Schedule Q - Attachment VI
Schedule Q - Attachment VI
Schedule Q - Attachment VI
6600042823 (IK)
ATTACHMENT VI TO SCHEDULE Q
1.2 For any equipment or material items that have no specified inspection
levels identified in SAEP-1151, CONTRACTOR shall prepare a special
form 175 for approval by the Company Representative.
1.3 Inspection levels specified in Attachment VI shall not be any lower than the
level of inspection specified in SAEP-1151.
2.4 CONTRACTOR shall establish a system of serialized log for all NDT
uniquely identifying the individual welds to be tested and method applied.
This log is to be an ongoing log of NDT requests and completions as the
Project progresses. The log reference (serial number) for each weld or
Q-VI-1
MP-LSTK, MP-IK-LSTK, MP-OK-LSTK, MP-IK-LS, MP-IK-LSPB,
OFF-IK-LSPB, OFF-OK-LSPB, OFF-IK-LS, OFF-OK-LS, C/R
Revised 05/17
SCHEDULE Q – ATTACHMENT VI CONTRACT NO. 6600042823 (IK)
welds examined shall be included in NDT reports. NDT of any repair shall
be sequentially identified in the log and include the log reference of the
initial NDT that determined need for the repair.
3. CONTINUAL IMPROVEMENTS
The Project Quality Index (PQI) shall be evaluated and scored monthly from the
start of procurement activities and continue until the end of construction activities.
4. INTENTIONALLY DELETED
5.3 CONTRACTOR shall submit the Inspectable Material Take off list for the
COMPANY approval within thirty (30) calendar days after the issuance of
Notice to Proceed.
Q-VI-2
MP-LSTK, MP-IK-LSTK, MP-OK-LSTK, MP-IK-LS, MP-IK-LSPB,
OFF-IK-LSPB, OFF-OK-LSPB, OFF-IK-LS, OFF-OK-LS, C/R
Revised 05/17
SCHEDULE Q – ATTACHMENT VI CONTRACT NO. 6600042823 (IK)
6.1 Paragraph 3.2 of this Schedule Q is deleted and replaced in its entirety
with the following:
6.3 Paragraph 3.6 of Schedule Q is deleted in its entirety and replaced with
the following:
“CONTRACTOR shall modify its Quality Plan(s) and ITPs, to reflect any
significant changes identified by CONTRACTOR or COMPANY.
CONTRACTOR’s revised Quality Plan(s) shall then be resubmitted for
COMPANY’s approval within seven (7) calendar days from date of
submittal.”
6.4 Paragraph 7.7 of Schedule “Q” is deleted in its entirety and replaced with
the following:
Q-VI-3
MP-LSTK, MP-IK-LSTK, MP-OK-LSTK, MP-IK-LS, MP-IK-LSPB,
OFF-IK-LSPB, OFF-OK-LSPB, OFF-IK-LS, OFF-OK-LS, C/R
Revised 05/17
SCHEDULE Q – ATTACHMENT VI CONTRACT NO. 6600042823 (IK)
Personnel
Work Personnel
Qualification
Procedure Qualification
Special Process Procedure
Approval (A) Approval
(Note1) Approval
or Review Required
Required
(R) Required (Yes/No)
(Yes/No)
Soil/Ground Improvements R No No
Mechanical Processes
Welding/Brazing A Yes Yes
Nondestructive Testing (NDT) R Yes (Note 1) Yes
Positive Material Identification
R No Yes
(PMI) & Color-Code Verification
Heat Treatment & associated
R No No
Hardness Testing
Hydrostatic Pressure Testing R No No
Valve Testing and Installation R No No
Coatings & Lining R No Yes
Gasket Installation & Bolt
R No No
Tightening
Gap Control (Socket welds,
thread engagement, back welding R No No
of threaded joints)
Hot Taps (Calcs) & Tie-ins A No No
Refractory Installation R No No
HVAC Testing & Balancing A No No
RTR Pipe work R No Yes
Electrical, Instrumentation & Communication Processes
High/Medium Voltage (HV/MV)
R No Yes
Cable Splicing/Termination
Electric Power Systems
R No No
Energization
Fiber Optic Cable
R No No
Installation/Termination
Cable Gland/Seal & Conduit Seal
R No Yes
Installation
Q-VI-5
MP-LSTK, MP-IK-LSTK, MP-OK-LSTK, MP-IK-LS, MP-IK-LSPB,
OFF-IK-LSPB, OFF-OK-LSPB, OFF-IK-LS, OFF-OK-LS, C/R
Revised 05/17
CONTRACT NO. 6600042823 (IK)
Q-VI-7
MP-LSTK, MP-IK-LSTK, MP-OK-LSTK, MP-IK-LS, MP-IK-LSPB,
OFF-IK-LSPB, OFF-OK-LSPB, OFF-IK-LS, OFF-OK-LS, C/R
Revised 05/17
SCHEDULE Q – ATTACHMENT VI CONTRACT NO. 6600042823 (IK)
Q-VI-8
MP-LSTK, MP-IK-LSTK, MP-OK-LSTK, MP-IK-LS, MP-IK-LSPB,
OFF-IK-LSPB, OFF-OK-LSPB, OFF-IK-LS, OFF-OK-LS, C/R
Revised 05/17
SCHEDULE Q – ATTACHMENT VI CONTRACT NO. 6600042823 (IK)
2 One (1) Primary Inspector can conduct Earthwork, Foundation, Steel Structure and Thrust Boring
inspections when Approved by COMPANY.
3 One (1) Primary Inspector can conduct multiple welding inspections within the same wellhead area
when Approved by COMPANY.
4 An additional CONTRACTOR Supervising Inspector can be provided by a Subcontractor when
Approved by COMPANY.
(Note: The Construction Phase quality personnel numbers and disciplines are provided
as guidelines in this EXHIBIT I. The Company Representative has the privilege to tailor
the content as applicable to the scope of work.)
Q-VI-9
MP-LSTK, MP-IK-LSTK, MP-OK-LSTK, MP-IK-LS, MP-IK-LSPB,
OFF-IK-LSPB, OFF-OK-LSPB, OFF-IK-LS, OFF-OK-LS, C/R
Revised 05/17