Velocity Chart Template

The document presents a velocity chart template to track a project's velocity over 4 sprints. It shows the story points completed in each sprint. The total story points were 41 and the average velocity was 9 story points per sprint, indicating the team could typically complete 9 points per sprint.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
150 views4 pages

Velocity Chart Template

The document presents a velocity chart template to track a project's velocity over 4 sprints. It shows the story points completed in each sprint. The total story points were 41 and the average velocity was 9 story points per sprint, indicating the team could typically complete 9 points per sprint.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 4

Velocity Chart Template

Velocity = Total Story Points Delivered over a Sprint


The example below illustrates a basic example of a 4 Sprint Project. Being the Sprints in this case 2 weeks long this is a 2 mont
It has 15 user stories in total. I've used the name "User Story #" in the essence of time, but you would of course write the actu
Assumption: The team discards the user stories which aren't delivered since after discussion they don't consider required any

Sprint 1 Story Points


User Story 6 3 Note: this user story wasn't delivered in Sprint 1 since the tea
User Story 11 3
User Story 2 5
User Story 8 1
Total 12 Velocity Sprint 1 9

Sprint 2
User Story 1 5
User Story 13 1
User Story 5 1
Total 7 Velocity Sprint 2 7

Sprint 3
User Story 3 5
User Story 4 3
User Story 15 1
Total 9 Velocity Sprint 3 9

Sprint 4
User Story 9 3 Note: this user story wasn't delivered in Sprint 4 since the tea
User Story 7 5
User Story 14 3
User Story 10 1
User Story 12 1
Total 13 Velocity Sprint 4 10

Total Story Points 41 Average Velocity 9 Which means that on average the team
This is an indication of execution that al

Velocity Chart
Sprint Velocity Velocity Chart
1 9
2 7
3 9 10
9 9
4 10
7
Velocity
10
9 9

Velocity
1 2 3 4
Sprint
e 2 weeks long this is a 2 month project.
would of course write the actual user story using the format described in the other tab
y don't consider required any longer. Keep in mind, that if they were required they would be added to another Sprint

vered in Sprint 1 since the team didn't have time to complete it

vered in Sprint 4 since the team didn't have time to complete it

eans that on average the team is delivering 9 story points per Sprint. This is known as the project's Velocity
indication of execution that allows for future planning and workload management.

10
10