Towns North of Colombo Water Supply Project
Towns North of Colombo Water Supply Project
Towns North of Colombo Water Supply Project
1.1 Background
Sri Lanka is an island country located 30km southeast of India. The total area of the country
is approximately 0.8 times the size of Hokkaido in Japan. The target area of the project in
1 2
Towns North of Colombo has a total extent of 14.3 km and a total population of 530,000.
The population is similar to the population of Meguro-ku in Tokyo, and the extent of the area is
similar to the area of Himeji City in Hyogo Prefecture in Japan.
Most of the residents of the target area used wells or common taps as only small-scale water
supply systems from springs and wells or extensions of neighboring water supply systems were
available in the area. Some wells in the area, especially in the industrial area, were
contaminated by industrial waste water, and others in the coastal area were often contaminated
by salt water. The area has a lot of industrial estates; however, the unavailability of stable
water supply was an obstacle to production activities.
In this way, the absence of water supply was a burden for residents and a hindrance to
economic development of the area. Therefore, it was urgently necessary to construct water
transmission and distribution facilities and enhance water supply capacity in the area.
1
“Towns North of Colombo” is not an administrative area of the government of Sri Lanka but an administrative area
of the National Water Supply and Drainage Board. It is in Gampaha District and bordered on the south by Colombo
City. The target area of the project was a part of the Towns North of Colombo. See the map in Annex 1 for details.
1
1.2 Objective
The objective of this project is to enhance the water supply capacity of Towns North of
Colombo, where there is increasing water demand, by constructing transmission and distribution
facilities, thereby contributing to the industrial development and improvement of public health
in the area.
2
2.1.2. Relevance with needs
The need for water supply services and urgency of its expansion were high in the target area
at the time of project appraisal as well as the ex-post evaluation, as the population was
increasing and industrialization was accelerating.
2.2.1 Output
(1) Transmission and distribution facilities
As Table 1 shows, all the planned works for transmission and distribution facilities were
conducted almost as planned. At the time of the change of the project scope, the anticipated
scope was divided into two, “Stage I” and “Stage II”. Considering the limited amount of yen
loans as well as the time period, it was decided that the project would implement only the work
in “Stage I”. However, a part of “Stage II”, which was urgent, was also conducted under the
project.
3
Table 1 Comparison of planned and actual outputs
4
(3) Consulting Services
Review of F/S, detail design, supervision of construction and training were planned under the
consulting services. The services were conducted as planned. Planned and actual MM of the
services were somewhat different, as the actual MM was longer than the planned MM, due to
extension of the project period.
Plan: Foreign: 91MM, Local: 190MM
Actual: Foreign: 101.3MM, Local: 270MM
5
the project created various positive impacts. For example, water supply services for the
existing customers were significantly improved by the extension of water supply hours and an
increase in water pressure. There were a positive impact to the industries in the area and an
improvement in the sanitation and living conditions of the people in the area.
The source of the piped water supply for Colombo District and its suburbs, including the
target area of the project, used to be the Kelani River. The Ambatale water treatment plant, of
which capacity was enhanced under the project, was treating all the water to be supplied to the
entire area. At the time of the project appraisal, water demand was continuously increasing as
the population of the area was increasing year by year. However, it was difficult for NWSDB
to make an additional intake at the Ambatale water treatment plant as there was a risk of
saltwater contamination.
Under these circumstances, in order to meet the water demand in the future, NWSDB was
planning to implement several projects for the development of water sources and the
construction of water treatment plants. The figures showing planned newly-connected
population and average consumption per day in Table 2 and 3 were projected on the assumption
2
In the consumer survey conducted as a part of the ex-post evaluation, the average number of family members per
household was considered as five.
6
that the following projects would be realized in time.
(a) Construction of Kalu Ganga water treatment plant
As a part of the Kalu Ganga (Kalu River) Development Project, the Kalu Ganga water
treatment plant will be constructed. After the completion of the plant, treated water from the
Kalu Ganga plant will be supplied to South Colombo which is located near the Kalu Ganga.
Therefore, the Ambatale plant will be able to reserve its capacity, and a larger volume of water
will be sent to North Colombo, including the target area of the project. Eventually, the amount
of treated water supplied to the project area will increase.
(b) Construction of Kelani River Right Bank water treatment plant
The Kelani River Right Bank water treatment plant will be constructed with financial
assistance from the Government of Denmark. The volume of treated water supplied to the
Towns North of Colombo area, including the target area of the project, will greatly increase, as
the plant, in addition to the Ambatale water treatment plant, will supply treated water to the
area.
(c) Implementation of the stage II of the Towns North of Colombo Water Supply Project
The stage II of the Towns North of Colombo Water Supply Project will be implemented in
parallel to the project (Stage I). Facilities to be constructed in Stage II will be commissioned
from 2005 onwards, and thereafter, the number of connected households will increase
dramatically.
However, the volume of treated water supplied to the target area did not increase as expected,
as only a part of the above-mentioned assumptions were realized at the time of the ex-post
evaluation, as explained as follows, and there is still a limitation on the capacity of the Ambatale
water treatment plant due to the risk of salt water contamination, as mentioned earlier.
(a) Construction of Kalu Ganga water treatment plant
The Kalu Ganga Development Project was postponed due to the financial situation of
NWSDB. At present, the phase I of this project (Kalu Ganga Water Supply for Greater
Colombo Project; L/A signed in 1996), which was implemented with the support of an ODA
loan from JICA (former JBIC), has been completed. However, the phase II (Water Sector
Development Project II; L/A signed in 2008), including the construction of a water treatment
plant, has just commenced. Therefore, the Ambatale water treatment plant does not have the
extra capacity to supply more water to the target area.
(b) Construction of Kelani River Right Bank water treatment plant
Construction of Kelani River Right Bank water treatment plant became more urgent for
NWSDB as construction of the Kalu Ganga water treatment plant was delayed as mentioned
above. This project was funded by the Government of Denmark as planned. However,
construction of the plant was delayed for five years due to problems in the process of the
procurement of a civil contractor. Currently, the construction of the plant has not been
completed; therefore, water supply from the plant to the Towns North of Colombo area has not
started.
7
(c) Implementation of the stage II of the Towns North of Colombo Water Supply Project
The stage II of the Towns North of Colombo Water Supply Project was not implemented in
parallel to the stage I, as the implementation of the project (the stage II) was not considered to
be urgent, because the above-mentioned (a) and (b) projects delayed. At the moment, the
project is being implemented with the assistance of an ODA loan from JICA as a part of the
Water Sector Development Project I, signed in 2007, and the facility which will be constructed
by the project is planned to be commissioned in 2011.
NWSDB considers that the delay in the construction of the Kalu Ganga water treatment plant,
which was supposed to supply a large volume of water to the target area, should be the main
reason behind the shortage of treated water in the area. NWSDB has stopped the extension of
the distribution network and the provision of new connections at present due to the shortage of
the treated water. Therefore, it is not in a position to improve the levels of achievement shown
in Table 2 and 3.
8
number of the service hours per day was 4.1 hours.
(Unit: hours/ day)
Before After
24 23.8
21
19.5 19.9 19.7
18.2
17.2
15.6 15.6
14.3
12.1
10.6
8.1
Figure 2 shows the distribution of households in terms of the service hours both before and
after the project.
(Unit: hours/day)
100%
90%
80%
70%
60%
19‐24
50%
13‐18
40%
7‐12
30%
1‐6
20%
0
10%
0%
Before After Before After Before After Before After Before After Before After
Figure 2 shows that there was a significant improvement for the households which had very
limited service hours before the project. Details of the improvement are described below.
Before the project, there were many households which had a connection to water but did not
have any service. After the project, there are no such households.
9
In every area, except for Kandana, 12% – 20% of the households among the samples had
the connection but did not have any water supply. This was a significant problem in
Ja-Ela, where the ratio of such households among the samples was 20%. This was a
particular problem seen in the households located at the end of the distribution network or
where water pressure was very low. They had water supply at the time they were
connected to the distribution network several years ago, but they gradually lost the service
when water demand in the neighboring areas increased due to an increase of population and
urbanization. After the project, all these households obtained several hours of water
supply per day and there were no households that do not receive any supply at the moment.
The number of households that have less than six hours of service was reduced
The number of households that have less than six hours of service per day was drastically
reduced, in addition to the above-mentioned benefit to the households that did not have any
supply. For example, in Ja-Ela, the ratio of the households that had less than six hours of
service per day was 43% among the samples before the project, but this was reduced to 8%
after the project. In Pamunugama, too, the ratio of such households was 30% before the
project, but it was reduced to 20% after the project.
2.4 Impacts
The project contributed to the development of commercial and industrial activities and the
improvement of sanitary and living conditions of the community in the target area, and thus it is
evaluated that the project produced the expected impacts.
10
At the moment, NWSDB gives priority to the benefits for general consumers, and could not
answer requests from factories in the area for new connections due to the limitations on the
amount of treated water. Meanwhile, the following case study confirmed that a factory in the
target area, which already had a connection, benefitted from the project because of the increase
of service hours and improvement of water pressure.
11
groundwater3. Figure 3 shows the result of the interviews.
(Unit: persons)
0 5 10 15 20 25 30 35 40
Hygiene status was improved 38
Living environment was improved 37
housework, such as water drawing
35
outside, was reduced
Free time was increased 32
Opportunity for employment or self‐
21
employment was increased
Electricity consumption for pumping‐up
8
water from the well was reduced
Expenses for firewood or gas to boil
8
water for drinking was reduced
Figure 3 Impact on sanitary and living conditions owing to the supply of piped water
(Source: interview with the selected 39 households)
Figure 3 shows that most of the respondents recognized that “Sanitary and living conditions
were improved owing to the supply of piped water.” It is assumed that the supply of the
piped water solved the above-mentioned problems because the residents were able to obtain
adequate amounts of good quality water.
According to the interviews, 90% of the respondents mentioned that their “workload, such
as water drawing outside of their premises, was reduced.” As 74% of the respondents had a
well within their premises, it was assumed to be a reduction of the workload of drawing water
from a well on the premises and carrying the water to the kitchen and bathroom.
There were comparatively fewer households that recognized a reduction of electricity
consumption spent for pumping up water from a well, and a reduction of expenses for
firewood or gas spent for boiling water for drinking. Results from the questionnaire survey
showed that around 40% of consumers boiled water for drinking before and after they
obtained new connections of piped water supply; it is thus understood that there is no
particular relationship between a reduction of expenses for electricity, firewood and gas and
the supply of piped water with regard to the households in the target area.
A half of the respondents replied that opportunities for employment or self-employment
increased after they obtained the piped water supply. This is because they had more
available time due to the reduction of their workload for drawing and carrying water.
3
Places which may have problems with groundwater were identified by the information from the OICs (officers’
in-charge) of NWSDB in the target area. It was confirmed that the survey included a considerable number of
households which have problems with groundwater, as 40% of the respondents replied that “water in the well is dried
up during dry seasons” and 33% replied that “there were problems with the quality of water in wells, such as odor
and color” in response to a question about the quality of water from their well. .
12
(3) Benefit for medical institutions
The following case study shows that the project improved water supply services to a main
medical institution in the target area.
13
A case study – Talahena village in Pamunugama area
(The following is a summary of interviews with residents in Talahena village)
Talahena is a coastal village located northwest of the target area. It was not included in the
project area. Ground water under the village has been contaminated with mud and become
turbid and brownish in color from long ago. Residents of the village pumped up the ground
water from wells in the garden, filtered it and used it for domestic use. They used hand-made
filters made of gravel and pebbles. They said that the filtered water can be used for domestic
use, but it is not suitable to use for drinking at all.
The village obtained piped water supply around 15 years ago. However, from around 2000,
the water pressure and volume of water were extremely reduced due to an increase of demand
caused by the growing population and increase in the number of connections in the area. From
around 2002 onwards, the water was not supplied at all to the households located at the end of
the distribution network. In other words, these households had connections, but did not
receive even a drop of water from the supply. Other households in the village also had very
low water pressure. Water was not delivered up to taps in kitchens and bathrooms due to the
low pressure. They had to dig out a pipe laid under the gardens, attach a tap, and obtain water at
night and store it in a tank for drinking. If they could not obtain water by such means, they had
to bring water from a common tap several kilometers away from their residences. This
situation continued for around five years.
NWSDB recognized the serious problem of the residents, and made an arrangement to
connect a transmission line constructed by the project to the distribution network of the area.
The volume of water supplied to the area was subsequently increased by the arrangement. As a
result, the villagers were again able to obtain water supply for several hours a day. Households
located at the end of the distribution network were able to obtain water for drinking. Other
households became able to obtain water even for kitchens and bathrooms.
However, some of the residents still have to store water at night from a tap attached to a pipe
in the ground, store it in a tank and pump it to the taps in the house, as water pressure is still
very low. The residents use water from wells, too, as the volume of piped water supply is not
sufficient. They greatly hope the volume of piped water supply will increase soon, so that they
can become freed from the costly and troublesome work of pumping muddy water from a well,
filtering it, and pumping it again to the house. There are several households that do not have
connections to the piped water supply, and they must obtain water for drinking from
neighboring households. They are eagerly awaiting connections to the piped water supply.
<Reference>
Assumed number of direct beneficiaries:Around 130,000 persons (water supply–connected
domestic population in the target area)
Assumed number of indirect beneficiaries:Around 200,000 persons (users of hospitals,
schools, factories, shops, government institutions, religious facilities, etc.)
14
2.4.2. Impact on Natural Environment
(1) Impact by the construction work
There was no impact on the natural environment caused by the construction work of the
project.
15
and Area Engineer’s Office of NWSDB. The manager of Towns North of Colombo Manager’s
Office has the overall responsibility for distribution. Around 200 staff in total are engaged in
O&M work for the target area, including treatment, transmission and distribution of water.
There are no particular issues with regard to institutional aspects of O&M. Responsibilities of
the above-mentioned production unit and offices for distribution are clearly defined, and the
organizational structure for O&M is well established.
16
The financial status of NWSDB had been improving until 2006. However, in 2007, the
financial status, such as operating profit, net profit and assets-operation income ratio, suffered a
reverse mainly because the cost of inputs, such as electricity, chemicals, fuel and salaries,
became extremely high. According to an interview with senior officials of NWSDB, the
financial status in 2008, which was not officially revealed, did not show improvement. The
Water Sector Development Project, for which an agreement for a Japanese ODA loan was
signed in 2007, is assisting the enhancement of the management and financial capacity building
of NWSDB.
Table 6 shows NRW ratio for Colombo Municipal Council area and for Greater Colombo.
They are slightly improving, but they are still very high.
Table 6 Non-Revenue Water Ratio for Colombo City and Greater Colombo
(Unit :%)
Year 1997 2000 2005 2007
Colombo Municipal 57.0 53.7 51.3 52.7
Council area
Greater Colombo 47.0 38.7 35.9 37.84
(Source: Document submitted by NWSDB)
The Water Sector Development Project II, for which a Japanese ODA loan agreement was
17
signed, is going to assist NWSDB in improving the NRW ratios by implementing civil
construction in the city. A technical cooperation project of JICA for the improvement of the
NRW ratios will be implemented from late 2009 onwards for a period of three years.
(5) Conversion of the pumps installed at Ambatale Water Treatment Plant and gravity
18
transmission mains from Ambatale to Church Hill
Treated water will be supplied to the target area of the project mainly from the Kelani River
Right Bank Water Treatment Plant once it is completed. NWSDB is working out a plan for
future usage of the two pumps installed at the Ambatale Water Treatment Plant and the
transmission mains from Ambatale to Church Hill. There is an idea to use the pumps to
enhance water supply to the Greater Colombo area under the Greater Colombo Water Supply
Improvement project, which is one of the components of the Water Sector Development Project
currently being implemented with the financial support of an ODA loan from Japan. There is
an idea to use a part of the transmission mains from Ambatale to Church Hill to transmit water
from the Kelani River Right Bank Water Treatment Plant to the Church Hill Reservoir and the
rest of them to transmit water from the Kelani River Right Bank Water Treatment Plant to the
Ambatale Water Treatment Plant for water supply to the Colombo City area. NWSDB has to
study technical viability of these ideas in due course.
Water quality 99% 1%
0%
Tariff (old) 86% 6% 8%
19
3.1. Conclusion
Although the effectiveness and the efficiency of the project were moderate, the relevance and
the sustainability of the project were high. In light of the above, this project is evaluated to be
satisfactory.
3.3 Recommendations
It is recommended that the effects and impacts of the project and status of usage of the
facility constructed by the project should be studied after completion of the Kelani River
Right Bank Water Treatment Plant and the phase II of Towns North of Colombo Water
Supply Project4, when effects of the project will be fully realized.
It is recommended that the improvement of the financial status of NWSDB and the NRW
ratios also should be confirmed by continuous monitoring in the future as well, even though
several measures have already been taken.
4
Signed in 2007 as one of the components of the Water Sector Development Project, which is financed by a
Japanese ODA loan.
20
Comparison of original and actual project scope
(2) Period October 1996 – May 2002 October 1996 – November 2004
(68 months) (98 months)( 144% of plan)
Note: additional works were
conducted for 24 months from
November 2004 onwards.
Completion of the project was
November 2006.
(3) Cost
Foreign currency 4,679 million yen 3,991 million yen
Domestic currency 1,566 million yen 2,483 million yen
(811 million rupees) ( 2,269 million rupees)
Total 6,245 million yen 6,474 million yen
ODA loan portion 5,308 million yen 5,122 million yen
Exchange rate Rs.1.0=¥1.93(as of October 1996) Rs.1.0=¥1.11 (Average between
1998 and 2007)
21