Report 1 - Final
Report 1 - Final
2019-2020
On
Has been
Submitted by
3) Vaibhav Bari
Dr.S.S.ZOPE
Lecturer
Department of Electrical Engineering
Maharashtra State Board of Technical Education Mumbai
Submission
We the students of Sixth Semester Electrical Engineering submit the report onMicro Project
work titled as“VISIT ELECTRICAL MACHINE MANUFACTURING UNIT AND COLLECT DATA OF
VARIOUS TESTS CONDUCTED ON IT.”
of
Mr.Dr.S.S.ZOPE
Lecturer
Submitted by
3) Vaibhav Bari.
Certificate
This is to certify that the report on micro project work titled as
“VISIT ELECTRICAL MACHINE MANUFACTURING UNIT AND
COLLECT DATA OF VARIOUS TESTS CONDUCTED ON IT.”
3) Vaibhav Bari
Principal
Maharashtra State Board of Technical Education Mumbai
Acknowledgement
First and foremost, we would like to thank God, the Almighty, for nothing is possible
without His will.
We grateful to the invaluable motivation and guidance of my Guide, ShriDr.S.S.ZOPE who
has always been a source of inspiration and encouragement for me. He has been an outstanding
caring person and a guide as well. we express my sincere gratitude for his priceless cooperation
and support throughout the work. He has always been ready to help and guide me in the ups and
downs and his sympathetic comments, reminders and assurance has been a source of inspiration
for me.
My sincere vote of thanks also goes to Head of Department, Shri S S Zope for well-timed
alarming, and keeping me well in contact with the entire system. we am most thankful to his an
extraordinary considerations.
We would like to express my special gratitude to my Honourable Principal Shri P B Patil,
really a man of principle, for providing a motivational ambiance in the completion of my work. we
am so thankful to his kind nature and nourishing attitude.
we would like to acknowledge the support and encouragement of all the faculty members, my
fellows, lab supporting staff and others.
1) Deepak Dude
2) ChetanBhoi
3) Vaibhav Bari
PART A
Plan
Title of Micro-Project:“VISIT ELECTRICAL MACHINE MANUFACTURING UNIT
AND COLLECT DATA OF VARIOUS TESTS CONDUCTED ON IT.’’
1.0Brief Introduction.
The various types of the protective relays are available for protecting the motor from faults. These relays
sense the abnormal operating condition and make the circuit breaker to trip. The motors provide
protection against faults in windings and associated circuits, excessive overload and short circuits, under
voltages, phase unbalances and single phasing, phase reversal and switching overvoltages.
2.0 Aim of the Micro-Project
8. Report writing
4.0 Resources Required (major resources such as raw material, some machining facility, software
etc.)
3 Project Proposal
6 Quality of Prototype/Model
7 Report Preparation
8 Presentation
9 Defense
Note:
Every course teacher is expected to assign marks for group evolution in first 3 columns &
individual evaluation in 4TH columns for each group of students as per rubrics.
Signature…………………………………………………………………………………………...
PART B
Plan
When transformers are received from the factory or reallocated from another
location it is necessary to verify that each transformer is dry, no damage has
occurred during shipping, internal connections have not been loosened, the
transformer’s ratio, polarity, and impedance agree with its nameplate, its major
insulation structure is intact, wiring insulation has not been bridged, and the
transformer is ready for service. Physical size, voltage class, and kVA rating
are the major factors that dictate the amount of preparation required to put
transformers in service. Size and kVA rating also dictate the kind and number
of auxiliary devices a transformer will require. All of these factors affect the
amount of testing necessary to certify that a transformer is ready to be
energized and placed in service. There are a multitude of checks and tests
performed as a transformer is being assembled at a substation. The test engineer
may not directly perform all of the following tests and inspections but must be
sure they are satisfactorily completed, so that the final decision over
transformer bank readiness for energization can be made. Some tests and
procedures may be performed by specialists during the assembly phase.
Special tests, other than those listed, may also be required. Many require
special equipment and expertise that construction electricians do not have and
are not expected to provide. Some tests are performed by an assembly crew,
while other tests are done by the person(s) making the final electrical tests on
the transformers.BPA has hundreds of power transformers installed throughout
the system, and few of them are identical. The following information is not
intended to describe, or include, the details for performing the entire array of
tests needed to prepare transformers for service, only the tests that may be
performed by field personnel. Even though details have been limited,
descriptions should allow field personnel to perform, or assist in performing,
the basic tests they may be asked to do. Procedures and tests are described
somewhat generically, but apply to most transformers in one way or another.
