENT
02
COST AGGREGATION
Aggregate the cost estimate for work package, then aggregated for the
higher component levels of the WBS (such as control accounts) and,
ultimately, for the entire project.
03 DATA ANALYSIS
04 HISTORICAL INFORMATION REVIEW
Assist in developing parametric estimates or analogous estimates.
$
05
FUNDING LIMIT RECONCILIATION
The expenditure of funds should be reconciled with any funding limits on the
commitment of funds for the project.
06 FINANCING: Financing entails acquiring funding for projects. the funding
entity may have certain requirements that are required to be met.
238
7.3 Determine Budget Tools & Techniques
Cost Aggregation
239
7.3 Determine Budget Output
01
COST BASELINE
It is the approved version of the project budget, excluding any management
reserves, Can only be changed through formal change control procedures.
240
Project budget.
241
Legend:
New Item
7.4 Control Costs Already Explained Item
242
7.4 Control Costs
243
7.4 Control Costs Input
02 Project documents
• Lessons learned register
01
EXPERT JUDGMENT
02
DATA ANALYSIS
✓ Earned value analysis (EVA). compares the performance measurement baseline to the
actual schedule and cost performance.
Planned value (PV) # Earned value (EV) # Actual cost (AC)
❖ Cost performance index (CPI) is a measure of the cost efficiency of budgeted resources,
CPI = EV / AC
CPI < 1.0 indicates a cost overrun
CPI > 1.0 indicates a cost underrun of performance to date.
CPI= Neutral indicates a cost on planned cost
>1 <1
246
7.4 Control Costs Tools & Techniques
❖ The cost variance at the end of the project will be the difference between the budget at
completion (BAC) and the actual amount spent.
247
7.4 Control Costs Tools & Techniques
❖ Forecasting. the project team may develop a forecast Estimate at Completion (EAC)
that may differ from the budget at completion (BAC) based on the project performance
1.If the CPI is expected to be the same for the remainder of the project,
EAC = BAC/CPI
• The efficiency that must be maintained in order to complete the current EAC.
TCPI = (BAC – EV) / (EAC – AC)
TCPI > 1.0 Harder to complete
TCPI = 1.0 Same to complete >1 <1
TCPI <1 .0 Easier to complete
04
PROJECT MANAGEMENT INFORMATION SYSTEM (PMIS)
249
7.4 Control Costs Output
02 Cost forecasts
03 Change requests
251
Answer
PV ; EV ; AC ;
PV = 200 + 200 + 200 = 600
EV = 200 + 200 +100 = 500
AC = 200 + 220 + 140 = 560
CV= EV-AC SV=EV-PV
CPI = EV/AC SPI = EV/PV
252
EVM Example:
253
8. PROJECT
QUALITY MANAGEMENT
Presented by :
Abdulfattah Ajlan
Certified PMP Trainer
Project Quality Management
255
Project Management Process Groups
Knowledge Areas
Initiating Planning Executing Monitoring and Controlling Closing
Project Integration 4.1 Develop 4.2 Develop Project Management Plan 4.3 Direct and Manage Project Work 4.5 Monitor and Control Project Work 4.7 Close
Management Project Charter 4.4 Manage Project Knowledge 4.6 Perform Integrated Change Project
Control
Project Scope 5.1 Plan Scope Management 5.5 Validate Scope
Management 5.2 Collect Requirements 5.6 Control Scope
5.3 Define Scope
5.4 Create WBS
Project Schedule 6.1 Plan Schedule 6.6 Control Schedule
Management 6.2 Define Activities
6.3 Sequence Activities
6.4 Estimate Activity Durations
6.5 Develop Schedule Management
Project Cost 7.1 Plan Cost Management 7.4 Control Costs
Management 7.2 Estimate Costs
7.3 Determine Budge
Project Quality 8.1 Plan Quality Management 8.2 Manage Quality 8.3 Control Quality
Management
Project Resource 9.1 Plan Resource Management 9.3 Acquire Resources 9.6 Control Resources
Management 9.2 Estimate Activity Resources 9.4 Develop Team
9.5 Manage Team
Project 10.1 Plan Communications 10.2 Manage Communications 10.3 Monitor Communications
Communications Management
Management
Project Risk 11.1 Plan Risk Management 11.6 Implement Risk Responses 11.7 Monitor Risks
Management 11.2 Identify Risks
11.3 Perform Qualitative Risk Analysis
11.4 Perform Quantitative Risk Analysis
11.5 Plan Risk Responses
Project Procurement 12.1 Plan Procurement Management 12.2 Conduct Procurements 12.3 Control Procurements
Management
Project Stakeholder 13.1 Identify 13.2 Plan Stakeholder Engagement 13.3 Manage Stakeholder 13.4 Monitor Stakeholder Engagement
Management Stakeholders Engagement 256
Quality Management Process Interrelations
257
Key concepts for Project Quality Management
Project Quality Management addresses the management of the project and it’s
deliverables. It applies to all projects, regardless of the nature of their deliverables.
Prevention vs Inspection.
• Prevention (keeping errors out of the process)
• Inspection (keeping errors out of the hands of the customer);
The cost of preventing mistakes is generally much less than the cost of
correcting mistakes.
258
Key concepts for Project Quality Management
Attribute sampling: it's a binary, it either conforms to quality or it doesn't (YES or NO).
Cost of quality (COQ): all costs incurred over the life of the product by investment in
preventing nonconformance to requirements, appraising the product or service for
conformance to requirements.
Cost of poor quality: categorized into internal (found by the project team) and external
(found by the customer).
259
Legend:
New Item
8.1 Plan Quality Management Already Explained Item
Meetings 28
260
8.1 Plan Quality Management
261
8.1 Plan Quality Management Input
01 PROJECT CHARTER
05
ORGANIZATIONAL PROCESS ASSETS 262
8.1 Plan Quality Management Tools & Techniques
33
%
01 EXPERT JUDGMENT
95
02 DATA GATHERING 95
%
03 DATA ANALYSIS %
Cost-benefit analysis
Is financial analysis tool used for estimate the strength and weakness of alternatives
to determine the best alternative.
Cost of Quality.
• Prevention costs: Related to the prevention of poor quality in the deliverables.
• Appraisal costs: Related to evaluating, measuring, auditing, and testing the
deliverables.
• Failure costs (internal/external): Related to nonconformance of the deliverables to
the needs or expectations of the stakeholders.
263
8.1 Plan Quality Management Tools & Techniques
05 DATA REPRESENTATION
Flowcharts or Process maps because they display the sequence of steps and the
branching possibilities that exist for a process that transforms one or more inputs into
one or more outputs (Decision points).
✓ SIPOC (Suppliers, Inputs, Process, Outputs, and Customers) value chain model.
✓ Process flows or process flow diagrams When flowcharts used to represent steps
in a process, and they can be used for process improvement as well as identifying
where quality defects can occur or where to incorporate quality checks.
265
8.1 Plan Quality Management Tools & Techniques
267
8.1 Plan Quality Management Tools & Techniques
Matrix diagrams. Matrix diagrams help find the strength of relationships among
different factors, causes, and objectives that exist between the rows and columns that
form the matrix.
It facilitate identifying the key quality metrics that are important for the success of the
project.
Mind mapping The mind-mapping technique may help in the rapid gathering of project
quality requirements, constraints, dependencies, and relationships.
268
8.1 Plan Quality Management Tools & Techniques
Matrix Diagrams
270
8.1 Plan Quality Management Tools & Techniques
07 MEETINGS
33
%
95
%
95
%
271
8.1 Plan Quality Management Output
01
QUALITY MANAGEMENT PLAN
• Describes how applicable policies, procedures, and guidelines will be
implemented to achieve the quality objectives.
• It describes the activities and resources necessary for the project
management team to achieve the quality objectives set for the project.
It may Includes:
• Quality standards.
• Quality objectives.
• Quality roles and responsibilities;
• Quality tools.
• Major procedures relevant for the project, such as dealing with
nonconformance, corrective actions procedures, and continuous
improvement procedures
272
8.1 Plan Quality Management Output
02 QUALITY METRICS
Specifically describes a project or product attribute and how the Control Quality
process will verify compliance to it. Like percentage of tasks completed on time,
failure rate, number of defects identified per day, or total downtime per month.
04
PROJECT DOCUMENTS UPDATES
• Lessons learned register
• Requirements traceability matrix.
• Risk register.
• Stakeholder register.
273
8.2 Manage Quality
Key Benefits:
• increases the probability of meeting the quality objectives
• Identifying ineffective processes and causes of poor quality
QA
• Sometimes called Quality Assurance,
• QA focus on the processes used in the project.
• QA is about using project processes effectively.
• It involves following and meeting standards to assure the final product
will meet stakeholders needs, expectations, and requirements.
274
8.2 Manage Quality
The project manager and project team may use the organization’s quality
assurance department.
275
Legend:
New Item
8.2 Manage Quality Already Explained Item
Audits 3
Design for X 1
Problem solving 2
277
8.2 Manage Quality Input
01
PROJECT MANAGEMENT PLAN
• Quality management plan
02
PROJECT DOCUMENTS
• Lessons learned register
• Quality control measurements: used to analyse and evaluate the quality of the
processes and deliverables of the project against the standards of the performing
organization or the requirements specified
• Quality metrics
• Risk report
03
ORGANIZATIONAL PROCESS ASSETS
278
8.2 Manage Quality Tools & Techniques
DATA GATHERING
01
Checklist
Is a structured tool used to verify that a set of required steps has been
performed or to check if a list of requirements has been satisfied.
DATA ANALYSIS
02
➢ Alternatives analysis.
➢ Document analysis.
➢ Process analysis. Identifies opportunities for process
improvements.
➢ Root cause analysis (RCA).
279
8.2 Manage Quality Tools & Techniques
04
DATA REPRESENTATION
➢ Affinity diagrams.
➢ Cause-and-effect diagrams: or fishbone diagrams or why-why diagrams or
Ishikawa diagrams. This type of diagram breaks down the causes of the problem
statement identified into discrete branches, helping to identify the main or root
cause of the problem.
➢ Flowcharts.
33
%
95
%
280
8.2 Manage Quality Tools & Techniques
Cause-and-effect diagrams
3
%
95
%
281
8.2 Manage Quality Tools & Techniques
➢ Matrix diagrams.
➢ Scatter diagrams. Graph that shows the relationship between two variables.
282
8.2 Manage Quality Tools & Techniques
Weight
Age
283
8.2 Manage Quality Tools & Techniques
05
AUDITS
An audit is a structured, independent process used to determine if project
activities comply with organizational and project policies, processes, and
procedures. Usually conducted by a team external to the project.
Plan-do-check-act and Six Sigma are two of the most common quality
improvement tools.
284
8.2 Manage Quality Tools & Techniques
07 DESIGN FOR X
• Is a set of technical guidelines that may be applied during
the design of a product for the optimization of a specific
aspect of the design.
• DFX can control or improve the product’s final characteristics.
• The X in DfX can be different aspects of product development,
such as reliability, development, cost, usability, safety, and
quality.
08
PROBLEM SOLVING
• Problems can arise from Manage or Control Quality processes and can be associated with a
processes or deliverables.
• Problem-solving method will help eliminate the problem and develop a long-lasting solution.
• Defining - Identifying cause - Generating solutions - Choosing solution - Implementing -
Verifying effectiveness.
285
8.2 Manage Quality Output
01
QUALITY REPORTS
The quality reports can be graphical, numerical, or qualitative, include all quality
management issues escalated by the team; recommendations process, project,
and product improvements; corrective actions recommendations (including rework,
defect/bugs repair).
03 CHANGE REQUESTS
286
8.2 Manage Quality Output
05
Project documents updates
• Issue log
• Lessons learned register
• Risk register
287
Legend:
8.3 Control Quality New Item
Already Explained Item
Meetings 28
288
8.3 Control Quality
289
8.3 Control Quality Input
01 DATA GATHERING
• Checklist
• Check sheets. (Tally sheets), used to organize facts in a
manner that will facilitate the effective collection of useful data
about a potential quality problem.
• Statistical sampling. involves choosing part of a population of
interest for inspection. Sample frequency and sizes should be
determined during the Plan Quality Management process
• Questionnaires and Surveys
02 DATA ANALYSIS
• Performance reviews. measure, compare, and analyze the quality metrics defined by
the Plan process against the actual results.
• Root cause analysis (RCA)
04 TESTING/PRODUCT EVALUATIONS
Testing is an organized and constructed investigation conducted to provide objective
information about the quality of the product or service in accordance with requirements.
95
%
292
8.3 Control Quality Tools & Techniques
05
DATA REPRESENTATION
• Cause-and-effect diagrams
• Histograms
• Scatter diagrams.
• Control Charts.
Used to determine whether or not a process is stable or has predictable performance.
• Upper and lower specification limits are based on the requirements.
• The control limits are determined using standard statistical calculations and
principles to ultimately establish the natural capability for a stable process.
• The PM and Stakeholder use the statistically calculated control limits to identify
33
the points at which corrective action will be taken to prevent performance that %
remains outside the control limits.
95
%
293
8.3 Control Quality Tools & Techniques
Control charts
• Can be used to monitor various types of output variables.
• Control charts may also be used to monitor cost and schedule variances, volume,
frequency of scope changes, or other management results
33
06 MEETINGS %
• To review the Approved Change Requests
95
• To review the lesson learned: to improve the quality in future. %
294
8.3 Control Quality Output
01 QUALITY CONTROL MEASUREMENTS. documented results of Control Quality activities
02 VERIFIED DELIVERABLES
The results of performing the Control Quality process are verified deliverables that become an
input to the Validate Scope process for formalized acceptance.
Final Product,
4.3 Direct Verified 5.5 Accepted 4.7 Close Service, or
8.3 Control
and Manage Deliverables Quality
Validate Project or
Project Work Deliverables Scope Deliverables Phase Result
Transition
Presented by :
Abdulfattah Ajlan
Certified PMP Trainer
296
Project Resource Management
Project management styles are shifting from a command and control structure
for managing projects and toward a more collaborative and supportive
management approach that empowers teams by delegating decision making to
the team members.
Self-organizing teams. functions using agile approaches rise the use of self-
organizing team, where the team with an absence of centralized control.
299
Legend:
New Item
9.1 Plan Resource Management Already Explained Item
Project management plan (Quality 7 Data representation (Hierarchical charts) 2 Team charter 1
management plan)
Project management plan (Scope 16
Data representation (Responsibility 1
Project documents updates 17
baseline) assignment matrix) (Assumption log)
Project documents updates (Risk
Project documents (Project schedule) 11 Data representation (Text-oriented formats) 1 23
register)
Project documents (Requirements 13 Organizational theory 1
documentation)
Project documents (Risk register) 22 Meetings 28
300
9.1 Plan Resource Management
301
9.1 Plan Resource Management Input
01
Project charter
03 Project documents
• Project schedule
• Requirements documentation
• Risk register
• Stakeholder register
01
EXPERT JUDGMENT
02
DATA REPRESENTATION
❖ Hierarchical charts. The traditional
chart structure can be used to show
positions and relationships in a
graphical, top-down format. Such as
organizational chart and WBS.
Hierarchical charts
303
9.1 Plan Resource Management Tools & Techniques
❖ Responsibility Assignment Matrix - RAM: Shows the project resources assigned to each
work package. One example of a RAM is a RACI (Responsible, Accountable, Consulted, Informed)
❖ Text-oriented formats. Team member responsibilities that require detailed descriptions can
be specified in text oriented formats.
• Usually in outline form, these documents provide information such as responsibilities,
authority, competencies, and qualifications, such as Job Description
304
9.1 Plan Resource Management Tools & Techniques
03 ORGANIZATIONAL THEORY
Provides information regarding the way in which people, teams, and organizational
units behave. Effective use of common techniques identified in organizational
theory can shorten the amount of time, cost, and effort needed to create the
Resource Management Plan.
04
MEETINGS
305
9.1 Plan Resource Management Output
01
RESOURCE MANAGEMENT PLAN
Provides guidance on how project resources should be categorized, allocated, managed, and
released.
Resource Management Plan may include :
❖ Identification of resources
❖ Acquiring resources instructions
❖ Roles and responsibilities
❖ Project organization charts.
❖ Training
❖ Team development
❖ Resource control
❖ Recognition and rewards plan
306
9.1 Plan Resource Management Output
02 TEAM CHARTER
A document that establishes the team values, agreements, and operating guidelines for
behavior of the team.
It may includes:
• Communication guidelines.
• Decision-making criteria and process.
• Conflict resolution process.
• Meeting guidelines.
• Team agreements.
307
Legend:
New Item
9.2 Estimate Activity Resources Already Explained Item
308
9.2 Estimate Activity Resources
309
9.2 Estimate Activity Resources Input
01
PROJECT MANAGEMENT PLAN
• Resource management plan
• Scope baseline
02 PROJECT DOCUMENTS
• Activity attributes
• Activity list
• Assumption log
• Cost estimates
• Resource calendars
• Risk register
03 EEF
04 OPA
310
9.2 Estimate Activity Resources Tools & Techniques
01
EXPERT JUDGMENT
02 BOTTOM-UP ESTIMATING
03 ANALOGOUS ESTIMATING
04 PARAMETRIC ESTIMATING
05 DATA ANALYSIS
• Alternatives Analysis
07 MEETINGS
311
9.2 Estimate Activity Resources Tools & Techniques
Bottom-up Estimating
312
9.2 Estimate Activity Resources Output
01 RESOURCE REQUIREMENTS
Identify the types and quantities of resources required for each work package or
activity in a work package and can be aggregated to determine the estimated
resources for each work package, each WBS branch, and the project as a whole.
02 BASIS OF ESTIMATES
The amount and type of additional details supporting the resource estimate vary by
application area.
314
9.3 Acquire Resources
ACQUIRE RESOURCES
Is the process of obtaining team members, facilities, equipment, materials,
supplies, and other resources necessary to complete project work.
315
9.3 Acquire Resources
The resources needed for the project can be internal or external to the project-performing
organization.
• Internal resources are acquired (assigned) from functional or resource managers.
• External resources are acquired through the procurement processes.
The project manager or project management team will be required to document the
impact of the unavailability of required resources in the project schedule, project budget,
project risks, project quality, training plans, and other project management plans
316
Legend:
9.3 Acquire Resources New Item
Already Explained Item
317
9.3 Acquire Resources
318
9.3 Acquire Resources Input
02
PROJECT DOCUMENTS
• Project schedule
• Resource calendars
• Resource requirements
• Stakeholder register
03
Enterprise environmental factors
319
9.3 Acquire Resources Tools & Techniques
01 DECISION MAKING
Using a Multi-criteria decision analysis tool, criteria are developed and used to rate or
score potential ,The criteria are weighted according to their relative importance and values
can be changed for different types of resources.
320
9.3 Acquire Resources Tools & Techniques
02
INTERPERSONAL AND TEAM SKILLS
❖ Negotiate:
The project management team may need to negotiate with:
• Functional managers.
• Other project management teams.
• External organizations and suppliers.
03 PRE-ASSIGNMENT
When physical or team resources for a project are determined in advance, they are
considered pre-assigned. (when resources being identified as part of a competitive
proposal, or if the project is dependent upon the expertise of particular persons).
321
9.3 Acquire Resources Tools & Techniques
04 VIRTUAL TEAMS
Virtual teams can be defined as groups of people with a shared goal who fulfill their roles
with little or no time spent meeting face to face.
The availability of communication technology has made virtual teams feasible. The virtual
team model makes it possible to:
• Form teams of people who live in widespread geographic areas.
• Add special expertise.
• Work from home offices.
• Form teams of people who work different shifts, hours, or days.
• Include people with mobility limitations or disabilities.
• Move forward with projects that would have been held or canceled due to travel
expenses.
• Save the expense of offices and all physical equipment.
322
9.3 Acquire Resources Output
03 RESOURCE CALENDARS
Identifies the working days, shifts, start and end of normal business hours, weekends,
and public holidays when each specific resource is available.
Also specify when and for how long identified team and physical resources will be
available during the project.
04 CHANGE REQUESTS
323
9.3 Acquire Resources Output
05 PROJECT MANAGEMENT PLAN UPDATES
• Resource management plan.
• Cost baseline.
324
9.4 Develop Team
DEVELOP TEAM
is the process of improving competencies, team member interaction,
and the overall team environment to enhance project performance.
325
9.4 Develop Team
The Tuckman Model
326
Legend:
9.4 Develop Team New Item
Already Explained Item
Meetings 28
327
9.4 Develop Team
328
9.4 Develop Team Input
02 PROJECT DOCUMENTS
• Lessons learned register
• Project schedule
• Project team assignments
• Resource calendars
• Team charter
329
9.4 Develop Team Tools & Techniques
01 COLOCATION: involves placing many or all of the most active project team members in the same
physical location to enhance their ability to perform as a team.
02 VIRTUAL TEAMS
03 COMMUNICATION TECHNOLOGY
• Shared portal.
• Conferencing.
• Audio conferencing.
• Email/chat..
330
9.4 Develop Team Tools & Techniques
06 TRAINING
Includes all activities designed to enhance the competencies of the project team members.
Can be formal or informal.
08 MEETINGS
331
9.4 Develop Team Output
01 TEAM PERFORMANCE ASSESSMENTS
As a result of conducting an evaluation of the project management team Project
Manager can:
identify the specific training, coaching, mentoring, assistance, or changes required to
improve the team’s performance.
02 CHANGE REQUESTS
332
9.5 MANAGE TEAM
MANAGE TEAM
Is the process of tracking team member performance, providing
feedback, resolving issues, and managing team changes to optimize
project performance.
333
Legend:
New Item
9.5 MANAGE TEAM Already Explained Item
334
9.5 MANAGE TEAM
335
9.5 MANAGE TEAM Input
02
PROJECT DOCUMENTS
• Issue log
• Lessons learned register
• Project team assignments
• Team charter
03
WORK PERFORMANCE REPORTS
04
TEAM PERFORMANCE ASSESSMENTS
01
INTERPERSONAL AND TEAM SKILLS
Conflict Management.
Sources of conflict include :
• Scarce resources.
• Scheduling priorities.
• Personal work styles.
Team ground rules, group norms, solid project management practices, and
337
9.5 MANAGE TEAM Tools & Techniques
338
9.5 MANAGE TEAM Tools & Techniques
• Decision making.
Involves the ability to negotiate and influence the organization and the project
management team.
• Emotional intelligence.
Emotional intelligence is the ability to identify, assess, and manage the personal
emotions of oneself and other people, as well as the collective emotions of groups of
people.
The team can use emotional intelligence to reduce tension and increase cooperation by
identifying, assessing, and controlling the sentiments of project team members,
anticipating their actions, acknowledging their concerns, and following up on their
issues.
339
9.5 MANAGE TEAM Tools & Techniques
Influencing.
Because project managers often have little or no direct authority over team members in
a matrix environment, their ability to influence stakeholders on a timely basis is critical
to project success.
Leadership. is the ability to lead a team and inspire them to do their jobs well.
Leadership is important through all phases of the project life cycle.
340
9.5 MANAGE TEAM Output
01 CHANGE REQUESTS
02
PROJECT MANAGEMENT PLAN UPDATES
• Resource management plan
• Schedule baseline
• Cost baseline
04
ENTERPRISE ENVIRONMENTAL FACTORS UPDATES
341
9.6 Control Resources
CONTROL RESOURCES
Is the process of ensuring that the physical resources assigned and
allocated to the project are available as planned, as well as
monitoring the planned versus actual utilization of resources and
taking corrective action as necessary.
342
Legend:
New Item
9.6 Control Resources Already Explained Item
343
9.6 Control Resources
344
9.6 Control Resources Input
02 PROJECT DOCUMENTS
• Issue log
• Lessons learned register
• Physical resource assignments
• Project schedule
• Resource breakdown structure
• Resource requirements
• Risk register
04 AGREEMENTS
345
9.6 Control Resources Tools & Techniques
01 DATA ANALYSIS
• Alternatives analysis
• Cost-benefit analysis
• Performance reviews. compare, and analyze planned resource utilization to actual
resource utilization.
• Trend analysis. examines project performance over time and can be used to
determine whether performance is improving or deteriorating.
02
PROBLEM SOLVING
The project manager should use methodical steps to deal with problem solving,
1. Identify the problem. Specify the problem.
2. Define the problem. Break it into smaller, manageable problems.
3. Investigate. Collect data.
4. Analyze. Find the root cause of the problem.
5. Solve. Choose the suitable solution from a variety of available ones.
6. Check the solution. Determine if the problem has been fixed.
346
9.6 Control Resources Tools & Techniques
03
INTERPERSONAL AND TEAM SKILLS
sometimes known as “soft skills,” include:
• Negotiation.
• Influencing.
04
PROJECT MANAGEMENT INFORMATION SYSTEM (PMIS)
347
9.6 Control Resources Output
02 CHANGE REQUESTS
348
10. PROJECT
COMMUNICATIONS
MANAGEMENT
Presented by :
Abdulfattah Ajlan
Certified PMP Trainer
349
Project Communications Management
350
Key concepts for project communication management
Project managers spend most of their time communicating with team members and other
project stakeholders, both internal (at all organizational levels) and external to the organization
351
Key concepts for project communication management
352
Key concepts for project communication management
Dimensions of communications
➢ Internal & External
➢ Formal & Informal
➢ Hierarchical focus
▪ Upward: Senior management
▪ Downward: The team
▪ Horizontal: Peers of the project manager or team
➢ Official & Unofficial
➢ Written & Oral.
353
Project Management Process Groups
Knowledge Areas
Initiating Planning Executing Monitoring and Controlling Closing
Project Integration 4.1 Develop 4.2 Develop Project Management Plan 4.3 Direct and Manage Project Work 4.5 Monitor and Control Project Work 4.7 Close
Management Project Charter 4.4 Manage Project Knowledge 4.6 Perform Integrated Change Project
Control
Project Scope 5.1 Plan Scope Management 5.5 Validate Scope
Management 5.2 Collect Requirements 5.6 Control Scope
5.3 Define Scope
5.4 Create WBS
Project Schedule 6.1 Plan Schedule 6.6 Control Schedule
Management 6.2 Define Activities
6.3 Sequence Activities
6.4 Estimate Activity Durations
6.5 Develop Schedule Management
Project Cost 7.1 Plan Cost Management 7.4 Control Costs
Management 7.2 Estimate Costs
7.3 Determine Budge
Project Quality 8.1 Plan Quality Management 8.2 Manage Quality 8.3 Control Quality
Management
Project Resource 9.1 Plan Resource Management 9.3 Acquire Resources 9.6 Control Resources
Management 9.2 Estimate Activity Resources 9.4 Develop Team
9.5 Manage Team
Project 10.1 Plan Communications 10.2 Manage Communications 10.3 Monitor Communications
Communications Management
Management
Project Risk 11.1 Plan Risk Management 11.6 Implement Risk Responses 11.7 Monitor Risks
Management 11.2 Identify Risks
11.3 Perform Qualitative Risk Analysis
11.4 Perform Quantitative Risk Analysis
11.5 Plan Risk Responses
Project Procurement 12.1 Plan Procurement Management 12.2 Conduct Procurements 12.3 Control Procurements
Management
Project Stakeholder 13.1 Identify 13.2 Plan Stakeholder Engagement 13.3 Manage Stakeholder 13.4 Monitor Stakeholder Engagement
Management Stakeholders Engagement 354
10.1 Plan communication management
355
Legend:
New Item
10.1 Plan communication management Already Explained Item
356
10.1 Plan communication management
Data Flow Diagrams
357
10.1 Plan communication management Input:
01
Project charter
03 Project documents
• Requirements documentation
• Stakeholder register
05
Organizational process assets
358
10.1 Plan communication management Tools & Techniques
01 Expert judgment
02
Communication requirements analysis
Determines the information needed by the project stakeholders.
Sources of project communication requirements:
• Stakeholder register and stakeholder engagement plan
• Number of potential communication channels
(one-to-one, one-to-many, and many-to-many).
• Organizational charts;
• Stakeholder responsibility, relationships, and interdependencies;
• Development approach;
• Disciplines, departments, and specialties involved in the project;
• Logistics of how many stakholders and their locations;
• Internal and External information
• Legal requirements.
359
10.1 Plan communication management Tools & Techniques
03
Communication technology
The methods used to transfer information among stakeholders.
360
10.1 Plan communication management Tools & Techniques
04
Communication models
Sample basic sender/receiver communication model.
361
10.1 Plan communication management Tools & Techniques
05 Communication Method
• Interactive communication: like Telephone call with feedback required.
• Push communication: Like sending an email.
• Pull communication: Like downloading a report from server or cloud folder.
07 Data representation
• Stakeholder engagement assessment matrix (Stakeholder)
08 Meetings
362
10.1 Plan communication management Tools & Techniques
363
10.1 Plan communication management Output:
02
Project management plan updates
• Stakeholder engagement plan
364
Legend:
New Item
10.2 Manage Communications Already Explained Item
Meetings 28
365
10.2 Manage Communications
Data Flow Diagrams
366
10.2 Manage Communications Input:
02 Project documents
• Change log • Lessons learned register
• Issue log • Quality report
• Risk report • Stakeholder register
03 Work performance reports
367
10.2 Manage Communications Tools & Techniques
01
Communication technology
02
Communication methods
03
Communication skills
• Communication competence: a combination of tailored communication skills.
• Feedback: is information about reactions to communications.
• Nonverbal: body language, tone of voice, and facial expressions
• Presentations: formal delivery of information and/or documentation.
04
Project management information system
05
Project reporting: is the act of collecting and distributing project information
368
10.2 Manage Communications Tools & Techniques
06
Interpersonal and team skills
• Active listening
• Conflict management
• Cultural awareness
• Meeting management
• Networking
• Political awareness
07
Meetings
369
10.2 Manage Communications Output:
01
Project communications
02
Project management plan updates
• Communications management plan
• Stakeholder engagement plan
03
Project documents updates
• Issue log
• Lessons learned register
• Project schedule
• Risk register
• Stakeholder register
04
Organizational process assets updates
370
Legend:
New Item
10.3 Monitor Communications Already Explained Item
372
10.3 Monitor Communications Input:
02 Project documents
• Issue log
• Lessons learned register
• Project communications
05
Organizational process assets
373
10.3 Monitor Communications Tools & Techniques
01 Expert judgment
02 Project management information system
03 Data representation
• Stakeholder engagement assessment matrix
04 Interpersonal and team skills
• Observation/conversation
05 Meetings
374
10.3 Monitor Communications Output:
02
Change requests
03
Project management plan updates
• Communications management plan
• Stakeholder engagement plan
375
11. PROJECT
RISK MANAGEMENT
Presented by :
Abdulfattah Ajlan
Certified PMP Trainer
What is The objectives of project risk management?!
377
Key concepts for Project Risk Management
378
Key concepts for Project Risk Management
381
Legend:
11.1 Plan Risk Management New Item
Already Explained Item
382
11.1 Plan Risk Management
383
11.1 Plan Risk Management Input
01 PROJECT CHARTER
03 PROJECT DOCUMENTS
• Stakeholder register
384
11.1 Plan Risk Management Tools & Techniques
01
EXPERT JUDGMENT
02 DATA ANALYSIS
03 Meetings
33
%
95
%
95
%
385
11.1 Plan Risk Management Output
Methodology. specific approaches, tools, and data sources that will be used to
perform risk management on the project.
Roles and responsibilities. The risk management team for each activity and their
responsibilities.
Funding. The funds needed to perform activities related to Project Risk Management
Risk categories. Grouping individual project risks using a risk breakdown structure
(RBS).
386
11.1 Plan Risk Management Output
Risk categories.
Risk Breakdown Structure
(RBS)
387
11.1 Plan Risk Management Output
Stakeholder risk appetite. The risk appetites of key stakeholders on the project are recorded
in the risk management plan, as they inform the details of the Plan Risk Management process
stakeholder risk appetite should be expressed as measurable risk thresholds
Definitions of risk probability and impacts. used to evaluate both threats and opportunities
by interpreting the impact definitions as negative for threats (delay, additional cost, and
performance shortfall) and positive for opportunities (reduced time or cost, and performance
enhancement).
388
11.1 Plan Risk Management Output
Probability and impact matrix. Opportunities and threats are represented in a common probability
and impact matrix using positive definitions of impact for opportunities and negative impact definitions
for threats. Where numeric values are used, these can be multiplied to give a probability-impact score
for each risk,
389
11.1 Plan Risk Management Output
Reporting formats. Reporting formats define how the outcomes of the Project Risk
Management process will be documented, analyzed, and communicated.
390
Legend:
11.2 Identify Risks New Item
Already Explained Item
Project management plan (Schedule management plan) 7 Data gathering (Brainstorming) 6 Risk report 1
Agreements 11
Procurement documentation 4
392
11.2 Identify Risks Input
01 PROJECT MANAGEMENT PLAN
• Requirements management plan • Risk management plan
• Schedule management plan • Scope baseline
• Cost management plan • Schedule baseline
• Quality management plan • Cost baseline
• Resource management plan
02 PROJECT DOCUMENTS
• Assumption log • Lessons learned register
• Cost estimates • Requirements documentation
• Duration estimates • Resource requirements
• Issue log • Stakeholder register
03
AGREEMENTS
04 PROCUREMENT DOCUMENTATION
01 EXPERT JUDGMENT
02 DATA GATHERING
• Brainstorming. to obtain a comprehensive list of individual project risks and sources of
overall project risk.
• Checklists. developed based on historical information and knowledge that has been
accumulated from similar projects and from other sources of information.
• Interviews. interviewing experienced participants, stakeholders, and subject matter
experts to identify risks
03 DATA ANALYSIS
• Root cause analysis. to discover the underlying causes that lead to a problem, and
develop preventive action.
