General Information
Lifting Plan No.: NRLP – C – 113 Mad Tank - 20 T ZB556 Date: 25 – 05 – 2023
Location: ZB-556 Contractor/Sub-Contractor SLB / IDC – 37
Permit-To-Work No: Risk Assessment No:
Description of lifting operation:
Lloading / Positioning on Mad Tank On Ground to Truck – Crane by Tandem Lift
50 t HOOK BLOOKS ON 7 PARTS OF LINE MUST BE INSTALLED ON BOTH (TADANO TG – 500 E ) AS AGREED WITH ENI LTA
Method Statement:
To perform Lloading / Positioning on Mad tank +Intermediate tank + Mixing Tank + Reserve Tank +Suction Tank +Trip Tank + Water Tank
+ poor boy + MI + Cooling System +Suction tank On Ground to Truck – Crane by Tandem Lift.
By: 2 X Mobile Cranes, Lifting Supervisor, 2X Slingers, 1X Banks man, and Flagmen as required
All required documents shall be in place and shall be confirmed before starting the job (JSA, PTW, LP, TBT, etc.)
using two of 3rd party mobile cranes For Lifting Operation.
Pre-work check of site, load, and lifting equipment (lifting appliances and lifting accessories)
All lifting equipment shall have clear and legible SWL, all lifting accessories shall be correctly colour coded
Size, weight, shape, CoG of load shall be confirmed
Load shall be checked for any loose / potential dropped objects
Check proximity hazards, obstructions, load path and lay down area load bearing capacity.
Pre-work check of environmental conditions (wind speed shall not exceed 10 m/s, rainfall, foggy weather, etc.)
Confirm competency requirements match lift team personnel
Confirm and agree methods of communication: standard hand signals & radio.
Responsibilities to be clearly defined for all personnel
Lifts to be controlled by banks man who is clearly identifiable by wearing high visibility waistcoat
Establish barrier surrounding lifting operation area, non-essential personnel to be excluded at all times
Safe access, egress and escape routes (scaffolding, platforms etc.)
Tagline requirement: Tag lines are not required for tandem lift
No hand contact with loads until below waist height, no hands and fingers near pinch points.
Cable trays, beams, and any other obstructions shall be removed to allow the proper set-up of the crane prior to lift.
Any obstacle that might become in contact with the sling shall be removed.
Part of lines: Crane #1: 7 - Crane #2: 7
Details of the Load
Description of load/s:
Mad Tank + Intermediate tank + Mixing Tank + Reserve Tank +Suction Tank Trip Tank Water Tank
+ poor boy +MI + Cooling System +Suction tank
Overall dimensions [m]: 11.60 M X 2.8 X 3
Weight of load [t]: [A] 20 T √ Known weight □ Estimated weight
Centre of Gravity: OFFSET □ Known (by drawing) √ Estimated position
Details of the Lifting Appliance # 1
Type of Lift. Appliance: Mobile Crane Model: NK-500B-V
Jib length [m] (if applicable): N/A Fly jib offset [angle]: N/A
SWL at maximum involved
18.6 Load share on crane #1 [Total Weight (10) × 1.25] =12.5 t for each crane
radius [t]: [B]
Details of the Lifting Appliance # 2
Type of Lift. Appliance: Mobile Crane Model: NK – 500 E -III
Boom length [m]: 18.1 m Radius [m]: 7.5 Minimum Applicable , Radius)
Jib length [m] (if applicable): N/A Fly jib offset [angle]: N/A
SWL at maximum involved
18.5 t Load share on crane #1 [Total Weight (10) × 1.25] =12.5 t for each crane
radius [t]: [B]
Details of the Lifting Accessories
Types of Lifting accessory: Slings / webbing / chains / shackles / spreader beam
Weight SWL
Type Quantity Identification Number Certificate # Expiry Date
[Kg] [t]
50
Crane(1) HOOK BLOCK - (NK-500B-V) 1 570 2010120 St-3620-02 6-10-2022
Ton
18.3
2 Legs wire rope sling 1 100 B3757 LTG – IQ /A260133 15 – 09 – 2023
TON
50
Crane(2) HOOK BLOCK - (tg-500E-III ) 1 570 436762 Ras-t-221230400 6-12-2022
TON
18.3
2 Legs wire rope sling 1 100 B3758 LTG – IQ /A260133 15 – 09 – 2023
TON
Total weight of Lifting accessories [t] : [C]=(D/1000) Crane #1 = 0.67 T Crane #2 = 0.67 T
Colour code: Blue Certification of Lifting accessories: □ YES □ NO
Unity Check of # 1 [%]: 70.80 % Unity Check of # 2 [%]: 71.18 %
ENSURE THAT ALL LIFTING EQUIPMENT HAVE BEEN CHECKED AND DEEMED SUITABLE AND SAFE
Lifting Sketch – As required
Sketch of the General Arrangement / Rigging:
[crane position / lifted item / obstacles and any additional details, as required]
FOR EACH CRANE
2 X Leg Wire Rope Slings
SWL :- 18.3 TON L=6M
Boom Length 18 ,1 M
NK-550
NK-500E-III
Radius : 7.5 m
Radius = 7.5 m
Is lay down / landing area(s) adequate in both size and load bearing capacity? Yes
Obstacles Has route to be travelled been selected and cleared of obstructions? Yes
Lighting Is the lighting condition adequate to perform the operations safely? Yes
Demarcation Have barriers been positioned to prevent access to unauthorised personnel? Yes
Environment Are the weather conditions within limits to avoid their effects on the safety of the lifting operation? Yes
IF ANY OF THE CONTROLS IS NOT IN PLACE, THE OPERATION SHALL NOT START!
Communication What are the means of communication between the lifting team?
The Non-Routine Simple lifting plan shall be submitted to LTA for review and approval. LTA shall evaluate, in collaboration with
other members of the team, all possible corrective actions and advice to:
STOP! Further engineering inputs and risk assessment are required.
PROCEED WITH CAUTION! Operation may be performed providing that all necessary actions
have been taken and JSA updated accordingly.
GO! Proceed with lifting operation following the instruction given by the PIC.
Reference documents
Reference Documents / Evidences / Attachments:
NOTE - HSE documentation (JSA/RA) shall be updated accordingly, in collaboration with HSE involved personnel, to reflect the proposed actions.
Preparation and Review
Prepared by: Signature: Date: 25 – 05 – 2023
Reviewed by: Signature: Date:
LTA comments and review
Reviewed and Acknowledged by LTA and PIC
LTA: Signature: Date:
PIC: Signature: Date: