GD18 - VIP400 Test Report
GD18 - VIP400 Test Report
Setting Details
Name of the Relay and the Settings File:
Relay:
Waste Water Treatment RMU/# VIP 400 _ 1 MVA Transformer Feeder (CB number to be confirmed) G/D/18
Project Details:
Project Name: Fonterra Te Awamutu WWT Plant – Protection Settings
As part of the Waste Water Treatment plant workstream, Fonterra is adding a new HV
Ring Main Unit with three transformer feeder circuit breaker and two ring feeders to the
existing 11 kV network.
Project Description:
This setting summary sheet focuses on the HV protection settings for the 1 MVA
Transformer feeder to MBR Plant MCC.
Setting Notes:
General
CT ratio: 200/1
Unconditional Tripping
Note: The INST value is only possible if the MIN TRIP TIME parameter is set to OFF.
Setting Changes:
• Please confirm that the setting range is for VIP 400 and wiring is as per switchgear snippet below
Test Requirements:
CT Ratios
1. Overcurrent
a. Pickup/Dropout and Timing Test
- Carry out secondary injection tests as detailed below under ‘1.1 Test Points’.
- Confirm that the trip output contacts operate the circuit breaker correctly.
(Note: See separate report for the timing test. Secondary injection was not possible to perform on this relay type.
1.1. Test Points Primary injection was done to measure timing. Feedback were measured from the CB open contact thus 80-100ms
delay was expected)
Basic Operation
Note: Make sure that the alarms and indications are tested from the actual field sources
COMPLETION NOTICE
At the completion of the work the Contractor is to electronically complete the table below and issue the Setting
Change Note(s), As-left settings, electronically signed Test Report(s) and any other relevant documentation to
Fonterra.
If this Setting Change Note applies to more than one relay then, if required, the Completion Notice can be
completed on a relay-by-relay basis and issued to Fonterra.