• Assumption and constraint analysis. To explores the validity of assumptions and
constraints to determine which pose a risk to the project
33%
• SWOT analysis. examines the project from each of the strengths, weaknesses,
opportunities, and threats (SWOT) perspectives.
• Document analysis.
95%
95
394
395
395
11.2 Identify Risks Tools & Techniques
05
PROMPT LISTS
A prompt list is a predetermined list of risk categories that might give rise to individual
project risks and that could also act as sources of overall project risk.
common strategic frameworks for identifying sources of overall project risk
• PESTLE (political, economic, social, technological, legal, environmental),
• TECOP (technical, environmental, commercial, operational, political), or
• VUCA (volatility, uncertainty, complexity, ambiguity).
06 MEETINGS
33
(often called a risk workshop).
%
95
%
396
11.2 Identify Risks Output
01 RISK REGISTER
The risk register captures details of identified individual project risks. include :
• List of identified risks.
• Potential risk owners.
• List of potential risk responses.
It is continuously reviewed throughout the project.
02 RISK REPORT:
Presents information on sources of overall project risk, together with summary information
on identified individual project risks.
03
PROJECT DOCUMENTS UPDATES
• Assumption log.
• Issue log..
• Lessons learned register
397
11.2 Identify Risks Output
Risk Register
398
11.3 Perform Qualitative Risk Analysis Legend:
New Item
Already Explained Item
Risk categorization 1
Meetings 28
399
11.3 Perform Qualitative Risk Analysis
400
11.3 Perform Qualitative Risk Analysis Input
02 PROJECT DOCUMENTS
• Assumption log
• Risk register
• Stakeholder register
401
11.3 Perform Qualitative Risk Analysis Tools & Techniques
01 EXPERT JUDGMENT
02
DATA GATHERING
03 DATA ANALYSIS
Risk data quality assessment: evaluates the degree to which the data about individual
project risks is accurate and reliable as a basis for qualitative risk analysis.
Risk probability and impact assessment: considers the likelihood that a specific risk
will occur and considers the potential effect on project objectives ( schedule, cost, quality,
or performance). Impacts will be negative for threats and positive for opportunities.
33
%
95
%
402
11.3 Perform Qualitative Risk Analysis Tools & Techniques
Assessment of other risk parameters.
Consider other characteristics of risk, like:
• Urgency. The period of time within which a response to the risk is to be implemented in order to be
effective. (A short period indicates high urgency.) (Ex. Storms lead to Power Outage)
• Proximity. The period of time before the risk might have an impact on one or more project
objectives. (A short period indicates high proximity.) (Ex. Delay order).
• Dormancy. The period of time that may elapse after a risk has occurred before its impact is
discovered. (A short period indicates low dormancy.) (Ex. Quit of quality employee).
• Manageability. The ease with which the risk owner can manage the occurrence or impact of risk.
• Detectability. The ease with which the results of the risk occurring, or being about to occur, can be
detected and recognized.
• Controllability. The degree to which the risk owner is able to control the risk’s outcome.
• Connectivity. The extent to which the risk is related to other individual project risks.
• Strategic impact. The potential for the risk to have a positive or negative effect on the
organization’s strategic goals
• Propinquity. The degree to which a risk is perceived to matter by one or more stakeholders. Where
a risk is perceived as very significant, propinquity is high.
403
11.3 Perform Qualitative Risk Analysis Tools & Techniques
04 INTERPERSONAL AND TEAM SKILLS (Facilitation)
05 RISK CATEGORIZATION
Risks to the project can be categorized by sources of risk (RBS); or other useful categories
(e.g., project phase, project budget, and roles and responsibilities)
06 DATA REPRESENTATION
✓ Probability and impact matrix.
Is a grid for mapping the probability of each risk occurrence and its impact on project
objectives if that risk occurs
✓ Hierarchical Charts
Where risks have been categorized using more than two parameters.
Ex: Bubble chart which displays three dimensions of data, where each risk is plotted
(bubble), and the three parameters are represented by the x-axis value, the y-axis value,
and the bubble size. 33
%
07 MEETINGS
95
%
404
11.3 Perform Qualitative Risk Analysis Tools & Techniques
95
%
405
11.3 Perform Qualitative Risk Analysis Tools & Techniques
33
%
95
%
406
11.3 Perform Qualitative Risk Analysis Output
407
Legend:
11.4 Perform Quantitative Risk Analysis New Item
Already Explained Item
408
11.4 Perform Quantitative Risk Analysis
409
11.4 Perform Quantitative Risk Analysis Input
01 PROJECT MANAGEMENT PLAN
• Risk management plan • Schedule baseline
• Scope baseline • Cost baseline
02
PROJECT DOCUMENTS
• Assumption log • Milestone list
• Basis of estimates • Resource requirements
• Cost estimates • Risk register
• Cost forecasts • Risk report
• Duration estimates • Schedule forecasts
04
ORGANIZATIONAL PROCESS ASSETS
410
11.4 Perform Quantitative Risk Analysis Tools & Techniques
01 EXPERT JUDGMENT
02 DATA GATHERING
03 INTERPERSONAL AND TEAM SKILLS
04 REPRESENTATIONS OF UNCERTAINTY
Representations of an individual project’s risks, such as time, cost, or other resources.
This may take several forms. triangular, normal, lognormal, beta, uniform, or discrete distributions.
Care should be taken when selecting an appropriate probability distribution to reflect the range of
possible values for the planned activity.
05 DATA ANALYSIS
Simulation. Simulates the combined effects of individual project risks and other sources of
uncertainty to evaluate their potential impact on achieving project objectives performed using a
Monte Carlo analysis. (EX. Impact Covid-19 on schedule and cost of project), studying the 95
probability of complete the project within specific time and cost) %
411
11.4 Perform Quantitative Risk Analysis Tools & Techniques
Influence diagrams. represents a project or situation within the project as a set of entities,
outcomes, and influences, together with the relationships and effects between them.
412
11.4 Perform Quantitative Risk Analysis Tools & Techniques
TORNADO DIAGRAM
33
%
95
%
413
11.4 Perform Quantitative Risk Analysis Tools & Techniques
Prototype
A company is trying
to determine if
Expected Monetary Value : P * I Pass: No Impact
prototyping is worth
while on the project
415
Legend:
11.5 Plan Risk Responses New Item
Already Explained Item
Project documents (Risk report) 10 Data analysis (Cost-benefit analysis) 5 Project management plan updates (Cost baseline) 12
417
11.5 Plan Risk Responses Input
01 PROJECT MANAGEMENT PLAN
• Resource management plan
• Risk management plan
• Cost baseline
02 PROJECT DOCUMENTS
• Lessons learned register • Risk register
• Project schedule • Risk report
• Project team assignments • Stakeholder register
• Resource calendars
04
ORGANIZATIONAL PROCESS ASSETS
418
11.5 Plan Risk Responses Tools & Techniques
01 EXPERT JUDGMENT
02
DATA GATHERING
3. Transfer. shifting ownership of a threat to a third party to manage the risk. Like insurance
4. Mitigate. action is taken to reduce the probability of occurrence and/or impact of a threat. Like
dealing with professional supplier.
5. Accept. acknowledges the existence of a threat, but no proactive action is taken, appropriate for low-
priority threats. Like using the contingency reserved.
419
11.5 Plan Risk Responses Tools & Techniques
05 STRATEGIES FOR OPPORTUNITIES
1. Escalate.
2. Exploit. The exploit strategy may be selected for high-priority opportunities where the organization
wants to ensure that the opportunity is realized. by ensuring that it definitely happens, increasing the
probability of occurrence to 100%. Like using new technology to reduce cost and duration.
3. Share. Sharing involves transferring ownership of an opportunity to a third party so that it shares
some of the benefit if the opportunity occurs. Like joint-venture between companies.
4. Enhance. used to increase the probability and/or impact of an opportunity. Like add more resources
to activity to finish it early.
5. Accept. Accepting an opportunity acknowledges its existence but no proactive action is taken. This
strategy may be appropriate for low-priority opportunities.
420
11.5 Plan Risk Responses Tools & Techniques
08 DATA ANALYSIS
• Alternatives analysis
• Cost-benefit analysis.
09 DECISION MAKING
421
11.5 Plan Risk Responses Output
01 CHANGE REQUESTS
02
PROJECT MANAGEMENT PLAN UPDATES
• Schedule management plan • Procurement management plan
• Cost management plan • Scope baseline
• Quality management plan • Schedule baseline
• Resource management plan • Cost baseline
422
Legend:
11.6 Implement Risk Responses New Item
Already Explained Item
423
11.6 Implement Risk Responses
424
11.6 Implement Risk Responses Input
01 PROJECT MANAGEMENT PLAN
• Risk management plan
02
PROJECT DOCUMENTS
• Lessons learned register
• Risk register
• Risk report
425
11.6 Implement Risk Responses Tools & Techniques
01 EXPERT JUDGMENT
33
%
95
%
95
%
426
11.6 Implement Risk Responses Output
01
CHANGE REQUESTS
427
Legend:
11.7 Monitor Risks New Item
Already Explained Item
428
11.7 Monitor Risks
429
11.7 Monitor Risks Input
02
PROJECT DOCUMENTS
• Issue log
• Lessons learned register
• Risk register
• Risk report
430
11.7 Monitor Risks Tools & Techniques
01
DATA ANALYSIS
02 AUDITS
Effectiveness of the risk management process & reasons of risk occurrence 33
%
03 MEETINGS 95
%
95
%
431
11.7 Monitor Risks Output
04
ORGANIZATIONAL PROCESS ASSETS UPDATES
432
12. PROJECT
PROCUREMENT
MANAGEMENT
Presented by :
Abdulfattah Ajlan
Certified PMP Trainer
433
PROJECT
PROCUREMENT
MANAGEMENT
434
Project Management Process Groups
Knowledge Areas
Initiating Planning Executing Monitoring and Controlling Closing
Project Integration 4.1 Develop 4.2 Develop Project Management Plan 4.3 Direct and Manage Project Work 4.5 Monitor and Control Project Work 4.7 Close
Management Project Charter 4.4 Manage Project Knowledge 4.6 Perform Integrated Change Project
Control
Project Scope 5.1 Plan Scope Management 5.5 Validate Scope
Management 5.2 Collect Requirements 5.6 Control Scope
5.3 Define Scope
5.4 Create WBS
Project Schedule 6.1 Plan Schedule 6.6 Control Schedule
Management 6.2 Define Activities
6.3 Sequence Activities
6.4 Estimate Activity Durations
6.5 Develop Schedule Management
Project Cost 7.1 Plan Cost Management 7.4 Control Costs
Management 7.2 Estimate Costs
7.3 Determine Budge
Project Quality 8.1 Plan Quality Management 8.2 Manage Quality 8.3 Control Quality
Management
Project Resource 9.1 Plan Resource Management 9.3 Acquire Resources 9.6 Control Resources
Management 9.2 Estimate Activity Resources 9.4 Develop Team
9.5 Manage Team
Project 10.1 Plan Communications 10.2 Manage Communications 10.3 Monitor Communications
Communications Management
Management
Project Risk 11.1 Plan Risk Management 11.6 Implement Risk Responses 11.7 Monitor Risks
Management 11.2 Identify Risks
11.3 Perform Qualitative Risk Analysis
11.4 Perform Quantitative Risk Analysis
11.5 Plan Risk Responses
Project Procurement 12.1 Plan Procurement Management 12.2 Conduct Procurements 12.3 Control Procurements
Management
Project Stakeholder 13.1 Identify 13.2 Plan Stakeholder Engagement 13.3 Manage Stakeholder 13.4 Monitor Stakeholder Engagement
Management Stakeholders Engagement 435
Trends and emerging practices in Procurement Management
Trial engagements.
▪ Some projects will engage several candidate sellers for initial deliverables and work products on a
paid basis before making the full commitment to a larger portion of the project scope.
▪ This accelerates momentum by allowing the buyer to evaluate potential partners, while
simultaneously making progress on project work.
436
Contracts Type
Cost Reimbursable Contracts (CR) (scope is expected to change significantly during the execution)
Cost Plus Fixed Fee (CPFF)
Cost Plus Incentive Fee Contracts (CPIF)
Cost Plus Award Fee Contracts (CAF)
Time and Material Contracts (T&M): (used for external staff hiring, acquisition of experts)
Marge of above two contracts types
437
Buyer Seller
Business documents (Business case) 6 Data gathering (Market research) 1 Procurement strategy 1
Project management plan (Quality management plan) 7 Meetings 28 Source selection criteria 1
440
12.1 Plan Procurement Management
441
12.1 Plan Procurement Management Input
01 PROJECT CHARTER
02
BUSINESS DOCUMENTS
• Business case
• Benefits management plan
04
PROJECT MANAGEMENT PLAN.
• Milestone list. • Resource requirements.
• Project team assignments. • Risk register.
• Requirements documentation. • Stakeholder register.
• Requirements traceability matrix.
01 EXPERT JUDGMENT
02 DATA GATHERING
• Market research:
includes examination of industry and specific seller capabilities.
03 DATA ANALYSIS
• Make-or-buy analysis
05 Meeting
443
12.1 Plan Procurement Management Output
03 BID DOCUMENTS
Biding document can include:
o Request for information (RFI): is used when more information on the goods and services to be
acquired, needed from the sellers.
o Request for quotation (RFQ) : used when more information is needed on how vendors would
satisfy the requirements and/or how much it will cost.
o Request for proposal (RFP). is used when there is a problem in the project and the solution is
not easy to determine.
444
12.1 Plan Procurement Management Output
04 PROCUREMENT STATEMENT OF WORK (SOW)
• The SOW describes the procurement item in sufficient detail (specifications, quantity desired,
quality levels, performance data, period of performance, work location, and other requirements).
445
12.1 Plan Procurement Management Output
06 MAKE-OR-BUY DECISIONS
08
CHANGE REQUESTS
09
PROJECT DOCUMENTS UPDATES.
• Lessons learned register. • Requirements traceability matrix.
• Milestone list. • Risk register.
• Requirements documentation. • Stakeholder register.
446
Legend:
12.2 Conduct Procurement Management New Item
Already Explained Item
PMP (Risk management plan) 12 Data analysis (Proposal evaluation) 1 PMP updates (Requirements management plan) 2
Project documents (Lessons learned register) 27 PMP updates (Procurement management plan) 3
447
12.2 Conduct Procurement Management
Data Flow Diagrams
448
12.2 Conduct Procurement Management Input
02
PROJECT DOCUMENTS
• Lessons learned register.
• Project schedule.
• Requirements documentation.
• Risk register.
• Stakeholder register.
449
12.2 Conduct Procurement Management Input
03
PROCUREMENT DOCUMENTATION
• Bid documents.
• Procurement statement of work.
• Independent cost estimates.
• Source selection criteria.
04 SELLER PROPOSALS
• If the seller is going to submit a price proposal, good practice is to require that it be
separate from the technical proposal.
• The evaluation body reviews each submitted proposal according to the source
selection criteria and selects the seller that can best satisfy the buying organization’s
requirements.
05 EEF
06 OPA
450
12.2 Conduct Procurement Management Tools & Techniques
01 EXPERT JUDGMENT
02 ADVERTISING
• Advertising is communicating with potential users of a product, service, or result.
• Existing lists of potential sellers often can be expanded by placing advertisements in
general circulation publications such as selected newspapers or in specialty trade
publications.
• Most government jurisdictions require public advertising or online posting of pending
government contracts.
03 BIDDER CONFERENCES
• (also called contractor conferences, vendor conferences, and pre-bid conferences)
are meetings between the buyer and prospective sellers prior to proposal submittal.
• They are used to ensure that all prospective bidders have a clear and common
understanding of the procurement and no bidders receive preferential treatment.
451
12.2 Conduct Procurement Management Tools & Techniques
04
DATA ANALYSIS
• Proposal evaluation. to ensure they are complete and respond in full to the bid
documents, procurement statement of work, source selection criteria, and any other
documents that went out in the bid package.
452
12.2 Conduct Procurement Management Outputs
01 SELECTED SELLERS
• The selected sellers are those who have been judged to be in a competitive range
based on the outcome of the proposal or bid evaluation.
• Final approval of complex, high-value, high-risk procurements will generally require
organizational senior management approval prior to award.
02 AGREEMENTS
Agreements are used to define initial intentions for a project. Agreements may take the
form of contracts, memorandums of understanding (MOUs), service level agreements
(SLA), letters of agreement, letters of intent, verbal agreements, email, or other written
agreements.
03 CHANGE REQUESTS.
453
12.2 Conduct Procurement Management Outputs
A Contract
A contract is a mutually binding agreement that
• obligates the seller to provide the specified products,
services, or results;
• obligates the buyer to compensate the seller;
And represents a legal relationship that is subject to
remedy in the courts.
454
12.2 Conduct Procurement Management Outputs
06
ORGANIZATIONAL PROCESS ASSETS UPDATES
455
Legend:
12.3 Control Procurement Management New Item
Already Explained Item
PMP (Procurement management plan) 3 Data analysis (Performance reviews) 4 Procurement documentation updates 1
PMP (Change management plan) 4 Data analysis (Earned value analysis) 4 Change requests 24
PMP (Schedule baseline) 5 Data analysis (Trend analysis) 7 PMP updates (Risk management plan) 4
Procurement documentation 4
457
12.3 Control Procurement Management Input
02 PROJECT DOCUMENTS
• Assumption log.
• Lessons learned register.
• Milestone list.
• Quality reports.
• Requirements documentation.
• Requirements traceability matrix.
• Risk register.
• Stakeholder register.
03 AGREEMENTS
458
12.3 Control Procurement Management Input
04 PROCUREMENT DOCUMENTATION
459
12.3 Control Procurement Management Tools & Techniques
01
EXPERT JUDGMENT
02 CLAIMS ADMINISTRATION
• The contested changes are called claims. When they cannot be resolved, they become
disputes and finally appeals.
• Claims are documented, processed, monitored, and managed throughout the contract life
cycle, usually in accordance with the terms of the contract.
• If the parties themselves do not resolve a claim, it may have to be handled in accordance with
alternative dispute resolution (ADR) typically following procedures established in the contract.
• Settlement of all claims and disputes through negotiation is the preferred method.
03 DATA ANALYSIS
• Performance Reviews. Measure, compare, and analyze quality, resource, schedule,
and cost performance against the agreement.
• Earned Value Analysis (EVA).
• Trend Analysis. Trend analysis can develop a forecast estimate at completion (EAC)
460
12.3 Control Procurement Management Tools & Techniques
04 INSPECTION
a structured review of the work being performed
by the contractor.
05 AUDITS
• A structured review of the procurement process.
• Rights and obligations related to audits should be described in
the procurement contract.
• Resulting audit observations should be brought to the attention
of the buyer’s project manager and the seller’s project manager
for adjustments to the project, when necessary.
01 CLOSED PROCUREMENTS
• The buyer, usually through its authorized procurement administrator, provides the seller
with formal written notice that the contract has been completed.
• Requirements for formal procurement closure are usually defined in the terms and
conditions of the contract and are included in the procurement management plan.
• Typically, all deliverables should have been provided on time and meet technical and
quality requirements, there should be no outstanding claims or invoices, and all final
payments should have been made.
• The project management team should have approved all deliverables prior to closure.
462
12.3 Control Procurement Management Output
04
PROJECT MANAGEMENT PLAN UPDATES
• Risk management plan.
• Procurement management plan.
• Cost baseline.
• Schedule baseline.
463
12.3 Control Procurement Management Output
05
PROJECT DOCUMENTS UPDATES
• Lessons learned register.
• Resource requirements.
• Requirements traceability matrix.
• Risk register.
• Stakeholder register.
464
13. PROJECT
STAKEHOLDER MANAGEMENT
Presented by :
Abdulfattah Ajlan
Certified PMP Trainer
465
PROJECT
STAKEHOLDER
MANAGEMENT
Project Stakeholder Management includes the processes required to identify the people,
groups, or organizations that could impact or be impacted by the project, to analyze
stakeholder expectations and their impact on the project, and to develop appropriate
management strategies for effectively engaging stakeholders in project decisions and execution.
466
Project Management Process Groups
Knowledge Areas
Initiating Planning Executing Monitoring and Controlling Closing
Project Integration 4.1 Develop 4.2 Develop Project Management Plan 4.3 Direct and Manage Project Work 4.5 Monitor and Control Project Work 4.7 Close
Management Project Charter 4.4 Manage Project Knowledge 4.6 Perform Integrated Change Project
Control
Project Scope 5.1 Plan Scope Management 5.5 Validate Scope
Management 5.2 Collect Requirements 5.6 Control Scope
5.3 Define Scope
5.4 Create WBS
Project Schedule 6.1 Plan Schedule 6.6 Control Schedule
Management 6.2 Define Activities
6.3 Sequence Activities
6.4 Estimate Activity Durations
6.5 Develop Schedule Management
Project Cost 7.1 Plan Cost Management 7.4 Control Costs
Management 7.2 Estimate Costs
7.3 Determine Budge
Project Quality 8.1 Plan Quality Management 8.2 Manage Quality 8.3 Control Quality
Management
Project Resource 9.1 Plan Resource Management 9.3 Acquire Resources 9.6 Control Resources
Management 9.2 Estimate Activity Resources 9.4 Develop Team
9.5 Manage Team
Project 10.1 Plan Communications 10.2 Manage Communications 10.3 Monitor Communications
Communications Management
Management
Project Risk 11.1 Plan Risk Management 11.6 Implement Risk Responses 11.7 Monitor Risks
Management 11.2 Identify Risks
11.3 Perform Qualitative Risk Analysis
11.4 Perform Quantitative Risk Analysis
11.5 Plan Risk Responses
Project Procurement 12.1 Plan Procurement Management 12.2 Conduct Procurements 12.3 Control Procurements
Management
Project Stakeholder 13.1 Identify 13.2 Plan Stakeholder Engagement 13.3 Manage Stakeholder 13.4 Monitor Stakeholder Engagement
Management Stakeholders Engagement 467
Legend:
New Item
13.1 Identify Stakeholders Already Explained Item
469
13.1 Identify Stakeholders Input
01 PROJECT CHARTER
02 BUSINESS DOCUMENTS
• Business case.
• Benefits management plan.
04 PROJECT DOCUMENTS
• Change log
• Issue log
• Requirements documentation
05 AGREEMENTS
06 ENTERPRISE ENVIRONMENTAL FACTORS
07 ORGANIZATIONAL PROCESS ASSETS 470
13.1 Identify Stakeholders Tools & Techniques
01
Expert judgment.
02 DATA GATHERING.
471
13.1 Identify Stakeholders Tools & Techniques
03 DATA ANALYSIS
✓ Stakeholder analysis.
It results in a list of stakeholders and relevant information such as their positions in the
organization, roles on the project, “stakes,” expectations, attitudes (their levels of support for
the project), and their interest in information about the project.
• Interest.
• Rights
• Ownership.
• Knowledge.
• Contribution.
✓ Document analysis. Assessing the available project documentation and lessons learned
from previous projects to identify stakeholders and other supporting information.
472
13.1 Identify Stakeholders Tools & Techniques
04 DATA REPRESENTATION
❖ Stakeholder mapping/ representation.
A method of categorizing stakeholders using various methods.to assists the team in building
relationships with the identified project stakeholders. Include:
1. Power/interest grid, power/influence grid, or impact/influence grid.
▪ Group stakeholders according to their:
✓ level of authority (power)
✓ level of concern about the project’s outcomes (interest)
✓ ability to influence the outcomes of the project (influence)
✓ ability to cause changes to the project’s planning or execution (impact).
2. Stakeholder cube.
▪ This is a refinement of the grid models previously mentioned using 3 variables .
3. Salience model.
▪ Describes classes of stakeholders based on assessments of their power ,influence,
urgency
▪ The salience model is useful for large complex communities of stakeholders or where
there are complex networks of relationships within the community.
473
13.1 Identify Stakeholders Tools & Techniques
474
13.1 Identify Stakeholders Tools & Techniques
Salience model
475
13.1 Identify Stakeholders Tools & Techniques
4. Directions of influence.
Classifies stakeholders according to their influence on the work of the project or the project team
itself. As the following :
▪ Upward: senior management of the performing organization or customer organization,
sponsor, and steering committee.
▪ Downward: the team or specialists contributing knowledge or skills in a temporary capacity,
▪ Outward: stakeholder groups and their representatives outside the project team, such as
suppliers, government departments, the public, end-users, and regulators.
▪ Sideward: the peers of the project manager, such as other project managers or middle
managers who are in competition for scarce project resources or who collaborate with the
project manager in sharing resources or information.
5. Prioritization.
Necessary for projects with a large number of stakeholders, where the membership of the
stakeholder community is changing frequently, or when the relationships between stakeholders
and the project team or within the stakeholder community are complex.
05 MEETINGS
476
13.1 Identify Stakeholders Output
01 STAKEHOLDER REGISTER
This document contains information about identified stakeholders
• Identification information. Name, organizational position, location and contact
details, and role on the project.
• Assessment information. Major requirements, expectations, potential for
influencing project outcomes, and the phase of the project life cycle where the
stakeholder has the most influence or impact.
• Stakeholder classification. Internal/external, impact/influence/power/interest,
upward/downward/outward/ sideward, or any other classification model chosen by
the project manager.
