04 AHU Installation
04 AHU Installation
REFERENCE DOCUMENTS:
RISK ASSESSMENT:
- Tools Required:
1. Precautions, manpower, and equipment are available before the commencement of work.
2. The Site Team shall make sure that access roads are always clear from any obstruction
and the site is always accessible.
Site clearance
1. Before commencing the work, the area shall be cleared of all debris,
materials, or other obstructions.
2. The Site Team with the assistance of the Safety Officers shall coordinate logistics
and materials movement through the site following the direction on site.
3. The Work Permits and Operator Certificates shall be compiled and files for
reference by authorized personnel.
Pre-construction Safety Meetings
1. The meeting shall be scheduled prior to the beginning of the work and before any
Subcontractor starts on the project.
2. Safety awareness meetings will be conducted every working day morning/every other
day to brief the workforce on safety prevention measures. The equipment check for
safety shall be recorded/ documented during the daily Safety Awareness Meeting.
3. Traffic safety will be discussed to emphasize these meetings.
4. Each worker will be instructed to follow specific safety requirements related to his
trade. They will be required to follow installed safety signs, observe barricades and
use PPEs.
5. The Safety personnel will perform hazard risk analysis by identifying all steps, hazards
identified in those steps, with a focus on the relationship between the work task, the
tools, and the work environment. After identifying uncontrolled hazards; the Contractor
will take steps to eliminate or reduce them to an acceptable risk level.
6. General Contractual Safety, Health, and Environmental requirements.
7. Roles of the contractor, subcontractors, authorized representatives, and all project workers.
8. Accident reporting requirements.
9. Specific details of the work to be performed along with the use of personal protective
equipment.
10. Emergency procedure.
Operating Procedures
A site investigation has to be carried out to develop safety precautions and measures prior to
the commencement of the work. After such investigation, relevant signboards will be displayed
and
barricades will be installed where and as necessary, such as but not limited to the following:
1. Relevant information, advanced signs, warning, and mandatory signs will be placed as
required.
2. After completion of the work, safety cones and barricades have to be removed accordingly.
METHODOLOGY:
The installation AHU will be according to the recommendation from the manufacturer’s Method
Statement.
OFFLOADING:
1. Special care must be taken to ensure that units are offloaded from the containers.
2. Rough handling can result in damage to the aluminium framework and double-skin panels.
3. It is possible to lift the sections by slings or by forklift. Slings, preferable nylon, must be
placed around the structural base frame.
4. In the case in which the lifting tube is utilized, it must be inserted into the specific hole,
then the sling, which is equipped with a particular loop, must be connected to the tube.
After that, the section can be lifted.
5. Note: It is strongly recommended that offloading and installation operations will be carried
out by specialists with the necessary equipment and proper tools.
6. Special care must be taken to ensure that units are offloaded from the containers.
7. Rough handling can result in damage to the aluminium framework and double-skin panels.
8. It is possible to lift the sections by slings or by forklift. Slings, preferable nylon, must be
placed around the structural base frame.
9. In the case in which the lifting tube is utilized, it must be inserted into the specific hole,
then the sling, which is equipped with a particular loop, must be connected to the tube.
After that, the section can be lifted.
10. Note: It is strongly recommended that offloading and installation operations will be carried
out by specialists with the necessary equipment and proper tools.
INSTALLATION:
1. Prior to installation, it must be ensured that adequate access exists for connecting all supplies,
disposal of condensate/overflows, inspection, maintenance, and replacement of renewal parts
such as filters, belts, bearings, etc.
2. Installation of units must be in ·accordance with good engineering practice. Structural base
units must be level and rigid. Further, it must be ensured that the base is high enough from
the floor to allow the installation of a condensate drain with the necessary trap for easy flow.
General Installation of Floor Mounted AHU
3. Arrange installation of units to provide access space around AHU for service and maintenance
(coil removal). Floor mounted AHUs with internal isolation shall be supported with internal
supplies, disposal of condensate/overflows, inspection, maintenance, and replacement of
renewal parts such as filters, belts, bearings, etc.
ASSEMBLY:
1. Units are normally designed to make the best use of containers (shipping) volume in two or
more sections depending on the design of units. However, all the sections are externally marked
and their sequence of assembly can be easily identified from the enclosed drawings. Once all
the sections are located, they can be easily aligned and locked together.
2. First of all, between the sides of the sections that shall be connected, it must be inserted with a
continuous foam gasket for an airtight seal, Push the sections towards one another, making sure
that they are lined up with one another as shown below.
SETTING UP OF COMPONENTS:
• DUCT CONNECTION
When duct flanges are connected to damper frames, it must be ensured that the fixing bolts are
of the correct length and do not obstruct the movement of the damper lever/linkages.
• DAMPERS
All dampers must be checked for free movement prior to proceeding further.
1. Manually operated dampers can be adjusted to obtain the required airflow, by loosening
the bakelite knob and then turning the control lever. The Bakelite knob must be
tightened after setting up at the desired location on the locking quadrant.
2. Motorized dampers are supplied with the linkage rod for connection to the actuator. It
must be ensured that the actuator motors are rigidly fixed to the structural framework of
the unit and
not to the double-skinned panels. Care must be taken to ensure that the actuator does not at-
tempt to push the damper beyond fully open or fully closed positions.
• FILTERS
1. Check the type and quality of filters are in accordance with the drawing.
2. Panel Filters: flat or corrugated media are normally fitted within the unit prior to shipping.
3. Bag Filters: pre-filters (if any) are normally shipped in closed carton boxes, as supplied by the
filter manufacturer, to avoid any collection of dust and loss of efficiency prior to commissioning.