Also, the following test descriptions provide an anchor point from which to ask
for help when needed. The following items are discussed or described:
• Some tests are done at manufacturer premises before delivering the transformer. Mainly two
types of transformer testing are done at manufacturer premises- type test of transformer and
routine test of transformer. In addition to that some transformer tests are also carried out at
the consumer site before commissioning. Type of Transformer Testing:Tests done at factory
1. Type tests 2. Routine tests 3. Special tests Tests done at site 1. Pre-commissioning tests
To prove that the transformer meets customer’s specifications and design expectations, the
transformer tests are carried out for confirming the basic design expectation of that transformer. These
tests are done mainly in a prototype unit not in all manufactured units in a lot. Type test of transformer
confirms main and basic design criteria of a production lot. Type tests of transformer includes : 1.
Transformer winding resistance measurement 2. Transformer ratio test. 3. Transformer vector group
test. 4. Measurement of impedance voltage/short circuit impedance (principal tap) and load loss (Short
circuit test). 5. Measurement of no load loss and current (Open circuit test). 6. Measurement of
Routine tests of transformer is mainly for confirming operational performance of individual unit in a
production lot. Routine tests are carried out on every unit manufactured. These tests are: 1.
Transformer winding resistance measurement. 2. Transformer ratio test. 3. Transformer vector group
test. 4. Measurement of impedance voltage/short circuit impedance (principal tap) and load loss (Short
circuit test). 5. Measurement of no load loss and current (Open circuit test) 6. Measurement of
insulation resistance. 7. Dielectric tests of transformer. 8. Tests on on-load tap-changer. 9. Oil pressure
test on transformer to check against leakages past joints and gaskets. That means Routine tests of
transformer include all the type tests except temperature rise and vacuum tests.
Special tests of transformer is done as per customer requirement to obtain information useful to the
user during operation or maintenance of the transformer. 1. Dielectric tests.2. Measurement of zero-
noise level. 5. Measurement of the harmonics of the no-load current. 6. Measurement of the power
taken by the fans and oil pumps. 7. Tests on bought out components / accessories such as buchhloz
relay, temperature indicators, pressure relief devices, oil preservation system etc.
Dielectric tests.
Measurement of zero-sequence impedance of three-phase transformers
Short-circuit test
Measurement of acoustic noise level
Measurement of the harmonics of the no-load current.
Measurement of the power taken by the fans and oil pumps.
Tests on bought out components / accessories such as buchhloz relay, temperature indicators, pressure
relief devices, oil preservation system etc.
Transformer Winding Resistance Measurement
Transformer winding resistance measurement is carried out to calculate the I2R losses and to calculate
winding temperature at the end of a temperature rise test. It is carried out as a type test as well as
routine test. It is also done at site to ensure healthiness of a transformer that is to check loose
connections, broken strands of conductor, high contact resistance in tap changers, high voltage leads
and bushings etc.
There are different methods for measuring of the transformer winding, likewise:
The procedure of the transformer ratio test is simple. We just apply three phase 415 V supply to HV
winding, with keeping LV winding open. We measure the induced voltages at HV and LV terminals of the
transformer to find out actual voltage ratio of the transformer. We repeat the test for all tap position
separately.
There are three limbs placed side by side in a core of the transformer. One phase winding is wound in
one limb. The voltage induced in different phases depends upon the respective position of the limb in
the core. The voltage induced in different phases of a transformer in respect to neutral terminals given
in the table below.
An agreement to within 30% of the measured exciting current with the previous test is usually
considered satisfactory. If the measured exciting current value is 50 times higher than the value
measured during factory test, there is a likelihood of a fault in the winding which needs further analysis.
Caution: This magnetizing current test of a transformer is to be carried out before DC resistance
measurement.
There are several internal connections of three-phase transformer are available on the market. These
several connections give various magnitudes and phase of the secondary voltage; the magnitude can be
adjusted for parallel operation by suitable choice of turn ratio, but the phase divergence cannot be
compensated.
So we have to choose a transformer suitable for parallel operation whose phase sequence and phase
divergence are same. All the transformers with the same vector ground have same phase sequence and
phase divergence between primary and secondary.
Before procuring an electrical power transformer, you should ensure the vector group of the
transformer, whether it will be matched with his or her existing system or not. The vector group test of
transformer confirms his or her requirements.
First one is called Separate Source Voltage Withstand Test of transformer, where a single phase power
frequency voltage of prescribed level, is applied on transformer winding under test for 60 seconds while
the other windings and tank are connected to the earth, and it is observed that whether any failure of
insulation occurs or not during the test.
The second one is the induced voltage test of Transformer where, three-phase voltage, twice of rated
secondary voltage is applied to the secondary winding for 60 seconds by keeping the primary of the
transformer open circuited.
The frequency of the applied voltage should be double of power frequency too. Here also if no failure of
insulation, the test is successful.
In addition to dielectric tests of transformers, there are other types of test for checking insulation of
transformer, such as lightning impulse test, switching impulse test and partial discharge test.