Tdoc 014 REV.01 - ITP FOR EXCAVATION & COMPACTION (ITP 002)
Tdoc 014 REV.01 - ITP FOR EXCAVATION & COMPACTION (ITP 002)
Tdoc 014 REV.01 - ITP FOR EXCAVATION & COMPACTION (ITP 002)
01
RATLS CONTRACTING LLC DATE: 8-Jan-2014
PAGES: 1 OF 1
CONTRACTOR: TROJAN General Contracting L.L.C. R =Review Records C1=Contractor Mandatory A= Authority/Client
RESPONSIBILITY
SL. SPECIFICATION / VERIFYING DOCUMENTS / RESPONSIBLE PERSON AT
ACTIVITY DESCRIPTION INSPECTION/TEST METHOD MODE OF CHECK STAGE / FREQUENCY
NO DRAWING REFERENCE ACCEPTANCE CRITERIA LOCATION SC C E/A
1 Document Verification Check Drawings are approved & at correct revision obtained. By reviewing the documents Prior to start activities Approved Drawing Project Engineer C1 R
QA/QC Engineer
By reviewing the documents
2 Preliminary activities Check excavation permit have been obtained. Prior to start activities Permits of Excavation C1 R
Survey and mark out all excavations details prior to
By Survey Instruments
3 Reference point establishment commencement of work. Prior to start activity Q.C Check list Surveyor C1 S
(Dumpy Level, Total Station) a. Drawings
Verify the existing utilities, relocate & protect as necessary. a. Q.C Check list
Trial pits. Before and during
4 Protection of existing utilities Visually b. General requirement b. Submission of water level C1 S
excavation
W ater level. documents Surveyor, Foreman
Ensure all grades, Dimensions and elevations are c. Project Quality Plan Project Engineer
accordance with relevant drawings and survey Before and during QA/QC Engineer
5 Level and dimension Visually Q.C Check list C1 W
requirements. excavation d. Specification: Division
31 "EARTH W ORK" /
Section "Excavation
Ensure that all excavation works, whether by machine Support & Protection" -
6 Excavation work or by hand, are performed in a safe working manner. Visually During Excavation 315000 Q.C Check list Project Engineer C1 S
HSE Officer
e. Method Statement
7 Bottom of excavation a. Check the Depth/W idth.
b. Check that bottom of excavations are free from extraneous Foreman
materials, ground water, and ready for PCC works. Visually, Inspection Request Project Engineer
( This Inspection shall be done
c. Check that Bottom of Excavation/sub grade is smooth and Measuring Tape After Excavation C1
together with Field Density Test, Q.C Check list QA/QC Engineer
conforms to the alignment, grade and cross-section. Dumpy Level
PCC and Ant termite)
TGC/QAQC/FRM/PR/14 Rev.01