02 CHANGE REQUESTS
477
13.1 Identify Stakeholders Output
03 PROJECT MANAGEMENT PLAN UPDATES
✓ Requirements management plan.
✓ Communications management plan.
✓ Risk management plan.
✓ Stakeholder engagement plan.
478
Legend:
New Item
13.2 Plan Stakeholder Engagement Already Explained Item
Agreements 11
479
13.2 Plan Stakeholder Engagement
480
13.2 Plan Stakeholder Engagement Input
01 PROJECT CHARTER
02 PROJECT MANAGEMENT PLAN
• Resource management plan
• Communications management plan
• Risk management plan
03 PROJECT DOCUMENTS
• Assumption log
• Change log
• Issue log
• Project schedule
• Risk register
• Stakeholder register
04 AGREEMENTS
05 ENTERPRISE ENVIRONMENTAL FACTORS
06 ORGANIZATIONAL PROCESS ASSETS
481
13.2 Plan Stakeholder Engagement Tools & Techniques
01 Expert judgment
02 DATA GATHERING
Benchmarking. The results of stakeholder analysis are compared with information
from other organizations or other projects that are considered to be world class.
03
DATA ANALYSIS
✓ Assumption and constraint analysis : Analysis of current assumptions and
constraints may be conducted in order to tailor appropriate engagement strategies.
✓ Root cause analysis : identifies underlying reasons for the level of support of
project stakeholders in order to select the appropriate strategy to improve their level
of engagement.
04 DECISION MAKING 33
✓ Prioritization/Ranking : Stakeholder requirements need to be prioritized and %
ranked, as do the stakeholders themselves. Stakeholders with the most interest
and the highest influence are often prioritized at the top of the list. 95
% 95
%
482
G20 2019 Family Photo
483
484
485
13.2 Plan Stakeholder Engagement Tools & Techniques
05 DATA REPRESENTATION
▪ Mind mapping
486
13.2 Plan Stakeholder Engagement Tools & Techniques
06 MEETINGS
487
13.2 PLAN STAKEHOLDER ENGAGEMENT Output
01 STAKEHOLDER ENGAGEMENT PLAN
✓ A component of the project management plan that identifies the
strategies and actions required to promote productive involvement
of stakeholders in decision making and execution.
488
Legend:
New Item
13.3 MANAGE STAKEHOLDER ENGAGEMENT Already Explained Item
489
13.3 MANAGE STAKEHOLDER ENGAGEMENT
490
13.3 MANAGE STAKEHOLDER ENGAGEMENT Input
01 PROJECT MANAGEMENT PLAN
✓ Communications management plan.
✓ Risk management plan.
✓ Stakeholder engagement plan.
✓ Change management plan.
02 PROJECT DOCUMENTS
✓ Change log.
✓ Issue log.
✓ Lessons learned register.
✓ Stakeholder register.
01
EXPERT JUDGMENT
02 COMMUNICATION SKILLS
✓ The methods of communication identified for each stakeholder in the
communications management plan are applied during stakeholder engagement
management.
✓ The project management team uses feedback to assist in understanding stakeholder
reaction to the various project management activities and key decisions.
✓ Feedback may be collected in the following ways:
▪ Conversations; both formal and informal.
▪ Issue identification and discussion.
▪ Meetings.
▪ Progress reporting.
▪ Surveys.
492
13.3 MANAGE STAKEHOLDER ENGAGEMENT Tools & Techniques
03
INTERPERSONAL AND TEAM SKILLS
❖ Conflict management. The project manager should ensure that conflicts are resolved in a
timely manner.
❖ Cultural awareness. is used to help the project manager and team to communicate
effectively by considering cultural differences and the requirements of stakeholders.
❖ Negotiation. is used to achieve support or agreement that supports the work of the project or
its outcomes and to resolve conflicts within the team or with other stakeholders.
❖ Observation/conversation. is used to stay in touch with he work and attitudes of project
team members and other stakeholders.
❖ Political awareness. is achieved through understanding the power relationships 33
%
within and around the project.
95
%
493
13.3 MANAGE STAKEHOLDER ENGAGEMENT Tools & Techniques
04
GROUND RULES
Defined in the team charter as output of Plan Resource Management
set the expected acceptable behavior for project team members, as
well as other stakeholders, with regard to stakeholder engagement.
05 MEETINGS
494
13.3 MANAGE STAKEHOLDER ENGAGEMENT Output
01 CHANGE REQUESTS
✓ Change log.
✓ Issue log.
✓ Lessons learned register
✓ Stakeholder register.
495
Legend:
13.4 MONITOR STAKEHOLDER ENGAGEMENT New Item
Already Explained Item
PMP (Communications management plan) 7 Data analysis (Root cause analysis) 6 Change requests 24
Meetings 28
496
13.4 MONITOR STAKEHOLDER ENGAGEMENT
497
13.4 MONITOR STAKEHOLDER ENGAGEMENT Input
02 Project documents
✓ Issue log.
✓ Lessons learned register.
✓ Project communications.
✓ Risk register.
✓ Stakeholder register.
03
WORK PERFORMANCE DATA
05
ORGANIZATIONAL PROCESS ASSETS.
498
13.4 MONITOR STAKEHOLDER ENGAGEMENT Tools & Techniques
01 DATA ANALYSIS
• Alternatives analysis.
• Root cause analysis.
• Stakeholder analysis.
02 DECISION MAKING
• Multicriteria decision analysis.
• Voting.
03
DATA REPRESENTATION
• Stakeholder Engagement Assessment Matrix.
499
13.4 MONITOR STAKEHOLDER ENGAGEMENT Tools & Techniques
04
COMMUNICATION SKILLS
• Feedback. is used to ensure that the information to stakeholders is received
and understood.
• Presentations. provide clear information to stakeholders.
05 INTERPERSONAL AND TEAM SKILLS
• Active listening. is used to reduce misunderstandings and other miscommunication.
• Cultural awareness. Cultural awareness and cultural sensitivity help the project manager
to plan communications based on the cultural differences and requirements of stakeholders
and team members.
• Leadership. Successful stakeholder engagement requires strong leadership skills to
communicate the vision and inspire stakeholders to support the work and outcomes of the
project.
• Networking. ensures access to information about levels of engagement of stakeholders.
• Political awareness. is used to understand the strategies of the organization, understand
who wields power and influence in this arena, and to develop an ability to communicate with
these stakeholders.
06
MEETINGS
500
13.4 MONITOR STAKEHOLDER ENGAGEMENT Output
01
WORK PERFORMANCE INFORMATION
02 CHANGE REQUESTS
501
Project Management Process Groups
Knowledge Areas
Initiating Planning Executing Monitoring and Controlling Closing
Project Integration 4.1 Develop 4.2 Develop Project Management Plan 4.3 Direct and Manage Project Work 4.5 Monitor and Control Project Work 4.7 Close
Management Project Charter 4.4 Manage Project Knowledge 4.6 Perform Integrated Change Control Project
5.1 Plan Scope Management
5.5 Validate Scope
Project Scope 5.2 Collect Requirements
5.6 Control Scope
Management 5.3 Define Scope
5.4 Create WBS
6.1 Plan Schedule
6.2 Define Activities
Project Schedule 6.6 Control Schedule
6.3 Sequence Activities
Management
6.4 Estimate Activity Durations
6.5 Develop Schedule Management
7.1 Plan Cost Management
Project Cost
7.2 Estimate Costs 7.4 Control Costs
Management
7.3 Determine Budge
Project Quality
8.1 Plan Quality Management 8.2 Manage Quality 8.3 Control Quality
Management
Project Resource 9.1 Plan Resource Management 9.3 Acquire Resources
9.6 Control Resources
Management 9.2 Estimate Activity Resources 9.4 Develop Team
9.5 Manage Team
Project 10.1 Plan Communications
Communications Management 10.2 Manage Communications 10.3 Monitor Communications
Management
11.1 Plan Risk Management
11.2 Identify Risks
Project Risk 11.6 Implement Risk Responses
11.3 Perform Qualitative Risk Analysis 11.7 Monitor Risks
Management
11.4 Perform Quantitative Risk Analysis
11.5 Plan Risk Responses
Project Procurement 12.2 Conduct Procurements 12.3 Control Procurements
12.1 Plan Procurement Management
Management
Project Stakeholder 13.1 Identify 13.4 Manage Stakeholder
13.2 Plan Stakeholder Engagement 13.4 Monitor Stakeholder Engagement
Management Stakeholders Engagement
THANKS
AND GOOD LUCK
TO BE PMP SOON
503