Fonterra is upgrading its Waste Water Treatment plant in Te Awamutu by adding a new 11kV ring main unit with three transformer feeder circuit breakers and two ring feeders. This document summarizes the protection settings for the 1MVA transformer feeder to the MBR plant, including overcurrent, earth fault protection, and test requirements to validate the settings.

Uploaded by

SindhuKumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
406 views3 pages

GD18 - VIP400 Test Report

Fonterra is upgrading its Waste Water Treatment plant in Te Awamutu by adding a new 11kV ring main unit with three transformer feeder circuit breakers and two ring feeders. This document summarizes the protection settings for the 1MVA transformer feeder to the MBR plant, including overcurrent, earth fault protection, and test requirements to validate the settings.

Uploaded by

SindhuKumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

Sensitivity: General

FONTERRA TE AWAMUTU WWTP Setting Summary

Setting Details
Name of the Relay and the Settings File:

Substation Switchboard: WWTP 11 kV RMU

Relay:
Waste Water Treatment RMU/# VIP 400 _ 1 MVA Transformer Feeder (CB number to be confirmed) G/D/18

Project Details:
Project Name: Fonterra Te Awamutu WWT Plant – Protection Settings

As part of the Waste Water Treatment plant workstream, Fonterra is adding a new HV
Ring Main Unit with three transformer feeder circuit breaker and two ring feeders to the
existing 11 kV network.
Project Description:
This setting summary sheet focuses on the HV protection settings for the 1 MVA
Transformer feeder to MBR Plant MCC.

Setting Notes:
General

CT ratio: 200/1

Unconditional Tripping

The following unconditional tripping is set:


- OC (51)
- OC (50)
- EF(51N)

Phase Over-Current Protection (I>)

OC(IT) pickup is set to 0.39 A (secondary).

OC(IT) time multiplier is set to 0.09.

Curve selection IEC-VI

Instantaneous Phase Overcurrent (I>>>)

OC(Inst) pickup is set at 6.5 A (secondary)

Note: The INST value is only possible if the MIN TRIP TIME parameter is set to OFF.

Earth-Fault Protection (Io>)

EF(DefT) pickup is set to 0.15 A (secondary).

EF(DefT) is set with a time delay of 0.2 s.

Protection Setting Summary Sheet 1 MVA TX_13082021_RevA.doc Page 1 of 3


Sensitivity: General

FONTERRA TE AWAMUTU WWTP Setting Summary

Setting Changes:

Prior to relay testing, please ensure the following:

• Please confirm that the setting range is for VIP 400 and wiring is as per switchgear snippet below

Protection Setting Summary Sheet 1 MVA TX_13082021_RevA.doc Page 2 of 3


Sensitivity: General

FONTERRA TE AWAMUTU WWTP Setting Summary

Test Requirements:

CT Ratios

Confirm the phase CT ratio is 200/1.

1. Overcurrent
a. Pickup/Dropout and Timing Test
- Carry out secondary injection tests as detailed below under ‘1.1 Test Points’.
- Confirm that the trip output contacts operate the circuit breaker correctly.
(Note: See separate report for the timing test. Secondary injection was not possible to perform on this relay type.
1.1. Test Points Primary injection was done to measure timing. Feedback were measured from the CB open contact thus 80-100ms
delay was expected)

Function Test Points


Test Point 1 Test Point 2
Current (A sec) Operate time (s) Current (A sec) Operate time (s)
OC(IT) 0.78 (2 x Pickup) 1.215 1.95 (5 x Pickup) 0.304
OC(Inst) 6.63 (17 x Pickup) 0.02
EF(DefT) 0.3 (2 x Pickup) 0.20 .75 (5 x Pickup) 0.20

Basic Operation

Verify correct front panel displays and LEDs indication


Verify that Inputs and outputs of the relay operate correctly.
Verify correct operation of CB control
Verify correct event logs, metering data and IO status can be retrieved from the relay
Verify Standard parameter settings

Note: Make sure that the alarms and indications are tested from the actual field sources

Contact for Queries:


Please call Willem Groenewald +64 9 300 9000

COMPLETION NOTICE

At the completion of the work the Contractor is to electronically complete the table below and issue the Setting
Change Note(s), As-left settings, electronically signed Test Report(s) and any other relevant documentation to
Fonterra.

Settings Name & Revision Tested by Company Date

G/D/18=1MVA Feeder Karlo Tan Electrix Ltd. 06-05-2022

If this Setting Change Note applies to more than one relay then, if required, the Completion Notice can be
completed on a relay-by-relay basis and issued to Fonterra.

Protection Setting Summary Sheet 1 MVA TX_13082021_RevA.doc Page 3 of 3