Each bag filter is housed within a special holding frame with the necessary locking spring to
ensure proper sealing. A bank of such special frames (quantity depends on the type and airflow)
is assembled within the peripheral aluminium framework of each bag filter section. The entire
assembly along with the pre-filter must be locked with four springs to ensure no leakage of air.
4. Automating roll filters have two headers, one house the clean spool, while the other dirty spool,
which is driven by a geared motor and chain drive actuated by differential pressure (D.P.)
switch. Normally filter media and D.P. switch are supplied loose for site installation. For
assembly, the filter media roll is mounted on the clean spool header, taken along the guide
channel through the working section, and locked to the dirty (driving) spool. D.P. switch must be
installed and connected to the control panel.
5. Automating roll filters have two headers, one house the clean spool, while the other dirty spool,
which is driven by a geared motor and chain drive actuated by differential pressure (D.P.)
switch. Normally filter media and D.P. switch are supplied loose for site installation. For
assembly, the filter media roll is mounted on the clean spool header, taken along the guide
channel through the working section, and locked to the dirty (driving) spool. D.P. switch must be
installed and connected to the control panel.
6. Absolute Filters are shipped in sealed carton boxes, as supplied by the filter manufacturer. They
are housed in a special purpose made of an aluminium frame with corner brackets and locking
devices for each cell. While assembly special care must be taken to ensure that each filter cell
is properly seated within the assembly frame and perfectly sealed against the neoprene foam
gasket with no possibility of air leakage.
7. Other types of filters such as actuated carbon, inertial (sand) filters, if installed, will be
supplied with the manufacturer’s instructions along with the units.
All coils are leak tested and checked prior to assembly. Fins are checked for proper
condition prior to shipping. However, during handling and installation, they might be
slightly bent and hence they must be checked and combed out if necessary. Do not remove
plastic protective covers from the header connections until the system is ready for hook up.
System layout should take into consideration of possible coil withdrawal. All connecting
pipework must be properly insulated.
1. Water Coils: system design, pipe connections, and valve arrangement must be in
accordance with good engineering practice. Flow and return connections are clearly
identified on the unit panels and pipework must be connected accordingly, preferably
through flexible couplings to avoid transmission of any vibration from the piping to coil.
The piping shall be free of any strain and shall not exert any load on AHUs and FAHUs (Fresh
Air Handling Units).
Excessive tightening torque might damage the coils. Pipework must be supported
independently to the coil and/or the unit. Use a pipe wrench to restrain the pipe connections
of the heat exchanger when tightening the external pipe connections.
2. Plugged drain: Plugged drain and vents are provided for each coil and their use must be
limited to the respective coil. They must not be used for draining or venting the other part
of the system. Sufficient anti-freeze chemicals must be added to the circulating water in
cooling coils when there is a possibility of being exposed to temperatures below 2°c. It is
recommended that the water flow is shut off when the fan is switched off.
Normally each heating coil should be provided with its own circulation pump. This ensures
even circulation of the water in the air heater, regardless of the position of the control
valve, and provides the following important benefit:
Appreciably less risk of freezing, due to the fact that the water velocity in the coil is always
sufficiently high.
3. Condensate Drains: All chilled water coils must be individually trapped and connected to
the drain with an adequate pitch for easy flow. It is recommended to install a trap.
Depending on the ambient temperature and plant location, it is recommended to insulate
the condensate drain pipework.
1. Anti-vibration mounts, on which fan & motor assembly is suspended, are locked Prior to
shipping to avoid damage during transit.
2. Once the unit is in position and the fan outlet is connected to ductwork, Anti-vibration
mounts must be released.
3. Check the type and voltage of the motor. If information is made available, cable entry holes
through the double-skinned panels can be factory drilled. However, it is a simple operation
to carry out the same on-site, but ensure that no holes drilled and no connections are made
through the access door. It is recommended to use a flexible armoured conduit between the
panel and motor terminal box. All conduits/wiring must be carried out in accordance with
local standards.
4. Check the type of start (direct online/star delta) that meets with the local electrical
regulations. Provide starter/controls/overload protecting devices/interlocks as required.
5. Manufacturer instructions, which are supplied along with the motor, must be carefully studied
and followed. Ductwork must be connected and insulated in accordance with good engineering
practice. Depending on specified noise levels, attenuators are to be selected and installed as
per the recommendations of acoustic specialists. It is recommended to protect all lining and
attenuation materials with smooth perforated metallic sheets to avoid migration of fibres into
occupied areas/blockage and subsequent replacement of filters frequently.
• BELT TENSION
1. The belts must be correctly tensioned to ensure good contact with the pulley. If
insufficiently tensioned, the belts may slip, and if excessively tensioned, the motor and
fan bearings may be over-loaded.
2. When correctly tensioned, the belt deflection L will be 15 mm per meter of distance between
centres when a force P1 ( N ) is applied and P < P1 < 1.5 P, where the force P is dependent
on the belt type. The deflection should be measured preferable by means of a tensiometer.
• ELECTRICAL CONNECTIONS
• TESTING
1. Leak test: After installation and completion of valve package connection. Fill the unit with
water and test connections for leaks. Repair leak and retest until no leak exist.
2. Fan operational test: After completion of electrical connection and energizing, start unit to
confirm proper motor rotation and unit operation, remove malfunctioning unit, replace with
the new unit, and retest.
3. Test and adjust control and safeties: Replace damaged and malfunctioning control and equipment.
QUALITY ASSURANCE:
1. The contractor shall provide the required documents for the Consultant’s approval
prior to initiating the execution of this activity as per project specifications.
2. The quality control requirement shall include related quality procedures QCP, ITP’s and
other related documents as applicable. Refer to Inspection Test Plan.
3. Applicable codes and standards for materials are project specifications.
The contractor shall notify the engineer prior to the start of the activity and Comments from
the site Instruction will be complied with the satisfaction of the consultant.
Accepted by: